35722 Special Provisions.pdf

PDF 937 KB Posted

Attached to
ITB - Condon Pedestrian Access Project
Solicitation number
S-73000-00007424
Issued by
Deschutes County, Corvallis City, Oregon

About this file

This document contains the Special Provisions for the Condon Pedestrian Access Project, which is a contract opportunity issued by the Oregon Department of Transportation (ODOT) for the benefit of Gilliam County. The work includes constructing sidewalks, driveways, and curb ramps on North Main Street and Frazer Street in the City of Condon, as well as grading, paving, and installing signing. The project is to be completed in accordance with the 2021 edition of the Oregon Standard Specifications for Construction, as modified by the Special Provisions. No quantities are provided, but the work is to be performed on the excavation basis.

The Special Provisions include detailed requirements for items such as traffic control, erosion and sediment control, hazardous materials management, and concrete construction. Payment for the work will be made as lump sum or unit price items, with no separate payment for certain specified activities. The project is funded by the state and local jurisdictions, but no details on funding amounts or sources are provided.

View the file

Other files

File Type Posted
Prelim Bid Results~87.xlsx XLSX spreadsheet
Bid Pricing Form~19.xlsx XLSX spreadsheet
35722 Invitation to Bid.docx DOCX document
ATTACHMENT 4 Budget Proposal.pdf PDF
35722 Plans.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPECIAL PROVISIONS

FOR HIGHWAY CONSTRUCTION

OREGON DEPARTMENT OF TRANSPORTATION

SALEM, OREGON

GRADING, PAVING, SIGNING & CURB RAMPS

CONDON PEDESTRIAN ACCESS PROJECT

JOHN DAY HIGHWAY

GILLIAM COUNTY

TABLE OF CONTENTS FOR SPECIAL PROVISIONS

WORK TO BE DONE

SECTION 00210 - MOBILIZATION

SECTION 00220 - ACCOMMODATIONS FOR PUBLIC TRAFFIC

SECTION 00221 - COMMON PROVISIONS FOR WORK ZONE TRAFFIC

CONTROL

SECTION 00222 – TEMPORARY TRAFFIC CONTROL SIGNS

SECTION 00223 - WORK ZONE TRAFFIC CONTROL LABOR AND VEHICLES

SECTION 00224 - TEMPORARY TRAFFIC CHANNELIZING DEVICES

SECTION 00228 - TEMPORARY PEDESTRIAN AND BICYCLIST ROUTING

SECTION 00280 - EROSION AND SEDIMENT CONTROL

SECTION 00290 - ENVIRONMENTAL PROTECTION

SECTION 00294 - CONTAMINATED MEDIA

SECTION 00296 - PAINT AND PAINTED MATERIALS

SECTION 00305 - CONSTRUCTION SURVEY WORK

SECTION 00310 - REMOVAL OF STRUCTURES AND OBSTRUCTIONS

SECTION 00330 - EARTHWORK

SECTION 00440 - COMMERCIAL GRADE CONCRETE

SECTION 00470 - MANHOLES, CATCH BASINS, AND INLETS

SECTION 00490 - WORK ON EXISTING SEWERS AND STRUCTURES

SECTION 00640 - AGGREGATE BASE AND SHOULDERS

SECTION 00759 - MISCELLANEOUS PORTLAND CEMENT CONCRETE

STRUCTURES

SECTION 00905 - REMOVAL AND REINSTALLATION OF EXISTING SIGNS

SECTION 00920 - SIGN SUPPORT FOOTINGS

SECTION 00930 - METAL SIGN SUPPORTS

SECTION 00940 - SIGNS

SECTION 02001 - CONCRETE

SECTION 02030 – SUPPLEMENTARY CEMENTITIOUS MATERIALS

SECTION 02050 - CURING MATERIALS

SECTION 02415 - PLASTIC PIPE

SECTION 02560 - FASTENERS

SECTION 02690 - PCC AGGREGATES

SECTION 02910 - SIGN MATERIALS

FOR

Grading, Paving, Signing & Curb Ramps Condon Pedestrian Access Project

John Day Highway Gilliam County

PROFESSIONAL OF RECORD CERTIFICATION:

I certify the Special Provision Section(s) listed below are applicable to the design for the subject project for all roadway related items and erosion control. Modified Special Provisions were prepared by me or under my supervision.

Section(s) 00280, 00310, 00330, 00350, 00470, 00490, 00640, 00730, 00740, 00759, 02001, 02415, 02690

FINAL ELECTRONIC DOCUMENT AVAILABLE UPON REQUEST

Seal w/signature I certify the Special Provision Sections listed below are applicable to the design for the subject project for Permanent Signing.

Modified Special Provisions were prepared by me or under my supervision.

Sections 00440, 00905, 00920, 00930, 00940, 02030, 02050 & 02560.

Seal w/signature I certify the Special Provision Section listed below is applicable to the design for the subject project for construction survey work.

Modified Special Provisions were prepared by me or under my supervision.

Section 305

Seal w/signature

I certify the Special Provision Section(s) listed below are applicable to the design for the subject project for hazardous materials. Modified Special Provisions were prepared by me or under my supervision.

Section(s) 00294 and 00296

SPS_20179, Condon Pedestrian Access Project 1

WORK TO BE DONE

The Work to be done under this Contract consists of the following:

1. Construct sidewalks, driveways, and curb ramps on North Main Street and Frazer Street in the City of Condon.

2. Construct grading and aggregate base.

3. Install signing.

4. Perform additional and Incidental Work as called for by the Specifications and Plans.

APPLICABLE SPECIFICATIONS

The technical Specifications that are applicable to the Work on this Project is the 2021 edition of the "Oregon Standard Specifications for Construction", as modified by these Special Provisions.

All number references in these Special Provisions shall be understood to refer to the Sections and subsections of the Standard Specifications bearing like numbers and to Sections and subsections contained in these Special Provisions in their entirety.

SPS_20179, Condon Pedestrian Access Project 2

SECTION 00210 - MOBILIZATION

Comply with Section 00210 of the Standard Specifications.

SECTION 00220 - ACCOMMODATIONS FOR PUBLIC TRAFFIC

Comply with Section 00220 of the Standard Specifications modified as follows:

00220.02(a) General Requirements - Add the following bullet to the end of the bullet list:

• When an abrupt edge is created by excavation, protect traffic according to the "Excavation Abrupt Edge" and the "Typical Abrupt Edge Delineation" configurations shown on the Standard Drawings.

00220.40(e)(1) Closed Lanes - Replace this subsection, except for the subsection number and title, with the following:

Traffic Lanes may be closed on Main St. when allowed, shown, or directed during the following periods of time except as specified in 00220.40(e)(2):

Single Lane Closures - One Traffic Lane on Main St. may be closed during the following times:

• Daily, Sunday through Saturday, at all times.

One Traffic Lane may be closed on all other adjacent Roadways within the Project Site not listed above, when allowed, shown, or directed during the following periods of time except as specified in 00220.40(e)(2):

• Daily, Sunday through Saturday, at all times.

SECTION 00221 - COMMON PROVISIONS FOR WORK ZONE TRAFFIC CONTROL

Comply with Section 00221 of the Standard Specifications modified as follows:

00221.03 Traffic Safety and Operations - Replace the bullet that begins “When paving operations create…” with the following bullet:

• When paving operations create an abrupt or sloped edge drop off greater than 1 inch, protect traffic by installing signing according to the "2 Lane, 2 Way Roadway Overlay Area" detail shown on the Standard Drawings. Protect longitudinal and transverse Pavement joints by placing and maintaining an asphalt concrete wedge according to 00221.07(c)(1).

SPS_20179, Condon Pedestrian Access Project 3

00221.07(c)(1) Paving - Replace this subsection, except subsection number and title, with the following:

When the longitudinal joint is greater than 1 inch in height, install additional TCD according to 00221.03. Complete the placing of ACP and construction of paving joints according to 00735.48, 00735.49, 00743.45, 00744.44, 00744.45, 00745.47, and 00745.48, as applicable.

00221.90(b) Temporary Protection and Direction of Traffic - Delete the bullet that begins “Moving temporary barrier to and from Contractor’s stockpile areas”.

Replace the bullet that begins "When the Schedule of Items does not include …" with the following bullet:

• Preparing and signing the daily “Traffic Control Inspection Report”, when a TCS is not included in the Schedule of Items or when a TCS is not onsite for a work shift.

SECTION 00222 – TEMPORARY TRAFFIC CONTROL SIGNS

Comply with Section 00222 of the Standard Specifications modified as follows:

00222.40(e) Temporary Sign Placement - Add the following to the end of the bullet list:

• Place a “WAIT FOR FLAGGER” (CR4-23) sign approximately 50 feet in advance of each flagger station, facing incoming pedestrian traffic. Install the sign on a conical marker or other temporary sign support, as shown or as directed. Do not allow the sign installation height or location to block the visibility of the flagger for incoming public traffic.

• At least ten Calendar Days before closing the sidewalks on Main St, place a “SIDEWALK CLOSED, Full Time” (CW11-4) sign in advance of each future closure point. Locate the sign so it is legible from the nearest alternate pedestrian pathway facing incoming pedestrian traffic. The sign may be mounted between the panels of a Type II barricade or on a single-post TSS. Do not place the sign or sign support such that it narrows the pedestrian pathway to a width of less than 4 feet.

• Before opening the TPAR, place TPAR signing and other TCM as shown, or as directed. Maintain the “SIDEWALK CLOSED, Full Time” (CW11-4) signs while the TPAR is open to pedestrian traffic.

• For paving operations on non-freeways, place “ABRUPT EDGE” (CW21-9) and “ROAD WORK XX MPH” (CW20-1a) signs as shown. Use an “XX” value equal to 10 mph below the current posted regulatory speed. If a speed is posted for a temporary regulatory speed reduction, that speed is the current posted regulatory speed.

• For all other moving operations that do not create an abrupt edge adjacent to traffic, omit the “ABRUPT EDGE” signs.

SPS_20179, Condon Pedestrian Access Project 4

SECTION 00223 - WORK ZONE TRAFFIC CONTROL LABOR AND VEHICLES

Comply with Section 00223 of the Standard Specifications modified as follows:

00223.31(b) Traffic Control Inspection Without TCS - Replace the bullet that begins “Prepares and signs a daily “Traffic Control Inspection Report”…” with the following bullet:

• Prepares and signs a “Traffic Control Inspection Report” (Form No. 734-2474) upon the initial installation of TCM and each working day when any modification, removal, or reinstallation of TCM are made, or as directed by the Engineer. Submit completed reports to the Engineer no later than the end of the next working day.

SECTION 00224 - TEMPORARY TRAFFIC CHANNELIZING DEVICES

Comply with Section 00224 of the Standard Specifications modified as follows:

00224.46 Pavement Edge Delineation - Replace the paragraph that begins “Place tubular or conical markers…” with the following paragraph:

Place tubular or conical markers to delineate the edge of Pavement immediately after construction Work or paving operations create an abrupt or sloped edge drop-off greater than 1 inch in height along the right hand or left hand Shoulder.

SECTION 00228 - TEMPORARY PEDESTRIAN AND BICYCLIST ROUTING

Comply with Section 00228 of the Standard Specifications modified as follows:

00228.00 Scope - Replace this subsection, except subsection number and title, with the following:

In addition to the requirements of Section 00221, this Work consists of furnishing, installing, operating, maintaining, inspecting, and removing temporary devices for accommodating pedestrians and bicyclists through a work zone.

00228.13 Temporary Curb Ramps - Add the following sentence to the end of this subsection:

Furnish truncated dome detectable warning surface for temporary curb ramps from the QPL according to 00759.12.

SPS_20179, Condon Pedestrian Access Project 5

00228.43 Temporary Curb Ramps - Add the following paragraph to the end of this subsection:

Install a minimum 2 foot wide truncated dome detectable warning surface on temporary curb ramps at pedestrian street crossings. Omit truncated dome detectable warning surfaces on temporary curb ramps that are not at a pedestrian street crossing.

00228.80(a) Length Basis - Replace this subsection, except subsection number and title, with the following:

Pedestrian channelizing devices and bicycle channelizing devices will be measured on the length basis upon delivery to the Project. The quantities will be limited to those in the approved TCP.

00228.80(b) Unit Basis - Replace this subsection, except for the subsection number and title, with the following:

Temporary curb ramps will be measured on the unit basis, at each location where a temporary curb ramp is constructed or placed.

00228.90 Payment - Add the following paragraph after the paragraph that begins “In item (c), the type…”:

Item (c) includes furnishing and installing truncated dome detectable warning surfaces.

SECTION 00280 - EROSION AND SEDIMENT CONTROL

Comply with Section 00280 of the Standard Specifications modified as follows:

00280.15(d) Temporary Slope Drains - Replace this subsection, except subsection number and title, with the following:

Furnish either plastic pipe and flared end sections meeting the requirements of Section 02415 or metal pipe and flared end sections meeting the requirements of Section 02420.

SECTION 00290 - ENVIRONMENTAL PROTECTION

Comply with Section 00290 of the Standard Specifications modified as follows:

00290.20(c)(2) Clean Fill - Add the following paragraph to the end of this subsection:

Manage all excavated soil that does not meet the definition of clean fill according to Section 00294.

SPS_20179, Condon Pedestrian Access Project 6

SECTION 00294 - CONTAMINATED MEDIA

Section 00294, which is not a Standard Specification, is included in this Project by Special Provision.

Description

00294.00 Scope - In addition to the requirements of Section 00290 and the Specifications, this Work consists of the following:

• Excavate, segregate, stockpile, transport, and dispose of Contaminated Soils and contaminated grubbing materials, as defined by 00294.01, from the following locations:

Contaminated Soil Location Table 00294-1

From Location/Station to

Location/Station

Depth below grade

(feet)

Approximate Quantity (cy)

Presumed Contaminants

Soil Meeting the Definition of Shoulder Soil

0 to 1.5 feet or required excavation depth, whichever is shallower

Petroleum Hydrocarbons and Metals including lead

Garage Facilities Approx. Sta. 10+40 to 10+80 Rt.

Approx. Sta. 11+30 to 11+70 Rt.

Approx. Sta. 11+85 to 12+45 Lt.

Soil removed within required excavation depth below existing base rock.

Petroleum Hydrocarbons, Solvents, Metals

Approximate Total Quantity 89 cy

Quantity to be reused on Project 0 cy

Quantity to be disposed at landfill 133 tons

• In areas where excavation is not required, leave contaminated Material and clearing and grubbing Material in place.

• Prepare a Health and Safety Plan (HASP) for work within the contaminated areas of the Project.

The December 29, 2020 ODOT report, titled Hazardous Materials Corridor Assessment documenting the contaminated media identified within the Project, is available from the Engineer.

SPS_20179, Condon Pedestrian Access Project 7

00294.01 Definitions:

Contaminated Soil - Soil that does not meet the DEQ definition of "Clean Fill", as defined by OAR 340-093-0030(18). This Contaminated Soil is a regulated waste, subject to OAR 340-093-0005 through OAR 340-093-0290. If the grubbing Material has been determined to be contaminated, it will be considered and treated as Contaminated Soil for the purposes of this Section.

Shoulder Soil - Soil outside of the existing Highway Pavement and within Highway Right-of- Way generated during Highway maintenance or construction activities. This definition applies to excess Soil generated to a maximum depth of 1.5 feet below ground surface. This definition does not apply to Soil that is covered by existing impervious surfaces, including but not limited to curbs, sidewalks and parking lots constructed of asphalt or concrete.

ODOT Beneficial Use Determination (ODOT BUD) - The statewide ODOT Beneficial Use Determination (ODOT BUD), approved by DEQ (No. BUD-20181204), outlines a series of pre-approved non-residential reuse options for excess Soil Materials that do not meet DEQ’s Clean Fill Standards in some circumstances. These options may vary based on project scope and location, and documentation may vary, as directed by the Engineer.

00294.02 Testing of Contaminated Soil and Groundwater - When additional testing of Contaminated Soil or groundwater is required to characterize the Material for reuse, recycle, or disposal, conduct the tests according to 00290.20(c).

Use analytical methods meeting DEQ's Clean Fill Guidance Screening Levels for each analyte. Contaminated Soil and groundwater sampling must be conducted by an Oregon Registered Geologist or Professional Engineer who has experience characterizing contaminated media.

Collect at least 2 composite Soil samples and submit for the following required testing:

Shoulder Soil

• TPH-Dx by Northwest methods.

• Polynuclear aromatic hydrocarbons (PAHs) by EPA Method 8270SIM.

• TCLP lead by using EPA Method 1311.

Garage Facility Soil

• TPH-Gx and TPH-Dx by Northwest methods.

• Volatile organic compounds (VOCs) full list by EPA Method 8260.

• Polynuclear aromatic hydrocarbons (PAHs) by EPA Method 8270SIM.

• Total metals (RCRA 8) by EPA 6000 and 7000 series.

• One TCLP lead, cadmium, and chromium by using EPA Method 1311.

00294.03 Submittals - Submit the following documents:

• A site specific HASP at least 10 Calendar Days before the pre-construction conference.

• Current employee training certificates and medical surveillance information before beginning Work within the contaminated areas.

SPS_20179, Condon Pedestrian Access Project 8

Submit the following documents within 48 hours of removal of contaminated media:

• Permits, permit applications, and documentation of compliance.

• All reuse, recycled, and disposal receipts.

• Final quantities of Soil reused, recycled, and disposed and their final location.

• All analytical test results.

00294.05 Health and Safety Plan - Prepare a site specific HASP that meets or exceeds the requirements of 29 CFR 1910.120 and include a personnel and equipment decontamination plan that details how decontamination media will be contained and disposed.

Maintain a copy of the HASP on site at all times and readily available to employees and Inspectors during construction activities. If additional information becomes available regarding the site specific conditions, revise the HASP and submit the revised version to the Engineer. Review or acknowledgment of the HASP by the Engineer is not an indication or representation that the HASP is fully compliant with State or federal requirements.

Compliance is the responsibility of the Contractor. Review by the Engineer will not impose liability upon the Agency or relieve the Contractor of any responsibilities under the Contract.

Do not begin Work in contaminated areas until the Engineer provides written acknowledgement of the HASP.

All personnel entering contaminated areas shall follow the requirements of the HASP.

Labor

00294.30 Personnel Qualifications - Provide employees meeting the following requirements:

• Hazardous Waste Operations and Emergency Response (HAZWOPER) trained workers (29 CFR 1910.120) that:

• Have completed a 40 hour HAZWOPER training course.

• Have completed an 8 hour HAZWOPER refresher training course within the last 12 months.

• Participates in the HAZWOPER Medical Surveillance Program.

• A Supervisor that:

• Has at least 2 years of experience cleaning up and managing Contaminated Soil or groundwater in Oregon.

• Meets the HAZWOPER training requirements plus completed an 8 hour HAZWOPER supervisor training course.

• An Oregon Registered Geologist or Professional Engineer who has experience handling contaminated media.

SPS_20179, Condon Pedestrian Access Project 9

Construction

00294.40 Contaminated Soil Excavation - Excavate and handle Contaminated Soil from Project excavations according to the following:

• Notify the Engineer 3 Calendar Days before beginning excavation activities within contaminated areas.

• Allow the Agency to collect Soil samples during excavation activities.

• Field screen Soil using a portable photo ionization detector, portable flame ionization detector, field test kits, or other instrumentation capable of detecting the contaminants identified for this Soil.

• Segregate non-Contaminated Soil from Contaminated Soil during excavation activities, based on the field screening and the provided Contaminated Soil location information.

• Load Contaminated Soil directly into trucks and transport directly to the recycling or disposal facility, or on-site reuse areas or, when approved by the Engineer, temporarily store Contaminated Soil on-site.

• Store Contaminated Soil i if needed and as directed by the Engineer in covered water tight containers or place Contaminated Soil on minimum 6 mil thick polyethylene sheeting that has an impermeable berm around the edge. Cover the Contaminated Soil with minimum 6 mil thick polyethylene sheeting. Do not allow precipitation run-off to enter the excavated Contaminated Soil. Label all stored Material with the type of Material, the contaminants, and the dates of accumulation.

• Remove contaminated media from the exterior of all vehicles before they leave the Project Site

• Cover trucks transporting contaminated Materials to prevent spillage during transit to the disposal facility according to OAR 340-093-0220.

• Where over excavation is required, backfill the excavation according to 00330.42.

00294.41 Contaminated Soil Management - Reuse, recycle, or dispose of Contaminated Soil according to any of the following:

(a) Landfill Disposal:

• The City of Condon has an agreement with Waste Management to dispose of contaminated soil from this project at no additional cost. Fill out a waste profile at www.wmsolutions.com using the contaminated soil analytical results. Transport the contaminated soil to Chemical Waste Management of the Northwest Landfill, located at 17629 Cedar Springs Lane, Arlington OR 97812 for disposal.

• Dispose of temporarily stored Contaminated Soils within 30 Days of beginning excavation work or before Second Notification, whichever occurs first.

• Complete and sign all manifests and bill-of-lading forms for handling, loading, transporting, and disposing of the Contaminated Soil.

• Pay all filing and permit fees.

SPS_20179, Condon Pedestrian Access Project 10

Measurement

00294.80 Measurement - Work performed under this Section will be measured according to the following:

No measurement of quantities will be made for the following:

• HASP

• Segregate and stockpile Contaminated Soil

Soil sample and analytical testing will be measured on the unit basis for each sample submitted and tested according to 00294.02 when test results are submitted according to 00294.03.

The quantities of Contaminated Soil disposed will be measured on the weight basis, based on weigh tickets from the recycling or disposal facility.

Clearing and grubbing will be measured according to 00320.80.

Payment

00294.90 Payment - The accepted quantities of Work performed under this Section will be paid for at the Contract unit price, per unit of measurement, for the following items:

Pay Item Unit of Measurement

(a) Health and Safety Plan ............................................. Lump Sum

(c) Segregate and Stockpile Contaminated Soil ............. Lump Sum

(d) Soil Sample Collection and Analytical Testing ............... Each

(e) Contaminated Soil Disposal ............................................ Ton

Item (c) includes segregating, handling, and stockpiling Contaminated Soil within the Project Site for the purpose of analytical testing, on-site reuse, or disposal.

Item (d) includes mobilization, Soil sampling, testing, analyses, and preparation of reports for tests required in 00294.02. Additional testing beyond that listed in 00294.02 will only be paid if authorized by the Engineer.

Item (e) includes all costs involved with the disposal of Contaminated Soil at a recycling or disposal facility.

No separate or additional payment will be made for the excavation or reuse of Contaminated Soil or contaminated Shoulder Soil. Payment will be included in payment made for the appropriate items under which the excavation or reuse of Contaminated Soils or contaminated Shoulder Soil is required.

SPS_20179, Condon Pedestrian Access Project 11

Clearing and grubbing will be paid for according to 00320.90.

Payment will be payment in full for removing and disposing of all Materials, and for furnishing all Equipment, labor, Plans, test results, and Incidentals necessary to complete the Work as specified.

SECTION 00296 - PAINT AND PAINTED MATERIALS

Section 00296, which is not a Standard Specification, is included in this Project by Special Provision.

Description

00296.00 Scope - In addition to the requirements of Section 00290, remove lead, chromium, and cadmium based paints, and materials coated with lead, chromium, and cadmium based paints, according to the following Specifications.

Lead, chromium and cadmium based paints coat some of the concrete curbs to be demolished for this project. Analysis of paint samples collected from these curbs detected concentrations of total lead, cadmium and chromium in the concrete paint indicated in Table 00296-1 below:

Table 00296-1

Sample Location and Material

Total Lead (mg/kg)

Total Chromium (mg/kg)

Total Cadmium (mg/kg)

Approx. Sta. 11+ 50 Rt. 66,000 13,700 0.862

ND = not detected above the laboratory detection limit.

Toxicity Characteristic Leaching Procedure (TCLP) analysis of bulk painted concrete samples, representative of the waste that will be generated during demolition, detected the concentrations of TCLP lead, chromium, and cadmium indicated in Table 00296-2 below:

Table 00296-2

Sample Location and Material

TCLP Lead (mg/L)

TCLP Chromium (mg/L)

TCLP Cadmium (mg/L)

Approx. Sta. 11+ 50 Rt. ND ND ND

ND = not detected above the laboratory detection limit.

The March 29. 2021 ODOT report, titled Curb Lead-Based Paint Survey documenting these analyses, is available from the Engineer.

Unless otherwise tested, assume that all coatings contain lead, chromium, and cadmium and handle paint and painted materials accordingly during demolition.

SPS_20179, Condon Pedestrian Access Project 12

00296.03 Submittals - Submit the following documents:

• A job specific written compliance program, according to 29 CFR 1926.62(e)(2), at least 10 Calendar Days before the pre-construction conference. When applicable, include compliance procedures for cadmium and chromium VI, according to 29 CFR 1926.1127 and 29 CFR 1926.1126.

• Modifications to the written compliance program within 7 Calendar Days of the modifications.

• Current employee training certificates and medical surveillance information before beginning work that disturbs paint containing lead, cadmium or chromium.

• Within 48 hours of completing or receiving them:

• Disposal and recycling facility permits.

• Transport manifests and bill-of-ladings.

• All reuse, recycling, and disposal receipts.

• All analytical test results.

00296.04 Documentation - Include paint and painted materials management and planned reuse, recycling, and disposal information in the pollution control plan. Obtain Engineer approval for the specific reuse, recycling, and disposal methods for all materials before beginning demolition work.

Complete, sign and pay all required fees for all required permits, manifests, and bill-of-lading forms for transport and disposal of the paint and painted materials.

Labor

00296.30 Personnel Qualifications - Provide employees trained in lead awareness, according to 29 CFR 1926.62(l), and also trained according to 29 CFR 1926.1126(j)(2) for chromium and 29 CFR 1926.1127(m)(4) for cadmium, during demolition of painted portions of the structures.

Construction

00296.40 Handling - Minimize employee exposure to the metals contained in the paint.

Provide containment that prevents release of paint chips to the environment. Do not remove or separate paint from painted substrates, unless required to accomplish repair activities.

00296.42 Painted Concrete Debris Management - Reuse, recycle, or dispose of painted concrete debris according to any of the following:

• Recycle or Dispose of at Landfill - Recycle at a permitted municipal solid waste landfill or a permitted construction and demolition landfill as aggregate material for roads or other infrastructures within the landfill area or dispose of at a permitted municipal solid waste landfill or a permitted construction and demolition landfill for disposal.

SPS_20179, Condon Pedestrian Access Project 13

00296.45 Non-Hazardous Waste Paint Management - When non-hazardous paint is separated from its substrate, contain all the paint waste and dispose of it at a permitted municipal solid waste landfill.

00296.46 Hazardous Waste Paint Management - When hazardous waste paint is separated from its substrate, store all the separated paint waste in labeled, sealed, watertight containers and handle the hazardous waste according to 00290.20(d).

Measurement

00296.80 Measurement - No measurement of quantities will be made for Work performed under this Section.

Payment

00296.90 Payment - No separate or additional payment will be made for Work performed under this Section. Payment will be included in payment made for the appropriate items under which this Work is required.

SPS_20179, Condon Pedestrian Access Project 14

SECTION 00305 - CONSTRUCTION SURVEY WORK

Comply with Section 00305 of the Standard Specifications modified as follows:

00305.05 3D Engineered Models - Replace the bullet that begins “A detailed outline and list of…” with the following bullet:

• An automated machine guidance (AMG) work plan containing a detailed outline, list of the Pay Items and Work that will be controlled by the 3D Construction Models, and a narrative outlining any differences between the Agency prepared 3D Engineered Models and the 3D Construction Models.

Delete the bullet that begins “A narrative outlining…”

SECTION 00310 - REMOVAL OF STRUCTURES AND OBSTRUCTIONS

Comply with Section 00310 of the Standard Specifications modified as follows:

00310.90 Payment - Add the following to the end of this subsection:

No separate or additional payment will be made for removal or disposal Work included in Section 00330 according to 00310.02.

SECTION 00330 - EARTHWORK

Comply with Section 00330 of the Standard Specifications modified as follows:

00330.03 Basis of Performance - Add the following paragraph to the end of this subsection:

Perform all earthwork under this Section on the excavation basis.

00330.14 Selected Granular Backfill - Delete the sentence that begins “Reclaimed glass meeting the requirements of Section 02695…”

00330.15 Selected Stone Backfill - Delete the sentence that begins “Reclaimed glass meeting the requirements of Section 02695…”

SPS_20179, Condon Pedestrian Access Project 15

00330.80 Measurement - Replace the lead-in sentence and two bullets with the following:

No measurement of quantities will be made for earthwork performed under this Section. The estimate quantity of earthwork is:

Item Estimated Quantity (Cubic Yard)

General Excavation 353

00330.90 Payment – Replace the sentence that begins “The accepted quantities…” with the following sentence:

The accepted quantities of earthwork will be paid for at the Contract lump sum amount for the item “General Excavation”.

00330.92 Kinds of Incidental Earthwork - Add the following bullets to the end of the bullet list:

• Earthwork required for driveways and road approaches. Earthwork for driveways and road approaches will be that which is outside the Neat Line limits shown on the typical sections.

SPS_20179, Condon Pedestrian Access Project 16

SECTION 00440 - COMMERCIAL GRADE CONCRETE

Comply with Section 00440 of the Standard Specifications modified as follows

00440.12 Properties of Commercial Grade Concrete - Replace the bullet that begins "Slump - 5 inches…" with the following bullets:

• Slump - 5 inches or less

• For concrete sidewalks, ramps, driveways, or other hand finished surface applications, and when using a high range water reducing admixture, provide a slump of 8 inches or less as approved by the Engineer.

00440.13 Field-Mixed Concrete - Replace the subsection, except for subsection number and title, with the following:

CGC Work items listed in 00440.14(a) may be field-mixed conventionally, or by volumetric/mobile mixers conforming to ASTM C685. When approved, concrete sidewalks, concrete curb ramps, concrete driveways, and other flat concrete surfaces may be field-mixed using volumetric/mobile mixers conforming to ASTM C685, request approval prior to placement. For all other CGC applications, submit written request to the Engineer for approval to use volumetric/mobile mixers conforming to ASTM C685 at least 21 Days prior to placement.

Pre-packaged dry blended concrete from the QPL may be used for Work items listed in 00440.14(a).

00440.40(b) Placing - Add the following bullet to the end of the bullet list:

• When haul time or placement conditions warrant exceeding the time of discharge, submit a detailed breakdown of the estimated time needed from batching to discharge of a load along with the measures that will be taken to ensure slump, temperature and uniformity will be maintained. Submit in advance to establish a new time limit at the Engineer’s discretion.

SECTION 00470 - MANHOLES, CATCH BASINS, AND INLETS

Comply with Section 00470 of the Standard Specifications modified as follows:

00470.41(c) Grates, Frames, Covers and Fittings - Replace this subsection, except for the subsection number and title, with the following:

Set metal frames for manholes on full non-shrink grout beds to prevent infiltration of surface water or groundwater between the frame and the concrete of the manhole section. If concrete is to be poured around the frames, coat the portion of the frame that will contact the concrete with hot asphalt before placing the concrete. Set frames, covers and grates true to the

SPS_20179, Condon Pedestrian Access Project 17 locations and grades established. Clean bearing surfaces and provide uniform contact. The use of a bolt adjustment system for frames from the QPL is allowed. Secure all fastenings.

Construct all mortared, sanitary sewer manhole necks and all riser ring joints made with non-shrink grout using an approved commercial concrete bonding agent applied to all cured concrete surfaces being grouted.

00470.42 Precast Concrete Catch Basins and Inlets - Add the following sentence to the end of this subsection:

Grade adjustments using a bolt system from the QPL is allowed.

SECTION 00490 - WORK ON EXISTING SEWERS AND STRUCTURES

Comply with Section 00490 of the Standard Specifications.

SPS_20179, Condon Pedestrian Access Project 18

SECTION 00640 - AGGREGATE BASE AND SHOULDERS

Comply with Section 00640 of the Standard Specifications.

SPS_20179, Condon Pedestrian Access Project 19

SECTION 00759 - MISCELLANEOUS PORTLAND CEMENT CONCRETE STRUCTURES

Comply with Section 00759 of the Standard Specifications modified as follows:

00759.03 Required Submittals - Replace this subsection, except for the subsection number and title, with the following:

Material ordered or Work done before the Engineer reviews and returns the documents shall be at the Contractor's risk.

Submit the following:

(a) ADA Certification for Contractors - For all supervisory personnel who directly supervise the curb ramp Work, submit the names, telephone numbers, and copies of the ODOT ADA Certification for Contractors at least 10 Calendar Days before the preplacement conference.

(b) Curb Ramp Work Plan - Do not begin any curb ramp Work before the plan for completing the Work has been approved. At least 21 Calendar Days before the curb ramp Work is scheduled to begin, submit a plan for accomplishing all phases of the curb ramp Work, including but not limited to the following (also see 00180.41):

• Surface preparation

• Compliance with Working Drawings and details submitted under 00759.03(c)

• Compliance with current Standard Drawings and Plans

• Waste handling and disposal

(c) Working Drawings - At least 10 Calendar Days before the construction of a grouping of one or more curb ramp location(s), not to exceed 32 ramps unless otherwise approved under 00180.41, submit unstamped Working Drawings according to 00150.35. Include field verification of each ramp site, and all dimensions, slopes and grades necessary to demonstrate compliance with the Standard Drawings and Plans. Marked up Supplemental Drawings, if field verified, may be submitted as Working Drawings. Notify the Engineer of any deficiencies or noncompliance with the Standard Drawings or Plans. The Engineer will provide additional or modified Plans as needed. Do not begin Work at a curb ramp until submittals for that curb ramp have been received, reviewed, and accepted in writing by the Engineer.

After submittal of the unstamped Working Drawings, according to 00150.35 a site visit may be requested by the Contractor or Engineer. The site visit will include a review of any field markings and discuss the submitted unstamped Working Drawings. The Engineer will provide additional or modified information, as needed.

Include the following in the Working Drawings:

• Verification of elevations, slopes, grades and dimensions necessary to demonstrate compliance with the Standard Drawings and Supplemental Drawings, SPS_20179, Condon Pedestrian Access Project 20

• Verification of potential utility conflicts or other street furnishings that may require relocation or adjustment.

• Identification of infeasibilities or constructability issues with the Standard Drawings and Supplemental drawings.

(d) Corrective Action Plan - Unless otherwise approved, notify the Engineer before performing corrective action. Include TPAR necessary to complete corrective action work.

At least 21 Calendar Days before concrete Structures Work is scheduled to begin, submit a corrective action plan. The corrective action plan shall address procedures to correct deficient Structures through minor corrective action or replacement according to 00759.55(a), and include:

• List of minor corrective actions that will be used to correct deficiencies, according to 00759.50 and 00759.55.

• Procedures for performing corrective action.

• Proposed concrete grinding Equipment and method of grinding.

• Proposed concrete repair Material used for resurfacing ground concrete surfaces according to Section 02015.

• Construction activities, Equipment and staging necessary to complete corrective action Work.

The Engineer will review the corrective action plan(s) and provide a response to the Contractor within 5 Days after receiving the plan. Do not begin concrete Structure Work until the corrective action plan is approved by the Engineer.

00759.04 Preplacement Conference - Replace this subsection, except for the subsection number and title, with the following:

Before beginning any curb ramp Work, meet with the Contractor's ODOT ADA Certified supervisory personnel and any quality control personnel if applicable, any curb ramp Subcontractors' supervisory personnel, and the Engineer at a mutually agreed upon time.

If the Contractor's personnel change, or if the Contractor proposes a significant revision to the plan for accomplishing the curb ramp Work, the Engineer may require additional preplacement conferences. If the Contractor’s schedule of work identifies multiple groups of curb ramp construction, as allowed by 00180.41, additional preplacement conferences may be required for each ramp group, at a mutually agreed upon time before Work begins.

All supervisory personnel who have an active ODOT ADA Certification for Contractors and directly supervise the curb ramp Work are required to attend the preplacement conference.

Add the following subsection:

00759.23 Concrete Resurfacing Equipment - Furnish power-operated scarifying Equipment capable of uniformly removing and preparing the existing surface to depths required. For concrete grinding operations, furnish 12 segment grinders, fine-toothed scarifying Equipment, or other approved grinding Equipment.

SPS_20179, Condon Pedestrian Access Project 21

00759.31 Qualifications - Add the following sentence to the end of the paragraph:

Provide onsite supervisory personnel that are ODOT ADA Certified during construction of the curb ramps.

00759.46 Concrete - Replace this subsection, except for the subsection number and title, with the following:

Construct the Structures between suitable forms or by the extrusion method. Place concrete according to the Plans, Section 00440, and this Section.

00759.50(a) General - Add the following paragraphs to the end of this subsection:

Install truncated domes as shown. Place according to the manufacturer's recommendation.

Install abutting truncated dome panels with no more than 1/4 inch spacing. Install anchors along cut edges of truncated dome panels according to manufacturer's recommendations.

In addition, finish concrete surfaces of Structures to be within the established Slopes and dimensions allowed by the Standard Drawings and Plans. Repair or remove and replace Structures not meeting the Standard Drawings and Plans at no additional cost to the Agency.

00759.50(c) Driveways, Walks, and Surfacings - Replace this subsection, except for the subsection number and title, with the following:

Prevent segregation of the concrete during placement. Strike-off the concrete to the grade shown, and float the surface smooth. After the water sheen disappears, edge the joints and remove edging tool marks prior to final finishing. Lightly cross-broom the surface to a uniform texture. Do not trowel joints or edges after brooming surface.

The 24 inch smart level will be used to measure driveway and sidewalk cross slopes on the Pedestrian Access Route.

00759.50(d) Curb Ramps - Replace this subsection, except for the subsection number and title, with the following:

Prevent segregation of the concrete during placement. Strike-off the concrete to the grade shown and float the surface smooth. After the water sheen disappears, edge the joints and remove edging tool marks prior to final finishing. Lightly cross-broom the surface to a uniform texture. Do not trowel joints or edges after brooming surface.

The 6 inch smart level will be used to measure curb running slope. The 6 inch smart level will be used to measure slopes on portions of the curb ramp, gutter pan, or adjacent surfaces that cannot accommodate a 24 inch smart level. All other curb ramp locations will use a 24 inch smart level to measure slopes.

SPS_20179, Condon Pedestrian Access Project 22

Add the following subsection:

00759.55 Correction of Deficient Structures - Unless otherwise approved, notify the Engineer before performing corrective action. Correct deficiencies at no additional cost to the Agency. Perform corrective actions as directed, according to the approved corrective action plan, and according to the following:

(a) Minor Corrective Action - Submit Equipment and procedure for minor corrective action to the Engineer for approval. Minor corrective action can be performed to correct a deficiency up to 1 square foot per panel. Corrective action exceeding 1 square foot per panel requires removal and replacement according to 00150.25. Perform minor corrective action according to the following:

(1) Concrete Grinding - Grinding to correct high area deficiencies is limited to 3/16 inch. Use equipment meeting the requirements of 00759.23. Resurface all ground concrete surfaces according to 00759.55(a)(2).

(2) Concrete Resurfacing - Resurfacing to correct low area deficiencies is limited to 3/16 inch depth. Existing concrete is to be at least 7 Days old prior to resurfacing.

Resurface repair areas according to the following:

a. Keyway - Sawcut a keyway at the boundaries of repair areas that are not already defined by panel control joints. Sawcut shall be 1/8 inch wide and 1/4 inch deeper than the edge of the repair area. Bevel inside edge of keyway at a 45 degree angle.

b. Surface Preparation - Prepare limits of repair area by grinding using Equipment from 00759.23. After grinding, sandblast the surface of the repair area. Clean the surface using a low pressure washer, less than 5,000 psi.

c. Presoak - Presoak the repair area for a minimum of 30 minutes to saturated surface dry. Prior to resurfacing, ensure there is no ponding water on the surface.

d. Resurface - Provide concrete resurfacer from the QPL according to 02015.60;

refer to QPL remarks to select an appropriate material based on allowable installation depths. Furnish resurfacer in a color that closely matches the color of surrounding concrete surfaces. Mask boundaries of the repair area. Use hand tools to work resurfacer into keyways and match existing grade at boundaries. Apply a light broom-finish to achieve non-slip surface.

e. Curing and Return to Traffic - Wet cure for a minimum of 1 hour or per the manufacturer’s recommendation, whichever is more restrictive. Follow manufacturer’s recommendation for return to traffic time.

(3) ACP Grinding - Taper grind to match existing Pavement with a minimum grinding width of 1 foot for each 1/4 inch of ACP removed.

(b) Acceptance of Structures - Once the corrective work or replacement has been completed, acceptance will be based on the Engineer’s inspection and approval of the Structure.

SPS_20179, Condon Pedestrian Access Project 23

00759.90 Payment -

Replace the paragraph that begins "Item (k) includes the additional Work required …" with the following paragraph:

Item (k) includes the additional Work required to construct a curb ramp or replace an existing curb ramp. Payment for the area of the curb ramp will be made under the concrete walks Pay Item.

Replace the paragraph that begins "No separate or additional payment will be…" with the following paragraph and bullet list:

No separate or additional payment will be made for:

• curb ramp Working Drawings

• curb ramp plan

• preplacement conference

• concrete form verification

• any necessary repair or removal and replacement of Structures

• providing supervisory personnel who have an active ODOT ADA Certification for Contractors to directly supervise the curb ramp Work

• developing corrective action plans

SPS_20179, Condon Pedestrian Access Project 24

SECTION 00905 - REMOVAL AND REINSTALLATION OF EXISTING SIGNS

Comply with Section 00905 of the Standard Specifications.

SECTION 00920 - SIGN SUPPORT FOOTINGS

Comply with Section 00920 of the Standard Specifications modified as follows:

00920.80 Measurement - Add the following to the end of this subsection:

The estimated quantities of concrete for minor sign supports are:

Support Type Quantity

Perforated Steel Square Tube Slip Base Sign Supports 0.3 cu. yd.

SECTION 00930 - METAL SIGN SUPPORTS

Comply with Section 00930 of the Standard Specifications.

00930.80 Measurement - Add the following to the end of this subsection:

The estimated quantities of structural steel are as follows:

Item Estimated Quantity (Pound)

Perforated Steel Square Tube Slip Base Sign Supports 288.2

SECTION 00940 - SIGNS

Comply with Section 00940 of the Standard Specifications modified as follows:

00940.47 Sign Erecting - Replace the paragraph that begins "When signs are installed on supports…" with the following paragraph:

When signs are installed on supports 10 feet or less from the edge of guardrail, curb, or Shoulder, set them to reflect 0 to 3 degrees away from traffic. When signs are installed on supports more than 10 feet from the edge of guardrail, curb or Shoulder, set them to reflect 0 to 3 degrees toward traffic.

SPS_20179, Condon Pedestrian Access Project 25

SECTION 02001 - CONCRETE

Comply with Section 02001 of the Standard Specifications modified as follows:

02001.02 Abbreviations and Definitions:

Add the following definition:

Lightweight Concrete - Structural concrete having a specified density using lightweight Aggregates.

Replace the sentence that begins “Pozzolans - Fly ash, silica fume…” with the following sentence:

Pozzolans - Fly ash, natural Pozzolans, silica fume, and high-reactivity Pozzolans.

Replace the sentence that begins “Supplementary Cementitious Materials - Fly ash, silica fume…” with the following sentence:

Supplementary Cementitious Materials - Pozzolans and ground granulated blast furnace slag.

02001.15(a) Current Mix Designs - Replace this subsection, except for the subsection number and title, with the following:

Mix designs that meet the requirements for the specified class of concrete and are currently being used or have been used within the past 24 months on any project, public or private, may be submitted for review. Provide individual test results that comprise the average if more than one data point exists. For paving designs the flexural strength testing must be from within the last two years. For HPC designs the length change and permeability tests must be from within the last two years.

02001.15(b)(1) Trial Batch Plastic Properties - Replace this subsection, except for the subsection number and title, with the following:

For each trial batch, test according to the following test methods:

Test Test Method Sampling Fresh Concrete WAQTC TM 2 Concrete Temperature AASHTO T 309 Slump AASHTO T 119 1 Air Content AASHTO T 152 or T 196 2 Density AASHTO T 121 Yield AASHTO T 121 Molding Concrete Specimens AASHTO T 23 or R 39 3 Water Cement Ratio 4

SPS_20179, Condon Pedestrian Access Project 26

1 For drilled shaft concrete test the slump retention by subsequent tests at half-hour intervals for the duration of the estimated drilled shaft placement, including temporary casing extraction. Report in table or graphical format.

2 Use AASHTO T 196 for lightweight concrete.

3 Cast cylinders in single use plastic molds.

4 Use ODOT's Field Operating Procedure for AASHTO T 121 in the MFTP.

02001.15(c)(12) Documentation of Average Compressive Strength - Replace this subsection, except for the subsection number and title, with the following:

Provide an analysis, showing applicable data and calculations for documentation of average compressive strength according to ACI 301.

02001.20(a) Strength - Replace Table 2001-1 with the following Table 2001-1:

Table 02001-1

Concrete Strength and Water/Cementitious Material (w/cm) Ratio

Type of Concrete

Strength 'c (psi)

Maximum w/cm Ratio

Structural

3300 0.50

(Seal)

0.45

0.48 4000

(Drilled Shaft)

HPC4500

0.40

HPC(IC)4500

5000 +

Paving 4000 0.44

PPCM’s (with cast-in-place decks and no entrained air)

5000 0.48

5500 0.44

6000 + 0.42

02001.20(a)(1) Required Average Compressive Strength (f’cr) - Replace this subsection, except for the subsection number and title, with the following:

Except for PPCM designs, provide the required average compressive strength according to ACI 301 for mix design approval.

02001.30(e)(1) HPC Coarse Aggregate Content - Delete the paragraph that begins “Two or more Aggregate products or sources…”

SPS_20179, Condon Pedestrian Access Project 27

SECTION 02030 – SUPPLEMENTARY CEMENTITIOUS MATERIALS

Comply with Section 02030, of the Standard Specifications modified as follows:

02030.00 Scope - Replace this subsection, except for the subsection number and title, with the following:

This Section includes the requirements for fly ash, natural pozzolans, silica fume, ground granulated blast furnace slag and high reactivity pozzolans used in portland cement concrete.

02030.10 Fly Ash - Replace this subsection, except for the subsection number and title, with the following:

Furnish Class C and Class F fly ash from the QPL and conforming to

AASHTO M 295 (ASTM C618).

Add the following subsection:

02030.15 Natural Pozzolans - Furnish Class N natural pozzolans from the QPL and conforming to AASHTO M 295 (ASTM C618).

02030.50 Metakaolin - Replace this subsection with the following:

02030.50 High Reactivity Pozzolans - Furnish high-reactivity pozzolans from the QPL and conforming to AASHTO M 321.

SECTION 02050 - CURING MATERIALS

Comply with Section…