Pre-Bid RFIs Answers.xlsx

XLSX spreadsheet 20 KB Posted

Attached to
Y1LC--Replace Steam Line Buildings 115, 118, and 400 [552-24-512]
Solicitation number
36C25025B0032_A00005
Issued by

About this file

This file is a Pre-Bid Request for Information (RFI) Answers document for a VA project to replace steam lines in Buildings 115, 118, and 400 at a Veterans Health Administration facility. The project involves roof replacement, utility work, and infrastructure improvements, with specific requirements including stainless steel hangers and rollers, a new sump pump installation, and utility relocations. Key project parameters include a 120-day period of performance, requirements for badging, background checks, and on-site safety protocols, with work to be completed primarily during regular hours.

Critical technical and logistical details include provisions for a contractor laydown area, parking along New Hampshire Avenue, use of VA indoor restrooms, and temporary fencing guidelines. The project requires dedicated on-site personnel including a superintendent, mandates specific safety and quality control measures, and involves infection control considerations, particularly in the basement of Building 400. Contractors must obtain VA-issued tax exemption certificates, comply with badging and tuberculosis testing requirements, and be prepared for a pre-construction meeting that will trigger the Notice to Proceed (NTP).

View the file

Other files

File Type Posted
Direct Bury Pipe - Salient Characteristics.pdf PDF
B-118 HV1.00.pdf PDF
024100 demolition.pdf PDF
B118 outside power and water.jpg JPG image
B-115 M-01.pdf PDF
B-118 HV200.pdf PDF
Building 118 Basement Photos.docx DOCX document
Electrical Distribution Plan B115 B118 B400.docx DOCX document
312011 earthwork.docx DOCX document
B-400 M-02.pdf PDF
015719 Temp Environ Cont.docx DOCX document
Building 400 Basement Photos.docx DOCX document
36C25025B0032 A00005.pdf PDF
Contractor Areas.jpg JPG image
Building 115 Basement Photos.docx DOCX document
Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Pre-Bid RFI Log - Replace Learning Exchange Roof
QuestionResponse
1Is there a requirement for a full time SSHO on this project? If so, can the superintendent, be it.superintendent can qualify, but cannot be Super/ SSHO/ and QC
2Is the A requirement for a QC on this project? If so, Can the superintendent, be it.see #1
3Will there be any drawings provided so that everyone is bidding the same thing.Yes, drawings and pictures will be provided.
4Will there be in abatement required?no
5Will there be division 1 specs issued, or any other specs issued?will be posted
6Is there a drawing providing existing utility layout for digging purposes around buildings and in roadways?no, contractor is responsible for all utility locates
7Need to have a drawing for power location for sump pump with the requirements. no mention of horsepower, if battery backup, or power requirements. no electrical specification or specific location for field verification.power is 110v, 1/2 hsp (min), heat resistant, no battery backup, will be placed in existing manhole, wire feed into B115
8Need to verify if the hangers and rollers need to stainless steel. Everything currently being used is put in stainless steel.all stainless steel
9When is the NTP be issued. This is required so we know if we will need to carry any winter conditions for concrete and asphalt work.NTP will be issued after the pre-construction meeting occurs.
10Is there a requirement for self-performing work on this projectyes
11Will a bid bond be required?Yes; in formation is located in the solicitation
12Will payment and performance bonds be required for the project?Yes, information is located in the solicitation
13The solicitation document, specifically the last line of block 10, states that drawings will be provided; however, there have been no drawings posted for this project. Will / Can drawings please be provided, as the lack of such will significantly hamper the competitiveness of this bid and will prevent many subcontractors from bidding this project. Furthermore, the lack of sufficient details in the SOW document and single specifications section provided are expected to cause unnecessary RFI's and possible delays to construction.some drawings will be provided, this is all the VA has on this project
14Can a second site visit be offered; this is especially critical if Drawings are not provided.no, additional pictures/ drawings will be provided
15Can the site visit list please be provided?Posted as A00002 on sam.gov
16Will the facility require any work to be completed off-hours? A) If so, please confirm tasks, scopes, etc. that need to be completed off hours. B) If so, can these tasks / scopes of work be completed in the evenings and/or weekends?no, but contractor may ask to work off hours/ weekends/ federal holidays at no additional cost to the government
17Where will the Contractor be permitted to create a laydown area?screenshot will be provided
18How much space will be permitted for the Contractor's laydown area?see provided screenshot for trailer and laydown area
19Is temporary power available for a Construction Trailer at the laydown/storage area?not for a construction trailer, there is 110v power available
20Will this project be Sales Tax Exempt?Contractor must request the tax exemption certificate after award is made.
21Will there be any limitations to much area the contractor can work on at any given time?Each building is being utilized by veterans and VA staff. B400 will require the traffic to be re-routed and the shared parking lot betwee B115/B118 cannot be completely blocked.
22Will water be provided for the contractor's use at no cost?there is water available on the E side of the protestant chapel
23Are there any known or suspected ACM materials included in the scope of work are for this project?no
24The SOW documents states to match existing stanchions, pads, hangars, rollers, concrete pads, expansion joints - please confirm the existing type and properties of all of these items.all stainless steel
25The SOW document states that intallation of new precast sidewalk caps are required: A) where are these located? B) What is the quantity sidewalk caps? C) What are the dimensions of the new sidewalk caps?A) the sidewalk from B115 to B400 B&C) contractor to verify
26What are the requirements for the new sump pump that is stated as being needed in the SOW? (HP rating, head, Voltage, Amperage, etc.)see #7
27Where will power need to be ran to in building 115 for powering the needed sump pump? A) Is there space within an existing panel for connection of a new sump pump? B) What are the requirements for routing power for the sump pump (conduit size/type, routing locations/limitations, distance to new sump pump location, etc.)In the basement of B115. Power panel is approximately 100' inside basement.
28The SOW states that the contractor is to repair areas of trench walls that are failing; please confirm the extent of such walls that need repaired.patching cracks and small chips
29Pleae provide details of the 14" tile that is noted to be required in the existing box for the new sump pump.14" perforated tile, 18" deep with 3" gravel base
30For gravel base for the sump pump, what is the required depth?18" minimum with 3" gravel base
31Please provide a copy of the Site Visit Attendance Sheet.Posted as A00002 on sam.gov
32Please confirm this is not a tax-exempt project. A) If tax-exempt, will the government provide the prime contractor with a tax-exempt certificate for use by subcontractors and vendors?Contractor must request the tax exemption certificate after award is made.
33Can both the bid and bid bond be emailed?Directions will be provided to Awardee after award
34In the event of a contract modifications/change orders, should performance and payment bond premiums be applied to each individual change order or wait until the end of the project where a final modification is issued for the overruns? We ask this because VA Acquisition Regulation (VAAR) clause 852.228-70, titled "Bond Premium Adjustment" states "in determinging the basis for final settlement"Wait until the end of the project
35Is a superintendent employed by the GC a requirement for this project?yes
36If a prime contractor is awarded multiple projects at the same VA Medical Center location, can the superintendent be shared across multiple projects at the same site/location, or should they only be dedicated full-time to this project?dedicated to this project only
37Is a Quality Control Manager (QCM) a requirement for this project? A) If a QCM is required, please provide specification 01 45 00. B) Please confirm that per 01 45 00 3.4 C, the Superintendent can also fulfill the QCM role. C) If the Super can't be the QCM, the average ADDITIONAL cost for a dedicated QCM is approximately $36,000 per month (salary, labor burden, per diem, housing, company vehicle, monthly return trips home, company phone, etc). We expect this project to be 4 months long, and the bid is expected to increase by $144,000. Please confirm a dedicated QCM is still required. D) If the Super can't be the QCM, is the QCM required to be onsite full-time, or can they make site visits as required for inspections? E) If the Super can't be the QCM and the QCM is required to be onsite full-time, should they be assigned to this project only, or can be assigned to another project as well on the same property? F) If the Super can't be the QCM, can a subcontractor (e.g., Terracon or a similar testing firm) fulfill the QCM role?see #1
38Is a Site Safety & Health Officer (SSHO) a requirement for this project? A) If a SSHO is required, please provide specification 01 35 26. B) Can the Superintendent fulfill the Site Safety & Health Officer (SSHO) role? Specification 01 35 26, 1.7 D in its reference to FAR 52.236-6, can be interpreted to mean that the SSHO can also be the Superintendent. Please confirm that the Superintendent can fulfill the Site Safety & Health Officer (SSHO) role. C) If the Super can’t be the SSHO, the average ADDITIONAL cost for a dedicated SSHO is approximately $36,000 per month (salary, labor burden, per diem, housing, company vehicle, monthly return trips home, company phone, etc). We expect this project to be 4 months long, and the bid is expected to increase by $144,000. Please confirm a dedicated SSHO is still required. D) If the Super can’t be the SSHO and the SSHO is required to be onsite full-time, should they be assigned to this project only, or can they be assigned to another project as well on the same property? E) If the Super can’t be the SSHO, can a subcontractor fulfill the SSHO role?see #1
39Is badging required for the project?yes
40Will background checks and fingerprints be required for any scope of work related to this project?yes
41How long is the turnaround time for background check results?usually a couple weeks, VA will provide temp badging until hard badges arrive
42How many hours should the prime contractor and subcontractors' budget for on-site badging, safety training, orientation, etc.?contractors discretion
43Please confirm if tuberculosis testing is required before contractors can commence work onsite.Per spec 01 35 26 para 1.16
44Please confirm if influence vaccines are required for all contractors and subcontractors' employees who work on the site or if masks will be required.no
45The period of performance (POP) on this project is given to be 120 days. However, we estimate the project will take 120 days for construction and 90 days for preconstruction activities. Contractors never know when the government will issue an NTP; sometimes, it's immediately after the award; sometimes, we receive an admin NTP to begin submittals, etc. We estimate the time to construct this job plus preconstruction activities to be longer than the stated POP. We request that the POP be extended by 90 days, assuming NTP is issued before preconstruction activities.NTP will be issued after the pre-construction meeting.
46Will the government provide call-in details and instructions for the bid opening to ensure transparency for all bidders?Yes
47Please provide the point of contact information for the BMS integration contractor.Will be provided to Awardee
48Please provide the point of contact information for the Fire Alarm integration contractor.Will be provided to Awardee
49Is any ICRA required? If so, where?only in basement of B400
50Please provide complete Infection Control Risk Assessment forms for each area which require different levels of infection control.ICRA level 1
51Will the VA allow a Temp Wall System (i.e., Starc Wall, Edge Guard, etc) instead of a rigid wall ICRA system? This usually provides substantial cost savings to the VA.yes, this will only be needed in B400
52Will the VA allow the use of Zip Wall (plastic sheathing with support poles) for barriers and containment on this project?yes, see #51
53If fire-rated walls are required, can we use one-hour-rated temporary walls, which are ASTM-certified?no fire-rated walls are needed
54Will the government accept ICRA Walls / Fire Rated Walls to the drop ceiling and fire-retardant plastic from the drop ceiling to the deck above?see #51/ 53
55If necessary, will negative air machines be permitted to exhaust through HEPA filter into the occupied space? A) If not, please provide locations where negative air machines can be exhausted.negative air system will not be required
56Is any scope of work for this project will be required to be performed outside of regular hours? A) If so, what trades or scopes will be required to be performed outside of regular work hours? B) If so, what will the work hours and days be for scopes required to be performed outside of regular work hours?see #16
57Are water connections available near the construction area?see #22
58Will the VA allow contractors to use water from VA sources?see #22
59Are electrical outlets available for contractors to connect to in the construction area? A) If not, where are electrical outlets available for contractors to connect to?there is one 110v outlet on the E side of the Protestant chapel
60Are contractors required to set a pole and meter electric usage? A) If a pole and meter are required, please provide the location of the pole and meter. B) If a pole and meter are required, please provide the location where power can be pulled from to feed the pole and meter.no
61Where are the designated contractors' and subcontractors' parking area?parking will be allowed along N side of New Hampshire Ave and N side of the church drive
62Is parking available for 2-3 vehicles for the prime contractor and each subcontractor for a total of 6-9 vehicles? A) Where shall these people park if the VA cannot make 2-3 spaces available for the prime contractor and each of the subs for a total of 6-9 vehicles?see #61
63Will the VA provide space for the Prime Contractor's Superintendent to set up, or should we add costs to our bid for a mobile office?See #17
64Where can the mobile office be located?see #17
65Where is the electrical connection for power to the mobile office?see#19
66Are contractors required to set a pole and meter electric usage in mobile office?no
67Is space available for a 8'X40' temporary ground-level office near the electrical connection?in the contractors laydown area
68Will the VA provide space for a 20-yard dumpster?see #67
69Where shall contractor dumpsters be located?see #67
70Can the VA accommodate a dumpster near the job site?see #67
71Will the VA allow contractors to use VA indoor restrooms?yes, in B115
72If required, can Porta Johns be placed within a 100' radius of the job site / work area?yes
73Other than around the excavation sites, is temporary construction fencing required anywhere else on the project or at the laydown area? A) Please confirm that 6' tall temporary construction fencing is acceptable. We ask this because the standard VA specifications is a minimum of 2.1m (seven feet) tall, which is not an industry standard height and would require a custom fence to be made at that height. Alternatively, an 8' high fence generally tends to blow over even with sandbags on the bases when the fabric is required to be fastened to the fence, since 8' tall panels with fabric have to potential to cause damage to property and injury to personal, we strongly recommend using 6' tall temporary construction fencing.6' tall temporary construction panels are acceptable on this project
74Can utility tie-ins be performed during regular hours?yes
75Can system commissioning activities be performed during regular hours?yes
76Will the VA allow for stored material so that we can procure and lay down long lead times and / or critical path material/equipment?yes
77Will the VA fully pay for this material/equipment if stored onsite? Please confirm that the current design documents meet current VA TIL guidelines.yes, contractor is responsible for stored material onsight FAR 52-232-5
78Is there any work not included in the drawings or contract documents that will need to be performed under the contract?no
79Please provide a wall and door protection schedule.na
80Please provide a Reflective Ceiling Plan indicating which types of ceilings will be affected by the work. (ACT with size or Gypsum Board).na
81If a Reflective Ceiling Plan is not available, which areas and types of ceilings will be affected by the work?na
82Please provide drawings, details and specifications for the following missing specifications: A) 01 56 26 - Temporary Fencing, B) 01 57 19 - Temporary Environmental Controls, C) 02 30 00.02 - Locating Services, D) 02 41 19 - Selective Demolition, E) 03 30 00.02 - Cast-in-Place, F) 22 00 00 - Plumbing, G) 23 05 93 - TAB, H) 23 09 23 - Direct Digital Control, I) 23 07 00 - Foam Glass Insulation, J) 26 05 19 - Electrical, K) 31 22 00 - Grading, L) 31 23 33 - Trenching and Backfilling, M) 32 12 16 - Asphalt Paving, N) 32 13 13 - Concrete Paving, O) 32 17 23 - Pavement Marking, P) 33 63 00 - Steam Energy DistributionA) see #73 B) provide erosion, and water controls C) see #6 E) 4 slump w/ WWM at 3000psi minimum G) NA H) NA I) see SOW M) para 2.1/ asphaltic base N) NA O) ODOT specicications
83Please provide drawings showing the routes for electrical & direct digital control wiring.See electrical distribution Plan.
84Please provide drawings showing the connection locations for the steam pipe in each building (118, 115, 400).See photos
85Is this project intended to be a design build project?Remove and replace as existing
86Please confirm that this bid needs to be hand delivered vs email?Per the solicitation, no emailed bids are authorized.