Post Award Schedule 6FL0704.pdf
PDF 60 KB Posted
- Solicitation number
- 6FL0704
About this file
This is an AAAP Project Specific Advertisement (PSA) Attachment detailing the post-award schedule for a GSA lease project. The schedule replaces the attachment referenced in section 1.05 of the RLP (R100) and applies to section 4.01 of the Lease (L100). The post-award schedule commences within 5 working days of lease award and governs the design and construction process through space acceptance.
The schedule outlines eleven sequential activities with defined working day allocations: Lessor-Provided Design Intent Drawings (10 days), Government review and approval of design drawings (15 days), Lessor preparation and submission of construction documents (10 days), Government review of construction drawings (5 days), Lessor preparation and submission of TI and BSAC price proposal (10 days), Government review, negotiation, and approval of pricing (15 days), Government issuance of Notice to Proceed (5 days), Lessor construction completion (30 days), Government inspection (5 days), and punchlist completion with Government acceptance (5 days). The cumulative timeline requires space acceptance by June 1, 2027. The document specifies that TI refers to tenant improvements and BSAC refers to building standard alterations and construction costs that require Government approval before construction commences.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SAM Ad 6FL0704 (1).pdf | ||
| Delineated Area Exhibit 6FL0704.pdf | ||
| USDA OIG ASR 6FL0704.pdf | ||
| Space Layout 6FL0704.pdf | ||
| SAM Ad 6FL0704.pdf | ||
| FPS ASR 6FL0704.pdf | ||
| DCSA ASR 6FL0704.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AAAP Project Specific Advertisement (PSA) Attachment: Post-Award Schedule
This attachment details the post-award schedule for this project. It hereby replaces the Attachment referenced in section
1.05 of the RLP (R100) and should be used when reviewing section 4.01 of the Lease (L100).
The below post-award schedule commences within 5 working days of lease award. The time frames below apply to the management of the design and construction process, concluding at the date of acceptance for the space.
Activity Working Days
Lessor-Provided Design Intent Drawings 10
Government (GSA and Client) Review and Approval of Lessor Provided Design Intent Drawings 15
Lessor Preparation and Submission of Construction Documents 10
Government Review of Construction Drawings 5
Lessor Preparation and Submission of the TI and BSAC Price Proposal 10
Government Reviews, Negotiates, and Approves Pricing 15
Government Issues Notice to Proceed with Construction 5
Lessor Completes Construction of TIs and Completion of Other Required Construction Work 30
Government Inspects Finished Space 5
Lessor Completes Punchlist and Government Accepts Finished Space 5
Total Work Days from Lease Award to Government Acceptance Space Acceptance by June 1, 2027
AAAP POST-AWARD SCHEDULE, PAGE 1 OF 1 PSA VERSION - REV (10/22)