This is a Project Statement from the State of Michigan Department of Technology, Management and Budget for the Department of Natural Resources, Parks and Recreation Division. The project involves professional architectural and engineering services for the design of a new ADA-compliant pedestrian bridge over the Little Iron River at Porcupine Mountains Wilderness State Park in Ontonagon County. The bridge will accommodate the Iron Belle/North Country Trail re-route and will be designed for pedestrian use only with aesthetics appropriate to a wilderness setting. The stream crossing spans approximately 31 feet in bank full width with approximately 63 feet from top of bank to top of bank, with the south bank rising approximately 15 feet and the north bank approximately 10 feet. The scope of work includes Phase 500, 600, and 700 design services with specific deliverables including a pre-design kickoff meeting with on-site walkthrough at park headquarters, a 50% plan review meeting, a 90% plan review meeting conducted via GoToMeeting or similar electronic format, and a 100% plan verification submittal. Design is required to be 100% complete by July 15, 2019, with construction completion desired prior to winter 2019. Proposals are due February 21, 2019, with five paper copies and five electronic versions to be submitted to DTMB Design and Construction. The contract award is anticipated on approximately April 1, 2019. No mandatory site walkthrough is required for proposal submittal, though PSC firms should visit the remote, snow-covered site as needed.

The project includes specific reimbursable expenses with established budgets: survey costs of $8,000, soil borings and soils analysis of $7,500, and DEQ inland lakes and streams permit application preparation and submittal of $1,000. The selected firm must maintain a complete electronic project file containing all documentation, correspondence, field orders, RFI responses, and communications. Final as-built drawings and CAD drawings must be provided to DTMB and DNR. The project requires compliance with all applicable federal codes and standards administered by EPA, OSHA, DOT, and state agencies including DCH, DEQ, DNR, and MIOSHA, as well as any applicable local regulations. Reference documents provided include preliminary trail findings, representative bridge design examples from comparable projects, site location maps, plat maps, site photographs, and Great Lakes road stream crossing inventory data. Questions regarding the RFP must be submitted to the listed DNR and DTMB contacts until seven calendar days prior to the proposal due date.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DMB-427 (R 6/11)

PROJECT STATEMENT

STATE OF MICHIGAN

DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET

Facilities and Business Services Administration

First Floor, Stevens T. Mason Building P.O. Box 30026

Lansing, Michigan 48909

FILE NUMBER

751/18360.RAA

INDEX NUMBER(S)

51110

PROPOSAL DUE DATE

February 21, 2019

CLIENT AGENCY

Department of Natural Resources – Parks and Recreation Division

PROJECT NAME AND LOCATION

Porcupine Mountains Wilderness State Park – Iron Belle Trail Pedestrian Bridge PROJECT ADDRESS (if applicable) Porcupine Mountains Wilderness State Park, T50N, R43W, S11 (N 46 degrees 44.81’, W 89 degrees 38.35’) Bridge Site Location

CLIENT AGENCY CONTACT

Eric Cadeau cadeaue@michigan.gov

TELEPHONE NUMBER

906 353 6651

DTMB - DCD PROJECT TEAM

Robert A. Adams adamsb1@michigan.gov /John Patrick patrickj1@michigan.gov Jeff Barsch barschj@michigan.gov/Dan Hall halld22@michigan.gov

TELEPHONE NUMBER

517 242 1088

NO MANDATORY WALKTHROUGH REQUIRED – PSC SHALL VISIT THE SITE AS REQUIRED FOR PROPOSAL SUBMITTAL. ALSO- SEE ATTACHMENTS and COORDINATES. SITE IS VERY REMOTE AND SNOW COVERED.

5 Paper copies and 5 electronic versions of the Proposal shall be sent to:

DTMB – Design and Construction -- Anne Watros/ Stella Holmes 3111 St Joseph Street Lansing Michigan 48917

PROJECT DESCRIPTION/SERVICES REQUESTED

The project scope of work includes Phase 500, Phase 600, and Phase 700 Professional Architectural and Engineering services for design of a new pedestrian bridge for the Iron Belle / North Country Trail at the Michigan Department of Natural Resource’s Porcupine Mountains Wilderness State Park.

The Iron Belle / North Country Trail is proposed to be re-routed into the Porcupine Mountains Wilderness State Park much further to the east than it currently is. In order to accommodate the trail re-route, a pedestrian bridge is proposed over the Little Iron River. The location of this bridge is in Ontonagon, County, T50N, R43W, Section 11 (N 46 degrees 44.81’, W 89 degrees 38.35’). The bank full width of the stream is approximately 31’. The distance from the top of one bank to the top of the other bank is approximately 63’. The south bank is approximately 15’ high. The north bank is approximately 10’ high. Both the north bank and the south bank are approximately a 1:1 slope from top of bank to toe of bank/toe of slope.

The bridge is proposed to be ADA compliant and is intended to be used for pedestrian use only. The bridge should allow for aesthetics similar to what you would expect to find in a wilderness setting. The bridge is not proposed within the Designated Wilderness Area portion of the park.

Provide a complete PSC Proposal for all required Professional Architectural and Engineering Services in compliance with the State of Michigan, Department of Technology Management and Budget MDTMB Project Statement Form (DMB427) and MDTMB form 430.

Provide a design schedule through Phase 500 and include:

1) One pre - design kick off meeting site visit, one 50% plan review meeting, one 90% plan review meeting, and one 100% complete Phase 500 plan verification submittal shall be required. The design kick off meeting shall be held at Porcupine Mountains Wilderness State Park Headquarters building and include an on-site walkthrough of the project. The 50% and 90% plan review meetings shall be conducted by Go- To meeting or another electronic format. A 100% plan submittal to DTMB and the DNR is required for verification of the 90% plan review comments being incorporated; a formal 100% complete plan review meeting is not required. The 50% and 90% plan review will provide the DNR and DTMB 10 working days to review the plans. The 100% plan submittal will provide 5 working days for verification. Include all required agendas, documents and construction estimates per the DTMB contract. Construction completion is desired prior to winter 2019.

mailto:adamsb1@michigan.gov mailto:patrickj1@michigan.gov mailto:barschj@michigan.gov/Dan

Professional Services shall include, but are not limited to the following:

- Phase 500, 600, and 700 design services.

- All applicable permits, plan reviews, standards and codes are required to be met by the project.

The scope of the Phase 500 design shall include the following scope items:

• Topographic survey of the proposed project location and stream crossing.

• Site survey

• Site soil investigations and analysis. State the proposed method in your PSC proposal.

• Obtaining the necessary construction easements to allow for PSC, sub-consultant, and contractor access to the site.

• DEQ inland lakes and streams permit application preparation and submittal.

• Design of an ADA compliant pedestrian bridge.

• Phase 500 design of bridge with detailed cost estimates for construction at 50% and 90% complete design.

• Design of a trail approach for 50’ in advance of each side of the bridge.

The scope of the Phase 500 design will not include design of the trail reroute from either direction beyond the trail approaches.

Schedule Phase 500 design to be 100% complete no later than July 15, 2019, an earlier Phase 500 date is requested, PSC to provide schedule with this RFP. Construction completion is desired prior to winter 2019.

Additional Considerations:

The project designer shall be responsible for verifying and gathering accurate base information, preparation of all necessary construction documents, approval of these documents by the required governing agencies and final as-built record drawings. Approval of the plans and specifications by MDNR, DTMB and LARA Plan Review is also required.

All other testing required ffoorr pprrooppeerr ddeessiiggnn ooff tthhee rreennoovvaattiioonnss sshhaallll bbee iiddeennttiiffiieedd aanndd iinncclluuddeedd iinn tthhee PPSSCC tteecchhnniiccaall pprrooppoossaall aanndd tthhee ccoosstt iitteemmiizzeedd iinn tthhee PPSSCC ccoosstt pprrooppoossaall aass rreeiimmbbuurrsseemmeennttss..

Identify and itemize all reimbursable and travel expenses in the PSC Cost proposal.

Reimbursable expenses shall include:

11.. Survey - $8,000.00 22.. Soil borings and soils analysis - $7,500.00 33.. DEQ Inland lakes and streams permit application preparation and submittal - $1,000.00

PPSSCC wwiillll bbee rreeqquuiirreedd ttoo mmaaiinnttaaiinn aa ccoommpplleettee eelleeccttrroonniicc pprroojjeecctt ffiillee ooff aallll pprroojjeecctt ddooccuummeennttaattiioonn iinncclluuddiinngg,, bbuutt nnoott lliimmiitteedd ttoo,, ccoonnttrraacctt ddooccuummeennttss,, aallll ccoorrrreessppoonnddeennccee,, aallll ee--mmaaiillss,, aallll RRFFII’’ss aanndd aannsswweerrss,, FFiieelldd OOrrddeerrss aanndd ccoommmmuunniiccaattiioonn tteelleepphhoonnee lloogg.. TThhee PPSSCC wwiillll pprroovviiddee ffiinnaall AASS--bbuuiilltt ddrraawwiinnggss,, aanndd ffiinnaall CCAADD ddrraawwiinnggss ttoo tthhee DDTTMMBB aanndd DDNNRR..

Reference documents include:

1) Preliminary trail findings for North Country Trail re-route.

2) Little Iron River bridge – preliminary bridge design plans – a representative example of a bridge design which would be acceptable to the DNR.

3) Craig Lake State Park – pedestrian suspension bridge – a second representative example of a bridge design which would be acceptable to the DNR.

4) Project location map and plat map.

5) Site photos.

6) Great lakes road stream crossing inventory datasheet

7) Site photos (Upstream and downstream conditions)

8) Topo map with construction easement & plat map.

NIGP CODES

90638,90672,92517,92519,92533

DESIRED SCHEDULE OF WORK

Completion of Phase 500 design by July 15, 2019. PSC to provide a schedule with this RFP. Assume Contract Award approximately April 1, 2019.

ACCEPTING RFP QUESTIONS UNTIL: 7 calendar days prior to due date. Copy all questions to the DNR/DTMB contacts above

REFERENCE STANDARDS: This project will comply with all codes, standards, regulations, and workers' safety rules that are administered by federal agencies (EPA, OSHA, and DOT), state agencies (DCH, DEQ, DNR, and MIOSHA), and any other local regulations and standards that may apply.