PLF EA_SOW Attachment C_Deliverables Table(1).docx

DOCX document 38 KB Posted

Attached to
Environmental Analysis for Propellant Facility at LMTF
Solicitation number
FA820125Q0018
Issued by

About this file

The document is a Statement of Work (SOW) Attachment C Deliverables Table for an Environmental Assessment (EA) contract for a Propellant Facility at Little Mountain Test Facility (LMTF) at Hill Air Force Base in Utah. The 12-month contract requires the contractor to produce a comprehensive Environmental Assessment following National Environmental Policy Act (NEPA) guidelines, with specific deliverables across seven primary task areas including project management, meetings, project coordination, consultations, Draft of Proposed Action and Alternatives (DOPAA), draft EA/Finding of No Significant Impact (FONSI), and final EA/FONSI preparation.

Key deliverables include monthly progress reports, virtual kickoff and coordination meetings, stakeholder engagement, regulatory interfaces, draft and final EA documents, and an administrative record. The contractor will be responsible for preparing coordination letters, identifying data gaps, conducting on-site data collection, and supporting an On-Board Review. Deliverables are to be submitted electronically to 75 CEG/CEIE, with some documents requiring hardcopy submissions. The solicitation (FA820125Q0018) is issued by the Department of the Air Force Materiel Command Air Force Sustainment Center, with the first deliverable due within 30 calendar days after contract award.

View the file

Other files

File Type Posted
Solicitation Amendment FA820125Q00180001 SF 30.pdf PDF
Solicitation FA820125Q0018 QandA.docx DOCX document
LMTF__PLF SOW.docx DOCX document
Solicitation - FA820125Q0018.pdf PDF
15-5483.txt TXT text file
EA_SOW Attachment B_DAF EA-EIS Format_Jan22.docx DOCX document
Attach A_25-027_ 813.pdf PDF
Combo Synopsis Solicitation Environmental Assessment For Little Mountain PLF - Hill AFB UT.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOW Attachment C – EA Deliverables Table

Task
Deliverable #
Deliverable Description
Frequency
# of Copies & Format
Submit To

Task 1: Project Management

Task 1.1 - Contractor’s Progress, Status, and Management Report
Deliverable 1.1
Monthly Contractor’s Progress, Status, and Management Report
· First submittal due no later than 30 calendar days after award.

· Subsequent submittals shall be monthly and are due no later than 20 calendar days after the end of the Contractor's cost accounting period

Electronic
· 75 CEG/CEIE
Task 1.2 –– Project Schedule
Deliverable 1.2
Initial project schedules and updates that include identification of planned and actual dates.
· Initial project schedules will be presented during the post award/kickoff meeting.

· Updated as needed

Electronic as needed
· 75 CEG/CEIE

· AFNWC POC

Task 2: Meetings

Task 2.1 - Post-Award Kickoff / Planning Meeting
Deliverable 2.1
Virtual kickoff meeting to initiate the contract and obtain project POCs, and plan for data gap identification/data collection, project coordination meetings
· Once

· Agenda items and presentation materials will be provided at least three (3) days prior to kick-off meeting.

1 Virtual Meeting Electronic as needed

· 75 CEG/CEIE

· AFNWC POC

Task 2.2 - Data Gap Identification / Data Collection
Deliverable 2.2
Identify and collect all relevant data. Contractor shall submit a list of data gaps needing to be supplied by 75 CEG/CEIE.
· Once following Post-Award Kickoff /Planning Meeting
Electronic as needed
· 75 CEG/CEIE

· AFNWC POC

SOW Attachment C – EA Deliverables Table

Task 2.3 - Coordination Meetings / Teleconferences
Deliverable 2.3
The Contractor shall prepare the agenda, minutes, and presentation materials for project coordination review meetings / teleconferences, twice (2) per month.
· Bi-weekly Agenda items and presentation materials will be provided at least two

· Two (2) days prior to meeting

Electronic as needed
· 75 CEG/CEIE

· AFNWC POC

Task 2.4 – On-Site Data Collection
Deliverable 2.4
Work with the installation on any data gaps identified
· Once, as scheduled
Electronic as needed
· 75 CEG/CEIE

· AFNWC POC

Task 2.5- On-Board Review (OBR)
Deliverable 2.5
The Contractor shall support OBR as Described in Task 2.5
· Once, as required by project schedule
Electronic as needed
· 75 CEG/CEIE

· AFNWC POC

Task 3: Project Coordination and Consultations

Task 3.1 – Regulatory and Professional Interface
Deliverable 3.1
The Contractor shall assist with oral/written interaction with interested parties related to the project.
· As required
Electronic as needed
· 75 CEG/CEIE

· AFNWC POC

Task 3.2 – Coordination and Consultation POC List
Deliverable 3.2
The Contractor shall identify key stakeholders and create a project POC list.
· As needed / required by project schedule
Electronic as needed
· 75 CEG/CEIE

· AFNWC POC

Task 3.3 – Interagency / Intergovernmental / Government-to- Government Coordination and Consultation

Deliverable 3.3
The Contractor shall prepare appropriate coordination and consultation letters and mail letters requiring read receipts.
· As required by SOW and project schedule
Electronic as needed

Hardcopies for mailing

· 75 CEG/CEIE

SOW Attachment C – EA Deliverables Table

Task
Deliverable #
Deliverable Description
Frequency
# of Copies & Format
Submit To

Task 4: DOPAA

Task 4.1 – Preliminary Draft DOPAA
Deliverable4.1
The Contractor shall provide a Preliminary Draft DOPAA for review and comment.
· Once, as required by project schedule
Electronic
· 75 CEG/CEIE

· AFNWC POC

Task 4.2 – Coordination & Consultation Letters
Deliverable 4.2
As described in SOW Task 3.3
· As described in SOW Task 3.3
Electronic as needed

Hardcopies for mailing

· 75 CEG/CEIE

· AFNWC POC

Task 5: Draft EA / FONSI

Task 5.1 – Preliminary Draft EA / FONSI
Deliverable 5.1
The Contractor shall provide a Preliminary Draft EA / FONSI for review and comment.
· Once, as required by project schedule
Electronic
· 75 CEG/CEIE

· AFNWC POC

Task 5.2 – Check Draft EA / FONSI
Deliverable 5.2
The Contractor shall provide a Check Draft EA / FONSI for review and comment.
· Once, as required by project schedule
Electronic
· 75 CEG/CEIE

· AFNWC POC

Task 5.3 – Draft EA / FONSI for Public Comment Period
Deliverable 5.3
The Contractor shall provide a Draft EA / FONSI to be published for public review and comment
· Once, as required by project schedule
Electronic as needed

One (1) Hardcopy for library

· 75 CEG/CEIE

· AFNWC POC

Task 5.4 – Draft EA / FONSI NOA, Newspaper
Deliverable 5.4
The Contractor shall prepare and publish a Draft EA NOA.
· Once, as required by SOW and project schedule
Electronic

One (1)Newspaper

· 75 CEG/CEIE

SOW Attachment C – EA Deliverables Table

Task
Deliverable #
Deliverable Description
Frequency
# of Copies & Format
Submit To

Task 6: Final EA / FONSI

Task 6.1 – Preliminary Final EA / FONSI
Deliverable 6.1
The Contractor shall provide a Preliminary Final EA / FONSI for review and comment.
· Once, as required by project schedule
Electronic
· 75 CEG/CEIE

· FNWC POC

Task 7: Administrative Record

Task 7.1 – Final AR
Deliverable 7.1
The Contractor shall provide Final AR.
· Once, as required by project schedule
Electronic
· 75 CEG/CEIE

File details come from the government source that posted it. Updated .