Plans.pdf
PDF 7 MB Posted
- Attached to
- Penn Manor Large Valve Vault Replacement
- Solicitation number
- 120583
- Issued by
- Prince George's County, Maryland
About this file
This file comprises detailed engineering plans and construction specifications prepared by Johnson, Mirmiran & Thompson for the Washington Suburban Sanitary Commission (WSSC) in Maryland for the Penn Manor Large Valve Vault Replacement project located on Penn Manor Lane in Bowie, Prince George's County. The project involves replacing a 24-inch large valve vault and approximately 161 feet of 24-inch water main, relocating approximately 51 feet of 24-inch water main, and relocating approximately 54 feet of water house connections. The contract number is BT7171B21, and sealed responses are due November 16, 2026, by 2:00 pm via WSSC's eProcurement Portal. Construction is limited to Monday through Friday from 9:00 am to 3:00 pm, with a requirement that no construction work begin until the school year concludes at Pointer Ridge Elementary School on June 8, 2026. The project involves three construction phases: Phase One includes test pitting existing 24-inch prestressed concrete cylinder pipe (PCCP) and replacing sections during a single 8-hour shutdown; Phase Two involves installing new 24-inch ductile iron pipe (DIP) with a precast vault without disrupting existing mains; and Phase Three includes removing the existing vault structure and connecting remaining pipe sections during a final 8-hour shutdown.
The construction specifications require ductile iron pipe with zinc coating (Class 54 minimum), V-BIO enhanced polyethylene encasement, and fusion-bonded epoxy-coated fittings, with all water mains installed at minimum 42 inches cover for same-trench replacement and 48 inches for offset/relocated mains. Contractors must perform compaction testing at a minimum rate of one test per 100 feet of fill and verify all connection points to existing PCCP mains via test pits. All new water lines must be disinfected per AWWA Standard C651 with bacteriological tests submitted to the Maryland Department of Environment for approval prior to placing the main into service. Sediment and erosion control measures must be approved by WSSC before work commences, with contractor responsibilities including maintaining 1-foot minimum clearance at utility and storm drain crossings, providing tree trunk protection within 15 feet of work areas, relocating water meter boxes to minimize tree impact, obtaining staging areas at no cost to WSSC, and restoring all disturbed areas to pre-construction condition. The WSSC will be responsible for final mill and overlay and pavement striping after project completion, while the contractor bears all costs for restoration, repairs to damaged house connections and water mains, and replacement of pavement markings. Key coordination contacts include the WSSC Environmental Group, Systems Control Manager Karen Wright, Construction Manager Jason Flory, and Pipeline Construction Division Inspector, with mandatory 48-hour advance notification to MISS Utility and 60-day advance notice for PCCP shutdown coordination.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ENGINEER:THESE DOCUMENTS CONTAIN
PRIVILEGED AND CONFIDENTIAL
INFORMATION WHICH SHALL NOT
BE REDISTRIBUTED WITHOUT
PRIOR WSSC APPROVAL
NAME: JOHNSON, MIRMIRAN & THOMPSON
ADDRESS: 40 WIGHT AVENUE, COCKEYSVILLE, MD 21030
PHONE: (410) 329-3100
CONTACT : STEVEN PICKEL, PE
202NE14
PROFESSIONAL CERTIFICATION
I HEREBY CERTIFY THAT THESE DOCUMENTS
WERE PREPARED OR APPROVED BY ME,
AND THAT I AM A DULY LICENSED
PROFESSIONAL ENGINEER UNDER
THE LAWS OF THE STATE OF MARYLAND.
NAME: STEVEN PICKEL, P.E.
LICENSE NO.: 50329
EXP. DATE: 12/18/2026
VE
R
IF
Y
SC
AL
E
- B
AR
IS
O N
E
IN
C H
O N
O R
IG
IN
AL
D
R
AW
IN
G
IF
N
O T
O N
E
IN
C H
O N
T H
IS
S
H
EE
T, A
D
JU
ST
S
C
AL
ES
A
C C
O R
D
IN
G
LY
HHG: 355
LHG: 281
PRESSURE ZONE= 317A
XX/XX/XX - PLOT DATE
WESTERN BRANCH MINI DRAINAGE BASIN NO. 130
WASHINGTON SUBURBAN SANITARY COMMISSION
WSSC
DELIVERING THE ESSENTIAL
PA
TH
WSSC Erosion and Sediment Control Approval Note This plan has been approved per requirements in the:
Standard Procedures of the WSSC Regulations for Utility Erosion and Sediment Control, Section V, Paragraph A.
Reviewed by:_________________________________________
Date:__________________ Plan No.______________________
WASHINGTON SUBURBAN SANITARY COMMISSION
14501 SWEITZER LANE, LAUREL MARYLAND
PENN MANOR LANE LARGE
VALVE VAULT REPLACEMENT
PRINCE GEORGE'S COUNTY, MD
CONTRACT NO. BT7171B21
LOCATION MAP
1'=800"
PRINCE GEORGE'S CO.
200'S OF
P.G.CO.D.P.W.&T.
SED. CONTROL
STATE HGWY. ADM.
STATE BD. HEALTH
M.N.C.P.&P.C.
WETLANDS / WATERWAYS
TREE
PAGE GRID
SCALE 1":2000'
Prince George's Co. 5533 D6
CONTRACT NO. BT7171B21
REQUIRED
NOT REQUIRED
DJC
SSP
M.D. D.O.E. - WMA
NOT REQUIRED
NOT REQUIRED
NOT REQUIRED
NOT REQUIRED
NOT REQUIRED
REQUIRED
QUEEN ANNE ELECTION DISTRICT NO. 7
PENN MANOR LANE LARGE VALVE VAULT REPLACEMENT
PENN MANOR LANE
BOWIE, PRINCE GEORGE'S COUNTY, MD 20716
MDE CONSTRUCTION REQUIRED
CITY OF BOWIE
NO
NOT REQUIRED
TE
M
PL
AT
E
LA
YO
U
T C
U R
R
EN
T as o f:
/1
4/
\\j m t.c or p.
lo ca l\j m td fs
\2
0\
7_
5_ W oo dy ar d_
R oa d_ La rg e_
\C
AD
D \C
IV
IL
\P en n M an or
\C O
VE
R
.d w g
OF
ADEQUATE SURVEY
DATE
DATE STARTED
DATE FINALED
Drawing No.
FINALED BY
DATE COMPLETED
TYPE MANHOLES
TYPE PIPE W.
S.C.1.
1. thru 6.
Sediment Control Notes & Details Plans/Profiles/Details
Description
CONTRACT MANAGER
INSPECTOR
CONTRACTOR
L & G
AS BUILT DATA
TOWN NOTIFICATION
PERMIT REQUIREMENTS
DATE REVISIONS
VICINITY MAP
ON PROP. R/W REQ'D
OFF PROP. R/W REQ'D
S.
FOR LOCATION OF UTILITIES CALL 8-1-1 OR 1-800-257-7777
OR LOG ON TO www.call811.com or www.missutility.net 48
HOURS IN ADVANCE OF ANY WORK IN THIS VICINITY
OTHER UTILITIES
*TO BE ACQUIRED BY APPLICANT
DRAWING INDEX
DRAWN
CHECK
PIPELINE DESIGN DIVISION
DATE DIVISION MANAGER
SECTION MANAGER
WATER INFRASTRUCTURE SECTION
1. ALL WATER MAINS TO BE DUCTILE IRON PIPE WITH ZINC COATING CLASS 54 MIN.
2. ALL DUCTILE IRON PIPE TO BE V-BIO ENHANCED POLYETHYLENE ENCASEMENT IN ACCORDANCE WITH AWWA
C105, METHOD A.
3. ALL DUCTILE IRON FITTINGS TO BE FUSION BONDED EPOXY COATED.
4. LICENSED GEOTECHNICAL ENGINEER T0 PERFORM COMPACTION TESTING FOLLOWING ASTM D1556, ASTM D6938 OR ASTM D2937 AT A MINIMUM RATE OF 1 TEST FOR EVERY 100 FEET OF FILL ALONG MAIN TRENCH AND
AT EVERY LATERAL TRENCH, STRUCTURE AND VALVE BOX IN RESTORATION OF TYPE I AREAS.
5. CONTRACTOR SHALL TEST PIT EXISTING WATER MAIN CONNECTION LOCATIONS. THERE IS THE POSSIBILITY OF ENCOUNTERING POURED LEAD JOINTS. IF POURED JOINT PIPE IS FOUND, REPLACE WITH MECHANICAL JOINT PIPE AND FITTINGS. REMOVAL OF THE JOINT IS INCIDENTAL TO THE CONTRACT. SEE SPECIAL CONSTRUCTION
REQUIREMENTS FOR WORK PERFORMED IN VICINITY OF EXISTING PCCP MAINS ON SHEET 2.
6. CONTRACTOR SHALL TEST PIT ALL UTILITY AND STORM DRAIN CROSSINGS A MINIMUM OF 2 WEEKS IN ADVANCE OF WORK, AND MAKE ANY ADJUSTMENTS AS NECESSARY WITH PRIOR APPROVAL OF WSSC AND AT NO COST TO WSSC. ONE FOOT MINIMUM CLEARANCE SHALL BE PROVIDED AT ALL UTILITY AND STORM DRAIN CROSSINGS
UNLESS OTHERWISE NOTED ON THE PLANS.
7. CONTRACTOR SHALL VERIFY THE TYPE, SIZE, AND LOCATION OF EXISTING FITTINGS ON THE WATER MAIN TO BE
REPLACED.
8. FOR SAME TRENCH REPLACEMENT, ALL EXISTING VALVES, VALVE BOXES, COPPER, BRASS, FITTINGS AND PIPE MUST BE REMOVED FOR SALVAGE AND RETURNED TO WSSC TEMPLE HILL WAREHOUSE, AT NO COST TO WSSC.
9. REPLACEMENT OF SINGLE WHC'S ARE TO BE 1" DIAMETER MINIMUM.
10. REPLACE EXISTING WHC'S WITH COPPER, TYPE K, TO THE PROPERTY LINE INCLUDING THE OUTSIDE METER
SETTINGS AND CURB STOPS, SEE STD. DETAIL W/5.6.
11. REPLACE/RECONNECT EXISTING WHC'S TO THE REPLACEMENT WATER MAIN AS NOTED IN THE EXISTING WATER
HOUSE CONNECTION INFORMATION TABLES.
12. LOCATE REPLACEMENT OUTSIDE METER SETTINGS AT THE SAME LOCATION AS EXISTING UNLESS OTHERWISE
SHOWN ON THE PLANS. SEE THE EXISTING WATER HOUSE CONNECTION INFORMATION TABLES.
13. INSTALL ALL WATER MAINS AND TEMPORARY CAPS/PLUGS ON BOTH THE REPLACEMENT AND EXISTING MAINS
AND TEST AS SHOWN ON THESE DRAWINGS.
14. CONTRACTOR SHALL NOTIFY MISS UTILITY AT LEAST 48 HOURS IN ADVANCE OF ANY WORK IN THIS AREA, SO APPROPRIATE MARKING OF EXISTING UTILITIES CAN BE MADE. CALL 811 OR 1-800-257-7777 OR LOG ON TO
WWW.CALL811.COM OR HTTP://WWW.MISSUTILITY.NET
15. 1"=10' SCALE DRAWINGS ARE BASED ON TOPOGRAPHIC SURVEY DATA COLLECTED BY JOHNSON, MIRMIRAN & THOMPSON IN FEBRUARY 2022. HORIZONTAL DATUM = NAD 83 AND VERTICAL DATUM = NGVD 29.
16. CONTRACTOR SHALL NOT STOCKPILE MATERIALS OR EQUIPMENT WITHIN THE DRIP-LINE OF ANY TREES.
17. PROVIDE TREE TRUNK PROTECTION FOR ALL TREES WITHIN 15 FEET OF ANY WORK. SEE STANDARD DETAIL
SC/19.0, EXCEPT NOMINAL 2"X10" OR 2"X12" PINE BOARDS MAY BE USED.
18. CONTRACTOR SHALL LOCATE ALL WHC'S IN THE FIELD. THE CONTRACTOR, AT NO COST TO WSSC, SHALL
REPAIR ANY DAMAGE TO HOUSE CONNECTIONS AND WATER MAINS THEY MAY CAUSE.
19. RELOCATED AND/OR REPLACED WHC'S SHALL BE PLACED IN LOCATIONS THAT MINIMIZE IMPACT TO TREES.
CONTRACTOR SHALL LOCATE WATER METER BOXES AND CURB STOPS AND ADJUST TO EXISTING GRADE.
20. CONTRACTOR SHALL BE RESPONSIBLE FOR OBTAINING STAGING AREA(S) AND FOR MOBILIZATION TO AND
FROM SUCH AREA(S) AT NO ADDITIONAL COST TO THE WSSC.
21. WHERE PAVEMENT MARKINGS WILL BE AFFECTED BY THE UTILITY WORK, THE PAVEMENT MARKINGS MUST BE IDENTIFIED SPECIFICALLY ON THE PLAN AND REPLACED IN KIND. THE CONTRACTOR SHALL SURVEY THE EXISTING MARKINGS, AS NEEDED, IN ORDER TO ENSURE THE NEW MARKINGS ARE RE-INSTALLED IN THE PROPER LOCATION. THE CONTRACTOR IS FULLY RESPONSIBLE FOR THE CORRECT REPLACEMENT OF ALL
IMPACTED PAVEMENT MARKINGS.
22. MAINTAIN 1' VERTICAL AND 5' HORIZONTAL CLEARANCE FROM OUTSIDE OF PIPE TO OUTSIDE OF PIPE FOR ANY OTHER APPURTENANCES. MAINTAIN A MINIMUM OF 2' CLEARANCE FROM CURB AND GUTTER UNLESS
OTHERWISE NOTED.
23. ALL ABANDONED IN PLACE EXISTING MAINS 8” AND LARGER AND APPURTENANCES SHALL BE FILLED ENTIRELY
WITH FLOWABLE FILL.
24. TEMPORARY WATER SERVICE PIPING SHALL BE LOCATED OUTSIDE OF THE PAVEMENT.
25. ALL ROADWAYS IMPACTED BY CONSTRUCTION SHALL BE OPENED TO TRAFFIC AT THE END OF EACH WORKING
DAY.
26. SAME TRENCH REPLACMENT DOES NOT PRECLUDE THE CONTRACTOR FROM MEETING ALL MINIMUM CLEARANCES SHOWN HEREIN. THE CONTRACTOR IS TO ADHERE TO LOCATION REQUIREMENTS SHOWN HEREIN FOR ALL PROPOSED/REPLACEMENT MAIN INCLUDING GRAPHICS, DIMENSIONS, AND STAKEOUT TABLES.
27. WATER METERS ARE TO BE LOCATED AT THE RIGHT-OF-WAY/FRONT PROPERTY LINE IN THE GRASSED AREA
WHENEVER POSSIBLE.
28. CONTRACTOR SHALL PROVIDE A SAFE, CLEAR, AND DETECTABLE PATH FOR PEDESTRIANS AT ALL TIMES
DURING CONSTRUCTION.
29. FOR ASPHALT INTERSECTIONS, EXTEND MILL AND OVERLAY TO PC/PT OF FILLETS.
30. VALVE STEM EXTENSIONS SHALL BE INSTALLED PER WSSC STANDARD DETAIL W/2.2 ON ALL OPERATING NUTS
WITH MORE THAN 4' OF COVER.
31. TO DETERMINE THE INVERT ELEVATION OF THE REPLACEMENT WATER MAINS FOR HYDROSTATIC PRESSURE
TESTING, USE THE AS-BUILT DRAWINGS.
32. CONTRACTOR SHALL PROVIDE STAKEOUT FOR THE PROPOSED RELOCATIONS.
33. PROVIDE TEMPORARY WATER SERVICE DURING CONSTRUCTION FOR WATER SERVICES AFFECTED BY THE WATER MAIN REPLACEMENTS. TEMPORARY WATER SERVICE CONNECTIONS SHALL BE AS PER STANDARD DETAILS W/5.16 AND W/5.16A. ALL SHUTDOWNS SHALL BE LIMITED TO NO LONGER THAN 8 HOURS, AND ALL CUSTOMERS AFFECTED BY THE SHUTDOWNS SHALL BE NOTIFIED AT LEAST 7 DAYS PRIOR TO THE SHUTDOWN.
GENERAL NOTES
N
AD
3/
N
G
VD
N
AD
3/
N
G
VD
SCALE: 1"= 2,000'
1,000' 1,000'0' 2,000'
INDEX OF SHEETS
DESIGNED BY DATE
FIELD REVIEWED BY DATE
SHEET NO. DESCRIPTION
1 TITLE SHEET
2 GENERAL NOTES
3 PLAN VIEW
4 PROFILE VIEW
5 DETAILS
6 TRAFFIC CONTROL
SCALE: 1"= 800'
400' 400'0' 800'
PROJECT
AREA
PROJECT
AREA
GENERAL NOTES (CONTINUED)
EXISTING WATER MAINS TO BE REPLACED
STREET EXISTING WATER MAIN SIZE REPLACEMENT SIZE LENGTH SHEET
PENN MANOR LANE 24" 24" 161 3
TOTAL 161
RESTORATION SCHEDULE
(ALL SHEETS)
LOCATION GRADING TYPE RESTORATION TYPE
ALL AREAS I "A" OR PAVING
COVER 1
34. NO VALVES ARE TO BE OPERATED WITHOUT A WSSC INSPECTOR ON SITE.
35. INSTALL SAME TRENCH REPLACEMENT WATER MAINS WITH A MINIMUM OF 42" COVER, AND OFFSET/ RELOCATED WATER MAINS
WITH MINIMUM OF 48" COVER UNLESS OTHERWISE NOTED ON THE DRAWING.
36. WSSC SHALL BE RESPONSIBLE FOR FINAL 2” MILL AND OVERLAY AND FINAL PAVEMENT STRIPPING. THE FINAL MILL AND OVERLAY AND PAVEMENT STRIPING SHALL BE PERFORMED AFTER COMPLETION OF EACH PHASE. THE CONTRACTOR SHALL NOT STORE CONSTRUCTION MATERIALS AND OPERATE/STORE EQUIPMENT ON THE NEWLY RESURFACED ROADWAYS.
37. ANY YARD WITH ZOYSIA GRASS THAT IS DISTURBED MUST BE REPLACED WITH ZOYSIA GRASS. FOLLOW RECOMMENDED TIME
FOR PLANTING ZOYSIA GRASS.
38. CONTRACTOR MUST CONTACT THE FOLLOWING PERSONS/AGENCIES AT LEAST SEVEN (7) DAYS PRIOR TO START OF ANY WORK UNDER THIS CONTRACT. BEFORE CONSTRUCTION, SCHEDULE OF 24" SHUTDOWN AND CONSTRUCTION SCHEDULE
MUST BE APPROVED THROUGH SYSTEMS CONTROL GROUP:
A. WSSC ENVIRONMENTAL GROUP, AT 301-206-8075.
B. KAREN WRIGHT, SYSTEMS CONTROL MANAGER, WSSC SYSTEMS CONTROL DIVISION, AT 301-206-8416.
C. JASON FLORY, CONSTRUCTION MANAGER, PIPELINE CONSTRUCTION DIVISION OF WSSC, ANACOSTIA DEPOT, AT
301-256-6851.
39. WATER MAINS SHALL BE LAID AT LEAST 10 FEET HORIZONTALLY FROM ANY EXISTING OR PROPOSED GRAVITY SANITARY OR STORM SEWER, SEPTIC TANK, OR SUBSOIL TREATMENT SYSTEM. THE DISTANCE SHALL BE MEASURED EDGE TO EDGE. WATER MAINS CROSSING SEWERS SHALL BE LAID TO PROVIDE A MINIMUM VERTICAL DISTANCE OF 18 INCHES. THIS SHALL BE THE CASE WHERE THE WATER MAIN IS EITHER ABOVE OR BELOW THE SEWER WITH PREFERENCE TO THE WATER MAIN LOCATED
ABOVE THE SEWER
40. ALL AREAS DISTURBED FROM THE CONTRACTOR'S CONSTRUCTION ACTIVITIES SHALL BE RESTORED TO A CONDITION AT LEAST EQUAL TO THAT WHICH EXISTED PRIOR TO START OF CONSTRUCTION. ROADSIDE DRAINAGE DITCHES, CULVERTS, UNDERDRAINS AND WATER AND SEWER HOUSE SERVICES WHICH ARE DAMAGED OR DESTROYED BY CONSTRUCTION, SHALL BE RESTORED TO A CONDITION AT LEAST EQUAL TO THAT WHICH EXISTED PRIOR TO THE START OF CONSTRUCTION. THE
COST OF ANY RESTORATION SHALL BE BORNE BY THE CONTRACTOR.
GENERAL NOTES (CONTINUED)
SC-1 SEDIMENT CONTROL DETAILS FOR UTILITY CONSTRUCTION
S . PN IE CV K
E E
T L
S
N 9o 2. 350
Docusign Envelope ID: B7C40696-C70F-49BC-81DD-AF032F73758F
Nov 25, 2025 | 10:07 AM PST
Nov 25, 2025 | 2:54 PM EST
Dec 1, 2025 | 9:24 AM EST
BT7171B21Dec 2, 2025 | 10:03 AM EST
Dec 2, 2025 | 10:36 AM EST
Dec 2, 2025 | 3:50 PM EST
CONSTRUCTION SHALL TAKE PLACE MONDAY - FRIDAY 9:00 AM - 3:00 PM. NO CONSTRUCTION WORK TO BEGIN
UNTIL SCHOOL YEAR HAS CONCLUDED AT POINTER RIDGE ELEMENTARY SCHOOL.
06/08/2026 REVISED GENERAL NOTE
Docusign Envelope ID: C4AD4B2A-87D4-8930-8148-201594D0CBA4
200'S
CONTRACT NO. BT7171B21
202NE14
ENGINEER:THESE DOCUMENTS CONTAIN
PRIVILEGED AND CONFIDENTIAL
INFORMATION WHICH SHALL NOT
BE REDISTRIBUTED WITHOUT
PRIOR WSSC APPROVAL
NAME: JOHNSON, MIRMIRAN & THOMPSON
ADDRESS: 40 WIGHT AVENUE, COCKEYSVILLE, MD 21030
PHONE: (410) 329-3100
CONTACT : STEVEN PICKEL, PE
QUEEN ANNE ELECTION DISTRICT NO. 7
PENN MANOR LANE LARGE VALVE VAULT REPLACEMENT
BOWIE, PRINCE GEORGE'S COUNTY, MD 20716
VE
R
IF
Y
SC
AL
E
- B
AR
IS
O N
E
IN
C H
O N
O R
IG
IN
AL
D
R
AW
IF
N
O T
O N
E
IN
C H
O N
T H
IS
S
H
EE
T, A
D
JU
ST
S
C
AL
ES
A
C C
O R
D
IN
G
LY
HHG: 355
LHG: 281
PRESSURE ZONE= 317A
WESTERN BRANCH MINI DRAINAGE BASIN NO. 130
WASHINGTON SUBURBAN SANITARY COMMISSION
WSSC
DELIVERING THE ESSENTIAL
PA
TH
XX/XX/XX - PLOT DATE
PROFESSIONAL CERTIFICATION
I HEREBY CERTIFY THAT THESE DOCUMENTS
WERE PREPARED OR APPROVED BY ME,
AND THAT I AM A DULY LICENSED
PROFESSIONAL ENGINEER UNDER
THE LAWS OF THE STATE OF MARYLAND.
NAME: STEVEN PICKEL, P.E.
LICENSE NO.: 50329
EXP. DATE: 12/18/2026
PENN MANOR LANE
TE
M
PL
AT
E
LA
YO
U
T C
U R
R
EN
T as o f:
/1
4/
\\j m t.c or p.
lo ca l\j m td fs
\2
0\
7_
5_ W oo dy ar d_
R oa d_ La rg e_
\C
AD
D \C
IV
IL
\P en n M an or
\G
EN
ER
AL
N O
TE
S.
dw g
OF 6
NO
WSSC Erosion and Sediment Control Approval Note This plan has been approved per requirements in the:
Standard Procedures of the WSSC Regulations for Utility Erosion and Sediment Control, Section V, Paragraph A.
Reviewed by:_________________________________________
Date:__________________ Plan No.______________________
DATE REVISIONS
DATE PROJECT MANAGER
WATER INFRASTRUCTURE SECTION
SPECIAL CONSTRUCTION REQUIREMENTS FOR WORK PERFORMED IN THE VICINITY
OF EXISTING PCCP WATER MAINS
MDE NOTES
BLOCKING NOTES
1. IN ACCORDANCE WITH TEN STATE STANDARDS, A MINIMUM OF TEN (10) FOOT HORIZONTAL AND EIGHTEEN (18) INCH VERTICAL SEPARATION MUST BE MAINTAINED BETWEEN WATER MAINS AND SANITARY SEWER. WHEN IT IS IMPOSSIBLE TO OBTAIN THE MINIMAL HORIZONTAL 10 FOOT HORIZONTAL SEPARATION AND/OR 18 INCH VERTICAL SEPARATION BETWEEN WATER MAINS AND SANITARY SEWER, MDE MUST SPECIFICALLY APPROVE ANY VARIANCE SUPPORTED BY DATA FROM THE DESIGN
ENGINEER.
2. IN ACCORDANCE WITH CODE OF MARYLAND REGULATIONS (COMAR) 26.04.01.33, DIRECT AND INDIRECT ADDITIVES, SUPPLIERS OF WATER SHALL ONLY USE PRODUCTS (AND MATERIALS THAT COME IN CONTACT WITH WATER INTENDED FOR USE IN PUBLIC WATER SUPPLY) THAT MEET THE APPLICABLE AMERICAN NATIONAL STANDARDS INSTITUTE / NSF INTERNATIONAL (ANSI/NSF) STANDARDS FOR DIRECT OR INDIRECT DRINKING WATER ADDITIVES. THE PRODUCTS CAN ALSO BE CERTIFIED BY AN ORGANIZATION ACCREDITED BY THE ANSI FOR SUCH TESTING (I.E., INTERNATIONAL ASSOCIATION OF PLUMBING AND MECHANICAL OFFICIALS RESEARCH AND TESTING, ONTARIO CA, UNDERWRITERS LABORATORY, NORTHBROOK IL, AND WATER
QUALITY ASSOCIATION, LISLE IL).
3. IN COMPLIANCE WITH COMAR 09.20.01.03 AND THE SAFE DRINKING WATER ACT (SECTION 1417(A)(4)(8)), MATERIALS THAT COME IN CONTACT WITH WATER INTENDED FOR USE IN PUBLIC WATER SUPPLY SHALL COMPLY WITH THE REDUCTION OF LEAD IN
DRINKING WATER ACT, WHICH WENT INTO EFFECT IN MARYLAND IN JANUARY 2012.
4. ALL WATER LINES SHALL BE DISINFECTED ACCORDING TO AWWA STANDARD C651. BACTERIOLOGICAL TESTS SHALL BE SUBMITTED TO MDE WATER SUPPLY PROGRAM FOR APPROVAL PRIOR TO PLACING THE MAIN INTO SERVICE.
1. RESTRAIN ALL PIPE JOINTS AND FITTINGS, SEE SPECIFICATION 02510.
2. INSTALL PRE-POURED THRUST BLOCKS, SEE DETAILS ON THESE SHEET 5.
GENERAL NOTES 2
1. ALL SEDIMENT AND EROSION CONTROL MEASURES SHALL BE INSPECTED AND APPROVED BY WSSC BEFORE ANY WORK CAN
COMMENCE.
2. CONTACT WSSC ENVIRONMENTAL PROGRAM SECTION 48 HOURS PRIOR TO UTILITY CONSTRUCTION AT 301-206-8077. THE
UTILITY SEDIMENT CONTROL PERMIT WILL BE ISSUED AT THE PRECONSTRUCTION MEETING.
3. ANY GROUND OR SURFACE WATER THAT IS PUMPED DURING THIS PROJECT SHALL BE DISCHARGED THROUGH A DEWATERING DEVICE APPROVED BY WSSC PRIOR TO BEING DISCHARGED OFFSITE, SEE STANDARD DETAIL SC/15.0 AND SC/15.1.
4. STREETS SHALL BE KEPT IN BROOM SWEPT CONDITION AT ALL TIMES.
5. INSTALL CURB INLET PROTECTION AS NEEDED, SEE STANDARD DETAIL SC/16.0 AND SC/16.1.
6. PLACE SILT FENCE PER STANDARD DETAIL SC/1.0 ALONG LOW SIDE OF EXCAVATED AREA WHEN WORKING IN NON-PAVED AREAS OR AS SHOWN ON PLANS, OR AS DIRECTED BY WSSC ENVIRONMENTAL STAFF IN THE FIELD. CONTRACTOR SHALL
PROVIDE DAILY TEMPORARY STABILIZATION FOR ALL DISTURBED NON-PAVED AREAS.
7. ANY EXCAVATED OR STOCKPILED MATERIAL LEFT OVERNIGHT SHALL BE COVERED WITH AN IMPERMEABLE MATERIAL.
PROVIDE SEDIMENT CONTROL FOR OFFSITE STAGING/STOCKPILES AREAS.
8. SLURRY GENERATED BY PAVEMENT SAW CUTTING SHALL BE CONTAINED BY THE CONTRACTOR. PREVENT SLURRY FROM ENTERING THE STORM DRAIN SYSTEM AND RECEIVING WATERWAY USING APPROVED METHODS, DEVICES OR AS DIRECTED BY WSSC ENVIRONMENTAL STAFF. CONTRACTOR SHALL REMOVE AND DISPOSE OF CONTAINED SLURRY PROPERLY AT THE
END OF EACH WORK DAY.
9. FOR AREAS WITHIN THE LIMIT OF DISTURBANCE WHICH DO NOT DRAIN TO AN APPROVED EROSION AND SEDIMENT CONTROL MEASURE AND/OR WHERE THE INSTALLATION OF CONTROLS IS NOT FEASIBLE (ROADWAY, SIDEWALK, ETC.) CONTRACTOR SHALL ONLY DISTURB AREA WHICH CAN BE COMPLETED AND STABILIZED BY THE END OF EACH WORKING DAY. STABILIZATION
SHALL BE AS FOLLOWS:
A. FOR AREAS TO BE PAVED: STONE BASE SHALL BE APPLIED
B. FOR AREAS TO BE VEGETATIVELY STABILIZED:
i. PERMANENT SEED AND SOIL STABILIZATION MATTING FOR SOD, FOR ALL STEEP SLOPES, CHANNELS, OR SWALES.
ii. PERMANENT SEED AND MULCH FOR ALL OTHER AREAS. ANY AREAS WHICH CAN NOT BE STABILIZED BY THE END
OF EACH WORKING DAY MUST HAVE SILT FENCE SC/1.0 INSTALLED ON THE DOWN SLOPE SIDE.
SEDIMENT CONTROL NOTES
1. CONSTRUCTION VEHICLES GENERATING LIVE LOADS GREATER THAN AASHTO HS20 (APPROX. 40,000 LBS OR GREATER), AND ANY VIBRATORY ROLLER COMPACTION EQUIPMENT, SHALL NOT BE PERMITTED WITHIN 10 FEET CLEAR OF THE OUTER EDGE
OF EX. PCCP WATER MAIN UNLESS APPROVED BY WSSC.
2. THE CONTRACTOR SHALL SUBMIT CONSTRUCTION VEHICLE SPECIFICATIONS FOR ALL VEHICLES PROPOSED FOR USE CLOSER THAN 10 FEET CLEAR, OR IF PROPOSED TO CROSS EX. PCCP WATER MAINS, TO THE WSSC PROJECT MANAGER/CONTACT PERSON FOR APPROVAL PRIOR TO COMMENCING WORK. ANY VEHICLE NOT PREVIOUSLY IDENTIFIED DURING THE DESIGN
REVIEW OF THESE PLANS WILL REQUIRE AN ADDITIONAL LOADING ANALYSIS REVIEW.
3. IF NECESSARY, HARDWOOD TIMBER MATS OF APPROPRIATE SIZE AND THICKNESS (SUFFICIENT TO FIT THE LARGEST CONSTRUCTION VEHICLE PROPOSED AND 1-FOOT THICK) SHALL BE PLACED OVER THE EXISTING PCCP MAIN TO ALLOW WSSC APPROVED CONSTRUCTION VEHICLE TRAFFIC TO CROSS OVER THE PIPELINE AND SAFELY DISTRIBUTE LIVE LOADS.
4. STOCKPILING OF SOIL OR OTHER MATERIAL IS NOT PERMITTED WITHIN 10 FEET CLEAR OF THE EDGE OF THE ROW OF THE EX.
MAINS, TO PREVENT ROW ENCROACHMENT.
5. THE CONTRACTOR SHALL LOCATE AND STAKEOUT THE EX. PCCP WATER MAINS AND EDGE OF THE ROW AND MAINTAIN THE MARKERS DURING CONSTRUCTION. UNLESS OTHERWISE APPROVED BY WSSC PROJECT MANAGER/ CONTACT PERSON, CONSTRUCTION VEHICLES ARE NOT PERMITTED WITHIN 10 FEET CLEAR OF EX. PCCP WATER MAIN AT ANY TIME, WHEN LESS THAN 6 FEET OF COVER EXISTS OVER THE MAIN. THE CONTRACTOR IS RESPONSIBLE FOR IDENTIFYING AREAS WHERE LESS THAN 6 FEET OF COVER EXISTS OVER THE MAINS DURING CONSTRUCTION VIA VACUUM TEST PITTING.
6. ALL BACKFILL AND COMPACTION OVER THE EX. PCCP MAINS, AT ANY DEPTH OF COVER, SHALL BE PERFORMED MANUALLY AND/OR WITH VEHICLES POSITIONED A MINIMUM OF 10 FEET CLEAR OF THE OUTER EDGE OF THE MAIN.
7. ALL ROCKS, BROKEN PAVEMENT, CURBING AND OTHER DEBRIS HAVING ANY DIMENSION GREATER THAN 3 INCHES SHALL BE REMOVED FROM ABOVE AND AROUND THE MAIN(S) PRIOR TO PLACING AND COMPACTING FILL, SUB GRADE MATERIAL OR
PAVING OVER THE MAIN (INCLUDING PIPE BEDDING).
8. THE CONTRACTOR SHALL NOTIFY THE APPROPRIATE PIPELINE CONSTRUCTION DIVISION INSPECTOR ASSIGNED TO THE PROJECT AT LEAST 72 HOURS IN ADVANCE OF ANY GRADING OR PAVING IN THE VICINITY OF THE EX. PCCP MAINS. ALL GRADING AND PAVING OVER THE MAINS SHALL BE COORDINATED AND PERFORMED UNDER THE SUPERVISION OF A WSSC
INSPECTOR.
9. THE CONTRACTOR SHALL USE SPECIAL CARE WHILE PERFORMING WORK IN THE VICINITY OF THE EX. PCCP WATER MAINS AND SHALL STRICTLY ADHERE TO THESE SPECIAL CONSTRUCTION REQUIREMENTS. THE CONTRACTOR IS RESPONSIBLE FOR ANY DAMAGE AND/OR REPLACEMENT REQUIRED AS A RESULT OF HIS WORK OVER THE MAINS AT NO ADDITIONAL COST TO WSSC.
10. IF SHUTDOWN AND DE-WATERING OF THE EX. PCCP WATER MAIN IS REQUIRED, COORDINATION WITH SYSTEMS CONTROL DIVISION (SCD) IS MANDATORY. A MINIMUM OF 60 DAYS ADVANCE NOTICE TO SCD IS REQUIRED TO COORDINATE WATER MAIN SHUTDOWN, DE-PRESSURIZATION, AND DE-WATERING OF EX. PCCP WATER MAINS AND REMOVAL OF THE ACOUSTIC FIBER OPTIC (AFO) MONITORING CABLE. SCD SHALL PERFORM THE SHUTDOWN SCHEDULING AND THE UTILITY SERVICES
DEPARTMENT SHALL EXECUTE THE SHUTDOWN, DE-PRESSURIZATION AND DE-WATERING.
11. TEST PITS TO VERIFY THE HORIZONTAL AND VERTICAL ALIGNMENT OF THE PCCP MAINS SHALL BE VIA VACUUM TEST PITTING RATHER THAN OPEN-CUT TRENCHING ON LIVE PCCP MAINS. VACUUM TEST PITTING IS PERFORMED ONLY TO THE CROWN OF THE EXISTING PCCP WATER MAINS. BACKFILL THE VACUUM TEST PIT IMMEDIATELY AFTER THE PERTINENT INFORMATION IS GATHERED. ANY DAMAGE TO THE EX. WATER MAIN COATING RESULTING FROM THE CONTRACTOR'S OPERATIONS SHALL BE REPAIRED AT THE CONTRACTOR'S EXPENSE. DAMAGE AND REPAIRS SHALL BE INSPECTED BY WSSC ENGINEERS AND/OR THE PIPE MANUFACTURER'S TECHNICAL FIELD REPRESENTATIVE, AND BE REPAIRED ACCORDINGLY PRIOR TO BACKFILLING.
12. DURING BACKFILLING, COMPACTED CR-6 OR #57 STONE SHALL BE USED TO 12 INCHES ABOVE THE CROWN OF THE PCCP MAIN.
THE REMAINING EXCAVATION SHALL BE BACKFILLED AND COMPACTED WITH SUITABLE MATERIAL IN ACCORDANCE WITH
STANDARD SPECIFICATION 02315.
NOTES:
· COORDINATE WITH ALL ONGOING CONSTRUCTION IN THE PROJECT AREA (IF ANY) TO RESOLVE ANY ISSUES
THAT WOULD BE IN CONFLICT WITH OTHER PROJECTS AND TRAFFIC CONTROLS.
· PEDESTRIAN ACCESS SHALL BE SAFELY MAINTAINED AT ALL TIMES.
· VERIFY LOCATION OF ALL UTILITIES PRIOR TO CONSTRUCTING WATER MAINS.
· TEST PIT CONNECTION LOCATIONS OF EXISTING WATER MAINS AND EXISTING UTILITY CROSSINGS.
· SHUTDOWNS SHOULD BE LIMITED TO 8 HOURS UNLESS OTHERWISE DIRECTED BY WSSC.
SITE B
1. PERFORM TEST PITS (VIA OPEN EXCAVATION) ON EX. 24" PCCP W TO LOCATE EXISTING PCCP JOINTS AT CONNECTION
LOCATIONS PRIOR TO ORDERING MATERIALS OR LAYING PIPE.
2. DURING A SINGLE 8 HOUR SHUTDOWN, PERFORM THE FOLLOWING WORK:
a. CLOSE THE FOLLOWING VALVES:
· V073 - NEAR PINECROFT LN AND PENN MANOR LN (200 FT SHEET 202NE14)
· V099 - NEAR PLACID CT AND PENN MANOR LN (200 FT SHEET 202NE14)
· V097 - NEAR POINTER RIDGE DR AND PENN MANOR LN (200 FT SHEET 202NE14)
· V096 - NEAR HALL RD AND POINTER RIDGE DR (200 FT SHEET 202NE14)
· V074 - NEAR PARKINGTON LN AND PENN MANOR LN (200 FT SHEET 202NE14)
· V075 - NEAR PENNYPACKER LN AND PENN MANOR LN (200 FT SHEET 202NE14)
· V077 - NEAR PACKTON LN AND PENN MANOR LN (200 FT SHEET 202NE14)
· V076 - NEAR PORT ECHO LN AND PENN MANOR LN (200 FT SHEET 202NE14)
· V078 - NEAR PENNINGTON LN AND PORT ECHO LN (200 FT SHEET 202NE14)
· V050 - NEAR 1206 PORT ECHO LN (200 FT SHEET 202NE14)
· V049 - NEAR 1206 PORT ECHO LN (200 FT SHEET 202NE14)
b. REPLACE EX. 24” W ON PENN MANOR LANE FROM STA. 0+10 TO STA. 0+58 AND FROM STA. 1+29 TO STA. 1+61 INCLUDING THRUST RINGS, REMOVE A MINIMUM OF TWO SECTIONS OF EXISTING PCCP PIPE AND CONNECT TO EXISTING JOINTS PER STD. DET. B/3.1b.
c. DISINFECT NEW 24" WATER MAIN.
d. OPEN VALVES CLOSED UNDER STEP 2a.
e. CONSTRUCT THRUST BLOCKS ON THRUST RINGS AND ALLOW TO CURE COMPLETELY.
3. WITHOUT DISRUPTING EXISTING WATER MAINS OR REQUIRING SHUTDOWNS, INSTALL 24” W FROM STA. 0+73 TO 1+02, INCLUDING CAST-IN-PLACE VAULT AND ALL APPURTENANCES. INSTALL TEMPORARY END CAPS AT STA. 0+73 AND STA 1+02.
4. ONCE CONCRETE HAS CURED TO DESIGN STRENGTH, DISINFECT AND TEST NEWLY INSTALLED PIPE.
5. DURING A SINGLE 8 HOUR SHUTDOWN, PERFORM THE FOLLOWING WORK:
a. CLOSE THE FOLLOWING VALVES:
· V073 - NEAR PINECROFT LN AND PENN MANREGEOR LN (200 FT SHEET 202NE14)
· V099 - NEAR PLACID CT AND PENN MANOR LN (200 FT SHEET 202NE14)
· V097 - NEAR POINTER RIDGE DR AND PENN MANOR LN (200 FT SHEET 202NE14)
· V096 - NEAR HALL RD AND POINTER RIDGE DR (200 FT SHEET 202NE14)
· V074 - NEAR PARKINGTON LN AND PENN MANOR LN (200 FT SHEET 202NE14)
· V075 - NEAR PENNYPACKER LN AND PENN MANOR LN (200 FT SHEET 202NE14)
· V077 - NEAR PACKTON LN AND PENN MANOR LN (200 FT SHEET 202NE14)
· V076 - NEAR PORT ECHO LN AND PENN MANOR LN (200 FT SHEET 202NE14)
· V078 - NEAR PENNINGTON LN AND PORT ECHO LN (200 FT SHEET 202NE14)
· V050 - NEAR 1206 PORT ECHO LN (200 FT SHEET 202NE14)
· V049 - NEAR 1206 PORT ECHO LN (200 FT SHEET 202NE14)
b. INSTALL NEW 24" W FROM STA. 0+58 TO 0+73 AND FROM STA. 1+02 TO 1+29, INCLUDING ALL APPURTENANCES.
c. DISINFECT NEW 24" WATER MAIN.
d. OPEN ALL VALVES CLOSED UNDER STEP 5a.
6. REMOVE EX. TOP SLAB AND LOWER VAULT WALLS TO 2 FEET BELOW GRADE AND AS REQUIRED TO INSTALL NEW 24"
WATER MAIN.
7. DURING A SINGLE 8 HOUR SHUTDOWN, PERFORM THE FOLLOWING WORK:
a. CLOSE THE FOLLOWING VALVES:
· V073 - NEAR PINECROFT LN AND PENN MANREGEOR LN (200 FT SHEET 202NE14)
· V099 - NEAR PLACID CT AND PENN MANOR LN (200 FT SHEET 202NE14)
· V097 - NEAR POINTER RIDGE DR AND PENN MANOR LN (200 FT SHEET 202NE14)
· V096 - NEAR HALL RD AND POINTER RIDGE DR (200 FT SHEET 202NE14)
· V074 - NEAR PARKINGTON LN AND PENN MANOR LN (200 FT SHEET 202NE14)
· V075 - NEAR PENNYPACKER LN AND PENN MANOR LN (200 FT SHEET 202NE14)
· V077 - NEAR PACKTON LN AND PENN MANOR LN (200 FT SHEET 202NE14)
· V076 - NEAR PORT ECHO LN AND PENN MANOR LN (200 FT SHEET 202NE14)
· V078 - NEAR PENNINGTON LN AND PORT ECHO LN (200 FT SHEET 202NE14)
· V050 - NEAR 1206 PORT ECHO LN (200 FT SHEET 202NE14)
· V049 - NEAR 1206 PORT ECHO LN (200 FT SHEET 202NE14)
b. REMOVE EXISTING 20" VALVE, 20" PIPING, AND REDUCERS. INSTALL NEW 24" W FROM STA. 0+00 TO 0+10, INCLUDING
ALL APPURTENANCES. FILL VAULT WITH CLSM PER SPECIFICATION 02510.
c. DISINFECT NEW 24" WATER MAIN.
d. OPEN ALL VALVES CLOSED UNDER STEP 7a.
6. RESTORE AREA.
SUGGESTED SEQUENCE OF CONSTRUCTION
PENN MANOR - TEST HOLE SUMMARY
T.H. # NORTHING EASTING UTILITY DEPTH TOP ELEV. DATE DUG
5 450586.7294 1390066.7062 24" PCCP WATER 4.65' 117.00' 6/15/2022
6 450641.8587 1390159.9816 24" PCCP WATER 4.44' 119.21' 6/15/2022
NOTIFICATION REQUIREMENTS FOR SHUTDOWN OF PCCP MAINS
1. THE APPLICANT’S CONTACT PERSON AT WSSC SHALL BE THE PROJECT MANAGER FOR PROJECTS UP TO AND INCLUDING
DESIGN PHASE. DURING CONSTRUCTION PHASE, THE APPLICANT’S CONTACT PERSON AT WSSC SHALL BE THE PIPELINE
CONSTRUCTION DIVISION INSPECTOR (JASON FLORY @ 301-256-6851).
2. THE APPLICANT SHALL COMMENCE COORDINATION OF THE PCCP PIPELINE SHUTDOWN PROCESS WITH THE WSSC CONTACT PERSON AT A MINIMUM OF 60 DAYS IN ADVANCE OF BEGINNING WORK TO COORDINATE THE PCCP ISOLATION VALVE INSPECTION, PIPELINE ISOLATION AND DEWATERING, AND/OR AFO MONITORING CABLE REMOVAL, AND RECHARGE OF THE
PIPELINE.
3. APPROVAL OF THE PCCP PIPELINE SHUTDOWN IS SUBJECT TO WATER MAIN TRANSMISSION SYSTEM CONDITIONS AT THE TIME OF REQUEST. RESCHEDULING OF THE PROPOSED SHUTDOWN TIME AND DURATION MAY BE REQUIRED AND IS AT THE
DISCRETION OF WSSC.
4. THE APPLICANT’S CONTACT PERSON AT WSSC SHALL COORDINATE THE PCCP SHUTDOWN A MINIMUM OF 60 DAYS IN ADVANCE OF WORK WITH THE SYSTEMS CONTROL DIVISION MANAGER (KAREN WRIGHT @ 301-206-8416), THE WATER/WASTEWATER SYSTEM ASSESSMENT DIVISION (ARTURO ACEVEDO @ 301-206-8478), THE PIPELINE CONSTRUCTION DIVISION INSPECTOR (JASON FLORY @ 301-256-6851), AND THE UTILITY SERVICES DIVISION MANAGER (LICETTE VILLAFANE @ 443-968-0540).
5. THE PCCP PIPELINE MAY HAVE AN ACOUSTIC FIBER OPTIC (AFO) MONITORING SYSTEM INSTALLED INSIDE THE PIPELINE.
COORDINATION WITH THE WATER/WASTEWATER SYSTEM ASSESSMENT DIVISION IS REQUIRED (AS SPECIFIED IN ITEM 2) TO REMOVE THE INTERNAL AFO CABLE PRIOR TO BEGINNING WORK. IF COORDINATION IS NOT ACCOMPLISHED, THE APPLICANT IS RESPONSIBLE FOR ANY DAMAGE AND/OR REPLACEMENT OF THE AFO CABLE AS RESULT OF THEIR WORK AT NO ADDITIONAL
COST TO WSSC.
6. IF THE PCCP PIPELINE DOES NOT HAVE AN AFO MONITORING SYSTEM INSTALLED, 60-DAY ADVANCE NOTIFICATION IS STILL REQUIRED TO COORDINATE THE REMOVAL & REPLACEMENT OF ANY PCCP PIPE SECTIONS, TO DOCUMENT THE EXTERNAL
CONDITIONS, AND TO COLLECT SAMPLES OF THE PIPE SECTION FOR FORENSIC ANALYSIS.
7. PCCP PIPELINE RECHARGE EFFORTS SHALL BE COORDINATED WITH WSSC STAFF SPECIFIED IN ITEM 4. THE PIPELINE RECHARGE EFFORTS AND AFO CABLE RE-INSTALLATION SHALL FOLLOW THE ADVANCE NOTIFICATION AS SPECIFIED IN ITEM 2 AND WILL BE UNDER THE DIRECTION OF THE UTILITY SERVICES DIVISION MANAGER (LICETTE VILLAFANE @ 443-968-0540).
8. THE APPLICANT IS RESPONSIBLE FOR ANY DAMAGE TO THE PCCP MAIN AT THE LOCATION OF WORK EFFORT AND SHALL BE RESPONSIBLE FOR REPLACEMENT OF ANY DAMAGED PCCP PIPE SECTIONS PER WSSC DIRECTION AT NO ADDITIONAL COST
TO WSSC.
S . PN IE CV K
E E
T L
S
N 9o 2. 350
Docusign Envelope ID: B7C40696-C70F-49BC-81DD-AF032F73758F
Dec 1, 2025 | 9:24 AM EST
BT7171B21Dec 2, 2025 | 10:03 AM EST
Dec 2, 2025 | 10:31 AM EST
PRECAST
1. CONTACT WSSC ENVIRONMENTAL PROGRAMS SECTION AT (301) 206-8077, 48 HOURS PRIOR TO STARTING ANY UTILITY WORK
UNDER THIS CONTRACT.
2. ANY GROUND WATER OR SURFACE WATER PUMPED DURING THIS PROJECT SHOULD BE DISCHARGED THROUGH AN
APPROVED DE-WATERING DEVICE. SEE STANDARD DETAIL SC/15.0, SC/15.1.
3. STREETS AND PAVED WALKWAYS SHALL BE BROOM SWEPT DAILY.
4. INSTALL CURB INLET OR AT-GRADE INLET PROTECTION AS NEEDED OR AS DIRECTED BY WSSCENVIRONMENTAL STAFF. SEE
STANDARD DETAIL SC/16.0, SC/16.1.
5. PLACE SILT FENCE PER STANDARD DETAIL SC/1.0 ALONG LOW SIDE OF EXCAVATED AREA WHEN WORKING IN NON-PAVED AREAS OR AS SHOWN ON PLANS, OR AS DIRECTED BY WSSC ENVIRONMENTAL STAFF IN THE FIELD. CONTRACTOR SHALL PROVIDE DAILY TEMPORARY STABILIZATION FOR ALL DISTURBED NON-PAVED AREAS. DAILY TEMPORARY STABILIZATION REQUIRED FOR AREAS NOT PROTECTED WITH SILT FENCE, OR WITH OTHER PERIMETER CONTROLS OR PERIMETER
CONTROLS.
6. ANY EXCAVATED OR STOCKPILED MATERIAL LEFT OVERNIGHT SHALL BE COVERED WITH AN IMPERMEABLE (PLASTIC)
MATERIAL. PROVIDE SEDIMENT CONTROL FOR ALL OFFSITE STAGING/STOCKPILE AREAS.
7. WHEN WORKING IN PAVED SURFACES, PLACE EXCAVATED MATERIAL ON HIGH SIDE OF TRENCH.
8. ANY SLURRY GENERATED BY PAVEMENT SAW CUTTING SHALL BE CONTAINED BY THE CONTRACTOR TO PREVENT SLURRY FROM ENTERING THE EXISTING STORM DRAIN SYSTEM OR WATERWAY BY USING APPROVED METHODS, DEVICES, OR AS DIRECTED BY THE WSSC ENVIRONMENTAL STAFF. CONTRACTOR SHALL PROPERLY REMOVE AND DISPOSE OF CONTAINED
SLURRY AT THE END OF EACH WORK DAY.
9. FOR AREAS WITHIN THE LIMIT OF DISTURBANCE WHICH DO NOT DRAIN TO AN APPROVED EROSION AND SEDIMENT CONTROL MEASURE AND/OR WHERE THE INSTALLATION OF CONTROLS IS NOT FEASIBLE (ROADWAY, SIDEWALK, ETC.)/CONTRACTOR SHALL ONLY DISTURB AREA WHICH CAN BE COMPLETED AND STABILIZED BY THE END OF EACH WORKING DAY. STABILIZATION
SHALL BE AS FOLLOWS:
A. FOR AREAS TO BE PAVED: STONE BASE SHALL BE APPLIED.
B. FOR AREAS TO BE VEGETATIVELY STABILIZED:
i. PERMANENT SEED AND SOIL STABILIZATION MATTING FOR SOD FOR ALL STEEP SLOPES, CHANNELS, OR SWALES
ii. PERMANENT SEED AND MULCH FOR ALL OTHER AREAS. ANY AREAS WHICH CAN NOT BE STABILIZED BY THE END OF
EACH WORKING DAY MUST HAVE SILT FENCE SC/1.0 INSTALLED ON THE DOWN SLOPE SIDE.
PHASE ONE
1. PERFORM TEST PITS (VIA OPEN EXCAVATION) ON EX. 24" PCCP W TO LOCATE EX. PCCP JOINTS AT CONNECTION
LOCATIONS PRIOR TO ORDERING MATERIALS OR LAYING PIPE.
2. ASSEMBLE PIPE SECTIONS TO BE INSTALLED FROM STA. 0+10 TO STA. 0+56 AND FROM STA. 1+20 TO STA. 1+61, INCLUDING THRUST RINGS. INSTALL TEMPORARY TEST CAPS ON PIPE SECTIONS AND TEST AND DISINFECT PIPE
SECTIONS.
3. DURING A SINGLE 8 HOUR SHUTDOWN, PERFORM THE FOLLOWING WORK:
a. CLOSE THE FOLLOWING VALVES:
· V049 - NEAR 1206 PORT ECHO LN (200 FT SHEET 202NE14)
· V050 - NEAR 1206 PORT ECHO LN (200 FT SHEET 202NE14)
· V073 - NEAR PINECROFT LN AND PENN MANOR LN (200 FT SHEET 202NE14)
· V074 - NEAR PARKINGTON LN AND PENN MANOR LN (200 FT SHEET 202NE14)
· V075 - NEAR PENNYPACKER LN AND PENN MANOR LN (200 FT SHEET 202NE14)
· V076 - NEAR PORT ECHO LN AND PENN MANOR LN (200 FT SHEET 202NE14)
· V077 - NEAR PACKTON LN AND PENN MANOR LN (200 FT SHEET 202NE14)
· V078 - NEAR PENNINGTON LN AND PORT ECHO LN (200 FT SHEET 202NE14)
· V096 - NEAR HALL RD AND POINTER RIDGE DR (200 FT SHEET 202NE14)
· V097 - NEAR POINTER RIDGE DR AND PENN MANOR LN (200 FT SHEET 202NE14)
· V099 - NEAR PLACID CT AND PENN MANOR LN (200 FT SHEET 202NE14)
b. DEWATER EX. 24” W AND DISCHARGE IN ACCORDANCE WITH SPECIFICATION 02511.
c. REPLACE EX. 24” W ON PENN MANOR LANE FROM STA. 0+10 TO STA. 0+56 AND FROM STA. 1+20 TO STA. 1+61.
REMOVE A MINIMUM OF TWO SECTIONS OF EXISTING PCCP PIPE AND CONNECT TO EXISTING JOINTS PER STD.
DET. B/3.1b.
d. REPLACE WHC TO 16100 PENN MANOR LN.
e. OPEN VALVES CLOSED UNDER STEP 3a.
4. CONSTRUCT THRUST BLOCKS AT STA. 0+24 AND STA. 1+45 AND ALLOW TO FULLY CURE.
PHASE TWO
1. WITHOUT DISRUPTING EXISTING WATER MAINS OR REQUIRING SHUTDOWNS, INSTALL 24” W FROM STA. 0+60 TO 1+16, INCLUDING PRECAST VAULT AND ALL APPURTENANCES. INSTALL TEMPORARY TEST CAPS AT STA. 0+60 AND STA 1+16
AND TEST AND DISINFECT NEWLY INSTALLED PIPE.
PHASE THREE
1. REMOVE EX. VALVE VAULT TOP SLAB AND LOWER VAULT WALLS TO 2 FEET BELOW GRADE AND AS REQUIRED TO
INSTALL NEW 24" WATER MAIN.
2. INSTALL TEMPORARY TEST CAPS ON PIPE TO BE INSTALLED FROM STA. 0+00 TO STA. 0+10 AND TEST AND DISINFECT
PIPE.
3. DURING A SINGLE 8 HOUR SHUTDOWN, PERFORM THE FOLLOWING WORK:
a. CLOSE THE FOLLOWING VALVES:
· V049 - NEAR 1206 PORT ECHO LN (200 FT SHEET 202NE14)
· V050 - NEAR 1206 PORT ECHO LN (200 FT SHEET 202NE14)
· V073 - NEAR PINECROFT LN AND PENN MANREGEOR LN (200 FT SHEET 202NE14)
· V074 - NEAR PARKINGTON LN AND PENN MANOR LN (200 FT SHEET 202NE14)
· V075 - NEAR PENNYPACKER LN AND PENN MANOR LN (200 FT SHEET 202NE14)
· V076 - NEAR PORT ECHO LN AND PENN MANOR LN (200 FT SHEET 202NE14)
· V077 - NEAR PACKTON LN AND PENN MANOR LN (200 FT SHEET 202NE14)
· V078 - NEAR PENNINGTON LN AND PORT ECHO LN (200 FT SHEET 202NE14)
· V096 - NEAR HALL RD AND POINTER RIDGE DR (200 FT SHEET 202NE14)
· V097 - NEAR POINTER RIDGE DR AND PENN MANOR LN (200 FT SHEET 202NE14)
· V099 - NEAR PLACID CT AND PENN MANOR LN (200 FT SHEET 202NE14)
b. DEWATER EX. 24” W AND DISCHARGE IN ACCORDANCE WITH SPECIFICATION SECTION 02511.
c. REMOVE EXISTING 20" VALVE, 20" PIPE, AND REDUCERS. INSTALL NEW 24" W FROM STA. 0+00 TO 0+10, INCLUDING ALL APPURTENANCES.
d. INSTALL NEW 24" W FROM STA. 0+56 TO 0+60 AND FROM STA. 1+16 TO 1+120, INCLUDING ALL APPURTENANCES.
e. REPLACE WHC TO 16101 PENN MANOR LN.
f. OPEN VALVES CLOSED UNDER STEP 3a.
4. FILL VAULT WITH CLSM PER SPECIFICATION 02510.
5. RESTORE THE AREA.
3/10/2026 REVISED SEQUENCE OF
CONSTRUCTION AND SEDIMENT
CONTROL NOTES
BGE #4
EX. C
ONC.W
ALK
EX. 12"
MAGNOLIA
EX. 8" MAPLE
EX. 18" MAPLEEX. 12" MAPLE
4"
TREE
EX. 12" M
APLE
GRASS
GRASS
GRASS
GRASS
GRASS
CONC.
EX.
24" P
.C.C.P. W (1
966-2539A)
EX. 8" S (1966-2539A)
EX.
8" S
(1 966-2539A)
EX. 8" S
(1966-2539A)
EX. 8" C.I. W
(1966-2539A)
EX. 6" GAS
EX. 6" GAS
EX. 6
" G
AS
EX. 0.5" G
H
C
(B
GE)
V073
V072
023U
EX. 8" S
(1966-2539C)
EX. 24" RCP
EX. 24" RCP
EX. 1
5" R
CP
EX. 24" RCP
EX. 3
6"
RCP
15901
PENN M
ANOR LN
16101
PENN M
ANOR LN
16100
PENN M
ANOR LN
PARKINGTON LN
EX. C
ONC. C
URB AND G
UTTER
EX. C
ONC. C
URB AND GUTTER
EX.
24" P
.C.C.P. W (1
966-2539A)
LOCK JO
INT PE-67-96-1
EX. 24" P.C.C.P. W (1966-2539C)
LOCK JOINT PE-68-13-1
EX. 2
4" R
CP
SB-1
PC-1
TP-1
TP-2
N 450670
E
E
N 450670
N 450550
E
STA. 1+18
INSTALL NEW
24"-1/8 H.B.
STA. 0+86
C/L OF VALVE VAULT. INSTALL
NEW 12'X7' VALVE VAULT AND 24"
HORIZONTAL VALVE. SEE WSSC
STD. DETAILS W/2.4, W/2.4a AND W/2.5.
STA. 0+40
INSTALL NEW
24"-1/32 H.B.
STA. 0+00
CONNECT TO EX. 24" PCCP W WITH P.C.C.P.
X DIP ADAPTOR, AND M.J. SOLID SLEEVE.
CONNECTION MUST BE MADE AT JOINT.
PER LAY SCHEDULE FOR AS-BUILT 66-2539A,
JOINT IS LOCATED APPROXIMATELY AT
AS-BUILT STA. 21+70. SEE WSSC STD. DETAIL B/3.1b
INSTALL NEW 24" DIP, CL 54 W FROM
0+00 TO 1+61. SEE PROFILE ON SHEET 4
REMOVE EX. 24" PCCP
FROM 1+20 TO 1+61
REMOVE EX. 24" PCCP
FROM 0+00 TO 0+58
STA. 1+03
INSTALL NEW
1" WHC
STA. 0+50
INSTALL
NEW 1" WHC
REMOVE EX. 24"
PCCP W AND REPLACE
WITH 24" DIP, CL 54 W
SALVAGE EX. VALVE, REDUCERS, FRAMES, AND
COVERS. REMOVE EX. TOP SLAB AND VAULT WALLS
TO 2 FEET BELOW GRADE. FILL VAULT WITH CLSM PER
SPECIFICATION 02510. RESTORE AREA
STA. 1+06
INSTALL NEW
24"-1/32 H.B.
STA. 0+24
CONSTRUCT THRUST BLOCK WITH
WELD-ON THRUST RING ON NEW 24" W.
SEE THRUST BLOCK DETAIL ON SHEET 5
STA. 1+45
CONSTRUCT THRUST BLOCK WITH
WELD-ON THRUST RING ON NEW 24" W.
SEE THRUST BLOCK DETAIL ON SHEET 5
STA. 1+02
INSTALL NEW
24"-1/16 H.B.
STA. 1+61
CONNECT TO EX. 24" PCCP W WITH P.C.C.P.
X DIP ADAPTOR, AND M.J. SOLID SLEEVE.
CONNECTION MUST BE MADE AT JOINT.
PER LAY SCHEDULE FOR AS-BUILT 66-2539A,
JOINT IS LOCATED APPROXIMATELY AT
AS-BUILT STA. 0+32. SEE WSSC STD. DETAIL B/3.1b
EX.24" WATER TO BE ABANDONED IN PALCE BY
CAP ENDS AND FILL WITH CLSM PER SPEC 02510
STA. 1+29
1.92° DEF.
STA. 0+58
INSTALL NEW
24"-1/8 H.B.
STA. 0+73
INSTALL NEW
24"-1/8 H.B.
STA. 1+53
0.93° DEF.
200'S
CONTRACT NO. BT7171B21
202NE14
ENGINEER:THESE DOCUMENTS CONTAIN
PRIVILEGED AND CONFIDENTIAL
INFORMATION WHICH SHALL NOT
BE REDISTRIBUTED WITHOUT
PRIOR WSSC APPROVAL
NAME: JOHNSON, MIRMIRAN & THOMPSON
ADDRESS: 40 WIGHT AVENUE, COCKEYSVILLE, MD 21030
PHONE: (410) 329-3100
CONTACT : STEVEN PICKEL, PE
QUEEN ANNE ELECTION DISTRICT NO. 7
PENN MANOR LANE LARGE VALVE VAULT REPLACEMENT
BOWIE, PRINCE GEORGE'S COUNTY, MD 20716
VE
R
IF
Y
SC
AL
E
- B
AR
IS
O N
E
IN
C H
O N
O R
IG
IN
AL
D
R
AW
IF
N
O T
O N
E
IN
C H
O N
T H
IS
S
H
EE
T, A
D
JU
ST
S
C
AL
ES
A
C C
O R
D
IN
G
LY
HHG: 355
LHG: 281
PRESSURE ZONE= 317A
WESTERN BRANCH MINI DRAINAGE BASIN NO. 130
WASHINGTON SUBURBAN SANITARY COMMISSION
WSSC
DELIVERING THE ESSENTIAL
PA
TH
XX/XX/XX - PLOT DATE
PROFESSIONAL CERTIFICATION
I HEREBY CERTIFY THAT THESE DOCUMENTS
WERE PREPARED OR APPROVED BY ME,
AND THAT I AM A DULY LICENSED
PROFESSIONAL ENGINEER UNDER
THE LAWS OF THE STATE OF MARYLAND.
NAME: STEVEN PICKEL, P.E.
LICENSE NO.: 50329
EXP. DATE: 12/18/2026
PENN MANOR LANE
TE
M
PL
AT
E
LA
YO
U
T C
U R
R
EN
T as o f:
/1
4/
\\j m t.c or p.
lo ca l\j m td fs
\2
0\
7_
5_ W oo dy ar d_
R oa d_ La rg e_
\C
AD
D \C
IV
IL
\P en n M an or
\P
EN
N M
AN
O
R P
LA
N
.d w g
OF 6
NO
WSSC Erosion and Sediment Control Approval Note This plan has been approved per requirements in the:
Standard Procedures of the WSSC Regulations for Utility Erosion and Sediment Control, Section V, Paragraph A.
Reviewed by:_________________________________________
Date:__________________ Plan No.______________________
DATE REVISIONS
DATE PROJECT MANAGER
WATER INFRASTRUCTURE SECTION
NEXT VALVE
V074± 190'
V075 ± 480'
V077 ± 760'
V076 ± 1,170'
V078 ± 1,370'
V049 ± 1,760'
PENN M
ANOR LANE
PINECROFT LANE
NEXT VALVE
V099 ± 1,780'
V097 ± 2,050'
V096 ± 2,370'
JMT1
R&C
ELEV. = 121.23
JMT2
R&C
ELEV. = 126.61
SCALE:1"=10'
PLAN - 16100 PENN MANOR LANE
LEGEND
EX. WATER MAIN
PROP. WATER MAIN
EX. SANITARY SEWER
EX. GAS
EX. ELECTRIC
EX. FIBER OPTIC
EX. WATER MAIN TO BE ABANDONED
EX. CABLE TV
EX. TELEPHONE
PROP. PAVEMENT CORE
PROP. SOIL BORING
PROP. TEST PIT
EX. WATER VALVE
PROP. THRUST BLOCK
EX. FIRE HYDRANT
EX. SANITARY MH
MILL AND OVERLAY
EX. CURB STOP
TREE PROTECTION FENCE
EX. STORM DRAIN
EX. RIGHT OF WAY
EX. INTERNAL PROPERTY LINE
ABBREVIATIONS
EXISTINGEX.
PROPOSEDPROP.
WATERW
REDUCERRED.
VALVEV
HORIZONTAL BENDH.B.
VERTICAL BENDV.B.
DEFLECTIONDEF.
FIRE HYDRANTF.H.
FIRE HYDRANT TEEF.H.T.
SOIL BORINGSB
PAVEMENT COREPC
TEST PITTP
BLOW OFFBO
CURB STOPCS
WATER METERWM
EX. WATER MANHOLE
PROP. WATER MANHOLE
PROP. 24" WATER VALVE
EX. OVERHEAD ELECTRIC
PLAN VIEW
N
AD
3/
N
G
VD
2.0'
PRESTRESSED CONCRETE CYLINDER PIPEP.C.C.P.
NOTES:
1. CONTRACTOR SHALL VERIFY ALL CONNECTION POINTS TO EXISTING 24" PCCP WATER
MAIN WITH TEST PITS AND ADJUST CONNECTION LOCATIONS TO EXISTING PIPE JOINTS
AS NECESSARY.
2. CONTRACTOR SHALL CONFIRM CONNECTING TO EXISTING PIPE BELL END OR SPIGOT
END PRIOR TO ORDERING PCCP X DIP ADAPTOR AND ANY ASSOCIATED DIMENSIONS
TO ENSURE PROPER CONNECTION TO EXISTING 24" PCCP.
TREE PROTECTION FENCE,
SEE WSSC STD. DETAIL SC/19.0
(TYP. OF 2)
S . PN IE CV K
E E
T L
S
N 9o 2. 350
Docusign Envelope ID: B7C40696-C70F-49BC-81DD-AF032F73758F
Dec 1, 2025 | 9:24 AM EST
BT7171B21Dec 2, 2025 | 10:03 AM EST
Dec 2, 2025 | 10:31 AM EST
PLACE
TP-5
TP-6
PCCP
PCCP
PCCP
PCCP
PCCP
PCCP
66-2539C
REVISED ABBREVIATIONS, SPELLING,
CONTRACT ID, AND TEST PIT
NUMBERS
3/10/2026
1+30 1+40 1+50 1+601+61
EX. GRADE
(FEBRUARY 2022)
PROP. 24" DI W
EX
. G
H C
EX. 8" S (1966-2539C)
EX. 24" W
(1966-2539C)
P.C.C.P.
EX. 24" SD
1+60 1+61
STA. 1+45
CONC. THRUST BLOCK
INV. = 117.4
STA. 1+61
REMOVE EX. 24" W AND
CONNECT TO EX. 24" 2
USING M.J. SOLID SLEEVES
AND PCCP X DIP ADAPTOR
INV. = 117.4 ±
LIMIT OF JMT SURVEY
RESTRAIN ALL JOINTS AND FITTINGS
EX. ASPHALT PAVEMENT
0+00 0+10 0+20 0+30 0+40 0+50 0+60 0+70 0+80 0+90 1+00 1+10 1+20 1+30
EX
. 4
" S
AN
EX. GRADE
(FEBRUARY 2022)
EX
. W
H C
EX. 8" S (1966-2539A)
PROP. 24" DI W
TP-01
TOP: 117.00
EX. 24" SD
EX
. W
H C
EX. 8" S (1966-2539C)
EX. 24" W
(1966-2539C)
P.C.C.P.
TP-02
TOP: 119.21
EX. 24" W
(1966-2539A)
P.C.C.P.
RESTRAIN ALL JOINTS AND FITTINGS
EX. ASPHALT PAVEMENT
LIMIT OF JMT SURVEY
STA. 0+00
REMOVE EX. 24" W AND
CONNECT TO EX. 24" W
USING M.J. SOLID SLEEVES
AND PCCP X DIP ADAPTOR
INV. = 115.1
STA. 0+24
CONC. THRUST BLOCK
INV. = 115.9
STA. 0+40
24" -1/8 H.B.
INV. = 116.0
STA. 0+49
1" WHC
INV. = 116.2
EX. VALVE
TO BE REMOVED
STA. 0+58
24" 1/8 H.B.
ROT. DOWN 3.5°
INV. = 116.4
EX. 24" W
(1966-2539A, LOCK JOINT PE-67-96-1,
TO BE ABANDONED)
STA. 0+73
24" 1/8 H.B.
ROT. UP 2.0°
INV. = 115.9
STA. 0+86
C/L OF VALVE VAULT
INV. = 115.9
EX. 24" W
(1966-2539A, LOCK JOINT PE-68-13-1
TO BE ABANDONED)
STA. 1+02
24"- 1/16 H.B.
ROT. UP 4.8°
INV. = 115.9
STA. 1+03
1" WHC
INV. = 116.0
STA. 1+06
24"- 1/32 H.B.
INV. = 116.2
STA. 1+18
24"-1/8 H.B.
ROT. DOWN 4.8°
INV. = 117.3
FLOOR ELEV. OF VAULT
INV. = 113.2
200'S
CONTRACT NO. BT7171B21
202NE14
ENGINEER:THESE DOCUMENTS CONTAIN
PRIVILEGED AND CONFIDENTIAL
INFORMATION WHICH SHALL NOT
BE REDISTRIBUTED WITHOUT
PRIOR WSSC APPROVAL
NAME: JOHNSON, MIRMIRAN & THOMPSON
ADDRESS: 40 WIGHT AVENUE, COCKEYSVILLE, MD 21030
PHONE: (410) 329-3100
CONTACT : STEVEN PICKEL, PE
QUEEN ANNE ELECTION DISTRICT NO. 7
PENN MANOR LANE LARGE VALVE VAULT REPLACEMENT
BOWIE, PRINCE GEORGE'S COUNTY, MD 20716
VE
R
IF
Y
SC
AL
E
- B
AR
IS
O N
E
IN
C H
O N
O R
IG
IN
AL
D
R
AW
IF
N
O T
O N
E
IN
C H
O N
T H
IS
S
H
EE
T, A
D
JU
ST
S
C
AL
ES
A
C C
O R
D
IN
G
LY
HHG: 355
LHG: 281
PRESSURE ZONE= 317A
WESTERN BRANCH MINI DRAINAGE BASIN NO. 130
WASHINGTON SUBURBAN SANITARY COMMISSION
WSSC
DELIVERING THE ESSENTIAL
PA
TH
XX/XX/XX - PLOT DATE
PROFESSIONAL CERTIFICATION
I HEREBY CERTIFY THAT THESE DOCUMENTS
WERE PREPARED OR APPROVED BY ME,
AND THAT I AM A DULY LICENSED
PROFESSIONAL ENGINEER UNDER
THE LAWS OF THE STATE OF MARYLAND.
NAME: STEVEN PICKEL, P.E.
LICENSE NO.: 50329
EXP. DATE: 12/18/2026
PENN MANOR LANE
TE
M
PL
AT
E
LA
YO
U
T C
U R
R
EN
T as o f:
/1
4/
\\j m t.c or p.
lo ca l\j m td fs
\2
0\
7_
5_ W oo dy ar d_
R oa d_ La rg e_
\C
AD
D \C
IV
IL
\P en n M an or
\P R
O
FI
LE
.d w g
OF 6
NO
WSSC Erosion and Sediment Control Approval Note This plan has been approved per requirements in the:
Standard Procedures of the WSSC Regulations for Utility Erosion and Sediment Control, Section V, Paragraph A.
Reviewed by:_________________________________________
Date:__________________ Plan No.______________________
DATE REVISIONS
DATE PROJECT MANAGER
WATER INFRASTRUCTURE SECTION
PROFILE VIEW 4
PROFILE- BT7171B21- PENN MANOR LANE (1+30 TO 1+61)
WATER STAKEOUT DATA
STATION ITEM NORTHING EASTING
0+00 CONNECT TO EX. 24" W 450587.84 1390067.27
0+24 CONC. THRUST BLOCK 450602.00 1390086.38
0+40 24" - 1/32 H.B. 450612.05 1390099.49
0+58 24" - 1/8 H.B. 450619.77 1390115.08
0+73 24" - 1/8 H.B. 450614.99 1390129.44
0+86 C/L OF VALVE VAULT 450620.67 1390140.84
1+02 24" - 1/16 H.B. 450627.70 1390154.95
1+06 24" - 1/32 H.B. 450631.48 1390158.23
1+18 24" - 1/8 H.B. 450642.01 1390163.79
1+29 1.92 DEG. DEFLECTION 450644.99 1390173.45
1+45 CONC. THRUST BLOCK 450649.51 1390188.73
1+53 0.93 DEG. DEFLECTION 450651.71 1390196.39
1+61 CONNECT TO EX. 24" W 450653.79 1390204.12
EXISTING WATER HOUSE CONNECTION INFORMATION
SHEET
NO. ADDRESS
PROPSED MAIN
SIZE (IN)
EX. WHC
SIZE (IN)
EX. METER
SIZE (IN)
EX. WHC
MATERIAL
METER
LOCATION
METER
TYPE
APPROX.
LENGTH OF
EX. WHC (LF)
APPROX.
LENGTH OF
PROPOSED
WHC (LF)
PROPOSED
WHC SIZE (IN) REMARKS
3 16100 PENN MANOR LN 24 3/4 5/8 COPPER OUTSIDE SINGLE 22 28 1 CONNECT TO EX. WHC
3 16101 PENN MANOR LN 24 3/4 5/8 COPPER OUTSIDE SINGLE 38 26 1 CONNECT TO EX. WHC
TOTAL 60 54
PROFILE- BT7171B21- PENN MANOR LANE (0+00 TO 1+30)
SCALE 1"= 5' HORIZONTAL
1"= 5' VERTICAL
SCALE 1"= 5' HORIZONTAL
1"= 5' VERTICAL
S . PN IE CV K
E E
T L
S
N 9o 2. 350
Docusign Envelope ID: B7C40696-C70F-49BC-81DD-AF032F73758F
Dec 1, 2025 | 9:24 AM EST
BT7171B21Dec 2, 2025 | 10:03 AM EST
Dec 2, 2025 | 10:31 AM EST
M A
T C
H
LI
N E
S T
A . 1
S
E E
T H
IS
S
H E
E T
M A
T C
H
LI
N E
S T
A . 1
S
E E
T H
IS
S
H E
E T
TP-05 TP-06
PCCP
PCCP
PCCP
1/32 H.B.
REVISED FITTING, ABBREVIATIONS
AND TEST PIT NUMBERS. ADDED
MATCHLINES
3/10/2026
H
EQ
EQ
L
EQUAL EQUAL
3" C
L.
(T
YP
D.I.P.
3"
CL. 3"CL.
(TYP.)
ELEVATION
CONCRETE THRUST BLOCK WITH WELD-ON THRUST RING DETAIL
N.T.S.
CONCRETE THRUST BLOCKS WITH WELD-ON THRUST RING
SHEET NO. 24" W STA. L H T R1 R1A R2 R2A R3 F
3 0+24 10' 7' 2' 16-#8 4-#8 10-#8 4-#8 16-#8 99K 3 1+45 10' 7' 2' 16-#8 4-#8 10-#8 4-#8 16-#8 99K
SECTION A-A
3" CL.
T
EQ. EQ.
H /2
H /2
1'- 6"
TYP.
R1 BARS,
EA FACE
R2 BARS, EA FACE
2" CL. (TYP.)
R1 BARS,
EA FACE
R2A BARS @
EA FACE (TYP.
EACH SIDE
D.I.P)
WELDED-ON THRUST COLLAR (BY OTHERS)
R2 BARS, EA FACE
R1A BARS @ EA FACE
(TYP. ABOVE AND BELOW
D.I.P)
A
A
R3 BARS AROUND PIPE
EACH FACE (TYP.)
NOTES:
1. ALL CONCRETE SHALL BE f 'c = 4500 PSI @ 28 DAYS AND AIR ENTRAINED. PIPELINE SHALL NOT BE PRESSURIZED UNTIL
CONCRETE STRENGTH REACHES 4500 PSI AND TRENCH HAS BEEN BACKFILLED.
2. ALL REBARS SHALL BE ASTM 615 GRADE 60.
3. REINFORCING BARS TO BE PLACED AS SHOWN BY "ELEVATION" AND "SECTION A-A."
4. DUCTILE IRON PIPE ONLY.
5. MAINTAIN 2" CLEAR BETWEEN ALL REBARS AND PIPE.
6. WELD-ON THRUST RINGS AND PIPE TO WHICH THEY ARE ATTACHED SHALL BE DESIGNED BY THE PIPE
MANUFACTURER FOR DESIGN THRUST OF "F" KIPS AS NOTED. THE AREA OF THE RING SHALL BE PROPORTIONED
SUCH THAT THE BEARING STRESS ON THE CONCRETE DOES NOT EXCEED 1000 PSI.
7. SEE PLAN VIEW SHEET 3 OF 6 FOR LOCATIONS OF CONCRETE THRUST BLOCKS.
8. CONSTRUCT THRUST BLOCKS IN ACCORDANCE WITH WSSC STANDARD SPECIFICATION SECTION 03300.
9. REPLACE ALL DISTURBED SOIL ON EACH SIDE OF THE THRUST BLOCK WITH CRUSHED STONE COMPACTED AS
STRUCTURAL FILL.
WELDED-ON THRUST
COLLAR TO BE DESIGNED &
FABRICATED BY PIPE
MANUFACTURER TO CARRY
DESIGN THRUST OF 'F' KIPS MIN.
DIAM. = PIPE O.D. + 2"
R2 BARS, EA FACE
REINFORCED CONCRETE
THRUST COLLAR
PROP. WATER
MAIN (D.I.P.)
ALL DISTURBED SOIL TO BE REPLACED
BY COMPACTED CRUSHED STONE
R1 BARS, EA FACE
APPLICATION POINT OF PLAN
STATION FOR THRUST COLLAR
1'-0" OF COMPACTED #57 CRUSHED STONE
ALL DISTURBED SOIL TO BE
REPLACED BY COMPACTED
CRUSHED STONE
R3 BARS AROUND
PIPE EACH FACE
2" CL. (TYP.)
3" CL. (TYP.)
R1A BARS @ EACH FACE (TYP.
ABOVE AND BELOW D.I.P)
R2A BARS @ EACH
FACE (TYP. EACH
SIDE OF D.I.P)
3" CL. (TYP.)
200'S
CONTRACT NO. BT7171B21
202NE14
ENGINEER:THESE DOCUMENTS CONTAIN
PRIVILEGED AND CONFIDENTIAL
INFORMATION WHICH SHALL NOT
BE REDISTRIBUTED WITHOUT
PRIOR WSSC APPROVAL
NAME: JOHNSON, MIRMIRAN & THOMPSON
ADDRESS: 40 WIGHT AVENUE, COCKEYSVILLE, MD 21030
PHONE: (410) 329-3100
CONTACT : STEVEN PICKEL, PE
QUEEN ANNE ELECTION DISTRICT NO. 7
PENN MANOR LANE LARGE VALVE VAULT REPLACEMENT
BOWIE, PRINCE GEORGE'S COUNTY, MD 20716
VE
R
IF
Y
SC
AL
E
- B
AR
IS
O N
E
IN
C H
O N
O R
IG
IN
AL
D
R
AW
IF
N
O T
O N
E
IN
C H
O N
T H
IS
S
H
EE
T, A
D
JU
ST
S
C
AL
ES
A
C C
O R
D
IN
G
LY
HHG: 355
LHG: 281
PRESSURE ZONE= 317A
WESTERN BRANCH MINI DRAINAGE BASIN NO. 130
WASHINGTON SUBURBAN SANITARY COMMISSION
WSSC
DELIVERING THE ESSENTIAL
PA
TH
XX/XX/XX - PLOT DATE
PROFESSIONAL CERTIFICATION
I HEREBY CERTIFY THAT THESE DOCUMENTS
WERE PREPARED OR APPROVED BY ME,
AND THAT I AM A DULY LICENSED
PROFESSIONAL ENGINEER UNDER
THE LAWS OF THE STATE OF MARYLAND.
NAME: STEVEN PICKEL, P.E.
LICENSE NO.: 50329
EXP. DATE: 12/18/2026
PENN MANOR LANE
TE
M
PL
AT
E
LA
YO
U
T C
U R
R
EN
T as o f:
/1
4/
\\j m t.c or p.
lo ca l\j m td fs
\2
0\
7_
5_ W oo dy ar d_
R oa d_ La rg e_
\C
AD
D \C
IV
IL
\P en n M an or
\D
ET
AI
LS
.d w g
OF 6
NO
WSSC Erosion and Sediment Control Approval Note This plan has been approved per requirements in the:
Standard Procedures of the WSSC Regulations for Utility Erosion and Sediment Control, Section V, Paragraph A.
Reviewed by:_________________________________________
Date:__________________ Plan No.______________________
DATE REVISIONS
DATE PROJECT MANAGER
WATER INFRASTRUCTURE SECTION
DETAILS 5
NAME: CHRISTOPHER KARG, P.E.
LICENSE NO.: 58577
EXP. DATE: 12/07/2027
Docusign Envelope ID: B7C40696-C70F-49BC-81DD-AF032F73758F
Dec 1, 2025 | 9:15 AM EST
BT7171B21Dec 2, 2025 | 10:03 AM EST
Dec 2, 2025 | 10:31 AM EST
Docusign Envelope ID: CECE829B-00F5-823D-8236-71A8476DA446
Jun 5, 2026 | 8:23 PM EDT Jun 6, 2026 | 10:37 PM EDT
WASHINGTON SUBURBAN SANITARY COMMISSION W.S.S.C.
CONTRACT
UTILITY CONSTRUCTION DRAWING NO. S.C.1
SEDIMENT CONTROL DETAILS FOR
REVISED OCTOBER 2023
BT7171B21
SC-1
SC-1
| BT7171B21_01 |
| COVER-Layout1 |
| BT7171B21_02 |
| GENERAL NOTES-Layout1 |
| BT7171B21_03 |
| PENN MANOR PLAN-Layout1 |
| BT7171B21_04 |
| PROFILE-Layout1 |
| BT7171B21_05 |
| DETAILS-Layout1 |
| BT7171B21_06 |
| PENN MANOR MOT-MOT |
| 2026-08-07T07:34:41-0700 | |
| Digitally verifiable PDF exported from www.docusign.com |
File details come from the government source that posted it. Updated .