PG&E_Trench_Packet.pdf

PDF 273 KB Posted

Attached to
River Park Electrical Relocation
Solicitation number
PK-26-15096-QB
Issued by
Santa Cruz County, California

About this file

This is a technical specification document issued by Pacific Gas and Electric Company (PG&E) detailing requirements for overhead and underground panel board construction for electrical service installations. The document, revised June 30, 2023 (Revision 16), establishes comprehensive standards applicable to residential, commercial, and agricultural service installations served from PG&E's lines. It provides detailed specifications for construction materials, dimensions, footing requirements, fasteners, clearances, and grounding procedures. The specifications cover wood and metal post materials, board and panel dimensions ranging from 48 to 96 inches in length with heights between 36 and 42 inches, concrete footing requirements with minimum 36-inch depth, and conduit installation requirements including sweep radius recommendations of 10 feet per inch of conduit diameter and minimum 24-inch bend radius for service and secondary conduit. The document includes seven figures illustrating typical panel board constructions for both underground and overhead installations, along with a material list table identifying 23 items to be furnished and installed by the customer, including pull boxes, metering equipment, conduit, posts, and grounding components.

The specifications establish mandatory construction standards to ensure safety, durability, and compliance with PG&E operational requirements. All wood materials must be pressure-treated on all surfaces, while metal components require galvanized steel or stainless steel construction with rust inhibitors. The document requires minimum 36 inches of clear working space in front of panel structures, meter heights between 60 and 75 inches measured from final grade to center, maximum equipment height of 84 inches from ground, and minimum 6 inches ground clearance for all equipment. For underground services exceeding 100 feet, a pull box must be installed between 6 and 30 feet from the panelboard. The specifications reference compliance with the National Electrical Code (NEC), local ordinances, and specific PG&E documents including the Electric and Gas Service Requirements Manual (Greenbook) and Electric Meter Work Practices (EMWP). This document directly applies to the River Park Electrical Relocation project in Watsonville, California, which involves removal of existing electrical service and construction of new PG&E electrical service at 100 East Front Street.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONDUIT, TRENCHING & BACKFILL:

- 4" OF SAND IS REQUIRED ABOVE & BELOW CONDUIT IF NATIVE SOILE IS NOT FREE OF

ROCKS, HARDPAN, ETC. BACKFILL SHALL MEET APPROVAL OF PG&E INSPECTOR

- SERVICE CONDUIT: 063928, PAGE 2 TABLE 1, 2 & 3 (COMMERCIAL / INDUSTRIAL)

- PROVIDE LONG CONDUIT SWEEPS WHERE INDICATED. RECOMMEND SWEEP RADIUS

(10' OF RADIUS PER INCH OF CONDUIT DIAMETER) EX: 4" CONDUIT = 40' RADIUS

- INSTALL 24" MINIMUM BEND RADIUS FOR SERVICE AND SECONDARY CONDUIT

REQUIRED PERMITS

OH: Services UG-1: Services

Greenbook

EMWP

Rev. #16: 6/30/2023 065374 Page 1 of 9

Daniel Jantz (DWJ7)

065374

Function:Asset Type:

Issued by: Date: 6/30/2023

Rev. #16: This document replaces PG&E Document 065374, Rev. #15. For a description of the changes, see Page 9.

OVERHEAD AND UNDERGROUND PANEL BOARD CONSTRUCTION

Prepared by: SXZO

DesignElectric Metering

This document also is included in the following manuals:

• Electric and Gas Service Requirements Manual (Greenbook)

• Electric Meter Work Practices (EMWP)

References Location Document Requirements for Customer-Owned Poles OH: Services/Greenbook 025055 Location, Clearances, and Mechanical Protection Details for Pad-Mounted and Subsurface Equipment UG-1: General/Greenbook 051122 Voltage Stabilizer for 480 Volt, Three-Phase, 3-Wire Ungrounded Service OH: Meters/EMWP 052497 Agricultural Underground Service, 500 hp or Less UG-1: Services/Greenbook 054619 Agricultural Overhead Service, 300 hp or Less OH: Services/Greenbook 058087

Purpose and Scope

This document illustrates the requirements applicable to residential, commercial, and agricultural overhead or underground service installations served from PG&E’s lines. This document is applicable where panel-type structures are used to mount customer-owned and installed equipment.

General Information

1. Construction Materials and Requirements

Ensure that all posts and panels on which the service and metering equipment are mounted meet the following minimum requirements. Equipment can be mounted to a panel, boards, or struts. See Note 5 on Page 3 for the maximum rating of service termination equipment.

A. Material Treatment and Specifications

(1) Ensure that the surface areas on all wood posts, boards, and solid panels are pressure treated, including the sides and areas that have been cut. Any other treating process that provides an equivalent penetration and retention must be approved by PG&E. Acceptable wood preservatives are water-borne salts and pentachlorophenol. Brush application of wood preservatives is ineffective and therefore unacceptable.

(2) Pipe posts must be galvanized rigid steel.

(3) All metal boards or solid metal panels must be rigid steel and have a rust inhibitor applied to all surface areas.

(4) Strut channels, fittings, and associated hardware must be stainless steel or galvanized steel.

http://www/techlib/default.asp?body=manuals/greenbook/ http://www/techlib/default.asp?body=manuals/elec_meter_work_practices/ http://wwwedm3/cgi-bin/getdocTDM.asp?itemid=981550065 http://wwwedm3/cgi-bin/getdocTDM.asp?itemid=981550065 http://wwwedm3/cgi-bin/getdocTDM.asp?itemid=981550065 http://wwwedm3/cgi-bin/getdocTDM.asp?itemid=981900029 http://wwwedm3/cgi-bin/getdocTDM.asp?itemid=981900029 http://wwwedm3/cgi-bin/getdocTDM.asp?itemid=981900029 http://wwwedm3/cgi-bin/getdocTDM.asp?itemid=981900029 http://wwwedm3/cgi-bin/getdocTDM.asp?itemid=981830029 http://wwwedm3/cgi-bin/getdocTDM.asp?itemid=981830029 http://wwwedm3/cgi-bin/getdocTDM.asp?itemid=981830029 http://wwwedm3/cgi-bin/getdocTDM.asp?itemid=981830029 http://wwwedm3/cgi-bin/getdocTDM.asp?itemid=981900043 http://wwwedm3/cgi-bin/getdocTDM.asp?itemid=981900043 http://wwwedm3/cgi-bin/getdocTDM.asp?itemid=981900043 http://wwwedm3/cgi-bin/getdocTDM.asp?itemid=981600029 http://wwwedm3/cgi-bin/getdocTDM.asp?itemid=981600029 http://wwwedm3/cgi-bin/getdocTDM.asp?itemid=981600029

Greenbook

EMWP

Overhead and Underground Panel Board Construction

Rev. #16: 6/30/2023065374 Page 2 of 9

General Information (continued)

B. Material Dimensions

(1) Structure: All structures must be a minimum length of 48 inches. For structures up to 72 inches long, the minimum combined height of the boards, panel, or struts must be 36 inches. For structures up to 96 inches long, the minimum combined height of the boards, panel, or struts must be 42 inches. For structures with lengths greater than 96 inches, use additional posts. The top of the structure must not exceed 84 inches high from the ground. There must be a minimum of 6 inches of clearance between the ground and all equipment, panels, boards, or struts.

(2) Boards: Place side by side.

(a) Wood: Minimum 2 inches thick by 12 inches wide (nominal).

(b) Metal: Minimum 1/2 inch thick by 12 inches wide.

(3) Panel: One solid sheet.

(a) Wood: 1 inch thick.

(b) Metal: 1/4 inch thick.

(4) Unistrut: At a minimum, two struts are needed to support each piece of service and metering equipment. It is recommended that one strut be attached towards the top and one strut be attached towards the bottom of the equipment. Add struts for additional equipment with different length dimensions. Use struts with or without boards or panels.

(a) Strut channel dimensions must be a minimum 1-1/2 inch x 1-1/2 inch. See Figure 10 on Page 8.

(5) Posts: Use a minimum of two posts to support panel-type construction. Add more posts if the construction exceeds the structural dimensions listed in Note 1B(1) on Page 1. If applicable, a PG&E-approved, customer-owned pole can be used as one of the posts. The customer-owned pole must be installed in accordance with Document 025055 and the panel board must be attached to the poles as shown in Figures 8 on Page 5 and Figure 10 on Page 8.

(a) Wood: Solid.

(i) Square, 6 inches by 6 inches cross section.

(ii) Round, 8 inches in diameter.

(b) Metal: Solid or hollow. If hollow a permanent post cap is required.

(i) Square, 3 inches by 3 inches cross section.

(ii) Round, 3 inches in diameter.

C. Footing and Support

(1) Place all posts in the center of a 12 inches minimum diameter concrete footing. Extend the footing a minimum of 36 inches into the ground (excluding gravel bedding), a minimum of 4 inches above ground level, and have a 1/2 inch slope away from the post to allow for drainage.

D. Fasteners

(1) For wood posts, use minimum 3/8 inch x 5 inches lag screws.

(2) For metal posts, use 3/8 inch minimum through bolts with nuts and washers.

(3) For Unistrut, use approved fasteners and hardware made for the strut channels. This should include through bolts with nuts and washers.

E. Screw Holes or Openings

(1) All unused or exposed screw holes and openings must be tightly secured by plugging or filling the entire hole with screws, bolts, or other type of metal fasteners. Sealants can be used along with the screws, bolts, and other metal fasteners.

F. Clearances and Barrier Posts (see Document 051122)

(1) A minimum 36 inches of clear and level working space must be maintained in front of the panel board structure at all times.

http://wwwedm3/cgi-bin/getdocTDM.asp?itemid=981550065 http://wwwedm3/cgi-bin/getdocTDM.asp?itemid=981900029

Greenbook

EMWP

Overhead and Underground Panel Board Construction

Rev. #16: 6/30/2023 065374 Page 3 of 9

(2) If any part of the panel board structure is located within 36 inches of a thoroughfare or road, then install barrier posts. If the thoroughfare or road has high vehicular traffic and the panel board structure is less than 108 inches (9 feet) away, then install barrier posts.

(3) The panel board and customer owned pole (if installed) must not be located less than 10 feet from the surface of the PG&E pole or within 10 feet of the vertical plane of a PG&E line.

2. Grounding

The customer is responsible for bonding and grounding metering and service termination equipment enclosures.

See the requirements in Greenbook Section 5.8. Grounding, including Figures 5−15 and 5−16. Also Ground and bond in accordance with the National Electrical Code (NEC) and local ordinances. PG&E prefers, but does not require, the grounding electrode conductor wire to be protected against physical damage by rigid steel conduit or armored cladding

3. A voltage stabilizer for 3-wire service will be furnished and installed by PG&E (see Document 052497).

4. Properly identify and mark meters as described in Section 5.5.1 on Page 5-10 of the Electric and Gas Service Requirements Manual (Greenbook).

5. Termination or metering equipment with an ampacity rating greater than 400 amps, 1-phase or 3-phase must be pad-mounted (free standing). Refer to Electric and Gas Service Requirements Manual (Greenbook), Section 9.10.

6. The minimum meter height for electric panels with current transformers (CT’s) is 60 inches as measured from final grade to the center of the meter. The maximum meter height is 75 inches.

7. Enclosure: For services greater than 100 feet install a pull box between 30 feet maximum and six feet minimum away from the Panelboard. See document 028028 Secondary Electric Underground Enclosures for the required minimum size enclosure to install.

http://wwwedm3/cgi-bin/getdocTDM.asp?itemid=981830029 http://www/techlib/default.asp?body=manuals/greenbook/default.asp http://www/techlib/default.asp?body=manuals/greenbook/default.asp http://www/techlib/default.asp?body=manuals/greenbook/ http://wwwedm3/cgi-bin/getdocTDM.asp?itemid=981900015

Greenbook

EMWP

Overhead and Underground Panel Board Construction

Rev. #16: 6/30/2023065374 Page 4 of 9

Typical Panel Board Construction

Notes

1. See Table 1 on Page 8 for the material list.

2. Item 2 may be replaced by Items 1 and 3.

3” Min. Galv. Rigid Steel Pipe or 6” x 6” or 8” Dia. Wood Post (see 1.B.(5) on Page 2)

Concrete Footing

36” Min.

Height

36” Min.

4” Min.

Figure 1 Panel Board Construction With Struts

12” Min.

6” Min. Ground Clearance to Equipment or Panels

1/2” Slope

84” Max.

Height

42” Min.

Height

Figure 2 Large Panel Board Construction With Struts

6” Min. Ground Clearance to Equipment or Panels

36” Min.

4” Min.

See 1.B.(1) on Page 2

1/2” Slope

See Note 1D on Page 2 for Fasteners

84” Max.

Height

48” - 72” Length

48” − 96” Length

See Note 1D on Page 2 for Fasteners

Panels, Boards, or Struts

42” Min.

Height

3” Min. Galv. Rigid Steel Pipe or 6” x 6” or 8” Dia. Wood Post

6” Min. Ground Clearance to Equipment or Panels

36” Min.

4” Min.

36” Min.

1/2” Slope

Panels, Boards, 36” Min.

Height

84” Max.

Height 4”

Min.

36” Min.

Concrete Footing

See 1.B.(1) on Page 2

1/2” Slope

12” Min.

6” Min. Ground Clearance to Equipment or Panels or Struts

Figure 3 Panel Board Construction

Figure 4 Large Panel Board Construction

84” Max.

Height

48” - 72” Length

48” - 96” Length

Greenbook

EMWP

Overhead and Underground Panel Board Construction

Rev. #16: 6/30/2023 065374 Page 5 of 9

Typical Underground Panel Board Construction

As Required See Document 063927 or Document 0639281

Figure 5 Underground Service With Second Meter Panel

30’ Max − 6’ Min.

Note: This type of configuration is acceptable for mounting multiple meters.

See Note 7 on Page 3 and Table 1 Footnote on

6” Min.

Increase Trench Depth to Accommodate for the Vertical Radial Bend

Note: See Figure 7 on Page 6 for an al-ternate elbow & cou-pling Option

Voltage Stabilizer

Voltage Stabilizer Alternate Location

To Load

Control Equipment

2 3 4

8 9

Figure 6 Underground Service Using Panel Board Construction

As Required See Document 063927 or Document 063928

See Note 3 on Page 3

See Note 6 on page 3

6” Min.

Increase Trench Depth to Accommodate for the Vertical Radial Bend

30’ Max − 6’ Min.

See Note 7 on Page 3 and Table 1 Footnote on

Note: See Figure 7 on Page 6 for an al-ternate elbow & cou-pling Option http://wwwedm3/cgi-bin/getdocTDM.asp?itemid=981900047 http://wwwedm3/cgi-bin/getdocTDM.asp?itemid=981900041 http://wwwedm3/cgi-bin/getdocTDM.asp?itemid=981900047 http://wwwedm3/cgi-bin/getdocTDM.asp?itemid=981900041

Greenbook

EMWP

Overhead and Underground Panel Board Construction

Rev. #16: 6/30/2023065374 Page 6 of 9

Figure 7 Alternate Option − PVC Elbow (Item 23) &

Plastic−to−Steel Adapter / Coupling (Item 20)

6” Min.

Increase Trench Depth to Accommodate for the Vertical Radial Bend

A support structure is required 6 inches minimum to 12 inches maximum above grade for coupling support. The support must be the same type (strut or treated board) as the rest of the panel board

12” Max.

Greenbook

EMWP

Overhead and Underground Panel Board Construction

Rev. #16: 6/30/2023 065374 Page 7 of 9

Typical Overhead Panel Board Construction

Figure 8 Overhead Service With Second Meter Panel

Note: This type of configuration is acceptable for mounting multiple meters.

13 14

See Note 6 on page 3

Control Equipment

See Note 3 on Page 3

Alternate Location

4 7

Figure 9 Overhead Service Using Panel Board Construction

18 17

See Note 6 on page 3

Voltage Stabilizer

Do Not Offset Conduit More Than 12 Inches

Greenbook

EMWP

Overhead and Underground Panel Board Construction

Rev. #16: 6/30/2023065374 Page 8 of 9

Figure 10 Typical Strut Channels Used for Panel Board Construction

1-1/2” Min.

1-1/2” Min. 1-1/2” Min.

1-1/2” Min.

Table 1 List of Material To Be Furnished and Installed by Customer

Item Description

1 Underground Pull Box, Required 1

2 Self-Contained, Bused Safety Socket Box

3 Combination Meter and Current Transformer Cabinet (See Note 6 on Page 3)

4 Main Switch of Service Equipment Enclosure

5 Service Conduit, As Required

6 UG Panel Board Construction (See Figures 5 − 6)

7 OH Panel Board Construction (See Figures 7 − 8)

8 Post (See Note 1 on Page 1)

9 Conduit, Riser, Galvanized Rigid Steel, Continuous without Couplings

10 Ground Rod (See Note 2 on Page 3)

11 Ground Wire, Copper, Bare

12 Ground Clamp (As Required) for Item 10

13 Sealable Gutter

14 Metal Myers Hub With Close Nipple

15 Heavy Duty 2-Hole Pipe Strap Every 36”

16 PVC Schedule 40, minimum

17 Weatherhead

18 PG&E-Approved, Customer-Owned Pole

19 Termination Enclosure

20 Plastic−to−Steel Adapter/Coupling

21 Conduit, Bend, Galvanized Rigid Steel, Continuous without Couplings

22 Service Conduit, Coupling, As Required

23 Conduit, Bend, PVC, Continuous without Couplings

1 The pull box is required to be installed but may be exempt only at the discretion of the PG&E inspector.

Greenbook

EMWP

Overhead and Underground Panel Board Construction

Rev. #16: 6/30/2023 065374 Page 9 of 9

Revision Notes

Revision 16 has the following changes:

1. Revised Note 5 on Page 3.

File details come from the government source that posted it. Updated .