This document is an Addendum No. 3 issued by Paragon Consulting Group, Inc. on behalf of the City of Griffin, Georgia for the Poplar Street Bridge Repair Bid #24-011. The addendum provides clarification on the availability of a laydown/storage area for materials near the work site. Specifically, the Griffin-Spalding County Land Bank Authority has agreed to allow the selected contractor to use two parcels located at 435 W. College Street and 437 W. College Street, approximately 0.10 miles west of the railroad track, as a laydown and storage area for the project. The contractor will be responsible for removing vegetation from the area and restoring it upon completion of the project. Additionally, a supplemental drawing, SD-2, has been attached to the addendum and incorporated into the contract documents.
The Poplar Street Bridge Repair project involves excavation, cleaning, and repair of fourteen bridge H-piles, including painting, encasement, and backfill. It also requires the removal of the asphalt overlay and seal to expose existing joints for placement of new header material and repair of steel angle, plate, or rail as directed by the Engineer. The contractor will also be responsible for the placement of new backer rod and seal for each joint.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CITY OF GRIFFIN
POPLAR STREET BRIDGE REPAIR
BID # 24-011
FROM: PARAGON CONSULTING GROUP, INC.
350 AIRPORT ROAD
GRIFFIN, GA 30224
TO: ALL BIDDERS OF RECORD
RE: Addendum No. 3, dated May 24, 2024
This Addendum forms a part of the Contract Documents and modifies the original Bidding
Documents dated April 2024.
This Addendum consists of one (1) page and one (1) Supplemental Drawing.
CONTRACT DOCUMENTS AND SPECIFICATIONS
Add. 3.1 Contractor Question: Does the City have a laydown location for materials near the work area?
Response: The Griffin-Spalding County Land Bank Authority has agreed to allow the selected contractor to use the parcels at 435 W. College Street and 437 W.
College Street as a laydown/storage area for the project. The parcels are approximately 0.10 mile west of the railroad track. Attached supplemental drawing SD-2 shows the location of the parcels in relation to the intersection of the railroad track and W. College Street, which is the location the contractor will use to access the underside of the bridge. The contractor is responsible for removal of vegetation from the laydown area to make it usable and for grassing and mulching the disturbed area upon completion of the project. The contractor is solely responsible for any items stored at this location during the course of the project.
Add. 3.2 Modification: Drawing SD-2 is attached to this addendum and becomes a part of the Contract Documents.
End of Addendum No. 3
SD-2
Project No.
PCG3152-22059
Issue Date:
MAY 2024
Checked By:
BKU
Drawn By:
JBGP N
C
ORA
O N S U L T I N G G R O U P
POPLAR STREET BRIDGE REPAIR
LAYDOWN/STORAGE AREA