Attachment_13_Solution_Delivery_Framework_SOP_v5.pptx
PPTX presentation 188 KB Posted
- Attached to
- Peace Corps Learning Management System Federal contract opportunity
- Solicitation number
- PC-17-Q-030
- Issued by
- Peace Corps
About this file
Attachment 13 Solution Delivery Framework
View the file
Other files for this federal contract opportunity
Show all 19
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 13 – Solution Delivery Framework (SDF)
Standard Operating Procedures (SOP) Solution Lifecycle The lifecycle of a solution begins with a project request and ends with retirement or replacement..
The following slides will outline how the Project Sponsor, Project Manager, and Operations Manager will plan, build, deploy, manage, and retire applications within the overall OCIO application paradigm.
The “Procedure Legend” below defines the diagram notation used in the following slides:
PROCEDURE LEGEND
Phase/Activity Start Middle Phase/Activity End of Lifecycle
Resource Milestone
Phase/Activity Input
Phase/Activity Output
Control Gate
Recurring Activity
Termination Point
Standard Operating Procedures (SOP) Solution Delivery Framework (SDF) Delivery (SDF) Maintenance (O&M) Disposition
Development of solutions within the Peace Corps are managed according to a strict framework. The lifecycle of an solution begins with a Request, or Concept Proposal. This concept proposal is presented to the Technology Advisory Board (TAB) and if approved, moves into the Solution Delivery Framework (SDF). Once approved, the idea is transformed into an active project, and an actionable Project Management Plan is developed which dictates how requirements are identified, and how the application will be developed, tested and deployed. This Delivery Phase is explained in the approved Peace Corps’ SDF.
The output of the SDF is the solution and attendant Operations & Maintenance Plan, which dictates the system’s architecture, configurations, roles, ownership, and procedures for upgrades, patches, and change requests. This document outlines the activities and management structure of the application during the Maintenance Phase.
The final phase of any application’s lifecycle is the Disposition Phase. The disposition phase manages the formal retirement of the system. The disposition shall be managed similar to a regular project (according to the SDF), with or without a replacement system, with the Disposition Plan acting as the project’s charter. Once the system is identified as a candidate for retirement, the Disposition Plan drafted by the O&M Manager will outline the required activities in order to successfully retire/replace the application.
Retirement
Project Manager Assigned Project Manager Assigned
Request Termination SDF: Request
IPT
Approval
Initiation N
Termination
Initiation Planning & Requirements Design Development Integration & Test Deployment Closeout
BAM/Requestor develops Concept Proposal elaborating upon PRF
Concept Proposal CIO IPT provides input and vets Concept Proposal including budget BAM/Requestor presents Concept Proposal to TAB
Concept Review (TAB) BAM/Requestor presents PRF to CIO IPT
TAB
Approval PM updates Project SharePoint site with status and Artifacts
PRF Review (IPT)
OCIO PM Assigned PM updates Project SharePoint site with Status and Artifacts Project placed in Approved Backlog Y Approved, Pending N Approved, Active Requestor develops Project Request Form (PRF)
Project Request Form
BAM/Requestor presents PRF to TAB
PRF Review (TAB)
TAB
Approval Y
PM prepares the Project Charter SDF: Initiation PM updates Project SharePoint site with status and artifacts
Requirements & Planning
Request Initiation Planning & Requirements Design Development Integration & Test Deployment
PM identifies Project Team members
Concept Proposal
Project Team establishes scope and defines high-level requirements PM presents Project Charter to CIO IPT
Initiation Review (IPT) PM conducts project kick-off meeting with Project Team
Project Charter PMO Manager reviews Project Charter
SDF: Planning & Requirements PM updates Project SharePoint site with Status and Artifacts
Development Type?
Design Waterfall Development Agile Development Go to Slide 7
Design, Develop, Test Go to Slide 11
Request Initiation Planning & Requirements Design Development Integration & Test Deployment
PM prepares PMP and Tailoring Guide
Project Charter
PMP, Tailoring Guide
PM assigns development of requirements to business analysts and technical SMEs Business analysts conducts requirements elaboration sessions Technical SMEs develop non-functional requirements PM presents Requirements Document and schedule to IPT
Requirements Review (IPT)
IPT
Approval Y N Project team documents detailed requirements PM develops schedule
Schedule PM initiates procurement activities
Requirements Document
Waterfall Development
SDF: Design (Waterfall) PM manages development of system design to meet requirements
Requirements Document
PM schedules Design Review for next CIO IPT PM briefs SDD to CIO IPT
Design Review Requirements and Design Documentation baselined and development scope set PM updates Project SharePoint site with Status and Artifacts
Development Developers document design in the System Design Document (SDD)
SDD
Initiation Planning & Requirements Design Development Integration & Test Deployment
SDF: Development (Waterfall) PM manages development against baselined Requirements and SDD
Requirements and SDD PM manages updates to project documentation PM provides Status Reports during weekly recurring IPTs
Updated Req. and SDD Tester builds Test Cases & Scripts based on the finalized requirements PM completes Test Readiness Review (TRR) Checklist PM schedules a TRR for the next CIO IPT PM briefs TRR to IPT
TRR (IPT)
Test Cases PM updates Project SharePoint site with Status and Artifacts
Integration & Test
Test Readiness Checklist
Initiation Planning & Requirements Design Development Integration & Test
SDF: Integration & Test (Waterfall) System and Security Testing begins
Tester updates Test Cases for User Acceptance Testing (UAT)
Pass Fail
Bug/Defect Fixes by Development Team
Test Results PM schedules UAT
Updated Test Cases Bug/Defect Fixes by Development Team PM manages UAT
UAT
Acceptance N PM completes Deployment Readiness Review (DRR) Checklist Y PM schedules DRR with IPT
Deployment Go to Slide 12
Request Initiation Planning & Requirements Design Development Integration & Test Deployment Closeout
Pass Fail PM briefs DRR to IPT
Deployment Review (IPT)
DRR Checklist
Agile Development
SDF: Design, Develop, Test (Agile)
Pass Fail Project Team continuously engages stakeholders to refine and capture required functionality Sprint Demo & Incremental Release Project Team conducts Sprint 0 – creating skeleton design of the solution Business Analyst decomposes requirements into User Stories and establishes Product Backlog Developers work against items in Sprint backlog
Tester prepares Test Cases/Scripts for each User Story Conduct Component and Security Testing Project Team conducts final UAT or demo
Test Results PM completes Deployment Readiness Review (DRR) Checklist
Additional Reqts P F
Request Initiation Planning & Requirements Design Development Integration & Test Deployment Closeout
Product Owner determines scope of upcoming Sprint
Y
DRR Checklist
PM briefs DRR to IPT
Deployment Review (IPT)
Updated Req. and SDD
SDF: Deployment PM/Requestor finalizes Operations & Maintenance Plan and Training Plan PM schedules Deployment
CCB
Approval PM presents O&M Plan and Training Documents to CIO IPT PM conducts planning and coordinates installation
Y
O&M and Training Plan Project deployed to production and handed off to O&M
O&M
Go-Live Review (IPT)
Initiation Planning & Requirements Design Development Integration & Test Deployment
PM submits Change Request (CR), Deployment Plan, Testing Results to Change Control Board (CCB)
SDF: Closeout PM/Requestor conducts Lessons Learned meeting with project team PM prepares Project Closeout Form PM presents Project Closeout Form to IPT PM updates and finalizes Project SharePoint site with Status and Artifacts
Project Closeout Form Project results presented to TAB
SDF Phase Complete PM formally releases OCIO resources back to respective directorates
Post Implementation Review
Initiation Planning & Requirements Design Development Integration & Test
Project Ends
Maintenance Phase Operations & Maintenance (O&M)
Maintenance Lifecycle
O&M Plan
Service Level Agreements (SLA)
Application Corrections / Bug Fix
Refresh/Updates/Patches
User/System Administration
Technical Maintenance
Disposition Plan
O&M Manager Assigned
Disposition Approval (TAB)
Delivery (SDF) Disposition
Quarterly Status Reports (TAB)
Recurring User Training The final output of the SDF is the Operations and Maintenance Plan, which dictates the system’s architecture, configurations, roles, ownership, and procedures for upgrades, patches, and change requests. This document outlines the activities and management structure of the application during the Maintenance Phase.
The Maintenance phase of the project is facilitated by an assigned O&M Manager from within the OCIO. The O&M Manager oversees aspects of the application’s uptime, bug fixes, patches, upgrades, maintenance, reporting and user training.
Any request for additional functionality of the project would have to be managed as a new project request, and the final Output of the SDF would be to update the applications current O&M Plan and a code merge.
At the stage when an application is identified for retirement, the O&M Manager will draft the Disposition Plan, and brief it to the TAB. On acceptance, the Maintenance phase will end, and the Disposition plan will begin.
Disposition Phase Solution Retirement
Maintenance Lifecycle
Disposition Plan
Project Management Plan
PM Assigned
PMP Approval (IPT) Delivery (SDF) Disposition The Final phase of any application’s lifecycle is the Disposition Phase. The disposition phase manages the formal retirement of the system. The disposition shall be managed similar to a regular project (according to the SDF), with or without a replacement system, with the Disposition Plan acting as the project’s charter. Once the system is identified as a candidate for retirement, the Disposition Plan drafted by the O&M Manager will outline the required activities in order to successfully retire/replace the application.
Once the Disposition Plan is approved by the TAB, a PM is assigned, and creates a Project Management Plan which supports the activities described in the Disposition Plan.
On approval from the IPT, the PM manages assigned project resources against the PMP to retire/replace the system. This effort can be a part of, or in conjunction with, another project replacing the legacy system.
Once complete and the application is retired, the PM will update the project SharePoint site, and archive project related documentation.
Resources Assigned
Project Retirement image2.png image1.png