The document is the Paving Plans for the Seven Mile Lane Left Turn Lane Paving project in Linn County, Oregon. The project involves asphalt paving, widening, and overlay work along Seven Mile Lane, with a total project length of 2,225 feet. The work is to be completed in April 2024 and includes items such as 4-inch asphalt pavement, 2-inch asphalt overlay, and driveway approaches. The project is being solicited through an Invitation to Bid (ITB) by Linn County, with the City of Albany also involved as a jurisdiction.

The project requires a 2-inch asphalt overlay, cold plane pavement removal, and asphalt widening plug work. Pricing terms, set asides, and funding sources are not explicitly stated in the document. Contractors will need to review the full ITB for additional details on pricing, bidding requirements, and contract terms.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

are set forth in OAR 952-001-0010 through OAR 952-001-0090. You may obtain a copies of the rules by calling the center. (Note: the telephone number for the Oregon Utility Notification Center is (503) 232-1987.)

Oregon law requires you to follow rules adopted by the Oregon Utility Notification Center. Those rules

N

O ATTENTION: CE

Asphalt Paving

SEVEN MILE LANE

LEFT TURN LANE PAVING

SEVEN MILE LANE

LINN COUNTY

APRIL 2024

SHEET INDEX

SHEET 1 COVER SHEET

DATE: REVISION: BY:

SCALE: no scale

SEVEN MILE LANE

LEFT TURN LANE PAVING

SEVEN MILE LANE

LINN COUNTY

APRIL 2024

E-MAIL: Roads@co.linn.or.us

FAX: (541) 924-0202

PHONE: (541) 967-3919

ROAD DEPARTMENT

ALBANY, OREGON 97322

3010 FERRY STREET SW

LINN COUNTY COMMISSION

WILLIAM TUCKER

SHERRIE SPRENGER

ROGER NYQUIST

CHAIRMAN

COUNTY

COUNTY ENGINEER

ROADMASTER

WAYNE E. MINK, P.E.

DAINEAL L. MALONE, P.E. SHEET 1

COVER SHEET

DA I NEAL LEAH MALONE

RE

GISTERED PROFESSIONALE NG I N E ER

Ma y 2 3 , 2 0 13

76365

OREGON

RENEWS: 12/31/2024

PROJECT LOCATION

OVERALL PROJECT LENGTH: 2,225 FT

E

E

SITE

DATE:ROAD NO:

DRAFTED BY: REVIEWED BY:

TRS:

03/12/2024CR0011

T11S R3W SEC33, 34, W.M.

d.malone

PROJECT NO: CR1704

SHEET 2 PLAN SHEET STA: -0+50 TO STA: 11+25

SHEET 3

PLAN SHEET STA: 11+25 TO STA: 15+75

RIGHT OF WAY

CENTERLINE

EXISTING EDGE OF PAVEMENT

SAW CUT

4" ASPHALT PAVEMENT WIDENING PLUG

2" ASPHALT PAVEMENT OVERLAY

4" ASPHALT PAVEMENT DRIVEWAY

COLD PLANE PAVEMENT REMOVAL

(2" TO 0" DEPTH)

AGGREGATE BASE AND SHOULDER

(INSTALLED BY OTHERS)

LEGEND

SHEET 4 PLAN SHEET STA: 15+75 TO STA: 21+75 AND

TYPICAL SECTIONS

PROJECT SITE

d.leard

AutoCAD SHX Text

LINN COUNTY ROAD DEPARTMENT

AutoCAD SHX Text

LINN COUNTY ROAD DEPARTMENT

AutoCAD SHX Text

NOTICE NOTICE NOTICE NOTICE

AutoCAD SHX Text

NOTICE NOTICE NOTICE NOTICE

AutoCAD SHX Text Units

AutoCAD SHX Text English

AutoCAD SHX Text NOTICE NOTICE NOTICE NOTICE NOTICE NOTICE NOTICE NOTICE NOTICE NOTICE NOTICE NOTICE

AutoCAD SHX Text Don't be a Weak Link

AutoCAD SHX Text N

AutoCAD SHX Text O

AutoCAD SHX Text T

AutoCAD SHX Text I

AutoCAD SHX Text C

AutoCAD SHX Text E

AutoCAD SHX Text Think SAFETY!

AutoCAD SHX Text N

AutoCAD SHX Text O

AutoCAD SHX Text T

AutoCAD SHX Text I

AutoCAD SHX Text C

AutoCAD SHX Text E

AutoCAD SHX Text NOTICE NOTICE NOTICE NOTICE NOTICE NOTICE NOTICE NOTICE NOTICE NOTICE NOTICE NOTICE

AutoCAD SHX Text T

AutoCAD SHX Text I

AutoCAD SHX Text C

AutoCAD SHX Text E

AutoCAD SHX Text N

AutoCAD SHX Text O

AutoCAD SHX Text T

AutoCAD SHX Text I

AutoCAD SHX Text

MIKE'S HOUSE

AutoCAD SHX Text I-5

AutoCAD SHX Text

HWY 34

AutoCAD SHX Text

FRY RD

AutoCAD SHX Text

SEVEN MILE LN

AutoCAD SHX Text

ALBANY

AutoCAD SHX Text

LEBANON

AutoCAD SHX Text

HWY 20

AutoCAD SHX Text

COLUMBUS ST

AutoCAD SHX Text

GRAND PRAIRIE RD

AutoCAD SHX Text

TANGENT DR

AutoCAD SHX Text

GOLTRA RD

AutoCAD SHX Text

HWY 34

-0 +5

0+

0+

1+

1+

2+

2+

3+

3+

4+

4+

4+

5+

5+

6+

6+

7+

7+

8+

8+

8+

9+

9+

+0

+5

+0

DATE: REVISION: BY:

SCALE: 1" = 30'

SEVEN MILE LANE

LEFT TURN LANE PAVING

SEVEN MILE LANE

LINN COUNTY

APRIL 2024

E-MAIL: Roads@co.linn.or.us

FAX: (541) 924-0202

PHONE: (541) 967-3919

ROAD DEPARTMENT

ALBANY, OREGON 97322

3010 FERRY STREET SW

LINN COUNTY COMMISSION

WILLIAM TUCKER

SHERRIE SPRENGER

ROGER NYQUIST

CHAIRMAN

COUNTY

COUNTY ENGINEER

ROADMASTER

WAYNE E. MINK, P.E.

DAINEAL L. MALONE, P.E. SHEET 2

PLAN SHEET

STA: -0+50 TO STA: 11+25

DA I NEAL LEAH MALONE

RE

GISTERED PROFESSIONALE NG I N E ER

Ma y 2 3 , 2 0 13

76365

OREGON

RENEWS: 12/31/2024

DATE:ROAD NO:

TRS:

03/12/2024CR0011

PROJECT NO: CR1704

If this bar does not measure 1" then drawing is not to scale

M

AT

C H

L

IN

E

SE

E

BE

LO

W

M

AT

C H

L

IN

E

SE

E

BE

LO

W

M

AT

C H

L

IN

E

SE

E

SH

EE

T

M

ATC

H

LIN

E 1

SEE ABO

VE

M

ATC

H

LIN

E 2

SEE ABO

VE

2" SAWCUT

50' BUTT GRIND

2" TO 0" DEPTH

AC WIDENING PLUG

WIDTH VARIES2" AC OVERLAY

AGGREGATE DRIVEWAY

APPROACH BY OTHER

4" THICK AC

DRIVEWAY APPROACH

4" THICK AC

DRIVEWAY APPROACH

AC WIDENING PLUG

WIDTH VARIES

2" AC OVERLAY

2" AC OVERLAYAC WIDENING PLUG

WIDTH VARIES

12' TRAVEL LANE

12' TRAVEL LANE

4' PAVED

SHOULDER

4' PAVED

SHOULDER

12' TRAVEL LANE

12' TRAVEL LANE

4' PAVED

SHOULDER

4' PAVED

SHOULDER

12' TRAVEL LANE

12' TRAVEL LANE

4' PAVED

SHOULDER

4' PAVED

SHOULDER

SEVEN MILE LANE

SEVEN MILE LANE

SEVEN MILE LANE

DRAFTED BY: REVIEWED BY:

T11S R3W SEC33, 34, W.M.

d.malone d.leard

12' TURN LANE

NOTE:

1). STRIPING TO BE INSTALLED BY OTHERS.

2). STRIPING SHOWN FOR TEMPORARY MARKING PURPOSES ONLY.

10'

10'

3' ASPHALT

WING-OUT

0+

0+

1+

1+

0+00

0+50

1+00

1+50

+5

+0

+5

+0

+5

+0

+5

+0

+5

DATE: REVISION: BY:

SCALE: 1" = 30'

SEVEN MILE LANE

LEFT TURN LANE PAVING

SEVEN MILE LANE

LINN COUNTY

APRIL 2024

E-MAIL: Roads@co.linn.or.us

FAX: (541) 924-0202

PHONE: (541) 967-3919

ROAD DEPARTMENT

ALBANY, OREGON 97322

3010 FERRY STREET SW

LINN COUNTY COMMISSION

WILLIAM TUCKER

SHERRIE SPRENGER

ROGER NYQUIST

CHAIRMAN

COUNTY

COUNTY ENGINEER

ROADMASTER

WAYNE E. MINK, P.E.

DAINEAL L. MALONE, P.E. SHEET 3

PLAN SHEET

STA: 11+25 TO STA: 15+75

DA I NEAL LEAH MALONE

RE

GISTERED PROFESSIONALE NG I N E ER

Ma y 2 3 , 2 0 13

76365

OREGON

RENEWS: 12/31/2024

DATE:ROAD NO:

TRS:

03/12/2024CR0011

PROJECT NO: CR1704

If this bar does not measure 1" then drawing is not to scale

M

AT

C H

L

IN

E

SE

E

SH

EE

T

M

ATC

H

LIN

E 3

SEE SH

EET 2

2" AC OVERLAY

4" THICK AC

DRIVEWAY APPROACH

AC WIDENING PLUG

WIDTH VARIES

12' TRAVEL LANE

12' TRAVEL LANE

4' PAVED

SHOULDER

4' PAVED

SHOULDER

SEVEN MILE LANE

SE

LM

ET

E

N

TR

AN

C

E

FRY ROAD

AC FEATHER

4' PAVED

SHOULDER

AC WIDENING PLUG

WIDTH VARIES

AC WIDENING PLUG

WIDTH VARIES

R61'R31'

12' TURN LANE

50' BUTT GRIND

0" TO 2" DEPTH

2" SAWCUT

DRAFTED BY: REVIEWED BY:

T11S R3W SEC33, 34, W.M.

d.malone d.leard

NOTE:

1). STRIPING TO BE INSTALLED BY OTHERS.

2). STRIPING SHOWN FOR TEMPORARY MARKING PURPOSES ONLY.

18'

2" AC OVERLAY

2" AC OVERLAY

+0

+5

+0

+5

+0

+5

+0

+5

+0

+0

+5

+0

+5

DATE: REVISION: BY:

SCALE: 1" = 30'

SEVEN MILE LANE

LEFT TURN LANE PAVING

SEVEN MILE LANE

LINN COUNTY

APRIL 2024

E-MAIL: Roads@co.linn.or.us

FAX: (541) 924-0202

PHONE: (541) 967-3919

ROAD DEPARTMENT

ALBANY, OREGON 97322

3010 FERRY STREET SW

LINN COUNTY COMMISSION

WILLIAM TUCKER

SHERRIE SPRENGER

ROGER NYQUIST

CHAIRMAN

COUNTY

COUNTY ENGINEER

ROADMASTER

WAYNE E. MINK, P.E.

DAINEAL L. MALONE, P.E. SHEET 4

PLAN SHEET

STA: 15+75 TO STA: 21+75 AND

TYPICAL SECTIONS

DA I NEAL LEAH MALONE

RE

GISTERED PROFESSIONALE NG I N E ER

Ma y 2 3 , 2 0 13

76365

OREGON

RENEWS: 12/31/2024

DATE:ROAD NO:

TRS:

03/12/2024CR0011

PROJECT NO: CR1704

If this bar does not measure 1" then drawing is not to scale

M

AT

C H

L

IN

E

SE

E

BE

LO

W

M

ATC

H

LIN

E 5

SEE ABO

VE

2" SAWCUT

2" AC OVERLAY

4" THICK AC

DRIVEWAY APPROACH

AGGREGATE

DRIVEWAY APPROACH

BY OTHERS

12' TRAVEL LANE

12' TRAVEL LANE 4' PAVED

SHOULDER

4' PAVED

SHOULDER

4' PAVED

SHOULDER

SEVEN MILE LANE

M

ATC

H

LIN

E 4

SEE SH

EET 3

SEVEN MILE LANE

AC WIDENING PLUG

WIDTH VARIES

AC WIDENING PLUG

WIDTH VARIES

4' PAVED

SHOULDER

2" AC OVERLAY

50' BUTT GRIND

0" OT 2" DEPTH

RETAIN AND PROTECT EXISTING ROADWAY SECTION

ASPHALT BASE COURSE, LEVEL 3, 1/2" ACP, 4" NOMINAL THICKNESS PLACED IN 2- 2" LIFTS

ASPHALT WEARING COURSE OVERLAY, LEVEL 3, 1/2" ACP, 2" NOMINAL THICKNESS

CONSTRUCTION

L C

12'

TRAVEL LANE

MATCH EX SLOPE MATCH EX SLOPE

SEVEN MILE LANE

TYPICAL ROADWAY SECTION

no scale

4' PAVED

SHOULDER

EXISTING

L C

WIDENING

STATIONING

STA: -0+50 to STA: 0+50 STA: 0+50 to STA: 11+87 STA: 11+87 to STA: 12+13 STA: 12+13 to STA: 21+75

WIDEN

WIDTH

0' 0' - 13.5'

INTERSECTION

13.5' - 0'

4' PAVED

SHOULDER

12'

TRAVEL LANE

*0' (NO MEDIAN)

** MEDIAN WIDTH VARIES

(SEE TABLE)

WIDEN WIDTH VARIES

(SEE TABLE)

SHOULDER ROCK TO BE

INSTALLED BY OTHERS

SHOULDER ROCK TO BE

INSTALLED BY OTHERS

*STA: -0+50 TO STA: 1+22.50

**STA: 1+22.50 TO STA:19+60

*STA: 19+60 TO STA: 21+75

MEDIAN LANE

STATIONING

STA: -0+50 to STA: 1+22.50 STA: 1+22.50 to STA: 6+62.48 STA: 6+62.48 to STA: 14+68.85 STA: 14+68.85 to STA: 19+60 STA: 19+60 to STA: 21+75

MEDIAN

WIDTH

0' 0' - 12'

12' 12' - 0'

0'

2% SLOPE

SELMET ENTRANCE

TYPICAL ROADWAY SECTION

no scale

STA: 0+29 TO STA: 1+50

22' EXISTING ROAD WIDTH

WIDEN WIDTH

~26' TO 0'

STA: 0+29 to STA: 1+05

WIDEN WIDTH

~14' TO 0'

STA: 0+29 to STA: 1+50

DRAFTED BY: REVIEWED BY:

T11S R3W SEC33, 34, W.M.

d.malone d.leard

NOTE:

1). STRIPING TO BE INSTALLED BY OTHERS.

2). STRIPING SHOWN FOR TEMPORARY MARKING PURPOSES ONLY.

20'

3' ASPHALT

WING-OUT

SHOULDER ROCK TO BE

INSTALLED BY OTHERS

SHOULDER ROCK TO BE

INSTALLED BY OTHERS

Sheets and Views
Paving Plan-Title
Paving Plan-2
Paving Plan-3
Paving Plan-4
2024-03-20T10:46:22-0700
Daineal Malone
2024-03-20T10:46:44-0700
Daineal Malone
2024-03-20T10:47:03-0700
Daineal Malone
2024-03-20T10:47:23-0700
Daineal Malone

File details come from the government source that posted it. Updated .