PAST PERFORMANCE SURVEY.docx

DOCX document 23 KB Posted

Attached to
5925--598-21-3-8200-0017 Little Rock VA Switchgear Upgrade 598-21-133
Solicitation number
36C25621R0116
Issued by

About this file

This document contains a past performance survey and details of a related federal contract opportunity for a switchgear upgrade project. The past performance survey is a template sent to references for a company competing for an award from the Department of Veterans Affairs in Jackson, Mississippi. It includes 19 questions on a scale of outstanding to unacceptable regarding the company's performance, resources, management, safety, and three yes/no questions. Additional sections ask about cure notices, cost savings, labor investigations, safety investigations, security investigations, terminations, and performance issues. The federal contract opportunity is for a switchgear upgrade at the John L. McClellan Memorial Veterans Hospital in Little Rock, Arkansas between $1 million to $5 million. The project includes replacing circuit breakers, installing remote operator panels and controls, and wiring corrections. Work may occur on nights and weekends to minimize hospital operations impacts. The NAICS code is 236220 for electrical contractors with a $39.5 million small business size standard. The acquisition is 100% set aside for service-disabled veteran-owned small businesses. The anticipated solicitation publication date is June 9, 2021.

View the file

Other files

File Type Posted
36C25621R0116 0007.docx DOCX document
36C25621R0116 0006.docx DOCX document
36C25621R0116 0005.docx DOCX document
36C25621R0116 0004.docx DOCX document
36C25621R0116 0003.docx DOCX document
SWITCHGEAR UPGRADE RFIs RESPONSES 8-31-21.pdf PDF
SWITCHGEAR UPGRADE_Site Visit Sign In.docx DOCX document
Updated PP Survey_Switchgear Upgrade.docx DOCX document
36C25621R0116 0002.docx DOCX document
USSA (SEC A B) SCHEMATICS_1.pdf PDF
USSB SCHEMATICS_2.pdf PDF
USSF SCHEMATICS_3.pdf PDF
USSG SCHEMATICS_4.pdf PDF
36C25621R0116 0001.docx DOCX document
Specifications 262300.docx DOCX document
36C25621R0116_ __01.docx DOCX document
SOW for 598-21-133 Little Rock VA Substation Upgrade JLM.docx DOCX document
Division Cost 02.docx DOCX document
WAGE DETERMINATIO1.docx DOCX document
Division Cost.docx DOCX document
Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C25620R0044

PAST PERFORMANCE SURVEY

Switchgear Upgrade John L. McClellan Memorial Veterans’ Hospital

To: ____________________ (Point of Contact)** ____________________ (Company)** ____________________ (Phone) ____________________ (Fax) ____________________ (E-Mail)** _____________________ (Name of Company requesting survey)**

The company from which you received this survey is competing for award of a contract with the Department of Veterans Affairs, Jackson, MS. As part of the process for screening potential Offerors, this company is soliciting your input and assessment of its past performance for one or more projects they performed for your firm. Please respond to each of the questions below and forward the completed survey directly to the CAVHS Contract Specialist.

To consider your responses, the Contract Officer must receive your responses, either by fax or e-mail.

If you have any questions or comments, feel free to contact me. Thank you in advance for your assistance.

Benjamin Dufour Contracting Officer Email: Benjamin.Dufour@va.gov

Please identify the project(s) that this company has performed for your organization, description, city, state, and award amount and final dollar value at completion of contract:

Respond to the question using the following scale: O- Outstanding, A- Acceptable, S-Satisfactory, M- Marginal, U-Unacceptable.

1. Did the contractor commit adequate resources in timely fashion to the contract to meet the requirements and to successfully solve problems? O A S M U

2. To what extent did the contractor respond positively and promptly to technical direction, contract change orders, etc.?

O A S M U

3. How reliably did the contractor follow through on commitments?

O A S M U
4.To what extent did the contractor’s management system provide visibility into problems and risks?

O A S M U

5. How responsive do you think the contractor was to information requests, issues, or problems during the course of the contract? O A S M U

6. How effective has the contractor been in identifying requirements?

O A S M U

7.To what extent did the contractor have the ability to administer and manage the contract?
O A S M U

8. To what extent did the contractor issue professional correspondence?

O A S M U

9. How well did the contractor adhere to the Statement of Work? O A S M U

10.What was your level of satisfaction with the contractor’s management and support staff?
O A S M U
11.What was your level of satisfaction with the contractor’s Supervisor(s)?
O A S M U

12. To what extent did the contractor submit required reports and documentation in a timely manner? O A S M U

13.To what extent were the contractor’s reports and documentation accurate and complete?
O A S M U
14.To what extent was the contractor’s maintenance and problem tracking/reporting documentation timely, accurate and of appropriate content?
O A S M U
15.To what extent did the contractor comply with safety requirements?
O A S M U
16.What was your level of satisfaction with the contractor’s overall quality of service?
O A S M U

17. To what extent was the contractor effective in interfacing with the Government staff? O A S M U

18. What was your level of overall customer satisfaction? O A S M U

19.To what extent were the contractor’s employees experienced and qualified?
O A S M U

Respond: Yes or No.

20. Were there any cure notices issued? Yes: ____ No: ____

21. Was contractor pro-active? Yes: ____ No: ____

22. Did contractor suggest cost-saving changes? Yes: ____ No: ____

23. Would you recommend this contractor? Yes: ____ No: ____

For Federal contracts:

24. Were there any Labor Department Investigations? Yes: ____ No: ____

24a. If yes, please describe reason and final outcome.

25. Were there any safety investigations? Yes: ____ No: ____

25a. If yes, please describe reason and final outcome.

26. Were there any security investigations? Yes: ____ No: ____

26a. If yes, please describe reason and final outcome.

27. Was there a partial or complete termination for default or convenience?

Yes: ____ No: ____

27a. If yes, please describe reason and final outcome.

28. Are there any pending terminations? Yes: ____ No: ____

29. What is/was the duration of the contract? _____________________

30. Were there any performance issues regarding the contractor’s work? If yes, please describe (use a separate sheet of paper if necessary).

Please provide other comments (Use a separate sheet of paper if necessary):

Signature: ____________________________

Date: ____________________________

**Required

File details come from the government source that posted it. Updated .