This document contains a pre-solicitation notice and questions and answers related to solicitation number 36C25621R0116 for switchgear upgrade work at the John L. McClellan Memorial Veterans Hospital in Little Rock, Arkansas. The contractor will upgrade switchgear equipment including replacing circuit breakers, installing remote operator panels and control switches, and correcting breaker wiring. The work may occur on nights and weekends and must minimize electrical power interruptions. The acquisition is set aside for Service-Disabled Veteran Owned Small Businesses under NAICS code 236220 with a size standard of $39.5 million. Offerors must register in VETBIZ and as interested vendors on beta.sam.gov to receive amendments. The anticipated solicitation issue date is June 9, 2021. The period of performance questions indicate work will be scheduled to allow at least two days between substations and minimize downtime of any critical areas without power.

View the file

Other files

File Type Posted
36C25621R0116 0006.docx DOCX document
36C25621R0116 0005.docx DOCX document
36C25621R0116 0004.docx DOCX document
36C25621R0116 0003.docx DOCX document
SWITCHGEAR UPGRADE RFIs RESPONSES 8-31-21.pdf PDF
SWITCHGEAR UPGRADE_Site Visit Sign In.docx DOCX document
Updated PP Survey_Switchgear Upgrade.docx DOCX document
36C25621R0116 0002.docx DOCX document
USSA (SEC A B) SCHEMATICS_1.pdf PDF
USSB SCHEMATICS_2.pdf PDF
USSF SCHEMATICS_3.pdf PDF
USSG SCHEMATICS_4.pdf PDF
36C25621R0116 0001.docx DOCX document
PAST PERFORMANCE SURVEY.docx DOCX document
Specifications 262300.docx DOCX document
36C25621R0116_ __01.docx DOCX document
SOW for 598-21-133 Little Rock VA Substation Upgrade JLM.docx DOCX document
Division Cost 02.docx DOCX document
WAGE DETERMINATIO1.docx DOCX document
Division Cost.docx DOCX document
Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 598-22-1-8200-0001 598-21-133 Department of Veterans Affairs Chief, A&MM (90C/NLR) Central Arkansas Veterans HCS 2200 Fort Roots Drive, Bldg 41, Room 200 North Little Rock

AR

72114 1706 Department of Veterans Affairs Chief, A&MM (90C/NLR) Central Arkansas Veterans HCS 2200 Fort Roots Drive, Bldg 41, Room 200 North Little Rock

AR

72114 1706 To all Offerors/Bidders

36C25621R0116 10-28-2021

X X

X See attached document of RFIs for the Switchgear Upgrade 598-21-133. As a reminder the revised proposal due date is November 5, 2021 at 2pm CST. Contractors are required to acknowledge receipt of this amendment. All other terms and conditions remain the same.

Brad Martin Contracting Officer

SWITCHGEAR UPGRADE

ADDITIONAL RFIs 36C25621R0116

1.A minimum of 10 hours of actual work time is required per substation shutdown. When the substation is down for retrofit, what is the maximum work time that the crew and contractor can anticipate from the VA? What is the maximum amount of outage time? The maximum amount of time is needed to account for and predict manpower requirements both in the dollar value of the price proposal and the schedule in the technical narrative proposal. Per SOW (1.4 L, P, Q, X, and Y) Contractors is allotted maximum 4-hour electrical services power outage to establish any required temporary power. In the event of longer outage times contractor shall supply to all impacted CAVHS services to maintain daily operations.
2.Is there any reason why the contractor should have to provide temporary power during a blackout period. Per SOW (1.4 L and P) yes, to maintain CAVHS services operational.
3.Is the VA aware of the exponential increase in cost for the contractor to engineer and provide temporary power during substation blackouts? If this question refers to facility incoming utility power service loss, the facility generators maintain the required emergency power during this event. Contractor is responsible for including bid price.
4.If temporary power is required during a blackout period, will the VA please provide a building drawing/layout as an amendment to the solicitation and identify exactly where and what floor the nearest source of power is located and the load capacity available from that location? The distance to the nearest suitable temporary power location is important to know for budgeting and planning purposes and needs to be provided before the bids are due because part of the bid and the scheduling is based on the answer to this question. Any drawings, coordination study and/or load study will be available upon project award. If this question refers to facility incoming utility power service loss, the facility generators maintain the required emergency power during this event.

5. If there is any need for temporary power, what is the actual expected/anticipated downstream ampacity load of each feeder that requires to have temporary power supply? This is important to know where the contractor will originate from and how much material and labor is required to make the temporary power available. Per SOW (1.4 A and W) Contractor shall verify.

6. Are the results of a power study available for all substations that are due to be retrofitted? Yes, and will be provided after award is made.

7. If no power study is available and temporary power is needed, who is responsible for providing the electrical engineering to determine the temporary power requirements? Per SOW (1.4 A and W) Contractor shall verify. If power load study is not available, temporary power requirements shall be based on existing service breaker.

8. Are there any critical areas associated with any of the substations that absolutely cannot be without power for an extended period of time? This is important to know so that the contractors can plan to provide temporary power to these areas. Please provide details as to the locations of these areas during the pre-bid phase to allow contractor to budget and plan for the anticipated expense of any temporary power needed during the period of performance. Per SOW (1.4 A, L, P, and Y) the contractor is responsible for verifying dimensions, existing mechanical and electrical equipment and other information presented in this document.

9. How much time does the VA need between shutdowns to allow staff to prepare the affected areas for the minimum 10 projected hours of downtime that the affected area will experience? This is important to know so that we can predict the number of weeks of total performance duration and crew commitment. Per SOW (1.4 P and Y) contractor is responsible to prepare temporary power. No services/areas are to be affected with a 10-hour downtime. Facility needs at least two (2) days after completion of one (1) substation before beginning the next substation.

10. When a substation is shut down, what is the worst-case furthest source of power the contractor should anticipate in order to have temporary lighting and a 110-volt power source for installation equipment? Per SOW (1.4 A and P) the contractor is responsible for verifying dimensions, existing mechanical and electrical equipment and other information presented in this document.

11. Will a VA representative be onsite to sign off on all retrofit installation at the time of installation? Per SOW (1.6 B. a. vi.) VA inspection and acceptance activity/event with a minimum duration of five work days at the end of each phase and immediately preceding any VA move activity/event required by the contract phasing for that phase.

12. Section 1.4 paragraph N states that staging is limited to two days ahead of shutdown. Prestaging and sorting is crucial to the successful flow of operations and to minimize down time during retrofit. Will the VA change this requirement by allowing the associated electrical rooms to be available for more time the week prior to the installation for prestaging, grouping, and preparation of material and equipment? Per SOW (1.4 N) Scheduling of material deliveries is required. Due to space restrictions, material deliveries should not be more than what can be installed within two working days.

13. Will the storage area provided by the VA be secured and have controlled access? Contractor is responsible for securing all contractor items.

14. SOW Section 1.4 para X states to request outages 21 days in advance. Will the contractor be able to schedule 21 days in advance, enough shutdowns to accomplish multiple days of sequential substation work without having to wait 21 days in between each substation request? For example, can the contractor make one request for multiple substation shutdowns sequentially, one week after another or will the VA require one substation to be completely finished before requesting another substation shutdown then wait another 21 days? Yes, outage request can be submitted sequentially. Upon beginning a substation, contractor shall ensure completion and proper operation of all substation equipment before moving/progressing on to another substation.

15. Does emergency power run through any of the switchgear substations proposed to be retrofitted? No, all CAVHS emergency power is routed via automatic transfer switches.