Past Performance Capability Information.docx

DOCX document 14 KB Posted

Attached to
UPDATED to add RFI form - Install Solar-Powered Parking Lot Lights - Riverside, CA
Solicitation number
12905B21R0007
Issued by

View the file

Other files

File Type Posted
RFIform.pdf PDF
RFI1with_response.pdf PDF
QUESTIONS AND ANSWERS.docx DOCX document
QUESTIONS AND ANSWERS.docx DOCX document
Lights_User Manual.pdf PDF
PreRegistrants for the site visit.xlsx XLSX spreadsheet
Base Pole spec sheet.pdf PDF
SLI-STEALTH-LED-Solar-street-light Stealth 80W9116.pdf PDF
12905B21R0007.pdf PDF
ARS-372.pdf PDF
SOW US Salinity Lab Solar-Powered Lot Lights .pdf PDF
ARS-371.pdf PDF
WD.pdf PDF
Contractor Certification Regarding EMR.pdf PDF
Calculation of Self Performed Work.xlsx XLSX spreadsheet
Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PAST PERFORMANCE / CAPABILITY INFORMANTION

Name of the firm:

Experience of the Firm What contracts has your firm performed which are similar in scope, magnitude, and complexity to this project?

Name of Project
Type of Project
Scope/magnitude
Work performed for
Completion Date

What other contracts has your firm performed in the past three years that would show your firm’s capability to undertake this project?

Name of Project
Type of Project
Scope/magnitude
Work performed for
Completion Date

If you are a new firm or have no directly relevant experience, how do you propose to acquire the expertise to perform the contract? (e.g., subcontracting arrangements [list subcontractors and their experience], hiring experts [list key personnel and their experience])

Subcontractor
Expertise
Experience
Key Person
Expertise
Experience

Past Performance Information Whom may we contact concerning your performance on the projects listed above? (If reference is for a subcontractor or key person, identify which subcontractor/key person is referenced.)

Name
Address
Phone
e-mail
Project(s)

Understanding of the Work

1) How extensive was your site visit for this project? (e.g., ‘didn’t visit;’ ‘drove by some areas;’ ‘walked each acre.’)

2) What did the site visit reveal about the comparative difficulty of the project—e.g., the problems that are likely to be encountered during performance?

3) How many and what types of workers will be assigned to the project?

4) What equipment will you use for this project?

5) What is your plan for safety at the job site(s)? Identify the hazards specific to the site(s) and the types of work being performed and how you plan to mitigate the risks—to your workers, FS inspectors, and the public.

6) What sequence of work are you planning to ensure timely completion of the project? (i.e., what areas or work processes will be done first? next? last?)