Part 1 Suppl Terms & Conditions.pdf

PDF 294 KB Posted

Attached to
220025 & 220024 3600 Area Paving AVENUES & STREETS
Solicitation number
ITB-16531
Issued by
St. Johns County, Florida

About this file

This document comprises the General Terms and Conditions Part 1 - Supplemental Conditions for a construction contract issued by the Florida Department of Military Affairs for projects exceeding $200,000. The project involves the repaving of streets and avenues in the 3600 area at Camp Blanding Joint Training Center in Starke, Florida (Project Numbers 220025 and 220024). The work scope includes repaving identified roadways, replacing culverts with like-for-like replacements where new paving crosses them, adding concrete mitered ends, and removing grass from roadway edges and driveways. A mandatory site visit and pre-bid meeting are required as stated in the Invitation to Bid. The project must achieve substantial completion within 90 calendar days after the Notice to Proceed, with extension provisions available only in accordance with contract documents. The contract is administered by the Department of Military Affairs Construction and Facility Management Office, with plans and specifications developed by Camp Blanding Joint Training Center's Department of Public Works.

Liquidated damages are assessed at $193.00 per calendar day for avenues and $155.00 per calendar day for streets if substantial completion is not achieved by the required date. All bidders must submit a bid bond for bids exceeding $100,000. The contractor is responsible for all project costs including site security (24 hours daily from Notice to Proceed through Substantial Completion), provision and maintenance of a 12' x 12' watertight Architect/Engineer field office, telephone installation and charges, water and electricity for construction and system testing, project signage, and criminal history background checks for all employees and agents. Davis-Bacon requirements apply if applicable as detailed in Section D of the General Terms and Conditions. The contract documents are divided into two parts, with Part 1 customizable by the Architect-Engineer and Part 2 consisting of non-alterable PDF files containing general terms, conditions, and standardized forms.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Construction Contract Project Manual for the

GENERAL TERMS & CONDITIONS

PART 1 – SUPPLEMENTAL CONDITIONS

LEVELS 4 & 5

(Level 4 - $200,000 - $500,000) (Level 5 – Over $500,000)

Revised June 2023 (All previous revisions are obsolete)

STATE OF FLORIDA

DEPARTMENT OF MILITARY AFFAIRS

2305 STATE ROAD 207

St. Augustine, Florida 32086

INTRODUCTION TO ARCHITECT-ENGINEER

The following Non-Technical Specifications are part of the bidding and contract process for construction of projects over $200,000. These documents are designed to (i) ensure compliance with applicable laws, (ii) protect the State’s interests, and (iii) make the contracting process easier for all parties. Please check with this office to ensure that you have the most current version

The documents are divided into two parts, the first part includes instructions and forms that may be customized by the Architect-Engineer. The second part which is in .pdf format is not to be altered or revised. Part 1 and Part 2 must be included as part of the Technical Specifications in their entirety.

Part 1 – Portions of this section may be customized by the Architect-Engineer as needed.

a. Architect-Engineer Checklist – Verify that all items on this checklist have been completed.

b. Cover Sheet - This form may be customized but must be completed and included in the

Technical Specifications.

c. Supplementary Terms and Conditions – This form MUST be completed and included in the

Technical Specifications as it contains vital information pertaining to bid project.

d. Notice to Bidder Instructions – Please include this notice in the specifications.

e. Advertisement To Bid Form – This form is prepared by the DMA Contract Manager.

f. Bidder Proposal Letter – This form is prepared by the DMA Contract Manager.

Part 2 – General Terms and Conditions and Standardized Forms - (PDF files) - This section MUST be included in the Technical Specifications.

a. General Terms and Conditions

b. Agreement Between Contractor and Owner (Exhibit 1)

c. Performance and Labor and Material Bonds (Exhibits 2 & 3)

d. Owner’s Certificate of Partial Payment (Exhibit 4)

e. Contractor’s Affidavit of Contract Completion (Exhibit 5)

f. Contractor’s Status Report Of Minority & Disabled Veteran's Business Enterprise (Exhibit 6)

PROJECT NUMBERS: 220025 & 220024

PROJECT NAME: 3600 AREA PAVING STREETS AND AVENUES

CAMP BLANDING JOINT TRAINING CENTER, STARKE, FLORIDA

TO BE CONSTRUCTED FOR:

Department of Military Affairs

82 Marine Street St. Augustine, FL 32084

CONTRACT ADMINISTERED BY

Department of Military Affairs

Construction and Facility Management Office 2305 State Road 207

St. Augustine, Florida, 32033

Plans and Specs developed by:

Camp Blanding Joint Training Center (DPW)

Starke, Florida

SUPPLEMENTARY TERMS AND CONDITIONS

July 22, 2026

Project Numbers: 220025 and 220024

Project Name and Location: “3600 AREA STREETS AND AVENUES, CAMP BLANDING JOINT TRAINING CENTER, STARKE, FLORIDA

OWNER: Florida Department of Military Affairs

Project Designed By: Jeff Collins (CBJTC DPW)

This document forms an integral part of the Request for Proposal Documents and the Contract Documents. The receipt of this document must be acknowledged in the space provided on your Proposal. This General Terms and Conditions are hereby modified as follows:

1. SUBSTANTIAL COMPLETION AND LIQUIDATED DAMAGES: Section C-7 is amended in part as follows: This Project is to be substantially complete within -90 - calendar days after the date of the Notice to Proceed. This date may be extended only in accordance with the Contract Documents. If the project is not substantially completed by the required date, liquidated damages shall be assessed at the rate of $193.00 AVENUES / $155.00 STREETS per calendar day.

2. ARCHITECT/ENGINEER'S FIELD OFFICE. The Contractor shall provide and maintain a watertight office at the Project for the exclusive use of the Architect/Engineer and his representatives, not less than 12' x 12' in size, one room with at least one window in each exterior wall and an independent outside entrance door fitted with hardware and lock, artificial light, a bench with one drawer, a blueprint rack, a heater and a window air conditioner. This office and equipment shall become the property of the Contractor upon completion of the contract.

3. TELEPHONE. A telephone shall be installed in the Architect/Engineer's office and it shall remain until the full completion of the project. Charges for long distance calls shall be paid by the person making the calls. All other telephone charges shall be paid by the Contractor.

4. WATER. Water necessary for construction of the building and testing its plumbing and mechanical systems shall be furnished by the Contractor. He shall make all connections, install a meter, take out and pay for all permits necessary, do all piping and clear away all evidence of same after the job is completed.

5. ELECTRICITY. All electricity for light and power necessary for the construction of the building and testing of its electrical and mechanical systems shall be paid for by the Contractor. The Contractor shall make all necessary arrangements for this service and perform the work required.

6. PROJECT SIGN. A sign shall be erected at the site by the Contractor and shall be 3/4"- 4' X 8' exterior grade plywood mounted on 4 x 4 wood posts (p.t.), located in a prominent location approved by the Owner. Sign shall conform to the size, colors and design specifications provided by THE owner.

7. INITIAL CONSTRUCTION CONFERENCE. Immediately prior to starting construction or as soon as possible after the construction has started, the Owner will arrange a meeting with the project stakeholders. The purpose of this meeting shall be to discuss requirements and responsibilities of the various parties involved with the objective of expeditious handling of the construction contract. The Owner's Contract Manager and Project Manager will chair this meeting.

8. SITE SECURITY. The Contractor shall pay for and be responsible to secure the site and the project against theft, vandalism, fire and for public safety at all times (24 hours per day) from Notice to Proceed until Substantial Completion.

9. DAVIS-BACON REQUIREMENTS. If Davis-Bacon and related laws apply, they will be addressed in Section D of the General Terms and Conditions. If applicable, then all applicable federal labor standards clauses are incorporated into the Contract Documents. The Contractor agrees to familiarize itself with “Making Davis-Bacon Work – A Contractor’s Guide to Prevailing Wage Requirements for Federally-Assisted Construction Projects” and to comply with all applicable regulations.

EXCEPT AS SPECIFICALLY PROVIDED HEREIN, ALL OTHER TERMS AND CONDITIONS OF THE BIDDING

DOCUMENTS AND CONTRACT DOCUMENTS REMAIN UNCHANGED.

[END]

Date Issued:

A/I Initials:

NOTICE TO BIDDERS

The following General Terms and Conditions and the Supplemental Terms and Conditions are part of the bidding and contract process for construction projects in excess of $200,000. These non-technical documents are designed to (i) ensure compliance with applicable laws, (ii) protect the State’s interests, and (iii) make the contracting process easier for all parties. Please review carefully all sections in the non-technical specifications including the following items:

1. All Bidders must submit a bid bond with their bid proposal if the bid exceeds $100,000.00. For details please refer to Section B-11 of the General Terms and Conditions.

2. All Bidders must submit bids in accordance with the publicized Invitation to Bid (ITB). If prequalification to bid is required, it will be stated within the ITB along with instructions.

3. Criminal History Background Checks, if included in the General Terms and Conditions, must be obtained for all employees and agents of the Contractor and its subcontractors, their agents and employees, and all other persons performing any of the work under a contract to the Contractor working within buildings or facilities either owned or managed by the Department of Military Affairs.

Details of this responsibility are outlined in Article C-38 of the General Terms and Conditions.

4. All Bidders are responsible for the cost of insurance and bonds. Please refer to Sections C-1 through

C-3 of the General Terms and Conditions for required types of insurance and Exhibits 2 and 3 to review the requirements on the bond forms.

5. Proposal Form may be obtained with the ITB or as instructed in the ITB.

6. Samples of some Forms required by the Department of Military Affairs (DMA) are shown in the

General Terms and Conditions. Forms for use during contract performance will be provided by DMA after contract award.