Part 1 Pgs. 1-111 Staff Quarters_
4 MB Posted
- Solicitation number
- RFQ - 171 - 230000000142
- Issued by
- Ontonagon County, Michigan
About this file
This document is a Bidding and Contract Document for the Porcupine Mountains Wilderness State Park - Various Historic Buildings Upgrades project, issued by the State of Michigan Department of Technology, Management and Budget State Facilities Administration Design and Construction Division.
The project involves renovations to two buildings at the park: the Staff Quarters and the Lodge Building. The renovations include hazardous material abatement, roof work, foundation and drainage repairs, and interior renovations. Bids are due by February 1, 2023 at 2:00 pm local time. A mandatory pre-bid conference and site tour will be held on January 19, 2023. The contract completion times are August 25, 2023 for the Staff Quarters and October 27, 2023 for the Lodge Building. Liquidated damages of $500 per calendar day are specified for late completion. The bid requires a 5% bid guarantee, and performance and payment bonds are required for all contracts over $50,000.
Text of this file
Bidding and Contract Document (R 03/21) Project Name: Various Historic Buildings Upgrades File No. 751/19141.TAP
State of Michigan Department of Technology, Management and Budget
State Facilities Administration Design and Construction Division
DCSPEC
Bidding and Contract Document Minor Projects
File No. 751/19141.TAP Funding Code 5518
Department of Natural Resources Porcupine Mountains Wilderness State Park
Various Historic Buildings Upgrades Silver City, Michigan
Staff Quarters & Lodge Buildings
100% Submittal January 4, 2023
Bidding and Contract Document (R 03/21) Project Name: Various Historic Buildings Upgrades File No. 751/19141.TAP
DTMB-0401D (R 03/21)
BID SUMMARY
DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET
STATE FACILITIES ADMINISTRATION
DESIGN AND CONSTRUCTION DIVISION
3111 W. St. Joseph Street Lansing, Michigan 48917
Bids must be submitted electronically through the SIGMA VSS website at https://sigma.michigan.gov/webapp/PRDVSS2X1/AltSelfService
FILE NUMBER
751/19141.TAP
FUNDING CODE
DEPARTMENT/AGENCY
MDNR – Porcupine Mountains Wilderness State Park
CONTRACT TIME(S)
(See Section 00100)
PROJECT NAME
Various Historic Buildings Upgrades
LOCATION
Silver City, MI
BID OPENING DATE
February 1, 2023 at 2:00 pm Local Time (Eastern Time)
FOR AN EXAMINATION OF THE SITE CONTACT:
Only accessible at pre-bid meeting time and date
SEE SECTION 00100 INSTRUCTIONS TO BIDDERS AND SECTION 00700 GENERAL CONDITIONS PROVIDED WITH THE BIDDING DOCUMENTS.
BID: WE PROPOSE TO FURNISH, PERFORM AND COMPLETE THE ENTIRE WORK IN ACCORDANCE WITH THE CONTRACT DOCUMENTS IN
CONSIDERATION OF THE BID PRICE (S) STATED BELOW.
FIRM NAME AND COMPLETE ADDRESS TELEPHONE NUMBER and E-MAIL ADDRESS
□ Qualified Disabled Veteran
SIGMA VENDOR NUMBER
(protected information required for processing payments)
BIDDER'S SIGNATURE AND TITLE DATE
WITNESS' SIGNATURE DATE
By signing this bid above, bidder certifies their enclosed Qualified Disabled Veteran and Michigan-Based Business Certifications.
BASE BID FROM BID SCHEDULE (Include specified Allowances):
____________________________________________________________________________Dollars $____________________ (use words) (in figures)
Alternate1: (Add/Subtract) ______________________________________________________ Dollars $ ____________________ (use words) (in figures)
Alternate 2: (Add/Subtract) ______________________________________________________Dollars $ ____________________ (use words) (in figures)
Alternate 3: (Add/Subtract) ______________________________________________________Dollars $ ____________________ (use words) (in figures)
Builder’s Risk Insurance is NOT provided by the State of Michigan.
A PERFORMANCE BOND AND A PAYMENT BOND ARE REQUIRED FOR ALL BIDS OVER $50,000.00. EACH BID MUST BE
ACCOMPANIED BY A FIVE (5) PERCENT BID GUARANTEE.
BIDDERS ARE ALSO CAUTIONED TO FAMILIARIZE THEMSELVES WITH ALL OF THE OTHER CONDITIONS OF THE CONTRACT.
Project Scope of Work:
Two buildings at the park are proposed for renovations.
Staff Quarters:
- Hazardous Material Abatement.
- Roof renovations include removing the roof, new attic trusses, new roof system/eaves/soffits & chimney repairs.
- Foundation & drainage repairs.
- Electrical Improvements.
Bidding and Contract Document (R 03/21) Project Name: Various Historic Buildings Upgrades File No. 751/19141.TAP
Lodge Building:
- Hazardous Material Abatement.
- Roof renovations include removing the roof, new attic trusses, new roof system/eaves/soffits, and chimney repairs.
- Interior renovations include plumbing supply and waste piping replacement, furnace and boiler replacement, water heater replacement, and electrical wiring replacement.
The Bidder must figure its Base Bid on the specified, or Addendum-approved, materials and equipment only. No “or equal” or substitution proposals will be permitted after Bid opening, except as provided in the General Conditions.
Addenda: Bidder acknowledges receipt of Addenda: No. ___ dated: ________, No. ___ dated: ________ No. ___ dated: ________ FIRM NAME TELEPHONE NUMBER and E-MAIL ADDRESS
BID SCHEDULE
Base Bid Schedule - The Bidder will complete the Work and accept as full payment, for the Work items listed, the following Unit Prices and/or Item Bid Prices, as applicable:
Base Bid Item No.
Bid Quantity
Description (Bidder to write price in Words)
Unit Price
Item Bid Price
1 LS Staff Quarters Renovations
2 LS Lodge Building Renovations
CASH - ELECTRICAL UTILITY
ALLOWANCE
$5,000
PROVISIONARY ALLOWANCE
AMOUNT
$15,000
TOTAL (This amount should equal the Base Bid amount on the Bid Summary Form) $
Base Bid (Sum of Item Bid Prices for all Base Bid Items):
__________________________________________________________________ Dollars $__________________________ (use words) (in figures)
Bidding and Contract Document (R 03/21) Project Name: Various Historic Buildings Upgrades File No. 751/19141.TAP
Schedule of Alternates - The Bidder will complete (or deduct from the Contract) the parts of the Work designated by the Alternates that follow and accept in full payment (or allow in full credit) for those parts of the Work the following Item Bid Prices:
Alternate Item No.
Bid Quantity
Description (Bidder to write price in Words)
Item Bid Price
The Bidder further acknowledges and agrees that the separate prices bid on this “Schedule of Alternates,” where they are applicable and deemed acceptable by the Owner, will be used if incorporated into the Contract when the Owner issues the Notice of Award.
Schedule of Unit Prices or Contingent Change Order Prices - The Bidder shall use this “Schedule” to quote unit prices identified in the bid documents or propose other contingent Change Order prices. The proposed Unit Prices or contingent Change Order prices set forth in this schedule, at the sole discretion of the Owner, may, or may not be incorporated into the Contract Documents. The Owner reserves the right to negotiate Unit Prices or contingent Change Order prices set forth herein prior to their possible incorporation into the Contract Documents.
Item No.
Units or Quantity
Description
(Bidder to write price in Words)
Bidder’s Bid
Price
Price Proposed
By The Owner
Bidding and Contract Document (R 03/21) Project Name: Various Historic Buildings Upgrades File No. 751/19141.TAP
DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET
State Facilities Administration
Design & Construction Division
Qualified Disabled Veteran (QDV) Business Representation
‘Qualified Disabled Veteran,’ means a business entity that is 51% or more owned by one or more veterans with a service-connected disability.
‘Qualified Disabled,’ means a business entity that is 51% or more owned by one or more with a service-connected disability.
The vendor represents that it IS _____, a qualified disabled veteran.
The contractor represents and warrants that the company meets the above (when checked) and has attached supporting documentation per the following:
Each bid requesting the Qualified Disabled Veterans (QDV) preference, in accordance with Public Act 22 of 2010, MCL 18.1241.3 shall include a DD214 Proof of Service and Discharge, a Veterans Administration rating decision letter, proof of disability (if the disability is not indicated on the DD214), and appropriate legal documents setting forth the 51% natural persons QDV ownership.
Fraudulent Certification as a Qualified Disabled Veteran may result in debarment under MCL 18.264.
Certification of a Michigan Based Business
(Information Required Prior to Contract Award for Application of State Reciprocity Provisions)
To qualify as a Michigan Based Business:
Vendor must have, during the 12 months immediately preceding this bid deadline:
or If the business is newly established, for the period the business has been in existence, it has:
(check all that apply):
Filed a Michigan single business tax return showing a portion or all of the income tax base allocated or apportioned to the State of Michigan pursuant to the Michigan Single Business Tax Act, 1975 PA 228, MCL
208.1 – 208.145; or
Filed a Michigan income tax return showing income generated in or attributed to the State of Michigan; or
Withheld Michigan income tax from compensation paid to the bidder’s owners and remitted the tax to the
Department of Treasury; or
I certify that I have personal knowledge of such filing or withholding, that it was more than a nominal filing for the purpose of gaining the status of a Michigan business, and that it indicates a significant business presence in the state, considering the size of the business and the nature of its activities.
I authorize the Michigan Department of Treasury to verify that the business has or has not met the criteria for a Michigan business indicated above and to disclose the verifying information to the procuring agency.
Bidder shall also indicate one of the following:
Bidder qualifies as a Michigan business (provide zip code: ________________)
Bidder does not qualify as a Michigan business (provide name of State: _____________).
Principal place of business is outside the State of Michigan, however service/commodity provided by a location within the State of Michigan (provide zip code: (___________).
Fraudulent Certification as a Michigan business is prohibited by MCL 18.1268 § 268. A BUSINESS THAT PURPOSELY OR WILLFULLY SUBMITS A FALSE CERTIFICATION THAT IT IS A MICHIGAN BUSINESS OR FALSELY INDICATES THE STATE IN WHICH IT HAS ITS PRINCIPAL PLACE OF BUSINESS IS GUILTY OF A FELONY, PUNISHABLE BY A FINE OF NOT LESS THAN $25,000 and subject to debarment under MCL 18.264.
Bidding and Contract Document (R 03/21) Project Name: Various Historic Buildings Upgrades File No. 751/19141.TAP
BID BOND
BID SUBMITTED ON the _______ day of ________________, 20____.
Bid Security is in the form of: a Bid Bond _______ Bid Bond form has been duly executed _______; or
A Bank Certified or Cashier's check ___ or Money Order ___ is attached to this page ____ (If Bid Security is by Check or Money Order, the original check or money order must be delivered to the issuing office before Bid Due Time. ALL other SIGMA bid submittals are also still to be made).
If the Bidder is an Individual:
Name of Individual: _________________________________________________________
Name & Title of Person Authorized to sign: ___________________________________________
Signature: _________________________________________________________ (If not the Individual, Attach Power of Attorney) Date
Doing Business as: _________________________________________________________
Business Address: _________________________________________________________
County of registration _________________________
Telephone: _________________________ FAX: ______________________
If the Bidder is a Partnership:
By: _________________________________________________________ (True Name of the Partnership)
Partner Authorized to Sign Date
Signature: _________________________________________________________ (Attach evidence of Authority to sign) Date
Business Address: _________________________________________________________
County of registration _________________________
Telephone: _________________________ FAX _______________________
If the Bidder is a Corporation:
By: _________________________________________________________ (Legal Corporation Name)
Name & Title of Authorized Officer: __________________________________________________
Signature: _________________________________________________________ (Attach evidence of Authority to sign) Date
Name & Title of Officer Attesting: __________________________________________________
Signature: _________________________________________________________ Date
Business Address: _________________________________________________________
Telephone: _________________________ FAX _______________________
(State of Incorporation): _________________________________________________________
If The Bidder is A Joint Venture: JOINT VENTURE SIGNATURES MUST BE AS PROVIDED IN INSTRUCTIONS TO BIDDERS.
EACH JOINT VENTURER SIGNING THE BID MUST SIGN IN THE MANNER INDICATED FOR AN INDIVIDUAL, A PARTNERSHIP OR A CORPORATION. IF MORE THAN TWO JOINT VENTURERS OF THE SAME TYPE ARE INCLUDED, USE ADDITIONAL PAGES. JOINT VENTURE STATE OF INCORPORATION ___________________ OR COUNTY OF REGISTRATION
Bidding and Contract Document (R 03/21) Project Name: Various Historic Buildings Upgrades File No. 751/19141.TAP
POST-BID SUBMITTALS
The PSC will request this submittal after bid opening. Complete and submit these items within two business days after the request.
BIDDER’S EXPERIENCE MODIFICATION RATING (EMR) ____________
Attach letter of explanation if the Bidder does not have an EMR.
PROPOSED PROJECT SUPERINTENDENT _______________________________
Attach brief resume or list of similar successful projects.
LIST OF SIMILAR PROJECTS COMPLETED BY THE BIDDER
Please list at least three completed projects of similar size and complexity to the project being bid, with reference contact information
REFERENCE #___
Owner: _____________________________________________________________________________________
Project/Contract Name: ________________________________________________________________________
Location of Project/Contract: ____________________________________________________________________
Contract Price: _______________________ Project/Contract Started: ____________ Completed: ____________
Owner's Representative (Name and Telephone): _____________________________________________________
Scope of Project/Contract: ______________________________________________________________________
REFERENCE #___
Owner: _____________________________________________________________________________________
Project/Contract Name: ________________________________________________________________________
Location of Project/Contract: ____________________________________________________________________
Contract Price: _______________________ Project/Contract Started: ____________ Completed: ____________
Owner's Representative (Name and Telephone): _____________________________________________________
Scope of Project/Contract: ______________________________________________________________________
REFERENCE #___
Owner: _____________________________________________________________________________________
Project/Contract Name: ________________________________________________________________________
Location of Project/Contract: ____________________________________________________________________
Contract Price: _______________________ Project/Contract Started: ____________ Completed: ____________
Owner's Representative (Name and Telephone): _____________________________________________________
Scope of Project/Contract: ______________________________________________________________________
Bidding and Contract Document (R 03/21) Project Name: Various Historic Buildings Upgrades File No. 751/19141.TAP
POST BID SUBMITTALS: LIST OF SUBCONTRACTORS
The Apparent Low Bidder shall nominate for each Division of Specification and/or trade category, the Subcontractor to be awarded Sub-agreements, including the apparent Low Bidder if work is to be self-performed. Nominated subcontractors shall not be removed, replaced or added to except by written request for good reason, subject to Owner acceptance.
Division, Specification Section Nominated Amount of Subcontract Minority, Woman, and/or Trade Subcontractor(s) Handicapped?
1.________________________ _________________________ __________________ ______________
2.________________________ _________________________ __________________ ______________
3.________________________ _________________________ __________________ ______________
4.________________________ _________________________ __________________ ______________
5.________________________ _________________________ __________________ ______________
6.________________________ _________________________ __________________ ______________
7.________________________ _________________________ __________________ ______________
8.________________________ _________________________ __________________ ______________
9.________________________ _________________________ __________________ ______________
10._______________________ _________________________ __________________ ______________
11._______________________ _________________________ __________________ ______________
12._______________________ _________________________ __________________ ______________
13._______________________ _________________________ __________________ ______________
14._______________________ _________________________ __________________ ______________
The undersigned Apparent Low Bidder _____________________________________________________________ certifies that all the information and data furnished in this List of Subcontractors are current, accurate and complete as of the date stated below.
Signed by:____________________________Name_______________________________ Title ________________________ on this __________ day of ____________________, 20_______.
Bidding and Contract Document (R 03/21) Project Name: Various Historic Buildings Upgrades File No. 751/19141.TAP
PERFORMANCE BOND
SURETY COMPANY REFERENCE No. __________________________________
That "the Contractor," ___________________________________________________, a corporation ___, individual ___, partnership ___, joint venture ___ of the State of __________________, qualified to do business in the State of Michigan, as Principal, and "the Surety," ____________________________________________________________________, of the State of _________________, as surety, are held and bound unto the State of Michigan, "the Owner," as Obligee, in the amount of __________________________________________________________________________ Dollars ($_________________), for the payment of which the Contractor and Surety bind themselves, their respective heirs, successors, legal representatives and assigns, jointly and severally, in compliance with 1963 PA 213, as amended, MCL 129.201 et seq.
The Contractor has entered into "the Contract" with the Owner for _______________________________________________ _______________, "the Work," covered by the Contract Documents, which are incorporated into this Performance Bond by this reference;
If the Contractor faithfully performs and fulfills all the undertakings, covenants, terms, conditions, warranties, indemnifications and agreements of the Contract Documents within the Contract Time (including any authorized changes, with or without notice to the Surety) and during the Correction Period, and if the Contractor also performs and fulfills all the undertakings, covenants, terms, conditions, warranties, indemnifications and agreements of any and all duly authorized modifications of the Contract Documents, then THIS
OBLIGATION IS VOID, OTHERWISE TO REMAIN IN FULL
FORCE AND EFFECT.
A. No change in Contract Price or Contract Time, "or equal" or substitution or modification of the Contract Documents (including addition, deletion or other revision) releases the Surety of its obligations under this Section 00610 Performance Bond. The Surety expressly waives notice of any such change in Contract Price or Contract Time, "or equal" or substitution or modification of the Contract Documents (including addition, deletion or other revision).
B. This Performance Bond must be solely for the protection of the Owner and its successors, legal representatives or assigns.
C. It is the intention of the Contractor and Surety that they must be bound by all terms and conditions of the Contract Documents (including, but not limited to General Conditions and this Performance Bond). However, this Performance Bond is executed pursuant to 1963 PA 213, as amended, MCL 129.201 et seq., and if any provision(s) of this Performance Bond is/are illegal, invalid or unenforceable, all other provisions of this Performance Bond must nevertheless remain in full force and effect, and the Owner must be protected to the full extent provided by 1963 PA 213, as amended, MCL 129.201 et seq.
IMPORTANT: The Surety must be authorized to do business in the State of Michigan by the Department of Licensing and
Regulatory Affairs − Insurance Bureau, must be listed on the current U.S. Department of the Treasury Circular 570, and, unless otherwise authorized by the Owner in writing, must have at least an A− Best's rating and a Class VII or better financial size category per current A. M. Best Company ratings.
Name, Address and Telephone of the Surety:
Address and Telephone of Agent, who is either a resident of, or whose principal office is maintained in, the State of Michigan
Signed and sealed this __________ day of _______________________, 20_____.
THE CONTRACTOR: (Print Full Name and Sign) By:___________________________________________________________
WITNESS ______________________________ Name & Title: __________________________________________________
Telephone No. _________________________________________________
THE SURETY: (Print Full Name and Sign) Agent: ________________________________________________________
WITNESS ______________________________ Attorney-in-Fact: ________________________________________________
Telephone No. _______________________________________________
Bidding and Contract Document (R 03/21) Project Name: Various Historic Buildings Upgrades File No. 751/19141.TAP
PAYMENT BOND
SURETY COMPANY REFERENCE No.___________________________________
"the Contractor," ___________________________________________________, a corporation ___, individual ___, partnership ___, joint venture ___ of the State of __________________, qualified to do business in the State of Michigan, as Principal, and "the Surety," ____________________________________________________________________, of the State of _________________, as surety, are held and bound unto the State of Michigan, "the Owner," as Obligee, in the amount of __________________________________________________________________________ Dollars ($_________________), for the payment of which the Contractor and Surety bind themselves, their respective heirs, successors, legal representatives and assigns, jointly and severally, in compliance with 1963 PA 213, as amended, MCL 129.201 et seq.
The Contractor has entered into "the Contract" with the Owner for _____________________________________________ __________________, "the Work," covered by the Contract Documents, which are incorporated into this Payment Bond by this reference;
If the Contractor promptly pays all claimants supplying labor or materials to the Contractor or to the Contractor's Subcontractors in the prosecution of the Work, then THIS
OBLIGATION IS VOID, OTHERWISE TO REMAIN IN FULL
FORCE AND EFFECT.
A. All rights and remedies on this Payment Bond are solely for the protection of all claimants supplying labor and materials to the Contractor or the Contractor's Subcontractors in the prosecution of the Work, and must be determined in accordance with Michigan Law.
B. No change in Contract Price or Contract Time, "or equal" or substitution or modification of the Contract Documents (including addition, deletion or other revision) must release the Surety of its obligations under this Payment Bond. The Surety hereby expressly waives notice of any such change in Contract Price or Contract Time, "or equal" or substitution or modification of the Contract Documents (including addition, deletion or other revision).
C. It is the intention of the Contractor and Surety that they must be bound by all terms and conditions of the Contract Documents (including, but not limited to this Payment Bond). However, this Payment Bond is executed pursuant to 1963 PA 213, as amended, MCL 129.201 et seq., and if any provision(s) of this Payment Bond is/are illegal, invalid or unenforceable, all other provisions of this Payment Bond must nevertheless remain in full force and effect, and the Owner must be protected to the full extent provided by 1963 PA 213, as amended, MCL 129.201 et seq.
IMPORTANT: The Surety must be authorized to do business in the State of Michigan by the Department of Licensing and Regulatory
Affairs − Insurance Bureau, must be listed on the current U.S. Department of the Treasury Circular 570, and, unless otherwise authorized by the Owner in writing, must have at least an A− Best's rating and a Class VII or better financial size category per current A. M. Best Company ratings.
Name, Address and Telephone of the Surety:
Address and Telephone of Agent, who is either a resident of, or whose principal office is maintained in, the State of Michigan
Signed and sealed this __________ day of _______________________, 20_____.
THE CONTRACTOR: (Print Full Name and Sign) By:___________________________________________________________
WITNESS ______________________________ Name & Title: __________________________________________________
Telephone No. _________________________________________________
THE SURETY: (Print Full Name and Sign) Agent: ________________________________________________________
WITNESS ______________________________ Attorney-in-Fact: ________________________________________________
Telephone No. ____________________________________________________
Bidding and Contract Document (R 03/21) Project Name: Various Historic Buildings Upgrades File No. 751/19141.TAP
TABLE OF CONTENTS
CONTRACT FORMS
BID SUMMARY FORM
BID SCHEDULE
QUALIFIED DISABLED VETERAN (QDV) BUSINESS REPRESENTATION
CERTIFICATION OF A MICHIGAN BASED BUSINESS
BID BOND
POST-BID SUBMITTALS
PERFORMANCE BOND
PAYMENT BOND
TABLE OF CONTENTS
DIVISION 00 BIDDING REQUIREMENTS AND CONTRACT CONDITIONS
SECTION TITLE PAGES THRU
00010 PRE-BID INFORMATION 00-1
00100 INSTRUCTIONS TO BIDDERS 00-5 TO 00-8
00120 SUPPLEMENTARY INSTRUCTIONS 00-8
00200 INFORMATION TO BIDDERS 00-8 TO 00-9
00700 GENERAL CONDITIONS 00-9 TO 00-19
00750 SPECIAL WORKING CONDITIONS 00-19 TO 00-20
00800 SUPPLEMENTARY CONDITIONS 00-20
00850 FEDERALLY FUNDED WAGE DETERMINATION SCHEDULE 00-20
00900 ADDENDA 00-20
DIVISION 01 - GENERAL REQUIREMENTS
01010 SUMMARY OF WORK 01-1
01020 ALLOWANCES 01-1
01025 MEASUREMENT AND PAYMENT 01-1
01030 ALTERNATES 01-1
01040 COORDINATION 01-1 TO 01-2
01050 FIELD ENGINEERING 01-2
01060 REGULATORY REQUIREMENTS 01-2 TO 01-4
01090 REFERENCES 01-4
01100 PROJECT PROCEDURES 01-4 TO 01-5
01200 PROJECT MEETINGS 01-5
01300 SUBMITTALS 01-5 TO 01-6
01400 QUALITY CONTROL 01-6 TO 01-7
01500 CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS 01-7 TO 01-8
01600 MATERIAL AND EQUIPMENT 01-8
01650 FACILITY START-UP 01-8
01700 CONTRACT CLOSE-OUT 01-8 TO 01-9
01800 MAINTENANCE 01-9
APPENDIX I – GLOSSARY
APPENDIX II – SPECIAL WORKING CONDITIONS
APPENDIX III – SPECIAL PROJECT PROCEDURES
APPENDIX IV – REQUIRED PROJECT SIGN
Bidding and Contract Document (R 03/21) Project Name: Various Historic Buildings Upgrades File No. 751/19141.TAP
TECHNICAL SPECIFICATIONS
Division Section Title
DIVISION 02 – EXISTING CONDITIONS
02 22 20 Hazardous Materials Abatement 02 22 20.01 Asbestos Survey & Paint Sampling Report – Staff Quarters (BOUND SEPARATELY) 02 22 20.02 Asbestos Survey & Paint Sampling Report – Lodge (BOUND SEPARATELY) 02 41 19 Selective Building Demolition
DIVISION 03 – CONCRETE
03 10 00 Concrete Forming and Accessories 03 20 00 Concrete Reinforcing 03 30 00 Cast-in-Place Concrete 03 35 00 Concrete Finishing 03 39 00 Concrete Curing
DIVISION 04 – MASONRY
04 01 00 Maintenance of Masonry 04 05 03 Masonry Mortaring and Grouting 04 20 16 Reinforced Unit Masonry
DIVISION 05 – METALS
05 12 00 Structural Steel Framing
DIVISION 06 – WOOD, PLASTICS, AND COMPOSITES
06 10 00 Rough Carpentry 06 17 53 Shop-Fabricated Wood Trusses
DIVISION 07 – THERMAL AND MOISTURE PROTECTION
07 01 50 Preparation for Removal of Roofing 07 21 13 Board Insulation 07 21 16 Blanket Insulation 07 21 19 Foamed In-Place Insulation 07 31 13 Asphalt Shingles 07 71 23 Manufactured Gutters and Downspouts 07 90 00 Joint Protection
DIVISION 08 – OPENINGS
08 53 00 Plastic Windows
DIVISION 09 – FINISHES
09 21 16 Gypsum Board Assemblies 09 65 00 Resilient Flooring 09 90 00 Paint and Coating
DIVISION 22 – PLUMBING
22 05 29 Hangers and Supports for Plumbing Piping and Equipment 22 11 00 Facility Water Distribution 22 13 00 Facility Sanitary Sewerage 22 34 00 Fuel-Fired Domestic Water Heaters 22 40 00 Plumbing Fixtures
DIVISION 23 - HEATING, VENTILATING, AND AIR-CONDITIONING (HVAC)
23 05 93 Testing, Adjusting, and Balancing for HVAC 23 11 26 Facility Liquefied-Petroleum Gas Piping 23 31 00 HVAC Ducts and Casings 23 33 00 Air Duct Accessories 23 37 00 Air Outlets and Inlets 23 52 16 Condensing Boilers 23 54 00 Furnaces - Propane
Bidding and Contract Document (R 03/21) Project Name: Various Historic Buildings Upgrades File No. 751/19141.TAP
DIVISION 26 – ELECTRICAL
26 05 00 General Electrical Requirements 26 05 02 Minor Electrical Demolition 26 05 03 Equipment Wiring Connections 26 05 19 Low-Voltage Electrical Power Conductors and Cables 26 05 26 Grounding and Bonding for Electrical Systems 26 05 29 Hangers and Supports for Electrical Systems 26 05 33 Raceway and Boxes for Electrical Systems 26 05 53 Identification for Electrical Systems 26 09 23 Lighting Control Devices 26 24 16 Panelboards 26 27 26 Wiring Devices 26 51 00 Interior Lighting 26 56 00 Exterior Lighting
DIVISION 27 – COMMUNICATIONS
27 05 53 Identification for Communication 27 13 43 Tele Communication Cable and Equipment
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 31 00 Household Smoke Fire and CO Alarms
DIVISION 31 – EARTHWORK
31 22 13 Rough Grading 31 23 16 Excavation 31 23 23 Fill 31 25 13 Erosion Control
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 92 19 Seeding
Bidding and Contract Document (R 03/21) Project Name: Various Historic Buildings Upgrades File No. 751/19141.TAP
DRAWINGS - BOUND SEPARATELY
STAFF QUARTERS UPGRADES
NUMBER SHEET NAME
G001 Cover Sheet C100 Site Plan and Details S101 Abatement Plan S102 Basement Wall Demolition & Repair S103 Roof Demolition Plan S104 Roof Plan and Column Support Demolition Areas S105 Proposed Roof Framing S201 Exterior Elevations - Reference S301 Building and Rafter Sections S302 Roof Sections S501 Roof Details E001 Electrical Abbreviations ED101 Existing Demo Electrical Plan - Staff Quarters E101 Proposed Electrical Plans - Staff Quarters E102 Electrical Details - Staff Quarters E501 Panel Schedules
LODGE UPGRADES
NUMBER SHEET NAME
G001 Cover Sheet S001 Structural Notes S101 Roof Demolition & Abatement Plan S102 Proposed Roof Plan S301 Building and Rafter Sections S302 Roof Sections & Details P101 Plumbing Plan M101 Mechanical Plan E001 Electrical Abbreviations ED201 Existing Electrical Plan E201 Proposed Electrical Plan E501 Electrical Schedules & Details
Bidding and Contract Document (R 03/21) Project Name: Various Historic Buildings Upgrades File No. 751/19141.TAP
DIVISION 00
BIDDING REQUIREMENTS AND CONTRACT CONDITIONS
Bidding and Contract Document (R 03/21) Project Name: Various Historic Buildings Upgrades File No. 751/19141.TAP
00-1
SECTION 00010 PRE-BID INFORMATION
1. Invitation to Bid (ITB) Your firm is invited to submit a Bid. The State of Michigan as the Owner will receive bids electronically through the SIGMA VSS website at https://sigma.michigan.gov/webapp/PRDVSS2X1/AltSelfService, for Porcupine Mountains Wilderness State Park – Various Historic Buildings Upgrades until 2:00 p.m., local time, on February 1, 2023 local time (Eastern).
The State reserves the right to cancel this Invitation to Bid (ITB) or change the date and time for submitting Bids by announcing same at any time before the established date and time for Bid opening. Bids must remain open for acceptance by the Owner for no less than the Bid hold period. Contractor may agree to extend the Bid hold period. However, any such extension must be based upon no increase in the Bid Price and/or Contract Time.
2. Work Description The Work, Porcupine Mountains Wilderness State Park – Various Historic Buildings Upgrades, Agency No.
751, Funding Code. 5518, DTMB File No. 751/19141.TAP includes, but is not necessarily limited to:
Two buildings at the park are proposed for renovations.
Staff Quarters:
- Hazardous Material Abatement.
- Roof renovations include removing the roof, new attic trusses, new roof system/eaves/soffits & chimney repairs.
- Foundation & drainage repairs.
- Electrical Improvements.
Lodge Building:
- Hazardous Material Abatement.
- Roof renovations include removing the roof, new attic trusses, new roof system/eaves/soffits, and chimney repairs.
- Interior renovations include plumbing supply and waste piping replacement, furnace and boiler replacement, water heater replacement, and electrical wiring replacement.
The site is located Porcupine Mountains Wilderness State Park, Silver City, Michigan, as shown on the Drawings.
3. Bidding Documents Sets of Bidding Documents may be obtained at https://sigma.michigan.gov/webapp/PRDVSS2X1/AltSelfService .
4. Bid Security Each Bid must enclose Bid Security, in the amount of five percent (5%) of the Bidder's Base Bid, paid to the “State of Michigan” in the form of a certified or cashier’s check or money order drawn upon a bank insured by an agency of the Federal Government or a bid bond with an authorized surety company. If Bid Security is by check or money order, such certified or cashier’s check or money order must be delivered in original copy before the Bid Due Time to:
State Facilities Administration Design & Construction Division
3111 W. St. Joseph Street Lansing, Michigan 48917
All other Bid information must be submitted via SIGMA as per standard bidding procedure
5. Pre-Bid Conference A mandatory voluntary pre-bid conference will be held at park headquarter, Porcupine Mountains
Wilderness State Park, Silver City, MI on Thursday January 19, 2023, at 11:00 a.m. Local Time (Eastern). A tour of each of the structures will be held on the same day, starting immediately following the pre-bid meeting. All prospective Bidders are required encouraged to attend the tour, if held. Other parties interested in the Work are encouraged to attend the tour. Addenda may be issued, in response to issues raised at the pre-bid conference and tour, or as the Owner and/or Professional may otherwise consider necessary.
The purpose of the pre-bid conference and inspection is to answer questions and provide an inspection tour of the Project site at the scheduled time on the day of the meeting. A representative will be available to assist the Contractors. Other inspection visits may be allowed if needed. Individuals needing special services to fully participate in the meeting due to a disability may contact Mike Knack, Park Manager at 906-885-5274.
6. SIGMA VENDOR NUMBER: If you are bidding a State job for the first time, visit the State of Michigan SIGMA website, https://sigma.michigan.gov/webapp/PRDVSS2X1/AltSelfService, and follow the “SOM VSS User Guide for New Vendors” instructions, located under Forms and Reference Documents. Registration is required for bid submission. Do not wait until the last minute to submit a proposal, as the SIGMA system requires the creation of an account and entry of certain information, in addition to uploading and submitting the materials. The SIGMA system will not allow a proposal to be submitted after the proposal deadline, even if a portion of the proposal has been updated.
Questions on how to submit information or how to navigate in the SIGMA VSS system can be answered by calling (517) 373-4111 or
(888) 734-9749.
Bidding and Contract Document (R 03/21) Project Name: Various Historic Buildings Upgrades File No. 751/19141.TAP
00-2
7. Equal Employment Opportunity Covenants to not discriminate in employment by Contractors, Subcontractors and Suppliers required by Law are contained in Instructions to Bidders and General Conditions and are applicable to the Work and any Sub-agreement under the Contract.
8. Contract Times The Contract Times and the associated liquidated damages are specified in the Contract.
9. Contact Person All requests or inquiries concerning the Bidding Documents or the Work must be addressed to: Emmett Bjorn, PE, at U.P. Engineers & Architects, Inc., 100 Portage Street, Houghton, MI 49931 (erbjorn@upea.com). Questions will be accepted until January 24, 2023 at 5:00 p.m. Local Time (Eastern).
10. Award Subject to any agreed extension of the period for holding Bids, Bids must remain valid for acceptance by the Owner for
60 Calendar Days after the date of Bid opening. In addition, the Owner expressly reserves the right, within the Owner's sole discretion, to reject any or all Bids, to waive any irregularities, to issue post-Bid Addenda and re-bid the Work without re-advertising, to re-advertise for Bids, to withhold the award for any reason the Owner determines and/or to take any other appropriate action.
11. Performance and Payment Bonds – A performance bond and a payment bond are required for all contracts over $50,000.00.
END OF SECTION 00010
Bidding and Contract Document (R 03/21) Project Name: Various Historic Buildings Upgrades File No. 751/19141.TAP
00-3
SECTION 00100 INSTRUCTIONS TO BIDDERS
1. PREPARATION OF BID: Execute Bid fully and properly. Bid Summary Form (DTMB -0401D) and Bid Form Attachments must be used and completely filled out for the Bid to be considered responsive and meeting the requirements of the contract solicitation.
All Bid prices must be printed or typed in both words and figures.
2. BID CHECKLIST: Submit Bid Summary Form with original signatures plus Bid Form Attachments in accordance with the electronic bidding procedures on the SIGMA VSS website.
A complete Bid will consist of the following forms, which are included immediately following the Bid Summary Form:
Bids SUBMIT THESE Bid Forms and Bid Form Attachments
All Bids □ Signed and completed Bid Summary Form (DTMB-0401D);
□ Bid Schedule;
□ Qualified Disabled Veteran (QDV) Business Representation;
□ Bid Security in the amount of 5% of Base Bid Price;
If Bid Security is by check or money order, such certified or cashier’s check or money order must be delivered in original copy before the Bid Due Time to:
State Facilities Administration Design & Construction Division
3111 W. St. Joseph Street Lansing, Michigan 48917
All other Bid information must be submitted via SIGMA as per standard bidding procedure
□ Signature Authorization or copy of the partnership agreement if signed by all partners;
□ Other Forms; (Byrd Anti-Lobbying Certification, included in Appendix V)
Over $50K □ Forms listed under All Bids;
□ Payment and Performance Bond (upon issuing the Notice of Award).
Over $100K □ Forms listed under All Bids;
□ Certification of a Michigan Based Business;
Over $250K □ Forms listed under All Bids;
□ Certification of a Michigan Based Business;
Apparent Low Bidders ONLY (upon request from the Professional)
□ Experience Modification Rating (EMR), or a letter stating why the Bidder does not have one.
□ Identification of the proposed project superintendent, with a resume or list of similar projects handled by that individual.
□ A list of at least three (3) projects completed by the Bidder, within the last three (3) years of similar size and complexity, with contact information for references for each.
□ A list of nominated sub-contractors, including proposed self-performed categories, for each
Division/Trade/etc.
3. BID SUBMISSION: Bids must be submitted electronically through the SIGMA VSS website at https://sigma.michigan.gov/webapp/PRDVSS2X1/AltSelfService.
4. BID GUARANTEE: Each proposal must be accompanied by either a bank certified or cashier's check on an open, solvent bank or a bid bond with an authorized surety company (the surety must be listed on the current U.S. Department of the Treasury Circular 570) in the amount of five percent of the base bid payable to the State of Michigan, as a guarantee of good faith. If the successful Bidder fails to furnish satisfactory bonds and insurance within fifteen Calendar Days after Notice of Award, such guarantee must be forfeited to the State as liquidated damages. If Bid Security is by check or money order, such certified or cashier’s check or money order must be delivered in original copy before the Bid Due Time to the Issuing Office. The bid security, exclusive of https://sigma.michigan.gov/webapp/PRDVSS2X1/AltSelfService
Bidding and Contract Document (R 03/21) Project Name: Various Historic Buildings Upgrades File No. 751/19141.TAP
00-4 bid bonds, of all unsuccessful Bidders will be returned when an award is made or upon substitution of a bid bond. The bid security of the successful Bidder will be returned when the performance bond and labor and material bond are approved.
5. Left Blank Intentionally.
6. MICHIGAN BASED BUSINESS CERTIFICATION: All Bidders submitting Bids in excess of $100,000.00 must complete the
Certification of Michigan Based Business. This information will determine if a Bidder qualifies as a "Michigan" business for purposes of application of reciprocity where applicable.
7. POST-BID SUBMITTAL: For all projects, the Professional may request a Post-Bid Submittal from the Apparent Low
Bidders. The Apparent Low Bidders must submit to the Professional, within two Business Days after receipt of the Professional’s request,
• Experience Modification Rating (EMR), or a letter stating why the Bidder does not have one.
• Identification of the proposed project superintendent with a resume or list of similar projects managed by that individual.
• A list of at least three (3) projects completed by the Bidder, within the last three (3) years of similar size and complexity, with contact information for references for each.
Failure to provide the submittals may disqualify the Bid.
8. SIGNATURES: All Bids, notifications, claims, and statements must be signed as follows:
(a) Corporations: Signature of official must be accompanied by a certified copy of the Resolution of the Board of Directors authorizing the individual signing to bind the corporation.
(b) Partnerships: Signature of one partner must be accompanied by a signed copy of the legal document (e.g. Power of Attorney or partnering agreement) authorizing the individual signing to bind all partners. If Bid is signed by all partners, no authorization is required.
(c) Individual: No authorization is needed. Each signature must be witnessed.
9. BID PRICES: The Bidder’s Base Bid and Alternate Bid prices must include, and payment for completed Work will compensate in full for: all services, obligations, responsibilities, management, supervision, labor, materials, devices, equipment, construction equipment, general conditions, permits, patent fees and royalties, testing, inspection and approval responsibilities, warranties, temporary facilities, small tools, supplies, Bonds, insurance, taxes, mobilization, close-out, overhead and profit and all connections, appurtenances and any other incidental items of any kind or nature, as are necessary to complete the Work, in a neat, first quality, workmanlike and satisfactory manner in accordance with the Drawings and Specifications and as otherwise required to fulfill the requirements of the Bidding Documents. For each Cash Allowance item, the Bidder must include, within the Bid, all labor costs, construction equipment costs, insurance and Bond premiums and other general conditions costs and Fees (Bidder’s and Subcontractors’) to complete Work associated with the material, equipment or other designated item to be furnished under the Cash Allowance. For each Provisionary Allowance, the Bidder must include, within the Bid, insurance, premiums (not recoverable as labor burden) and Bond premiums required to complete Work that may be ordered under a Provisionary Allowance.
10. INSPECTION OF BIDDING DOCUMENTS AND SITE CONDITIONS: The Bidder must carefully review and inspect all documents referenced and made part of this ITB, site conditions, all applicable statutes, regulations, ordinances and resolutions addressing or relating to the goods and services under this contract. Failure to do so or failure to acquire clarifications and answers to any discovered conflicts, ambiguities, errors or omissions in the Bidding Documents will be at the Bidder’s sole risk.
11. SAFETY REQUIREMENTS AND LAWS: The Bidder awarded the Contract must comply with all applicable federal, state and local Laws including health and safety regulations, environmental protection, permits and licensing.
12. INTERPRETATIONS AND ALTERATIONS TO THE BID AND BIDDING DOCUMENTS: All requests for clarification or interpretation of the Bidding Documents, all proposals for any modifications to the Bidding Documents, all requests for information and all other questions or inquiries about the Bidding Documents and/or the Work shall be submitted in writing to the Contact Person identified in the Bid Documents. Requests or inquiries received less than seven Calendar Days before the date of Bid opening will be answered only if (a) the response can be given through an Addendum made available at least seventy-two hours before Bid opening (counting Business Days only), (b) the Bid opening is postponed by Addendum, or (c) the Work is rebid without readvertising following the issuance of post-Bid Addenda.
Bidders must not rely upon any oral statements or conversations regarding interpretations, clarifications, corrections, additions, deletions or other revisions or information to the Bidding Documents. Any addition, limitation or provision made with or attached to the Bid may render it non-responsive and/or irregular and be a cause for rejection. The Owner reserves the right to issue a post-Bid Addendum after opening the Bids and set a new date for the receipt and opening of sealed Bids. The Bidder acknowledges that any quantities of Unit Price Work given in this ITB are approximate only and payments will be made only for actual quantities of Unit Price Work completed in accordance with the Contract Documents.
13. MODIFICATION OF BID: The entire bid must be resubmitted on the SIGMA VSS website.
Bidding and Contract Document (R 03/21) Project Name: Various Historic Buildings Upgrades File No. 751/19141.TAP
00-5
14. BID WITHDRAWAL: Except for timely filed claims of mathematical or clerical errors granted by the State, no Bid may be withdrawn within sixty Calendar Days after the Bid Opening time and date or before the Bid expiration date without forfeiting Bid security. The request to withdraw a Bid due to error must be submitted in writing along with the supporting documents within two Business Days after the date of Bid Opening. The claim must describe in detail the error(s), include a signed affidavit stating the facts of the alleged error(s) and request that the Bidder be released from its Bid. The review of the claim and its supporting documents by the State is only for the purpose of evaluating the Bidder’s request and must not create duty or liability on the State to discover any other Bid error or mistake. The sole liability of any Bid error or mistake rests with Bidder.
15. OBJECTION TO THE AWARD: A Bidder may file a written protest with the Director-SFA to object to the Apparent Low Bidder. This objection must be filed within seven Calendar Days after the date of Bid opening and must describe in detail the basis for the protest and request a determination. The Director-SFA will either dismiss or uphold the protest and notify the protestor within ten Calendar Days after receipt of the written protest.
16. BID IRREGULARITIES: The following irregularities on any Bid Form or Bid Form Attachment must be resolved as follows:
(a) between SIGMA entry and signed Bid Summary attachment, the signed Bid Summary attachment will be used;
(b) between words and figures, the words must be used;
(c) between any sum, computed by the Bidder, and the correct sum, the sum computed by the Bidder must be used;
(d) between the product, computed by the Bidder, of any quantity and Bid Unit Price and the correct product of the Unit Price and the quantity of Unit Price Work, the product extended by the Bidder must be used;
(e) between a stipulated Allowance and the amount entered, the Allowance must be used;
(f) any mobilization pay item exceeding the maximum specified must be ignored and the Bid must remain unchanged;
(g) if any Bidder fails or neglects to bid a Unit Price for an item of Unit Price Work but shows an "Bid Price" for that i tem, the missing unit price must be computed from the respective quantity and the Item Bid Price shown;
(h) if any Bidder fails or neglects to show a "Bid Price" for an item of Unit Price Work but bids a unit price, the missing Bid Price must remain as “zero”; and
(i) if any Bidder fails or neglects to enter a Bid Price in both words and figures, the Bid Price printed or typed, whether in words or figures, must be used.
17. CERTIFICATION: The bidder certifies to the best of its knowledge and belief that, within the past three (3) years, the bidder, an officer of the bidder, or an owner of a 25% or greater interest in the bidder:
(a) Has not been convicted of a criminal offense incident to the application for or performance of a contract or subcontract with the State of Michigan or any of its agencies, authorities, boards, commissions, or departments.
(b) Has not had a felony conviction in any state (including the State of Michigan).
(c) Has not been convicted of a criminal offense which negatively reflects on the bidder’s business integrity, including but not limited to, embezzlement, theft, forgery, bribery, falsification or destruction of records, receiving stolen property, negligent misrepresentation, price-fixing, bid-rigging, or a violation of state or federal anti-trust statutes.
(d) Has not had a loss or suspension of a license or the right to do business or practice a profession, the loss or suspension of which indicates dishonesty, a lack of integrity, or a failure or refusal to perform in accordance with the ethical standards of the business or profession in question.
(e) Has not been terminated for cause by the Owner.
(f) Has not failed to pay any federal, state, or local taxes.
(g) Has not failed to comply with all requirements for foreign corporations.
(h) Has not been debarred from participation in the bid process pursuant to Section 264 of 1984 PA 431, as amended, MCL
18.1264, or debarred or suspended from consideration for award of contracts by any other State or any federal Agency.
This is the start of the file's text. The full file is on GovTribe.
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .