GOLDEN GATE
NATIONAL RECREATION AREA
Contract No. C8078080174
Task Order No. T8147110026 GOGA PMIS No. 164335
REHABILITATE STINSON BEACH WASTEWATER SYSTEM
FINAL CONSTRUCTION
DOCUMENTS
December 5, 2014
MARCH 23, 2015
NATIONAL PARK SERVICE
PACIFIC WEST REGION
GOGA – 164335 BID SCHEDULE - 1
CONTRACT BID SCHEDULE
REHABILITATE STINSON BEACH WASTEWATER SYSTEM
Submit bid for all items; failure to do so may render the bid non-responsive. On lump sum bid items, provide total price only; on unit price bid items, provide the unit price and the extended amount of bid. If no bid item exists for a portion of the work, include the cost in a relative bid item. In case of error in extension of prices, unit price governs. In case of error in summation, the total of the corrected bid amount governs.
Price award will be made based upon the following equation. The equation that is used will be at the
Government’s discretion based upon available funding at the time of award.
Equation 1: Base Price + Bid Option A + Bid Option B + Bid Option C + Bid Option D +
Bid Option E + Bid Option F + Bid Option G + Bid Option H + Bid Option I
Equation 2: Base Price + Bid Option A + Bid Option B + Bid Option C + Bid Option D +
Bid Option E + Bid Option F + Bid Option G + Bid Option H
Equation 3: Base Price + Bid Option A + Bid Option B + Bid Option C + Bid Option D +
Bid Option E + Bid Option F + Bid Option G
Equation 4: Base Price + Bid Option A + Bid Option B + Bid Option C + Bid Option D +
Bid Option E + Bid Option F
Equation 5: Base Price + Bid Option A + Bid Option B + Bid Option C + Bid Option D +
Bid Option E
Equation 6: Base Price + Bid Option A + Bid Option B + Bid Option C + Bid Option D
Equation 7: Base Price + Bid Option A + Bid Option B + Bid Option C
Equation 8: Base Price + Bid Option A + Bid Option B
Equation 9: Base Price + Bid Option A
Equation 10: Base Price
Description of Project Divisions
Base Price: Price Items 1 through 15
Bid Option A: Replace South Comfort Station Septic Tank
Bid Option B: Replace North Comfort Station Septic Tank
Bid Option C: Replace Central Comfort Station Septic and Wet Well Tanks
Bid Option D: Remote SCADA Call Out System
Bid Option E: Replace Electrical Panels at Comfort Stations
Bid Option F: Mill and Pave Lifeguard Driveway
Bid Option G: 3” Force Main from South Comfort station to Secondary Treatment
Bid Option H: Mill and Pave 10 Foot Wide Pedestrian Path
Bid Option I: Replace Admin / Maintenance Septic Tank
GOGA – 164335 BID SCHEDULE - 2
CONTRACT
LINE ITEM
NUMBER
(CLIN)
CONTRACT LINE ITEM (CLI) TITLE QUANTITY
UNIT OF
MEASURE
UNIT PRICE TOTAL PRICE
1 Mobilization and Demobilization 1 Lump Sum
2 SWPPP 1 Lump Sum
PG&E Permit and Service
Connection 1 Lump Sum
Disposal Field Vegetation
Removal 1 Lump Sum
5 Disposal Field and Fence 1 Lump Sum
3” Force Main (RTF to Disposal
Field) 775 Lineal Foot
3” Force Main
(Primary Treatment to RTF) (2,253 trench)
3,441 Lineal Foot
CONTRACT PRICE SCHEDULE
SOLICITATION NUMBER: TBD
PARK - PMIS: 164335
DEVELOPED AREA: STINSON BEACH
PROJECT TITLE: Replace Stinson Beach Wastewater System
Notice: Refer to FAR Clause 52.217-5, Evaluation of Options, as prescribed in FAR 17. Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced line items, provide the unit price and the extended total price. If no specific l ine item exists for a portion of the work, include the costs in a related item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts govern. Round totals and extended prices to whole dollars. The Government reserves the right to award any or no options at or after the time of award. At the option of the Government, the period for exercise of options at the proposed prices shall extend 180 calendar days from the date of award. Pricing will be evaluated based on what is determined to be the best value to the Government. Options may be exercised in any combination, order, or grouping deemed in the judgment of the
Contracting Officer to offer the best value to the Government.
In addition to the offer that conforms to the solicitation documents, offerors are encouraged to submit alternate proposals that will result in cost savings to the Government. Such proposals shall clearly identity why the acceptance of the alternate proposal would be advantageous to the Government, see FAR Clause 52.215-1, Instructions to Offerors - Competitive Acquisition-Alternate
II and DSC-36 Clause (Instructions for Submission of Offers and Other Information) in Section L of the Solicitation.
GOGA – 164335 BID SCHEDULE - 3
8 Asphalt Paving 18 Ton
Tank and Disposal Field
Abandonment 1 Lump Sum
10 Service and Pressure Test Tanks 1 Lump Sum
Lifeguard/Ranger Building Septic
And Wet Well Tanks 1 Lump Sum
Secondary Treatment
(RTF System and Wood Fence) 1 Lump Sum
Primary Treatment (Wet Wells)
Pump, Control and Local Alarm
System
1 Lump Sum
Gravity Sewer Main Lifeguard, Ranger Building, Admin/Maintenance
Area
277 Lineal Foot
Conduit and Pull Boxes for
Future Remote SCADA
Call Out System
3,741 Lineal Foot
OPTION A, Replace South Comfort
Station
Pump Vault
1 Lump Sum
OPTION B, Replace North
Comfort Station
Septic Tank
1 Lump Sum
OPTION C, Replace Central
Comfort Station
Septic and Wet Well Tanks
1 Lump Sum
OPTION D, Remote SCADA Call
Out System 1 Lump Sum
OPTION E, Replace Electrical
Panels at
Comfort Stations
3 Each
TOTAL BASE PRICE (Contract Line Item Number 1 through 15) ------------------------------------
GOGA – 164335 BID SCHEDULE - 4
OPTION F, Mill and Pave
Lifeguard Driveway 32 Ton
OPTION G, 3” Force Main from
South Comfort station to
Secondary Treatment
1 Lump Sum
OPTION H, Mill and Pave 10 Foot
Wide Pedestrian Path 123 Ton
OPTION I, Remove and Dispose
1,800 gallon Septic Tank. Install
1,200 gallon Septic Tank
1 Lump Sum
Al l measurement and payment information is included in the project speci fications , Section 012700.
TOTAL PRICE FOR ALL OPTIONS (Contract Line Item Numbers 16 through 24) ------------------------------------
TOTAL PROPOSED PRICE - BASE PLUS ALL OPTIONS (Contract Line Item Numbers 1 through 24) -----------
END OF SECTION
GOGA – 164335 TOC - 1
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS NO. OF PAGES
01 11 00 Summary of Work
01 27 00 Definition of Contract Line Items
01 31 00 Project Management & Coordination
01 32 16 Construction Schedule
01 32 33 Photographic Documentation
01 33 23 Submittal Procedures
01 34 00 Natural Habitat Requirements
01 35 13.22 Archeological Protection
01 35 23 Safety Requirements
01 35 30 Hazardous Material
01 35 91 Historic Preservation Treatment Procedures
01 40 00 Quality Requirements
01 42 00 References
01 50 00 Temporary Facilities & Controls
01 52 00 Field Offices & Sheds
01 54 00 Traffic Control
01 56 00 Barriers
01 57 19.12 Noise & Acoustics Management
01 57 23 Temporary Storm Water Pollution Prevention
01 67 00 Product Requirements
01 73 40 Execution
01 74 19 Construction Waste Management & Disposal
01 77 00 Closeout Procedures
01 78 23 Operation & Maintenance Data
01 79 00 Demonstration & Training
01 81 13.13 Sustainable Design Requirements
Appendix A Submittal List
Appendix B List of Closeout Requirements
DIVISION 02 – EXISTING CONDITIONS
02 05 00 General Site Construction Requirements
02 23 00 Clearing & Grubbing
02 41 00 Demolition & Abandonment
02 41 19 Selective Demolition
02 92 00 Soil Preparation
GOGA – 164335 TOC - 2
DIVISION 03 - CONCRETE
03 11 13 Cast-In-Place Concrete Forms
03 15 10 Concrete Accessories – Epoxy Anchors
03 21 00 Concrete Reinforcing Steel
03 30 00 Cast-In-Place Concrete Site Elements
03 31 00 Normal Weight Structural Concrete
03 40 00 Precast Concrete Items
DIVISION 04 – MASONRY (Section not used)
DIVISION 05 – METALS (Section not used)
DIVISION 06 – WOOD, PLASTICS, & COMPONENTS (Section not used)
DIVISION 07 – THERMAL & MOISTURE PROTECTION
07 13 00 Sheet Waterproofing (Not Used)
DIVISION 08 – OPENINGS (Section not used)
DIVISION 09 - FINISHES
09 90 00 General Painting & Coating Requirements
09 97 13.23 Exterior Painted Iron & Steel
DIVISION 10 – SPECIALTIES (Section not used)
DIVISION 11 – EQUIPMENT (Section not used)
DIVISION 12 – FURNISHINGS (Section not used)
DIVISION 13 – SPECIAL CONSTRUCTION
13 28 00 Lead Containing Paint Procedures
13 28 10 Mercury Procedures
DIVISION 14 – CONVEYING EQUIPMENT (Section not used)
DIVISION 21 – FIRE SUPPRESSION (Section not used)
GOGA – 164335 TOC - 3
DIVISION 22 - PLUMBING
22 00 00 Plumbing General Requirements
22 11 23.36 Pumps
22 13 13 Facility Sanitary Sewers
DIVISION 26 - ELECTRICAL
26 00 00 Electrical General Requirements
26 05 00 Common Work Results for Electrical
26 05 19 Low Voltage Electrical Power Conductors & Cables
26 05 26 Grounding & Bonding for Electrical Systems
26 05 29 Hangers & Supports for Electrical Systems
26 05 33 Raceways & Boxes for Electrical Systems
26 05 48 Seismic Requirements for Electrical Systems
26 05 53 Identification for Electrical Systems
26 22 00 Low Voltage Transformers
26 24 16 Panelboards (To be edited to include load centers)
26 27 26 Wiring Devices
26 28 13 Fuses
26 28 16 Enclosed Switches & Circuit Breakers
DIVISION 27 – COMMUNICATIONS (Section not used)
DIVISION 28 – ELECTRONIC SAFETY & SECURITY (Section not used)
DIVISION 31 – EARTHWORK
31 10 00 Site Clearing (general)
31 22 19 Finish Grading
31 23 16.10 Importing Soils & Fill Materials
31 23 33 Utility Excavation & Backfill
31 23 33.20 Restoration of Surfaces
31 25 00 Erosion & Sediment Control
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 11 23 Aggregate Base Course
32 12 16 Asphalt Concrete Paving
32 31 13 Chain Link Fencing
32 31 15 Wood Fences & Gates
GOGA – 164335 TOC - 4
DIVISION 33 – UTILITIES
33 05 23 Trenchless Sewer Pipe Installation – Pipe Bursting
33 05 26.16 Utility Line Identification Marking
33 11 00.10 Testing of HDPE Sewer Force Main Piping
33 34 00 HDPE Sanitary Sewer Force Main Piping
33 36 33.16 Pressurized Dispersal Drain Field System
DIVISION 34 – TRANSPORTATION (Section not used)
DIVISION 35 – WATERWAY & MARINE CONSTRUCTION (Section not used)
DIVISION 40 – PROCESS INTEGRATION (Section not used)
DIVISION 41 – MATERIAL PROCESSING & HANDLING EQUIPMENT (Section not used
DIVISION 42 – PROCESS HEATING, COOLING, & DRYING EQUIPMENT (Section not used)
DIVISION 43 – PROCESS GAS & LIQUID HANDLING, PURIFICATION,
& STORAGE EQUIPMENT (Section not used)
DIVISION 44 – POLLUTION CONTROL EQUIPMENT (Section not used)
DIVISION 45 – INDUSTRY – SPECIFIC MANUFACTURING EQUIPMENT (Section not used)
DIVISION 46 – WATER AND WASTEWATER EQUIPMENT
46 07 53 Packaged Wastewater Treatment
DIVISION 48 – ELECTRICAL POWER GENERATION (Section not used)
GOGA – 164335 TOC - 5
APPENDICES
APPENDIX A - Supplemental Exploration to “Pot Hole” Utilities and Observe Subsurface Conditions –
Letter Dated December 9, 2014.
APPENDIX B – Highway 1 Parcel Geo-tech Report for percolation for disposal area.
APPENDIX C - PG&E Engineering Estimate Fee.
APPENDIX D - NPS Standard BMPs.
APPENDIX E - NPS Standard Signage.
APPENDIX F - State Water Resource Control Board (SWRCB) Sewer Water Separation Conditional
Variance.
DIVISION 01
GENERAL REQUIREMENTS
GOGA – 164335 01 11 00 - 1
SUMMARY OF WORK
SECTION 01 11 00
PART 1 – GENERAL
1.1 SUMMARY
A. This Section includes the following:
1. Work covered by the Contract Documents.
2. Work phases.
3. Work under other contracts.
4. Contractor use of premises.
5. Occupancy requirements for buildings.
6. Work Restrictions.
7. Special Construction Requirements.
8. Additional Reports.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: Golden Gate National Recreation Area, California, Stinson Beach, Marin
County.
B. The Work consists of the following:
1. The Work includes the installation of a sewer recirculating textile treatment facility
(RTF) with inflow equalization tank and outflow distribution tank, pressure disposal drainfield, replacement/installation of one (1) septic tank, one (1) pump station vault, rehabilitation of two (2) pump station vaults, one (1) septic tank, replacement of six (6) lift station pumps, installation of two (2) new lift station pumps, four (4) force mains, three (3) gravity sewer service lines and related piping and appurtenances with alarm modifications and telemetry system additions within Stinson Beach. The work includes bid options for replacement/installation of two (2) septic tanks, two (2) pump station vaults, one (1) septic tank, one (1) force main.
2. All concrete septic and wet well tanks are to be pressure tested, those that fail will have penetrations sealed and tank retested. (EXCEPTION: If bid option to replace tank is awarded, tank to be replaced shall not be pressure tested. Only new tank replacement installed shall be tested.
3. This Project will be constructed under a single prime contract.
4. The Contractor will be responsible for their work which will include:
a. Clean and inspect septic tanks and pump vaults for serviceability. If found unserviceable Contractor shall excavate and replace tanks or vaults with appropriately sized concrete septic tanks and vaults as specified in the specifications. (Tanks having the highest risk of being unserviceable are bid options. Other tanks outside bid options found to be unserviceable will require an equitable adjustment for replacement.) Contractor shall use best management practices for all tank excavations and piping installation.
GOGA – 164335 01 11 00 - 2
b. Provide and install submersible pumps and pump chambers compatible to the pump vaults to include all wiring, controls, floats, alarms, and appurtenances as specified.
Pump vaults shall be plumbed into the riser of the pump vault and the pump controls wired to the central wastewater treatment system that will consist of a proprietary recirculating textile filter (RTF). Contractor shall employ best management practices for all underground piping and wiring installation.
c. Provide and construct the central wastewater treatment system that utilizes a proprietary RTF technology. Contractor shall ensure pumping stations and their controls are compatible and appropriately sized to support the centralized wastewater treatment system. Contractor shall employ best management practices for all underground tank, piping and wiring installation to prevent site environmental impacts.
d. Supply and install final lift station to pump treated effluent to the subsurface drainfield as shown on the plans and specifications. Work shall include all piping
(base bid item) and controls wiring (bid option item) necessary to manage and control the system from the NPS Supervisory Control and Data Acquisition
(SCADA).
i. SCADA integration is a bid option item.
ii. The NPS SCADA system to be integrated into is “Mission Control”
iii. Local audio/visual alarms is a base bid component
e. Provide and install subsurface drainfield with pre-fabricated infiltrators as shown on plans and specifications.
f. Contractor shall ensure all materials, equipment, equipment installation, and construction will produce fully functional lift stations, wastewater treatment systems, and subsurface drainfield that are capable of being controlled (by the
SCADA system – bid option).
g. Install electrical conduit and wire as depicted, including utility service and all of main conduit group between control building and electrical components.
h. Install communications conduit, cable, and ancillaries as depicted and specified.
i. Install piping and valves as shown on plans to convey septic tank effluent to the
RTF system, RTF treated effluent to the subsurface drainfield, and dispersal of treated wastewater through-out the subsurface drainfield.
j. Fill with imported material to rough grade elevation, including special foundation excavation and special engineered sub-grade for reinforced earth.
k. Construct, install, and integrate electrical and wastewater treatment system control equipment with the NPS SCADA system “Mission Control”.
i. SCADA integration is a bid option item.
ii. The NPS SCADA system to be integrated into is “Mission Control”
iii. Local audio/visual alarms is a base bid component.
l. Fine grade and restore site surfaces as depicted on plans.
m. Cleanup, repair, and restore areas temporarily used during construction, including fence repair and fence replacement.
GOGA – 164335 01 11 00 - 3
1.3 WORK PHASES
A. The Work shall be conducted in phases in the below order, with each phase substantially complete before beginning the next phase. Purpose of phasing is to minimize service outages/temporary services and impacts to adjacent property owners during construction. Note that local weather conditions will have greater impact to some of the phases with respect to the
State of California SWPPP permitting and monitoring and should be considered in the approach and scheduling of work. Modification to phasing may be considered if benefits can be demonstrated that achieve fundamental purpose of phasing.
Phase I: Disposal Field – Installation of complete disposal field system that will allow for system to be put into service without additional construction (other than calibration during startup of the force main pumping system to the disposal field). Includes soil stabilization requirements based on Golden Gate National Recreation Area (GGNRA) standard BMP’s as per Appendix D, and approved SWPPP/permit. Includes security fencing and site clean up;
does not include any required paving/patching as that can be done concurrently with other paving/patching for the project.
Phase II: Force Main Disposal Field to Secondary Treatment (RTF System) – Installation of 3” force main from disposal field to secondary treatment system, recirculating textile filter system located within the NPS administrative area. Work also includes vault for future connection of disinfection system and conduit and associated pull boxes from zone valve control box in disposal field to secondary treatment area.
Phase III: Secondary Treatment (RTF System) – Installation of recirculating textile filter system to include new power service, water system hose bibs for servicing RTF system pods, final grading and replace wood fence removed along west side of work area with new fence.
The RTF system will be ready for system startup and calibration by manufacture’s certified representative at completion of this phase.
Phase IV: NPS Administrative/Maintenance Area Tank and Gravity Sewer Main
(Base Bid) Installation of new gravity sewer main from existing septic tank to RTF equalization tank. Servicing the existing septic tank, sealing of penetrations as needed to pass pressure test and abandonment of existing wet well tank.
(Bid Option) Remove and dispose of existing 1,800 gallon septic tank. Replace with and install 1,200 gallon septic tank.
GOGA – 164335 01 11 00 - 4
Phase V: Secondary Treatment (RTF System) Start-Up and Initial Calibration – This phase will be initiated immediately following the work from Phase IV. Work includes RTF system startup by manufactures certified representative and initial system calibration.
Concurrently the NPS Administrative/Maintenance Area will be cut-over to the new RTF system and disposal field and utilized for system startup and calibration. Due to small waste water production by NPS Administrative/Maintenance Area, water may be required to be added to system for startup. Contractor is responsible for providing water as per specification 01 11
00 Summary of Work section 1.7 Work Restrictions. Contractor is responsible for maintaining, operating and servicing if necessary the RTF system and disposal field until whole project substantial completion and NPS owner training. Initial system startup and calibration by certified manufactures representative can NOT be conducted at same time as NPS owner training. NPS owner training will be done after substantial completion and final calibration of the RTF system and other project pump stations.
Phase VI: Force Main Conveyance
(Base Bid) Install 3” force mains from North Comfort Station, Central Comfort Station, Lifeguard/Ranger Building, South Comfort Station extension to secondary treatment system
(RTF). Includes all project paving and patching as necessary.
(Bid Options) Install new 3” HDPE force main along existing 3” force main and abandon existing force main in place.
Phase VII: South Comfort Station
(Base Bid) Work includes servicing existing 5,300 gallon septic tank and wet well tanks, sealing penetrations to pass pressure test. Remove existing pump and control system and replace with new pumps and control system with local audio/visual alarm system. Connect new pump system into existing 3” force main. At completion of phase, the comfort station will operate on new RTF and disposal field. Pressure test of existing wet well tank is not required if bid option to replace tank is awarded.
(Bid Options) Work includes removal and disposal of existing 5,300 gallon wet well tank and replace with 3,000 gallon concrete tank in same location pressure tested. Replace main 100amp electrical panel and provide SCADA call out notification system integrated with new local audio/visual alarm provided in base bid work.
Phase VIII: North Comfort Station replace with new pumps and control system with local audio/visual alarm system. Connect new pump system into new 3” force main. At completion of phase, the comfort station will operate on new RTF and disposal field. Pressure test of existing septic tank is not required if bid option to replace tank is awarded.
(Bid Options) Work includes removal and disposal of existing 5,300 gallon septic tank and replace with 3,000 gallon concrete tank in same location pressure tested. Replace main 100amp electrical panel and provide SCADA call out notification system integrated with new local audio/visual alarm provided in base bid work.
GOGA – 164335 01 11 00 - 5
Phase IX: Central Comfort Station replace with new pumps and control system with local audio/visual alarm system. Connect new pump system into new 3” force main. At completion of phase, the comfort station will operate on new RTF and disposal field. Pressure test of existing septic and wet well tanks is not required if bid option to replace tanks is awarded.
(Bid Options) Work includes demolition in place of the existing wet well tank and adaptive re-use (sitting area) of the existing septic tank. Install two new concrete 5,000 gallon septic and wet well tanks on east downslope side of comfort station. The work includes all mechanical piping and electrical to gravity flow from comfort station to septic tank and then to wet well tank. Replace main 100amp electrical panel and provide SCADA call out notification system integrated with new local audio/visual alarm provided in base bid work.
Phase X: Lifeguard/Ranger Building Primary Treatment System
(Base Bid) Work includes installation of new 1,500 gallon septic tank and wet well tanks.
Remove existing pump and control system (at Ranger Building) and replace with new pumps and control system in new wet well with local audio/visual alarm system. Demolish existing
5,300 gallon septic tank in place, demolish ranger building lift station. Connect new pump system into new 3” force main. At completion of phase, the lifeguard and ranger building will operate on new RTF and disposal field.
(Bid Options) Work includes providing SCADA call out notification system integrated with new local audio/visual alarm provided in base bid work.
Central Comfort Station and Lifeguard/Ranger Building change in phase order based on time of year, weather and visitation such that work is done during low visitation.
Phase XI: Substantial Completion
Within two (2) week of declaring substantial completion, final calibration of secondary treatment system (RTF) and new pump stations at each primary treatment location by authorized manufacture representative will be conducted. The day following final calibration will be NPS owner training by same representative who calibrated systems. Owner training will NOT occur until final calibration is completed, if calibration is not complete by scheduled date of owner training, the training will be rescheduled at cost to contractor.
1.4 CONTRACTOR USE OF SITE
A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to areas within the Contract limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Limits: Confine constructions operations to within the fenced perimeter of the Stinson
Beach as specifically delineated on the construction drawings
GOGA – 164335 01 11 00 - 6
2. Access: U.S. Highway 1 to Marine Way will be used for all access to Stinson Beach for construction personnel, construction equipment, deliveries, etc. Private Road to
Administrative building area shall not be used for these activities unless approved by
NPS COR for deliveries that exceed the bridge load limit for Marine Way road access.
3. Contractor is responsible upon start-up and cut over of facilities to the new secondary treatment system (RTF) and disposal field to maintain the operation of the secondary treatment system until substantial completion and owner training has been completed.
Contractor will provide certified manufactures representative to conduct field startup of the RTF system and upon substantial completion a second site visit to conduct final calibration of the system, ensure system is performing as per design/manufactured and finally conduct owner training.
4. Park Archeologist is required to be on site during all excavation, contractor’s weekly meeting two week look ahead must specifically address ground disturbance coordination. During excavation if any items encountered are of potential archeological importance, contractor will stop work in that location and relocate work effort to other parts of the project until the site is cleared by the NPS.
5. Utilities to support construction activities by contractor:
a. Water: Contractor to install NPS approved backflow preventer and meter at NPS specified location. Contractor will be billed monthly at rate of $65 per 1,000 gallons not to exceed 10,000 gallons per day. Prior to using water, agreement between NPS and contractor must be signed. Billings are sent electronically via email, thus additional information from contractor is point of contact information to send billings and finally company tax ID number.
b. Power: Contractor may use power from existing facilities while working directly on the facilities. Acceptable uses are for equipment associated with direct construction of the project. Objective to allowing contractor utilize power at facilities is to limit use of portable generators when possible to reduce noise and greenhouse gases
(carbon footprint of project).
B. Storage of Materials: Confine storage of materials to within the areas as described and delineated on the construction drawings for Stinson Beach wastewater system replacement.
C. Preservation of Natural Features:
1. All equipment shall be power washed and inspected before being off-loaded at Stinson
Beach Park to ensure it is free of non-native weeds and/or seeds. In addition sources of imported rock, sand, gravel, and soil shall be inspected for invasive non-native plants, weeds and/or seeds. The Contractor shall submit a list of proposed sources, end use and temporary storage requirements for imported material, 30 calendar days prior to delivery. Imported material shall be free of non-native weeds and/or seeds. Imported material shall be shipped directly from the source to the Park without intermediary storage or staging. Shipping vessels shall be covered to prevent spillage or blowing of their contents while in transit.
2. Prior to moving equipment from different locations on with the project site (i.e. South
Comfort Station Area to North Comfort Station Area) the equipment must be high air pressure cleaned and inspected by NPS COR prior to relocating in order to prevent spread of invasive plants.
GOGA – 164335 01 11 00 - 7
3. Prior to mobilizing equipment into each unique area within the project site (i.e. South
Comfort Station Area to North Comfort Station Area) contractor shall notify NPS two
(2) weeks prior so that arrangements can be made for removal of invasive weeds within work area; EXCEPTION is disposal field where contractor shall remove top 6” of soil from project site.
4. Top 6” of soil in any area will not be re-utilized as suitable fill within 18 inches from finish grade to prevent spread of invasive vegetation.
5. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
6. Provide temporary barriers to protect existing trees and plants and root zones.
7. Do not remove, injure, or destroy trees or other plants without prior approval.
8. Do not fasten ropes, cables, or guys to existing trees.
9. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
10. Erosion control measures will be in accordance with GGNRA’s BMP’s per Appendix
D, weed free, rice straw, and burlap outer filter/cover; NO plastic netting products.
11. The NPS will conduct re-vegetation and restoration of the project area post project completion. Contractor is responsible for erosion control and stabilization of each area as specified in construction drawings and in accordance with GGNRA’s BMP’s in appendix of the specifications; lastly in accordance with State of California General
Construction SWPPP Permit.
D. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
1. Schedule deliveries to minimize use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
E. Construction Camp: Establishment of a camp within the park will not be permitted.
F. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park
Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment. Ensure Marine Way (main public entrance to Stinson Beach) bridge load limit is not exceeded; contractor’s responsibility.
1.5 PUBLIC USE OF SITE
A. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public. Specific Stinson Beach comfort stations may be non-operational, when required, upon specific approval of Contracting Officer (CO) for a maximum of thirty (30) consecutive days in accordance with phasing 01 11 00 Summary of Work section 1.3 Work Phases. Only one comfort station may be out of service at one time. Exception may be granted for low visitation periods.
GOGA – 164335 01 11 00 - 8
1.6 OCCUPANCY REQUIRMENTS FOR BUILDINGS
A. Existing Buildings
1. Partial Government Occupancy: Government will occupy the premises during entire construction period, with the exception of areas under construction. Cooperate with
Government during construction operations to minimize conflicts and facilitate
Government usage. Perform the Work so as not to interfere with Government’s operations.
Maintain existing exits, unless otherwise indicated.
a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the Contracting Officer (CO).
1.7 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 8:00 a.m. to 4:30 p.m., Monday through Friday, no Federal Holidays. Extension of work hours may be authorized to allow for ten (10) hour work days with noise restrictions upon request and approval by Contracting Officer.
B. Vegetation Removal Restriction
1. No vegetation removal shall be performed during “Bird Nesting Season” from March
1st to July 31st.
C. Existing Utilities
1. Existing Utilities: USA Notification & Utility Field Meeting
a. The Contractor shall contact Underground Service Alert (USA) (1-800-642-2444) seven (7) calendar days prior to start of each ground disturbing phase and shall be responsible for maintaining a valid USA location tag through renewal during the construction. The Contractor shall schedule a utility field meeting prior to any excavation. This shall be so stated in the USA notification. The Contractor shall be responsible to coordinate the utility field meeting at which time he shall explain the limits and impacts to USA member utilities.
b. The majority of the utilities within Stinson Beach are owned by NPS. As such, very few utilities will actually be marked out by USA. It is the Contractor's responsibility to field locate & mark all utilities within the project work area. Field location and marking shall be performed a minimum of three (3) days prior to ground disturbance;
notify CO upon completion of field location and marking for CO review and approval.
No trenching shall be performed prior to CO approval.
2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
D. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by
Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify Contracting Officer not less than five (5) days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without Contracting Officer’s written permission.
GOGA – 164335 01 11 00 - 9
3. Hours for Utility Shutdowns: Specific Stinson Beach comfort stations may be non-operational, when required, upon specific approval of Contracting Officer for a maximum of thirty (30) consecutive days.
4. Contractor shall coordinate all power outages with PG&E; a minimum of two (2) weeks’ notice of outages will be provided to NPS; include all fees and inspection costs associated with new service connection. See appendix for PG&E estimated service connection costs.
1.8 SPECIAL CONSTRUCTION REQUIREMENTS
A. Contractor shall be responsible for all fees, inspection, and coordination associated with electrical power service; see Appendix C for PG&E engineering estimate fee.
B. State of California SWPPP: Contractor is required to provide QSD and QSP to include submit
SWPPP permit documents to the NPS. NPS will review and upon approval will pull permit;
contractor is required to pay permit fee(s). Typically it takes up to thirty (30) days between
NPS approved SWPPP document from contractor to issued permit; contractor to plan work schedule accordingly. Project anticipated level of SWPPP permit I or II depending largely on contractor’s schedule; likely that working through wet season (November thru April) will push permit into Level II.
C. Contractor is to provide public signage to inform public of closed facilities and notice of intent to close and/or open facility five (5) days prior to closure/opening. Signage for closed facilities will include what similar facilities are open to the public (Comfort Stations). Signs to be posted on “A” frames as per: http://www.plasticade.com/sign_frames/signicade/ or Equivalent.
Signs will conform to GGNRA standard signage; Appendix E.
1.9 ADDITIONAL REPORTS
A. Supplemental Exploration to “Pot Hole” Utilities and Observe Subsurface Conditions – Letter
Dated December 9, 2014. Exploration encountered subsurface ground water approximately five feet below ground surface in the parking lot area and filter treatment area; Appendix A.
B. Geotech Report done for percolation for disposal area; Appendix B.
C. PG&E Engineering Estimate Fee; Appendix C.
D. NPS Standard BMPs; Appendix D.
E. NPS Standard Signage; Appendix E.
F. State Water Resource Control Board (SWRCB) Sewer Water Separation Conditional Variance;
Appendix F
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
GOGA – 164335 01 27 00 - 1
DEFINITION OF CONTRACT LINE ITEMS
SECTION 01 27 00
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
PART 2 - PRODUCTS (Not Used)
PART 3 – EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
A. Contract Line Item No.1 – Mobilization & Demobilization
1. This item consists of mobilization, demobilization, and temporary controls.
2. No separate measurement will be made.
3. Payment will be made at the contract lump sum price.
B. Contract Line Item No.2 – Storm Water Pollution Prevention Plan (SWPPP)
1. This item consists of temporary erosion control measures for best management practices of storm water management and runoff.
C. Contract Line Item No.3 – PG&E Permit and Service Connection
1. This item consists of work and cost associate with the new PG&E service to the filtration system, including but not limited to utility permitting, review fees, utility submittals and coordination, temporary electrical service, all necessary components for a permanent electrical service.
D. Contract Line Item No.4 – Disposal Field Vegetation Removal
1. This item consists of work and cost associate with the removal of trees, limbing of trees, protection of trees and clearing and grubbing of approximately one half acre of gently sloping ground to prepare the site for a new drainfield.
GOGA – 164335 01 27 00 - 2
E. Contract Line Item No.5 – Pressure Disposal Field and Fence
1. This item consists of work and cost associated with the installation of a new pressure disposal field. Work includes trench excavation, installation of infiltrators, associated piping and valves, concrete inspection vaults with a dispersal design providing a fully functional operating system that meets county requirements for orifice sizing and spacing with appropriate system squirt heights. Work also includes installation of a 6-
ft. chain link fence with vehicular access gate to enclose the drain-field.
F. Contract Line Item No. 6 – Three Inch HDPE Force Main (Recirculating Treatment Facility
(RTF) to Disposal Field)
1. This item consists of work and cost associated with installation of a 3” HDPE force main and conduit for future valve control from the RTF to the pressure disposal field, associated components include concrete vault with tee in force main for future waste water treatment and (grey water) distribution, pull box.
3. Payment will be made at the contract lineal foot unit price.
G. Contract Line Item No. 7 – Three Inch HDPE Force Main (From Primary Treatment, i.e. North, Central and South Comfort Station Septic Tanks and Lifeguard Ranger Building Septic Tank
Pump Vaults)
1. This item consists of work and cost associated with installation of multiple stand alone
3” HDPE force mains from the North, Central and South Comfort Station Septic Tanks and Lifeguard Ranger Building Septic Tank Pump Vaults, associated components include two air vacuum and release valves in a concrete vault.
H. Contract Line Item No. 8 – Asphalt Paving
1. This item consists of work and cost associated with pavement mill grind removal and asphalt concrete replacement for trenching across or along paved pedestrian paths and drive aisles or driveways.
3. Payment will be made at the contract ton unit price.
I. Contract Line Item No. 9 – Tank and Disposal Field Abandonment
1. This item consists of work and cost associated with abandonment of the Lifeguard Tower
/ Ranger Building septic tank, Central Comfort Station septic tank and pump vault tank and three disposal fields.
GOGA – 164335 01 27 00 - 3
J. Contract Line Item No. 10 – Service and Pressure Test Tanks
1. This item consists of work and cost associated with pumping removal of tank contents, pressure wash cleaning of tank, leak testing of tanks and sealing tanks that do not pass leak test and leak re-testing tanks.
K. Contract Line Item No. 11 – Life Guard / Ranger Building Septic and Wet Well Tanks
1. This item consists of work and cost associated with installation of new septic tank and wet well tank installation and two separate gravity sewer laterals. Associated work involves tie in to existing gravity sewer laterals, adding clean outs and removal of one existing package lift station and disconnect.
L. Contract Line Item No. 12 – Wastewater Filter Secondary Treatment Facility, and Wood Fence
Removal and Replacement.
1. This item consists of work and cost associated with installation of the new wastewater filter treatment facility, associated inflow equalization tank and outflow distribution tank, all necessary components for a fully operational treatment system. Work also includes removal and replacement of existing wood fence necessary during construction.
M. Contract Line Item No. 13 – Primary Treatment, (Wet Wells) Pump, Control and Local Alarm
System.
1. This item consists of work and cost associated with demolition and replacement of pump vault pumps, and associated components including float level switches and alarms, conduit and wiring, and other electrical components.
N. Contract Line Item No. 14 – Gravity Sewer Main Lifeguard, Ranger Building, Administrative
/ Maintenance Area.
1. This item consists of work and cost associated with construction excavation and installation of three new gravity sewer laterals with clean outs, demolition of two package lift stations and disconnects. Associated work includes AC surface repair.
O. Contract Line Item No. 15 – Conduit and Pull Boxes for Future Remote SCADA Call Out
System.
1. This item consists of work and cost associated with installation of HDPE communication conduits and pull boxes for future SCADA system.
GOGA – 164335 01 27 00 - 4
3.2 LIST OF CONTRACT BID OPTIONS
A. Contract Bid Option No. A – Replace South Comfort Station Pump Vault
1. This item consists of removal and disposal of existing 5,300 gallon wet well tank and replacement with 3,000 gallon concrete tank in the same location, pressure tested.
2. No separate measurement will be made.
B. Contract Bid Option No. B – Replace North Comfort Station Septic Tank
1. This item consists of removal and disposal of existing 5,300 gallon septic tank and replacement with 3,000 gallon concrete tank in the same location, pressure tested.
C. Contract Bid Option No. C – Replace Central Comfort Station Septic Tank and Pump Vault
1. This item consists of demolition in place of the existing wet well tank and adaptive re-use (sitting area) of the existing septic tank. Install two new concrete 5,000 gallon septic and wet well tanks on east downslope side of comfort station. The work includes all mechanical piping and electrical to gravity flow from comfort station to septic tank and then to wet well tank.
D. Contract Bid Option No. D – Remote SCADA system.
1. This item consists of providing SCADA capable call out notification system integrated with new local audio/visual alarm provided in base bid work.
E. Contract Bid Option No. E – Replace Electrical Panels at Comfort Stations
1. This item consists of removal of old electrical panels and replace with main 100amp electrical panel.
3. Payment will be made at the contract each unit price.
GOGA – 164335 01 27 00 - 5
F. Contract Bid Option No. F – Mill and Pave Lifeguard Driveway
1. This item consists of mill grind removal of existing AC pavement driveway, reuse mill grind as base course material under new AC pavement, install new AC pavement driveway.
G. Contract Bid Option No. G – Pipe Burst Three Inch PVC Existing Force Main From South
Comfort Station to Secondary Treatment (RTF) With Three Inch HDPE Replacement
1. This item consists of pipe bursting existing 3 inch pvc force main from the South
Comfort Station wet well pump vault to the RTF with 3 inch HDPE piping.
H. Contract Bid Option No. H – Mill and Pave Ten Foot Wide Pedestrian Path
1. This item consists of mill grind removal of existing AC pavement pedestrian path, reuse mill grind as base course material under new AC pavement, fine grade path to meet
ADA/ABA requirements and regrade area between Ranger Building and where path joins the lifeguard tower pavement to eliminate existing ponding of water on path, install new AC pavement pedestrian pathway.
I. Contract Bid Option No. I – Replace 1,800 Gallon Septic Tank (Admin Area)
1. This item consists of removal and disposal of existing 1,800 gallon septic tank, with installation of new 1,200 gallon precast concrete septic tank. Includes asphalt concrete saw cut removal and asphalt concrete surface repair.
GOGA – 164335 01 31 00 - 1
PROJECT MANAGEMENT & COORDINATION
SECTION 01 31 00
A. This Section includes administrative provisions for coordinating construction operations on
Project including, but not limited to, the following:
1. Construction Coordination.
2. Coordination Drawings.
3. Requests for Information (RFIs).
4. Project meetings.
5. Environmental Coordination.
B. Related Requirements:
1. Section 01 32 16 “Construction Schedule” for preparing and submitting Contractor’s construction schedule.
2. Section 01 73 40 “Execution” for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
3. Section 01 77 00 “Closeout Procedures” for coordinating closeout of the Contract.
1.2 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of the
Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
GOGA – 164335 01 31 00 - 2
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor's Construction Schedule.
2. Preparation of the Schedule of Values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Pre-installation conferences.
7. Project closeout activities.
1.3 SUBMITTALS
A. Division 01 documents: The following items shall be submitted a minimum of one (1) week prior to the Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference.
1. Letter designating Contractor’s Project Superintendent and Project Manager.
2. Construction Schedule.
3. A comprehensive breakdown of the Schedule of Values.
4. Accident Prevention Plan.
5. A list of Subcontractors for this project.
6. Written statements from subcontractors certifying compliance with applicable labor standard clauses.
7. Satisfactory evidence of liability insurance coverage and workman’s compensation for the Contactor and all subcontractors.
8. Demolition Plan.
9. Waste Management Plan.
10. Quality Control Plan.
11. State of California SWPPP (Stormwater Pollution Prevention Plan).
12. Treatment System(s) and Controls Start Up Plan.
13. Traffic Control Plan.
B. All items listed must be provided to the Contracting Officer before the Pre-Construction
Conference is held. If all of these documents have not been received one week prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to
Proceed will not be issued, and the Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.
1.4 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified.
1. CO will return RFIs submitted by other entities controlled by Contractor with no response.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
GOGA – 164335 01 31 00 - 3
B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
1. Unique RFI number, numbered sequentially
2. Project name.
3. Contract number.
4. Date.
5. Name of Contractor.
6. RFI single subject/ topic.
7. Specification Section number and title and related paragraphs, as appropriate.
8. Drawing number and detail references, as appropriate.
9. Field dimensions and conditions, as appropriate.
10. Contractor's suggested resolution. If Contractor's suggested resolution impacts the
Contract Time or the Contract Sum, Contractor shall state impact in the RFI.
11. Contractor's signature.
12. Requested date for response.
13. Attachments:…