P15PS00203_Addendum_00001.docx
DOCX document 31 KB Posted
- Attached to
- AZ MABO MATOC IDIQ Federal contract opportunity
- Solicitation number
- P15PS00203
About this file
Addendum 00001
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Addendum_0005.docx | DOCX document | |
| Sol_P15PS00203_Amd_000005.pdf | ||
| Sol_P15PS00203_Amd_000004.pdf | ||
| Site_Visit_-_Sign-In_Sheets.pdf | ||
| P15PS00203_Provisions_and_Clauses.pdf | ||
| Sol_P15PS00203_Amd_000003.pdf | ||
| AZ_-_MATOC_Past_Performance_Survey_Questionnaire.pdf | ||
| AZ_-_MATOC_Specifications.pdf | ||
| TUZI_378_3014B_ id201955 .pdf | ||
| TUGI-_NEW_FLOOR_PLAN_Bid_Option_2.pdf | ||
| TUZI_Rehab_Restroom-SOW_SPEC-revised.pdf | ||
| MATOC_wages.pdf | ||
| Sol_P15PS00203_Amd_000002.pdf | ||
| TUZIBASE.DWG | DWG drawing | |
| Sol_P15PS00203_Amd_000001.pdf | ||
| TUZI-_NEW_FLOOR_PLAN_Bid_Option_2_(2).pdf | ||
| README.txt | TXT text file | |
| TUZI-_NEW_FLOOR_PLAN_Basis_of_design.pdf | ||
| TUZICOV.DWG | DWG drawing | |
| TUZI_378_3014B_As_Constructred_Drawing.pdf | ||
| PRE-SOL_NOTICE_MATOC_Feb_2015.docx | DOCX document |
Show all 21
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
P15PS00203 Addendum 00001
1. Q: Is the required bid bond for the seed project or the contract?
A: Yes, seed project
2. Q: Is the proposed staffing requirement listed in the RFP for the seed project or the contract?
A: Staffing requirement is for the contract
3. Q: Is there a bid schedule for the seed project? If so will you please post it? We are unable to locate it within the RFP package.
A: Yes, it's in the Clauses and Provisions, page 17.
4. Q: Do Exhaust fans to be installed by contractor and is made a part of the SOW.
A: If code requires that we have exhaust fans with AC then you need to design in exhaust fans.
5. Q: Will bidders be provided an approximate location of the propane tank the NPS is providing so that we can know how much gas line will be required?
A: The tank will be located approx. 25’ from the building.
6. Q: The electrical panel seems to be full. Are we to include a new electrical upgrade in our proposal? If so are we to set a subpanel or provide a new service to the building?
A: If the panel is deemed to be too full to add additional power for the exhaust fans and the AC then it is up to you as a design build firm to provide proposals for a a new subpanel or new power to the building per your electrical engineer.
7. Q: We understand the ADA portion will be bid as an option, should that option include an ADA compliant route from the parking to the restroom?
A: A new accessible ADA walkway to the building is not part of this contract. If Wendell wants to add it as an additional bid item that's fine by me but we have to send it out to everybody, of course.
8. Q: If we are to match the existing floor and wall tile in the ADA option, can the NPS provide any information as to type of tile exists?
A: The manufacture and type of tile used in that building is probably not available to us in the information that we have saved. It would be up to the bidders to determine whether they can match that tile based on the information they have available to us at this time.
Regarding the issues arising at the site-visit and are provided for clarification:
Furnace: A propane tank will be provided by NPS. The contractor will be responsible for running all connections for a workable system.
Portable Toilets: The contractor will provide
Drinking Fountain: NPS will provide
Waterless Urinals: NPS will provide, (This is part of the ADA option)
Hazmat Report: NPS will arrange immediately and provide to bidders upon receipt.
NPS will arrange Hazmat survey. The sampling is scheduled for Friday May, 8th. NPS will be responsible for all required work as a result of findings.
Adding six (6) attachments:
Readme.txt TUZI-New Floor Plan Basis of Design TUZI-New Floor Plan-Bid option 2 TUZI 378-3014B_As Constructed Drawing TUZIBase.dwg (CAD ) TUZICover.dwg (CAD)
Request for Information (RFI): Last day for submission is May 12, 2015
Bid opening extended to May 21, 2015. Time remains unchanged.
File details come from the government source that posted it. Updated .