This document outlines infection control precautions for a Class II construction project to replace the emergency department roof at Overton Brooks VAMC. During construction, measures are required such as reducing airborne dust within 25 feet of work, misting work surfaces to control dust, sealing unused doors, blocking and sealing air vents if HVAC is removed or isolated, placing dust mats at entrances and exits, and removing or isolating exhaust systems within 25 feet of work. Construction waste must be transported in tightly covered containers or containers with taped lids, and debris removed only via designated construction routes. Upon completion, surfaces must be wiped with cleaner/disinfectant, waste contained and transported as outlined, areas wet mopped and vacuumed with HEPA vacuum before leaving, and exhaust systems restored. Control measures must be maintained until all work is finished. Exceptions require infection prevention approval.
The related federal contract opportunity is solicitation number 667-23-100 for design/build services for the emergency department roof replacement project at Overton Brooks VAMC. The solicitation was issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 16.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25623R0006 0001.pdf | ||
| 1675887701205.jpeg | JPEG file | |
| 1675887593466.jpeg | JPEG file | |
| 1675887952406.jpeg | JPEG file | |
| 1675887555487.jpeg | JPEG file | |
| ED ROOF - Aerial View.pdf | ||
| ED ROOF - Sketch.pdf | ||
| RFI Responses.docx | DOCX document | |
| ED ROOF - Aerial Northwest Quarter.pdf | ||
| ED ROOF - Site Grounds Map.pdf | ||
| 1675887647620.jpeg | JPEG file | |
| 1675887841057.jpeg | JPEG file | |
| 1675887758930.jpeg | JPEG file | |
| P09 Revised SOW Replace ED Roof- 667-23-100 09-12-2022.docx | DOCX document | |
| 36C25623R0006 SOLICITATION .pdf | ||
| 36C25623R0006 - Exhibit A .docx | DOCX document | |
| 36C25623R0006 VHA Supplemental Contract Rqts for Combatting COVID-19 (2).docx | DOCX document | |
| 36C25623R0006 - Exhibit B.docx | DOCX document | |
| P09 ICRA - Replace Emergency Department Roof Preliminary.docx | DOCX document |
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Overton Brooks VAMC Infection Control Precautions for Class II Projects
Based on the Infection Control Risk Assessment of this construction/remodel project, the following activities are required.
PROJECT: Replace Emergency Dept Roof 667-23-100 Date: November 2, 2022
| During Construction Project | Upon Completion of Project | |
| Class II | ||
| 1. Provide active means to reduce airborne dust from dispersing into atmosphere WITHIN 25 feet of |
2. Water mist work surfaces to control dust while cutting.
3. Seal unused doors with duct tape.
4. Block off and seal air vents if the HVAC system is removed or isolated.
5. Place dust mat at entrance and exit of work area
6. Remove or isolate Exhaust system in areas within 25 feet of where work is being performed.
7. Construction Waste: if exterior trash chute is NOT used.
a. Transport in tightly covered container,
b. Containers without tight fitting solid lids must have covering taped in place BEFORE transport outside the project area,
c. Outside of containers must be cleaned when visibly soiled
8. When removing construction debris, utilize only the designated construction route.
1. Wipe work surfaces with cleaner/disinfectant.
2. Contain and transport construction waste as outline for “During Construction”.
3. Wet mop and/or vacuum with HEPA filtered vacuum before leaving work area.
4. Upon completion, restore exhaust system where work was performed.
5. Schedule Terminal Clean once work is complete
Maintain control measures until ALL Work is completed. Exceptions must be approved by Infection Prevention on a case-by-case basis.