P09 657-22-112JC Specs.pdf
PDF 4 MB Posted
- Solicitation number
- 36C25526R0095
About this file
This is a comprehensive specification document for the preparation of a site for new cathology laboratories (Rooms B510 and B516) at the John Cochran Division VA St. Louis Health Care System under project number 657-22-112JC. The contract number is 36C25523C0055 with a 210-day performance period.
The project encompasses extensive site preparation and interior renovation work divided into two phases: Phase I covering Room B510 and UPS alterations, and Phase II covering Room B516. Work includes demolition of existing structures and materials, removal and proper disposal of asbestos-containing materials and lead-based paint, comprehensive abatement procedures with detailed containment requirements, and full site preparation. The specification mandates compliance with federal safety regulations (OSHA 29 CFR 1926.1101 for asbestos, 29 CFR 1926.62 for lead), EPA requirements, and state/local regulations. Major construction activities include mechanical and electrical systems installation, HVAC modifications, plumbing and gas systems for laboratory facilities, fire suppression system commissioning, interior finishes (gypsum board, acoustical ceilings, flooring, painting), and comprehensive testing and commissioning of all systems. The contractor must develop detailed project schedules using Critical Path Method (CPM) with resource-loaded networks, submit a Schedule of Costs, and provide monthly updates. The specification requires an approved Accident Prevention Plan, Activity Hazard Analyses for all work phases, quality control procedures with three-phase control system (Preparatory, Initial, Follow-Up), comprehensive warranty management including 4 and 9-month post-construction inspections, and extensive documentation including as-built drawings. The work requires coordination with VA occupancy requirements, infection control protocols, and continuous VA facility operations in a healthcare setting.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25526R0095 0003.docx | DOCX document | |
| S06-657-22-112JC Pre-bid Meeting Sign in Sheet.pdf | ||
| S06-657A4-24-305 - Pre-Bid Sign In 07212025.pdf | ||
| S06 Questions response 657-22-112JC 26.05.14.pdf | ||
| 36C25526R0095 0002.docx | DOCX document | |
| S06 657-22-112JC Pre-bid Meeting Sign in Sheet.pdf | ||
| 36C25526R0095 0001.docx | DOCX document | |
| 36C25526R0095_1.docx | DOCX document | |
| P09 96 pgs 657-22-112JC_Release_for_Bidding_Drawings R1.pdf | ||
| 36C25526R0095 04082026 Final 02.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DESIGN-AIRE ENGINEERING INC.
John Cochran Division
VA St. Louis Health Care System 915 N. Grand Blvd.
St. Louis, MO 63106
Project #657-22-112JC
Prepare Site for New Cathology Labs, Rooms B510 & B516
CONTRACT/TO# 36C25523C0055 Obligation. #657-C30250
PO #657-C30250
SPECIFICATIONS – RELEASE FOR BIDDING
VA Project Number#657-22-112JC
Date: 27 JANUARY 2026
Prepare Site for Cathology Laboratories, Project #657-22-112JC
Rooms B510 and B516 Release for Bidding
John Cochran, VA St. Louis Health Care System 07-01-21
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
SECTION NO. DIVISION AND SECTION TITLES DATE
DIVISION 00 - SPECIAL SECTIONS
00 01 10 Table of Contents 07-21
00 01 15 List of Drawing Sheets 05-20
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 11-21
01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build) 12-25
01 33 23 Shop Drawings, Product Data, and Samples 06-25
01 35 26 Safety Requirements 05-24
01 42 19 Reference Standards 11-20
01 45 00 Quality Control 02-21
01 58 16 Temporary Interior Signage 07-15
01 74 19 Construction Waste Management 04-22
01 81 13 Sustainable Construction Requirements 10-17
01 91 00 General Commissioning Requirements 04-22
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 08-17
02 82 13.13 Glovebag Asbestos Abatement 01-21
02 83 33.13 Lead-Based Paint Removal and Disposal 01-21
DIVISION 03 – CONCRETE - NONE
DIVISION 04 – MASONRY- NONE
DIVISION 05 – METALS- NONE
DIVISION 06 – WOOD, PLASTICS AND COMPOSITES- NONE
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 01 50.19 Preparation for Re-Roofing 01-21
07 60 00 Flashing and Sheet Metal 01-21
07 84 00 Firestopping 01-21
07 92 00 Joint Sealants 04-22
DIVISION 08 – OPENINGS - NONE
DIVISION 09 – FINISHES
00 01 10-2
09 05 16 Subsurface Preparation for Floor Finishes 01-21
09 22 16 Non-Structural Metal Framing 06-18
09 29 00 Gypsum Board 04-20
09 51 00 Acoustical Ceilings 12-18
09 65 13 Resilient Base and Accessories 01-21
09 65 19 Resilient Tile Flooring 05-18
09 91 00 Painting 01-21
DIVISION 10 – SPECIALTIES - NONE
DIVISION 11 – EQUIPMENT - NONE
DIVISION 12 – FURNISHINGS - NONE
DIVISION 13 - SPECIAL CONSTRUCTION
13 49 00 Radiation Protection 01-21
DIVISION 14– CONVEYING EQUIPEMENT - NONE
DIVISION 21- FIRE SUPPRESSION
21 05 11 Common Work Results for Fire Suppression 11-09
21 08 00 Commissioning of Fire Suppression Systems 11-16
21 13 13 Wet-Pipe Sprinkler Systems 06-15
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 07-23
22 62 00 Vacuum Systems for Laboratory and Healthcare Facilities 05-23
22 63 00 Gas Systems for Laboratory and Healthcare Facilities 05-23
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 11 Common Work Results for HVAC 03-23
23 05 12 General Motor Requirements for HVAC and Steam
Generation Equipment
03-23
23 05 93 Testing, Adjusting, and Balancing for HVAC 03-23
23 07 11 HVAC and Boiler Plant Insulation 03-23
23 08 00 Commissioning of HVAC Systems 03-23
23 31 00 HVAC Ducts and Casings 03-23
23 37 00 Air Outlets and Inlets 03-23
DIVISION 25 – INTEGRATED AUTOMATION - NONE
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 11-22
00 01 10-3
26 05 19 Low-Voltage Electrical Power Conductors and Cables 11-22
26 05 26 Grounding and Bonding for Electrical Systems 11-22
26 05 33 Raceway and Boxes for Electrical Systems 11-22
26 05 36 Wireways for Radiology Equipment 01-18
26 08 00 Commissioning of Electrical Systems 11-16
26 27 26 Wiring Devices 11-22
26 29 21 Enclosed Switches and Circuit Breakers 11-22
26 51 00 Interior Lighting 03-24
DIVISION 27 – COMMUNICATIONS
27 05 11 Requirements for Communications Installations 09-19
27 05 26 Grounding and Bonding for Communications Systems 06-15
27 05 33 Raceways and Boxes for Communications Systems 10-18
27 08 00 Commissioning of Communications Systems 11-16
27 10 00 Control, Communication and Signal Wiring 06-15
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY - NONE
DIVISION 31 – EARTHWORK - NONE
DIVISION 32 – EXTERIOR IMPROVEMENTS - NONE
DIVISION 33 – UTILITIES - NONE
DIVISION 34 – TRANSPORTATION - NONE
DIVISION 48 – Electrical Power Generation - NONE
Prepare Site for Cathology Laboratories Project #657-22-112JC
John Cochran, VA St. Louis Health Care System 05-01-20
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
DRAWING INDEX
SH
NO.
Drawing
Number Sheet Title
1 01-GI-001 COVER SHEET
2 01-AE-100 ARCHITECTURAL GENERAL - CODE INFORMATION
3 01-AE-101 ARCHITECTURAL LOGISTICS AND ICRA PLAN
4 01-AE-102 ARCHITECTURAL DEMO AND FLOOR PLAN
5 01-AE-103 ARCHITECTURAL DEMO AND RCP
6 01-AE-104 ARCHITECTURAL DEMO AND FLOOR PLAN
7 01-PD-151 CATH. LAB 1 - ENLARGED PLUMBING DEMOLITION PLAN
8 01-PL-152 CATH. LAB 1 - ENLARGED PLUMBING PLAN
9 01-MH-153 LOCATION OF WORK
10 01-EG-501 ELECTRICAL SYMBOLS
11 01-EG-502 ELECTRICAL DETAILS
12 01-EG-451 LOCATION OF WORK
13 01-ED-151 ELECTRICAL - DEMOLITION PLAN
14 01-EL-152 ELECTRICAL - LIGHTING PLAN
15 01-EP-153 ELECTRICAL - CATHOLOGY LAB 1 CONDUIT ROUTING PLAN
16 01-EP-154 ELECTRICAL - CATHOLOGY LAB 2 CONDUIT ROUTING PLAN
17 01-EP-155 ONE-LINE DIAGRAM AND CONDUIT ROUTING PLAN
18 01-EK-551 PHILIPS INSTALLATION PLANS FOR AZURION 7 C12
19 01-EK-552 PHILIPS INSTALLATION PLANS FOR AZURION 7 C12
20 01-EK-553 PHILIPS INSTALLATION PLANS FOR AZURION 7 C12
21 01-EK-554 PHILIPS INSTALLATION PLANS FOR AZURION 7 C12
22 01-EK-555 PHILIPS INSTALLATION PLANS FOR AZURION 7 C12
23 01-EK-556 PHILIPS INSTALLATION PLANS FOR AZURION 7 C12
24 01-EK-557 PHILIPS INSTALLATION PLANS FOR AZURION 7 C12
25 01-EK-558 PHILIPS INSTALLATION PLANS FOR AZURION 7 C12
26 01-EK-559 PHILIPS INSTALLATION PLANS FOR AZURION 7 C12
27 01-EK-5510 PHILIPS INSTALLATION PLANS FOR AZURION 7 C12
28 01-EK-5511 PHILIPS INSTALLATION PLANS FOR AZURION 7 C12
29 01-EK-5512 PHILIPS INSTALLATION PLANS FOR AZURION 7 C12
30 01-EK-5513 PHILIPS INSTALLATION PLANS FOR AZURION 7 C12
31 01-EK-5514 PHILIPS INSTALLATION PLANS FOR AZURION 7 C12
32 01-EK-5515 PHILIPS INSTALLATION PLANS FOR AZURION 7 C12
00 01 15 - 2
33 01-EK-5516 PHILIPS INSTALLATION PLANS FOR AZURION 7 C12
34 01-EK-5517 PHILIPS INSTALLATION PLANS FOR AZURION 7 C12
35 01-EK-5518 PHILIPS INSTALLATION PLANS FOR AZURION 7 C12
36 01-EK-5519 PHILIPS INSTALLATION PLANS FOR AZURION 7 C12
37 01-EK-5520 PHILIPS INSTALLATION PLANS FOR AZURION 7 C12
38 01-EK-5521 PHILIPS INSTALLATION PLANS FOR AZURION 7 C12
39 01-EK-5522 PHILIPS INSTALLATION PLANS FOR AZURION 7 C12
40 01-EK-5523 PHILIPS INSTALLATION PLANS FOR AZURION 7 C12
41 01-EK-5524 PHILIPS INSTALLATION PLANS FOR AZURION 7 C12
42 01-EK-5525 PHILIPS INSTALLATION PLANS FOR AZURION 7 C12
43 01-EK-5526 PHILIPS INSTALLATION PLANS FOR AZURION 7 C12
44 01-EK-5527 PHILIPS INSTALLATION PLANS FOR AZURION 7 C12
45 01-EK-5528 PHILIPS INSTALLATION PLANS FOR AZURION 7 C12
46 01-EK-5529 PHILIPS INSTALLATION PLANS FOR AZURION 7 C12
47 01-EK-5530 PHILIPS INSTALLATION PLANS FOR AZURION 7 C12
48 01-EK-5531 PHILIPS INSTALLATION PLANS FOR AZURION 7 C12
49 01-EK-5532 PHILIPS INSTALLATION PLANS FOR AZURION 7 C12
50 01-EK-5533 PHILIPS INSTALLATION PLANS FOR AZURION 7 C12
51 01-EK-5534 PHILIPS INSTALLATION PLANS FOR AZURION 7 C12
52 01-EK-5535 PHILIPS INSTALLATION PLANS FOR AZURION 7 C12
53 01-EK-5536 PHILIPS INSTALLATION PLANS FOR AZURION 7 C12
54 01-EK-5537 PHILIPS INSTALLATION PLANS FOR AZURION 7 C12
55 01-EK-5538 PHILIPS INSTALLATION PLANS FOR AZURION 7 C12
56 01-EK-5539 PHILIPS INSTALLATION PLANS FOR AZURION 7 C12
57 01-EK-5540 PHILIPS INSTALLATION PLANS FOR AZURION 7 C20
58 01-EK-5541 PHILIPS INSTALLATION PLANS FOR AZURION 7 C20
59 01-EK-5542 PHILIPS INSTALLATION PLANS FOR AZURION 7 C20
60 01-EK-5543 PHILIPS INSTALLATION PLANS FOR AZURION 7 C20
61 01-EK-5544 PHILIPS INSTALLATION PLANS FOR AZURION 7 C20
62 01-EK-5545 PHILIPS INSTALLATION PLANS FOR AZURION 7 C20
63 01-EK-5546 PHILIPS INSTALLATION PLANS FOR AZURION 7 C20
64 01-EK-5547 PHILIPS INSTALLATION PLANS FOR AZURION 7 C20
65 01-EK-5548 PHILIPS INSTALLATION PLANS FOR AZURION 7 C20
66 01-EK-5549 PHILIPS INSTALLATION PLANS FOR AZURION 7 C20
67 01-EK-5550 PHILIPS INSTALLATION PLANS FOR AZURION 7 C20
68 01-EK-5551 PHILIPS INSTALLATION PLANS FOR AZURION 7 C20
69 01-EK-5552 PHILIPS INSTALLATION PLANS FOR AZURION 7 C20
70 01-EK-5553 PHILIPS INSTALLATION PLANS FOR AZURION 7 C20
71 01-EK-5554 PHILIPS INSTALLATION PLANS FOR AZURION 7 C20
00 01 15 - 3
72 01-EK-5555 PHILIPS INSTALLATION PLANS FOR AZURION 7 C20
73 01-EK-5556 PHILIPS INSTALLATION PLANS FOR AZURION 7 C20
74 01-EK-5557 PHILIPS INSTALLATION PLANS FOR AZURION 7 C20
75 01-EK-5558 PHILIPS INSTALLATION PLANS FOR AZURION 7 C20
76 01-EK-5559 PHILIPS INSTALLATION PLANS FOR AZURION 7 C20
77 01-EK-5560 PHILIPS INSTALLATION PLANS FOR AZURION 7 C20
78 01-EK-5561 PHILIPS INSTALLATION PLANS FOR AZURION 7 C20
79 01-EK-5562 PHILIPS INSTALLATION PLANS FOR AZURION 7 C20
80 01-EK-5563 PHILIPS INSTALLATION PLANS FOR AZURION 7 C20
81 01-EK-5564 PHILIPS INSTALLATION PLANS FOR AZURION 7 C20
82 01-EK-5565 PHILIPS INSTALLATION PLANS FOR AZURION 7 C20
83 01-EK-5566 PHILIPS INSTALLATION PLANS FOR AZURION 7 C20
84 01-EK-5567 PHILIPS INSTALLATION PLANS FOR AZURION 7 C20
85 01-EK-5568 PHILIPS INSTALLATION PLANS FOR AZURION 7 C20
86 01-EK-5569 PHILIPS INSTALLATION PLANS FOR AZURION 7 C20
87 01-EK-5570 PHILIPS INSTALLATION PLANS FOR AZURION 7 C20
88 01-EK-5571 PHILIPS INSTALLATION PLANS FOR AZURION 7 C20
89 01-EK-5572 PHILIPS INSTALLATION PLANS FOR AZURION 7 C20
90 01-EK-5573 PHILIPS INSTALLATION PLANS FOR AZURION 7 C20
91 01-EK-5574 PHILIPS INSTALLATION PLANS FOR AZURION 7 C20
92 01-EK-5575 PHILIPS INSTALLATION PLANS FOR AZURION 7 C20
93 01-EK-5576 PHILIPS INSTALLATION PLANS FOR AZURION 7 C20
94 01-EK-5577 PHILIPS INSTALLATION PLANS FOR AZURION 7 C20
95 01-EK-5578 PHILIPS INSTALLATION PLANS FOR AZURION 7 C20
96 01-EK-5579 PHILIPS INSTALLATION PLANS FOR AZURION 7 C20
- - - END - - -
John Cochran, VA St. Louis Health Care System 11-01-21
01 00 00 -1
SECTION 01 00 00
GENERAL REQUIREMENTS
GENERAL
1.1 SAFETY REQUIREMENTS
A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for 657-22-112JC Prepare Site for
Cath Labs Rooms 510 and 516 as required by drawings and specifications.
B. A Site visit will occur at the Pre-Bid Meeting. Only one site visit will be scheduled prior to the bid date. Attendance is highly recommended.
C. Offices of DAE, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by
Contracting Officer or his duly authorized representative.
D. Before placement and installation of work subject to tests by testing laboratory retained by the contractor, the Contractor shall notify the
COR and be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall not be less than three workdays unless otherwise designated by the COR. Provide the
COR with all testing reports.
E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access. Visits to the site by Bidders will only occur once during the Pre-Bid meeting. Attendance is highly recommended.
1.3 STATEMENT OF BID ITEM(S)
A. ITEM I, GENERAL CONSTRUCTION: BASE BID Work includes general construction, alterations, roads, walks, grading, drainage, necessary removal of existing structures and construction and certain other items. Period of Performance (POP) is 210 days.
01 00 00 -2
B. ALTERNATE NO.1: ALTERNATE 1 add addition of UPS alteration and addition. Period of Performance(POP) is 210 days.
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge and documentation of flue shot and attestation of COVID-19 vaccination. They may also be subject to inspection of their personal effects when entering or leaving the project site.
a. All contractor’s and subcontractor’s employees will be required to wear one of two badges on VA property. Consult the COR for appropriate type and the procedure for obtaining a badge.
1) PIV-I card issued by the VA HR department.
2) Visitor Badge issued by the VA. This badge is valid for 15 site visits in a calendar year and provides no access to restricted areas, i.e. mag-locked doors.
2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer’s Representative so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer. Patients and staff are not to be photographed at any time.
01 00 00 -3
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.
C. Guards: Not Applicable
D. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR) for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.
2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation.
E. Document Control:
1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of
“sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.
Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting
Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
01 00 00 -4
7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document
Management Software (EDMS).
Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the
EDMS system.
“Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
F. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
1.6 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the
Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the
Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the
Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting
Officer, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting
Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or
01 00 00 -5 sidewalks, the Contractor shall protect them from damage. The
Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. No areas outside the defined construction boundaries will be available to the contractor for staging, storage, preparation, etc.
1. Do not store materials and equipment in other than assigned areas. The COR may request items to be relocated at any point.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by
Department of Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to
Medical Center areas required to remain in operation.
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
E. Contractor shall be responsible for moving and storage of all furniture related to the project, including but not limited to furniture, equipment, signage, and artwork. All items become the responsibility of the contractor to store within the construction area or at an offsite location at the contractor’s expense. All items must be returned in the original condition and at the approval of the COR, any damaged items will be replaced at the expense of the contractor. Contractor shall provide written notice to the COR ten calendar days prior to moving furniture.
F. Workers are subject to rules of Medical Center applicable to their conduct.
G. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.
H. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of
01 00 00 -6 utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR
I. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR . All such actions shall be coordinated with the COR or Utility Company involved:
1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
J. Phasing:
1. The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:
2. To ensure such executions, Contractor shall furnish the COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR three weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing dates to ensure accomplishment of this work in successive phases mutually agreeable to Medical Center Director, COR and
Contractor, as follows:
01 00 00 -7
Phase I: Room B510 and UPS
Phase II: Room B516
K. Building(s) No.(s) JC Building will be occupied during performance of work; but immediate areas of alterations will be vacated.
1. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of
Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc. to facilitate patient and staff access.
Coordinate alteration work in areas occupied by Department of
Veterans Affairs so that Medical Center operations will continue during the construction period.
2. Immediate areas of alterations not mentioned in preceding Subparagraph 1 will be temporarily vacated while alterations are performed.
L. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.
2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from
Contractor's employee or watchman.
M. Utilities Services: Maintain existing utility services for Medical Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.
Where necessary to cut existing water, steam, gases, sewer or air
01 00 00 -8 pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized.
When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and 27 05 11 REQUIREMENTS
FOR COMMUNICATIONS INSTALLATIONS.
2. Contractor shall submit a request to interrupt any such services to COR, in writing, 21 days in advance of proposed interruption.
Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 21 calendar days prior to the desired time and shall be performed as directed by the COR.
5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
N. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, shall be
01 00 00 -9 removed back to their source. Those which are indicated to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
O. To minimize interference of construction activities with flow of Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.
P. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR and a representative of VA Supply Service, of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting Officer. This report shall list by rooms and spaces:
1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of building.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.
01 00 00 -10
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by Government.
Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR
52.243-4).
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and will form basis for determining extent of repair work required of
Contractor to restore damage caused by Contractor's workers in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
01 00 00 -11
1. Reserved items which are to remain property of the Government are noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
1.10 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the
COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
01 00 00 -12
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"
(FAR 52.243-4) and "DIFFERING SITE CONDITIONS" (FAR 52.236-2).
1.11 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.
C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.12 WARRANTY MANAGEMENT
A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of Construction in at least 30 days before the planned pre-warranty conference, submit one set of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the
Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was approved. Warranty information made available during the construction phase must be submitted to the Contracting Officer for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 4 month and 9 month warranty inspection will be conducted, measured from time of
01 00 00 -13 acceptance, by the Contactor and the Contracting Officer. Include in the warranty management plan, but not limited to, the following:
1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the Contractor, subcontractors, manufacturers or suppliers involved.
2. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.
3. Listing and status of delivery of all Certificates of Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.
4. A list for each warranted equipment item, feature of construction or system indicating:
a. Name of item.
b. Model and serial numbers.
c. Location where installed.
d. Name and phone numbers of manufacturers and suppliers.
e. Name and phone numbers of manufacturers or suppliers.
f. Names, addresses and phone numbers of sources of spare parts.
g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.
h. Starting point and duration of warranty period.
i. Summary of maintenance procedures required to continue the warranty in force.
j. Cross-reference to specific pertinent Operation and Maintenance manuals.
k. Organizations, names and phone numbers of persons to call for warranty service.
l. Typical response time and repair time expected for various warranted equipment.
5. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.
01 00 00 -14
6. Procedure and status of tagging of all equipment covered by extended warranties.
7. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.
B. Performance & Payment Bonds: The Performance & Payment Bonds must remain effective throughout the construction period.
1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.
2. In the event sufficient funds are not available to cover the construction warranty work performed by the Government at the contractor’s expenses, the Contracting Officer will have the right to recoup expenses from the bonding company.
3. Following oral or written notification of required construction warranty repair work, the Contractor shall respond in a timely manner. Written verification will follow oral instructions. Failure to respond will be cause for the Contracting Officer to proceed against the Contractor.
C. Pre-Warranty Conference: Prior to contract completion, and at a time designated by the Contracting Officer, the Contractor shall meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section. Communication procedures for
Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for
Contractor response, and other details deemed necessary by the
Contracting Officer for the execution of the construction warranty will be established/ reviewed at this meeting. In connection with these requirements and at the time of the Contractor’s quality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which is authorized to initiate and pursue construction warranty work action on behalf of the Contractor.
This point of contract will be located within the local service area of
01 00 00 -15 the warranted construction, be continuously available and be responsive to Government inquiry on warranty work action and status. This requirement does not relieve the Contractor of any of its responsibilities in conjunction with other portions of this provision.
D. Contractor’s Response to Construction Warranty Service Requirements:
E. Following oral or written notification by the Contracting Officer, the
Contractor shall respond to construction warranty service requirements in accordance with the “Construction Warranty Service Priority List” and the three categories of priorities listed below. Submit a report on any warranty item that has been repaired during the warranty period.
Include within the report the cause of the problem, date reported, corrective action taken, and when the repair was completed. If the
Contractor does not perform the construction warranty within the timeframe specified, the Government will perform the work and back charge the construction warranty payment item established.
1. First Priority Code 1. Perform onsite inspection to evaluate situation, and determine course of action within 4 hours, initiate work within 6 hours and work continuously to completion or relief.
2. Second Priority Code 2. Perform onsite inspection to evaluate situation, and determine course of action within 8 hours, initiate work within 24 hours and work continuously to completion or relief.
3. Third Priority Code 3. All other work to be initiated within 3 work days and work continuously to completion or relief.
4. The “Construction Warranty Service Priority List” is as follows:
a. Code 1-Life Safety Systems
Fire suppression systems.
Fire alarm system(s).
b. Code 1-Air Conditioning Systems Air conditioning leak in part of the building, if causing damage.
Air conditioning system not cooling properly.
Code 1 Doors
Overhead doors not operational, causing a security, fire or safety problem.
01 00 00 -16
Interior, exterior personnel doors or hardware, not functioning properly, causing security, fire or safety problem.
Code 3-Doors Overhead doors not operational.
Interior/exterior personnel doors or hardware not functioning properly.
Code 1-Electrical Power failure (entire area or any building operational after 1600 hours).
Security lights.
Smoke detectors.
Code 2-Electrical Power failure (no power to a room or part of building).
Receptacle and lights not operational (in a room or part of building).
Code 3-Electrical Exterior lights not operational.
Code 1-Gas Leaks and pipeline breaks.
Code 1-Heat Power failure affecting heat.
Code 1-Plumbing Hot water heater failure.
Leaking water supply pipes
Code 2-Plumbing Flush valves not operating properly Fixture drain, supply line or any water pipe leaking.
Toilet leaking at base.
Code 3- Plumbing Leaky faucets.
Code 3-Interior Floors damaged.
Paint chipping or peeling.
Casework damaged.
Code 1-Roof Leaks
01 00 00 -17
Damage to property is occurring.
Code 2-Water (Exterior)
No water to facility.
Code 2-Water (Hot)
No hot water in portion of building listed.
Code 3
All work not listed above.
F. Warranty Tags: At the time of installation, tag each warranted item with a durable, oil and water-resistant tag approved by the Contracting
Officer. Attach each tag with a copper wire and spray with a silicone waterproof coating. Also submit two record copies of the warranty tags showing the layout and design. The date of acceptance and the QC signature must remain blank until the project is accepted for beneficial occupancy. Show the following information on the tag.
Warranty Tags
Type of product/material
Model number
Serial number
Contract number
Warranty period from/to
Inspector’s signature
Construction Contractor
Address
Telephone number
Warranty Contact
Address
Telephone number
Warranty response time priority code
1.13 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:
1. Permission to use each unit or system must be given by COR in writing. If the equipment is not installed and maintained in
01 00 00 -18 accordance with the written agreement and following provisions, the
COR will withdraw permission for use of the equipment.
2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted.
Installation of temporary electrical equipment or devices shall be in accordance with NFPA 70, National Electrical Code, (2014
Edition), Article 590, Temporary Installations. Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded. The electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.
3. Units shall be properly lubricated, balanced, and aligned.
Vibrations must be eliminated.
4. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze-up damage.
5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be replaced at completion of construction and prior to testing and balancing of system.
6. All components of heat production and distribution system, metering equipment, condensate returns, and other auxiliary facilities used in temporary service shall be cleaned prior to use; maintained to prevent corrosion internally and externally during use; and cleaned, maintained and inspected prior to acceptance by the Government.
B. Prior to final inspection, the equipment or parts used which show wear and tear beyond normal, shall be replaced with identical replacements, at no additional cost to the Government.
C. This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.
D. Any damage to the equipment or excessive wear due to prolonged use will be repaired replaced by the contractor at the contractor’s expense.
01 00 00 -19
1.14 TEMPORARY USE OF EXISTING ELEVATORS
A. Use of existing elevator elevators for handling building materials and Contractor's personnel will be permitted subject to following provisions:
1. Contractor makes all arrangements with the COR for use of elevators.
The COR will ascertain that elevators are in proper condition.
Contractor may use elevators Nos. see plans for exclusive use for daily use between the hours of 5:30 AM and 6:30 and for special nonrecurring time intervals when permission is granted. Personnel for operating elevators will not be provided by the Department of
Veterans Affairs.
2. Contractor covers and provides maximum protection of following elevator components:
a. Entrance jambs, heads soffits and threshold plates.
b. Entrance columns, canopy, return panels and inside surfaces of car enclosure walls.
c. Finish flooring.
3. Government will accept hoisting ropes of elevator and rope of each speed governor if they are worn under normal operation. However, if these ropes are damaged by action of foreign matter such as sand, lime, grit, stones, etc., during temporary use, they shall be removed and replaced by new hoisting ropes at the contractors expense.
4. If brake lining of elevators are excessively worn or damaged during temporary use, they shall be removed and replaced by new brake lining at the contractors expense.
5. All parts of main controller, starter, relay panel, selector, etc., worn or damaged during temporary use shall be removed and replaced with new parts at the contractors expense, if recommended by elevator inspector after elevator is released by Contractor.
6. Place elevator in condition equal, less normal wear, to that existing at time it was placed in service of Contractor as approved by Contracting Officer.
1.15 TEMPORARY TOILETS
A. Provide where directed, (for use of all Contractor's workers) ample temporary sanitary toilet accommodations with suitable sewer and water
01 00 00 -20 connections; or, when approved by COR, provide suitable dry closets where directed. Keep such places clean and free from flies and all connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfectly clean.
1.16 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the Contractor for chargeable electrical services shall be the prevailing rates charged to the Government. The Contractor shall carefully conserve any utilities furnished without charge.
B. The Contractor, at Contractor's expense and in a workmanlike manner, in compliance with code and as satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections, and distribution lines, and all meters required to measure the amount of electricity used for the purpose of determining charges. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, and associated paraphernalia and repair restore the infrastructure as required.
C. Heat: Furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, will not be permitted. Maintain minimum temperatures as specified for various materials:
1. Obtain heat by connecting to Medical Center heating distribution system.
D. Electricity (for Construction and Testing): Furnish all temporary electric services.
1. Obtain electricity by connecting to the Medical Center electrical distribution system. The Contractor shall meter and pay for electricity required for electric cranes and hoisting devices, electrical welding devices and any electrical heating devices providing temporary heat. Electricity for all other uses is available at no cost to the Contractor.
E. Water (for Construction and Testing): Furnish temporary water service.
01 00 00 -21
1. Obtain water by connecting to the Medical Center water distribution system. Provide reduced pressure backflow preventer at each connection as per code. Water is available at no cost to the
Contractor.
2. Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted. Failure to stop leakage or other wastes will be cause for revocation (at COR discretion) of use of water from Medical Center's system.
1.17 TESTS
A. As per specification section 23 05 93 the contractor shall provide a written testing and commissioning plan complete with component level, equipment level, sub-system level and system level breakdowns.
This is the start of the file's text. The full file is on GovTribe.