P01 663-18-102.3 Phase IIb Roofs.pdf

PDF 1 MB Posted

Attached to
Y1DA--CON-NRM-663-18-102 Replace Roofs Phase 2 FY 24 Tier 2
Solicitation number
36C26024R0027
Issued by

About this file

This document is a set of drawings and specifications related to a federal contract opportunity to replace roofs at the VA Puget Sound Healthcare System in Seattle, Washington. The contract will be issued as a SVOSB set-aside under NAICS code 236220 with a planned solicitation date of November 10, 2023.

The drawings provide detailed information on the construction containment requirements, air filter schedules, and repair notes for various roof areas, including critical air intakes that will require temporary MERV-8 carbon pre-filters. The work includes renewing curb flashings, vent penetrations, and roof drains, as well as reinstalling temporarily removed rooftop equipment. Access to the roof will be limited to after-hours work due to the proximity of sensitive radiology equipment. Safety and fall protection requirements are emphasized. The Statement of Work and Wage Determination are provided as attachments to the solicitation.

View the file

Other files

File Type Posted
P01 Wage Determination-WA20240108.pdf PDF
P01 663-18-102 Construction SOW v2.pdf PDF
36C26024R0027.docx DOCX document
P01 663-18-102.2 Phase IIa Roofs.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DHHALK

GI001

COVER SHEET, DRAWING SHEET INDEX,

SITE MAPS

REPLACE ROOFS - PIII

SEATTLE VA MEDICAL CENTER

VA PUGET SOUND HEALTHCARE SYSTEM (VAPSHCS)

1660 SOUTH COLUMBIAN WAY

SEATTLE, WASHINGTON 98108

SO. SNOQUALMIE ST.

SO. ALASKA ST.

COLUMBIAN WAY SO.

BEAC

O

N

AVE SO

BOUNDARY LINE

B100-A B100-B B100-C

B100-D

CORE

B100-F

B100-H B100-J

B20

B22

B33

NURSING

TOWER

EQUIPMENT

SETUP AREA

EQUIPMENT

SETUP AREA

EQUIPMENT

SETUP AREA

NURSING HOME

EQUIPMENT

SETUP AREA

DHH DHH

NORTH

SHEET NOTES:

1. CONTRACTOR WILL NOT BE ALLOWED A LAYDOWN AREA ON THE VA PUGET SOUND

PREMISES. MATERIALS WILL BE BROUGHT TO THE SITE EACH DAY.

2. PHASING PLANS ARE INCLUDED IN SPECIFICATION SECTION 01 00 00. PROVIDE

WORK PLAN FOR EACH ROOF TO COR 30 DAYS PRIOR TO START OF WORK.

3. DUMPSTERS AND EQUIPMENT MAY BE SETUP IN THE HATCHED AREAS SHOWN ON

THE SITE PLAN.

4. TEMPORARY VEHICLE LOADING AND UNLOADING WILL BE ALLOWED. ACCESS

ROADS MUST REMAIN OPEN FOR EMERGENCY VEHICLES.

5. NO CONTRACTOR PARKING IS AVAILABLE ON THE VA PREMISES. COORDINATE

PARKING REQUIREMENTS WITH THE COR.

6. VERIFY ALL EQUIPMENT STAGING AND SETUP AREAS WITH COR.

GI002

PROJECT SITE PLAN

LEGEND:

ROOF AREA INCLUDED IN PHASE III PROJECT

EQUIPMENT SETUP AREA

ROOF AREA COMPLETED IN PHASE I PROJECT

BUILDING 100 - AIR FILTERS

FILTER NO. SYSTEM

CARTRIDGES

NO. SIZE ARRANGEMENT

100-PF-1 AC-1 18 24"x24"x30" 6 WIDE X 3 HIGH

6 24"x12"x30" 6 WIDE X 1 HIGH

100-PF-2 AC-2 18 24"x12"x30" 6 WIDE X 3 HIGH

6 24"x12"x30" 6 WIDE X 1 HIGH

100-PF-3 AC-3 24 24"x24"x30" 6 WIDE X 4 HIGH

100-PF-4 AC-4 24 24"x24"x30" 6 WIDE X 4 HIGH

100-PF-5 AC-5 24 24"x24"x30" 6 WIDE X 4 HIGH

100-PF-6 AC-6 8 24"x24"x30" 4 WIDE X 2 HIGH

100-PF-7 AC-7 8 24"x24"x30" 4 WIDE X 2 HIGH

100-PF-8 AC-8 3 24"x24"x30" 3 WIDE X 1 HIGH

3 24"x12"x30" 3 WIDE X 1 HIGH

100-PF-9 AC-9 4 24"x24"x30" 4 WIDE X 1 HIGH

4 24"x12"x30" 4 WIDE X 1 HIGH

100-PF-10 AC-10 10 24"x24"x30" 5 WIDE X 2 HIGH

100-PF-11 AC-11 8 24"x24"x30" 4 WIDE X 2 HIGH

100-PF-12 AC-12 3 24"x24"x30" 3 WIDE X 1 HIGH

3 24"x12"x30" 3 WIDE X 1 HIGH

100-PF-13 AC-13 15 24"x24"x30" 5 WIDE X 3 HIGH

100-PF-13a AC-13 10 24"x24"x30" 5 WIDE X 2 HIGH

100-PF-14 AC-14 12 24"x24"x30" 4 WIDE X 3 HIGH

100-PF-14a AC-14 8 24"x24"x30" 4 WIDE X 2 HIGH

100-PF-15 AC-15 8 24"x24"x30" 4 WIDE X 2 HIGH

100-PF-16 AC-16 8 24"x24"x30" 4 WIDE X 2 HIGH

100-PF-17 AC-17 5 24"x24"x30" 5 WIDE X 1 HIGH

5 24"x12"x30" 5 WIDE X 1 HIGH

100-PF-18 AC-18 10 24"x24"x30" 5 WIDE X 2 HIGH

5 24"x12"x30" 5 WIDE X 1 HIGH

100-PF-19 AC-19 8 24"x24"x30" 4 WIDE X 2 HIGH

100-PF-19a AC-19 8 24"x24"x30" 4 WIDE X 2 HIGH

100-PF-20 AC-20 10 24"x24"x30" 5 WIDE X 2 HIGH

100-PF-21 AC-21 4 24"x24"x30" 4 WIDE X 1 HIGH

4 24"x12"x30" 4 WIDE X 1 HIGH

100-PF-22 AC-22 8 24"x24"x30" 4 WIDE X 2 HIGH

4 24"x12"x30" 4 WIDE X 1 HIGH

100-PF-23 AC-23 4 24"x24"x30" 4 WIDE X 1 HIGH

4 24"x12"x30" 4 WIDE X 1 HIGH

100-PF-24 AC-24 15 24"x24"x30" 5 WIDE X 3 HIGH

100-PF-24a AC-24 15 24"x24"x30" 5 WIDE X 3 HIGH

100-PF-25 AC-25 8 24"x24"x30" 4 WIDE X 2 HIGH

100-PF-26 AC-26 4 24"x24"x30" 4 WIDE X 1 HIGH

4 24"x12"x30" 4 WIDE X 1 HIGH

100-PF-27 AC-27 1 24"x24"x30" 1 WIDE X 1 HIGH

100-PF-28 ELEC RM 2 20"x25" 2 WIDE X 1 HIGH

100-PF-29 AC-12 1 20"x25" 1 WIDE X 1 HIGH

100-PF-30 AC-1,2 4 16"x25" 2 WIDE X 2 HIGH

100-PF-31 AC-3,4 4 16"x25" 2 WIDE X 2 HIGH

100-PF-32 AC-5 4 16"x25" 2 WIDE X 2 HIGH

100-PF-33 AC-25,26 4 16"x25" 2 WIDE X 2 HIGH

100-PF-35 AC-23,24 4 16"x20" 2 WIDE X 2 HIGH

2 20"x25" 2 WIDE X 1 HIGH

100-PF-36 AC-20 2 20"x25" 2 WIDE X 1 HIGH

100-PF-37 AC-21,22 4 16"x20" 2 WIDE X 2 HIGH

100-PF-38 AC-15,16 2 20"x25" 2 WIDE X 1 HIGH

100-PF-39 AC-16 2 20"x25" 2 WIDE X 1 HIGH

100-PF-40 AC-18 2 20"x25" 2 WIDE X 1 HIGH

100-PF-41 AC-19 1 20"x25" 1 WIDE X 1 HIGH

100-PF-42 AC-13 2 20"x25" 2 WIDE X 1 HIGH

100-PF-43 AC-14 2 20"x25" 2 WIDE X 1 HIGH

100-PF-44 AC-11 2 20"x25" 2 WIDE X 1 HIGH

100-PF-45 AC-10 4 16"x25" 2 WIDE X 2 HIGH

100-PF-48 AC-6 4 16"x20" 2 WIDE X 2 HIGH

100-PF-49 AC-7 1 20"x25" 1 WIDE X 1 HIGH

100-PF-50 AC-10 4 16"x25" 2 WIDE X 2 HIGH

100-PF-53 PLUMBING 7 16"x20" 7 WIDE X 1 HIGH

7 16"x25" 7 WIDE X 1 HIGH

100-PF-54 AC-18 2 20"x25" 2 WIDE X 1 HIGH

100-PF-55 AC-21,22 2 20"x25" 2 WIDE X 1 HIGH

100-PF-56 AC-10 4 16"x25" 2 WIDE X 2 HIGH

100-PF-70 AC-70 1 24"x24"x4" 1 WIDE X 1 HIGH

BUILDING 1 - AIR FILTERS

FILTER NO. SYSTEM

CARTRIDGES

NO. SIZE ARRANGEMENT

1-PF1 1-AH1 20 24"x24"x4" 4 WIDE x 5 HIGH

1-PF2 1-AH2 12 24"x24"x4" 4 WIDE x 3 HIGH

1-PF3 1-AH3 16 24"x24"x4" 4 WIDE x 4 HIGH

1-PF4 1-AH4 16 24"x24"x4" 4 WIDE x 4 HIGH

1-PF5 1-AH5 20 24"x24"x4" 4 WIDE x 5 HIGH

1-PF6 1-AH6 6 24"x24"x4" 3 WIDE x 2 HIGH

1-PF7 1-AH7 12 24"x24"x4" 4 WIDE x 3 HIGH

1-PF8 1-AH8 6 24"x24"x4" 3 WIDE x 2 HIGH

1-PF9 1-AH9 6 24"x24"x4" 3 WIDE x 2 HIGH

1-PF10 1-AH10 12 24"x24"x4" 4 WIDE x 3 HIGH

GI004

ALK JWV

AIR FILTER NOTES:

1. VERIFY SIZING IN FIELD PRIOR TO PURCHASING AIR FILTERS.

2. COORDINATE INTAKE SYSTEMS AND LOCATIONS WITH COR.

3. FOR AIR INTAKES NOT SHOWN IN THE SCHEDULE LISTED ON THIS SHEET, VERIFY

FILTER REQUIREMENTS IN THE FIELD.

4. PROVIDE MERV 8 RATED CARBON IMPREGNATED FILTERS, DISPOSE OF REMOVED

PRE-FILTERS PRIOR TO BEGINNING WORK. MARK INSTALL DATE ON FILTERS.

5. REPLACE MERV 8 CARBON IMPREGNATED FILTERS EVERY 60 DAYS.

6. MERV 8 CARBON IMPREGNATED FILTERS MAY BE REMOVED 7 DAYS AFTER

COMPLETION OF ROOF CONSTRUCTION, FOLLOWING FINAL COR ACCEPTANCE.

AIR INTAKE FILTER SCHEDULES

THE FOLLOWING ROOFS (AS SCREENED OUT ABOVE) ARE NOT INCLUDED

IN THIS PROJECT, FIELD VERIFY AND COORDINATE WITH COR TO

DETERMINE IF THESE FILTERS WILL REQUIRE REPLACEMENT DURING

PHASE III CONSTRUCTION.

B1

-B

A D

DHH BAJ

SCALE: 18" = 1'-0"

0 4' 8' 24'16'

NORTH

SCALE:

GC101

B100-A CONSTRUCTION CONTAINMENT OVER EIGHTH FLOOR

1/8" = 1'-0"

ROOF AREA ≈ 5,698 GSF

GC101

B100-A CONSTRUCTION CONTAINMENT

OVER EIGHTH FLOOR

KEY NOTES:

1. CRITICAL AIR INTAKE, LOUVER ON EXTERIOR WALL. PROVIDE MERV-8 RATED

CARBON PRE-FILTER FOR ODOR CONTROL. CARBON PRE-FILTER MUST BE IN-PLACE

BEFORE BEGINNING WORK AND MUST REMAIN IN PLACE FOR 7 DAYS AFTER THE

COMPLETION OF ROOF CONSTRUCTION. COORDINATE INSTALLATION AND REMOVAL

OF CARBON PRE-FILTER WITH COR. SEE SHEET GI004 FOR AIR INTAKE FILTER

SCHEDULE AND ADDITIONAL INFORMATION.

-A

B1

-C

DHH BAJ

SCALE: 18" = 1'-0"

0 4' 8' 24'16'

NORTH

SCALE:

GC102

B100-B CONSTRUCTION CONTAINMENT OVER EIGHTH FLOOR

1/8" = 1'-0"

ROOF AREA ≈ 6,215 GSF

GC102

B100-B CONSTRUCTION CONTAINMENT

OVER EIGHTH FLOOR

KEY NOTES:

1. CRITICAL AIR INTAKE, VENT HOOD ON ROOF. PROVIDE MERV-8 RATED CARBON

PRE-FILTER FOR ODOR CONTROL. CARBON PRE-FILTER MUST BE IN-PLACE BEFORE

BEGINNING WORK AND MUST REMAIN IN PLACE FOR 7 DAYS AFTER THE COMPLETION

OF ROOF CONSTRUCTION. COORDINATE INSTALLATION AND REMOVAL OF CARBON

PRE-FILTER WITH COR. SEE SHEET GI004 FOR AIR INTAKE FILTER SCHEDULE AND

ADDITIONAL INFORMATION.

-B

HAZARDOUS

EXHAUST

DHH BAJ

SCALE: 18" = 1'-0"

0 4' 8' 24'16'

NORTH

SCALE:

GC103

B100-C CONSTRUCTION CONTAINMENT OVER EIGHTH FLOOR

1/8" = 1'-0"

ROOF AREA ≈ 5,730 GSF

GC103

B100-C CONSTRUCTION CONTAINMENT

OVER EIGHTH FLOOR

KEY NOTES:

1. CRITICAL AIR INTAKE, LOUVER ON EXTERIOR WALL. PROVIDE MERV-8 RATED

CARBON PRE-FILTER FOR ODOR CONTROL. CARBON PRE-FILTER MUST BE IN-PLACE

BEFORE BEGINNING WORK AND MUST REMAIN IN PLACE FOR 7 DAYS AFTER THE

COMPLETION OF ROOF CONSTRUCTION. COORDINATE INSTALLATION AND REMOVAL

OF CARBON PRE-FILTER WITH COR. SEE SHEET GI004 FOR AIR INTAKE FILTER

SCHEDULE AND ADDITIONAL INFORMATION.

2. HAZARDOUS EXHAUST. COORDINATE WORK AND SAFETY PLAN WITH COR 30 DAYS

PRIOR TO THE START OF WORK.

DHH BAJ

SCALE: 18" = 1'-0"

0 4' 8' 24'16'

NORTH

SCALE:

GC104

B100-D CONSTRUCTION CONTAINMENT OVER EIGHTH FLOOR

1/8" = 1'-0"

UPPER ROOF AREA ≈ 3,624 GSF

NORTH CONNECTOR ROOF AREA ≈ 600 GSF

SOUTH CONNECTOR ROOF AREA ≈ 851 GSF

GC104

B100-D CONSTRUCTION CONTAINMENT

OVER EIGHTH FLOOR

KEY NOTES:

1. CRITICAL AIR INTAKE, VENT HOOD ON ROOF. PROVIDE MERV-8 RATED CARBON

PRE-FILTER FOR ODOR CONTROL. CARBON PRE-FILTER MUST BE IN-PLACE BEFORE

BEGINNING WORK AND MUST REMAIN IN PLACE FOR 7 DAYS AFTER THE COMPLETION

OF ROOF CONSTRUCTION. COORDINATE INSTALLATION AND REMOVAL OF CARBON

PRE-FILTER WITH COR. SEE SHEET GI004 FOR AIR INTAKE FILTER SCHEDULE AND

ADDITIONAL INFORMATION.

2. CRITICAL AIR INTAKE, LOUVER ON EXTERIOR WALL. PROVIDE MERV-8 RATED

CARBON PRE-FILTER FOR ODOR CONTROL. CARBON PRE-FILTER MUST BE IN-PLACE

BEFORE BEGINNING WORK AND MUST REMAIN IN PLACE FOR 7 DAYS AFTER THE

COMPLETION OF ROOF CONSTRUCTION. COORDINATE INSTALLATION AND REMOVAL

OF CARBON PRE-FILTER WITH COR. SEE SHEET GI004 FOR AIR INTAKE FILTER

SCHEDULE AND ADDITIONAL INFORMATION.

E S

H

EE

T

AD

DHH BAJ

SCALE: 18" = 1'-0"

0 4' 8' 24'16'

NORTH

SCALE:

GC106

B100-F CONSTRUCTION CONTAINMENT OVER FIRST FLOOR

1/8" = 1'-0"

UPPER ROOF AREA ≈ 3,341 GSF

LOWER ROOF AREA ≈ 10,246 GSF

GC106

B100-F CONSTRUCTION CONTAINMENT

OVER FIRST FLOOR

KEY NOTES:

1. CRITICAL AIR INTAKE, AIR HANDLER ON ROOF. PROVIDE MERV-8 RATED CARBON

PRE-FILTER FOR ODOR CONTROL. CARBON PRE-FILTER MUST BE IN-PLACE BEFORE

BEGINNING WORK AND MUST REMAIN IN PLACE FOR 7 DAYS AFTER THE COMPLETION

OF ROOF CONSTRUCTION. COORDINATE INSTALLATION AND REMOVAL OF CARBON

PRE-FILTER WITH COR. SEE SHEET GI004 FOR AIR INTAKE FILTER SCHEDULE AND

INFORMATION.

DHH BAJ

SCALE: 18" = 1'-0"

0 4' 8' 24'16'

NORTH

SCALE:

GC108

B100-H CONSTRUCTION CONTAINMENT OVER FIRST FLOOR

1/8" = 1'-0"

ROOF AREA ≈ 1,470 GSF

GC108

B100-H CONSTRUCTION CONTAINMENT

OVER FIRST FLOOR

KEY NOTES:

1. CRITICAL AIR INTAKE, VENT HOOD ON ROOF. PROVIDE MERV-8 RATED CARBON

PRE-FILTER FOR ODOR CONTROL. CARBON PRE-FILTER MUST BE IN-PLACE BEFORE

BEGINNING WORK AND MUST REMAIN IN PLACE FOR 7 DAYS AFTER THE COMPLETION

OF ROOF CONSTRUCTION. COORDINATE INSTALLATION AND REMOVAL OF CARBON

PRE-FILTER WITH COR. SEE SHEET GI004 FOR AIR INTAKE FILTER SCHEDULE AND

ADDITIONAL INFORMATION.

J1 J1

J2

DHH BAJ

SCALE: 18" = 1'-0"

0 4' 8' 24'16'

NORTH

SCALE:

GC109

B100-J CONSTRUCTION CONTAINMENT OVER FIRST FLOOR

1/8" = 1'-0"

ROOF AREA J1 #1 ≈ 344 GSF

ROOF AREA J1 #2 ≈ 1,225 GSF

ROOF AREA J2 #3 ≈ 688 GSF

GC109

B100-J CONSTRUCTION CONTAINMENT

OVER FIRST FLOOR

KEY NOTES:

1. CRITICAL AIR INTAKE, AIR HANDLER ON ROOF. PROVIDE MERV-8 RATED CARBON

PRE-FILTER FOR ODOR CONTROL. CARBON PRE-FILTER MUST BE IN-PLACE BEFORE

BEGINNING WORK AND MUST REMAIN IN PLACE FOR 7 DAYS AFTER THE COMPLETION

OF ROOF CONSTRUCTION. COORDINATE INSTALLATION AND REMOVAL OF CARBON

PRE-FILTER WITH COR. SEE SHEET GI004 FOR AIR INTAKE FILTER SCHEDULE AND

B20 ROOF AREA B1 CONNECTION ROOF AREA

B22 CONNECTION ROOF AREA

DHH BAJ

SCALE: 18" = 1'-0"

0 4' 8' 24'16'

NORTH

SCALE:

GC122

B20 CONSTRUCTION CONTAINMENT OVER FIRST FLOOR

1/8" = 1'-0"

BUILDING 20 ROOF AREA ≈ 3,818 GSF

BUILDING 1 CONNECTION ROOF AREA ≈ 859 GSF

BUILDING 22 CONNECTION ROOF AREA ≈ 2,188 GSF

GC122

B20 CONSTRUCTION CONTAINMENT

OVER FIRST FLOOR

KEY NOTES:

1. CRITICAL AIR INTAKE, AIR HANDLER ON ROOF. PROVIDE MERV-8 RATED CARBON

PRE-FILTER FOR ODOR CONTROL. CARBON PRE-FILTER MUST BE IN-PLACE BEFORE

BEGINNING WORK AND MUST REMAIN IN PLACE FOR 7 DAYS AFTER THE COMPLETION

OF ROOF CONSTRUCTION. COORDINATE INSTALLATION AND REMOVAL OF CARBON

PRE-FILTER WITH COR. SEE SHEET GI004 FOR AIR INTAKE FILTER SCHEDULE AND

1 1

B20 CONNECTION ROOF AREA

DHH BAJ

SCALE: 18" = 1'-0"

0 4' 8' 24'16'

NORTH

SCALE:

GC123

B22 CONSTRUCTION CONTAINMENT OVER FIRST FLOOR

1/8" = 1'-0"

ROOF AREA ≈ 10,592 GSF

GC123

B22 CONSTRUCTION CONTAINMENT

OVER FIRST FLOOR

KEY NOTES:

1. CRITICAL AIR INTAKE, AIR HANDLER ON ROOF. PROVIDE MERV-8 RATED CARBON

PRE-FILTER FOR ODOR CONTROL. CARBON PRE-FILTER MUST BE IN-PLACE BEFORE

BEGINNING WORK AND MUST REMAIN IN PLACE FOR 7 DAYS AFTER THE COMPLETION

OF ROOF CONSTRUCTION. COORDINATE INSTALLATION AND REMOVAL OF CARBON

PRE-FILTER WITH COR. SEE SHEET GI004 FOR AIR INTAKE FILTER SCHEDULE AND

RADIOLOGY AREA BELOW: COORDINATE WORK W/ COR

RADIOLOGY LAB BELOW:

COORD WORK W/ COR

REPAIR NOTES:

1. RENEW CURB FLASHING.

2. VENT PENETRATION THROUGH ROOF TO REMAIN. RENEW PIPE FLASHING.

3. N/A TO THIS SHEET.

4. MULTIPLE PIPE PENETRATIONS THROUGH ROOF. RENEW PIPE FLASHINGS.

5. RENEW CURB FLASHING FOR AHU.

6. FLUSH OUT ROOF DRAINS AND PROVIDE CAST IRON DOME STRAINERS.

7. RENEW BASE FLASHING AT EQUIPMENT CURB.

DHH BAJ

SCALE: 18" = 1'-0"

0 4' 8' 24'16'

NORTH

SCALE:

AE124

B33 ROOF PLAN OVER FIRST FLOOR

1/8" = 1'-0"

ROOF AREA ≈ 12,700 GSF

SHEET NOTES:

1. PROVIDE REPAIRS TO EPDM ROOF MEMBRANE AND COMPONENTS AS INDICATED.

2. RE-INSTALL TEMPORARILY REMOVED, RELOCATED OR RAISED EXISTING ROOF

TOP EQUIPMENT TO REMAIN, SUCH AS: VENTILATORS, EXHAUST FANS, LIGHTNING

PROTECTION, LIGHT FIXTURES, LADDERS/CAGES, EXPANDED METAL WALKWAYS,

CONDENSING UNITS, CABLES AND OTHER MISCELLANEOUS ITEMS. VERIFY AND

COORDINATE LOCATIONS WITH COR.

3. ACCESS TO ROOF IS NOT AVAILABLE DURING NORMAL WORKING HOURS. WORK

WILL TYPICALLY BE PERFORMED AFTER 5 PM. COORDINATE WITH THE COR TO

PERFORM WORK WHEN RADIOLOGY EQUIPMENT IS NOT IN SERVICE.

4. PROVIDE CARBON FILTERS AT ALL AIR INTAKES.

5. PROVIDE OSHA COMPLIANT FALL PROTECTION FOR ALL WORKERS ON ROOF.

SAFETY WATCH IS NOT ALLOWED. FALL PROTECTION MUST BE INCLUDED IN

SAFETY PLAN AND COORDINATED WITH COR BEFORE STARTING WORK.

AE124

B33 ROOF PLAN

OVER FIRST FLOOR

LEGEND:

INDICATES LOCATION OF EXISTING ROOF DRAIN

File details come from the government source that posted it. Updated .