P-678 Dry Dock 8 Saltwater System Specs Part 1 Vol4of4 Final Design Submittal 02282022.pdf
PDF 2 MB Posted
- Attached to
- P-678 Dry Dock 8 Saltwater System for CVN-78, Norfolk Naval Shipyard, Portsmouth, Virginia
- Solicitation number
- N40085-22-R-2598_Specifications
About this file
This document provides specifications for the P-678 Dry Dock 8 Saltwater System project at Norfolk Naval Shipyard in Portsmouth, Virginia. The specifications cover work on dry dock saltwater piping and pumpwell systems. They include sections on concrete, metals, wood, thermal protection, openings, finishes, plumbing, HVAC, electrical systems, communications, security, and earthwork. The Navy is the contracting agency seeking these construction services.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
P-678 DRY DOCK 8
SALTWATER SYSTEM
PART 3, VOLUME 4
SPECIFICATIONS
DESIGN SUBMITTAL
Prepared for
NAVFAC MIDLANT
NORFOLK, VA
Contract No. N40085-22-R-2598 eProject #1364315
28 February 2022
Bertrand Gonzalez, AIA Architectural Cassandra Zwart, PE Civil Engineer
Adam Morel, PE Structural Engineer Roderick Whitsel, PE, SE Structural Engineer
Philip Bowman, PE Fire Protection Engineer
Tyler Godfrey, PE Mechanical Engineer
Justin Cashwell, PE Electrical Engineer
Dmitri Zaichenko, PE Electrical Engineer
P678 Dry Dock 8 Saltwater System for CVN-78 Norfolk Naval Shipyard, Portsmouth VA
WO#: 1364315
PROJECT TABLE OF CONTENTS Page 1
PROJECT TABLE OF CONTENTS
PART 1 – COMMON TO PHASE 1 AND PHASE 2
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 15 08/14 LIST OF DRAWINGS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 08/15 SUMMARY OF WORK
01 14 00.00 22 11/20 WORK RESTRICTIONS
01 20 00 02/21 PRICE AND PAYMENT PROCEDURES
01 30 00.00 22 11/20 ADMINISTRATIVE REQUIREMENTS
01 31 23.13 20 02/21 ELECTRONIC CONSTRUCTION AND FACILITY
SUPPORT CONTRACT MANAGEMENT SYSTEM
01 32 17.00 20 08/20 COST-LOADED NETWORK ANALYSIS SCHEDULES
(NAS)
01 33 00.00 22 08/18 SUBMITTAL PROCEDURES
01 33 29 02/21 SUSTAINABILITY REQUIREMENTS AND
REPORTING
01 35 13.00 22 11/20 SPECIAL PROJECT PROCEDURES
01 35 26.00 22 08/21 GOVERNMENTAL SAFETY REQUIREMENTS
01 35 40.00 22 04/15 MARINE MAMMAL PROTECTION
01 42 00 02/19 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 22 02/21 QUALITY CONTROL
01 50 00.00 22 11/20 TEMPORARY CONSTRUCTION FACILITIES AND
CONTROLS
01 57 19.00 22 04/21 TEMPORARY ENVIRONMENTAL CONTROLS
01 57 19.01 20 08/20 SUPPLEMENTAL TEMPORARY ENVIRONMENTAL
CONTROLS
01 58 00 11/20 PROJECT IDENTIFICATION
01 74 19.00 22 02/19 CONSTRUCTION WASTE MANAGEMENT AND
DISPOSAL
01 78 00 05/19 CLOSEOUT SUBMITTALS
01 78 23 11/20 OPERATION AND MAINTENANCE DATA
01 78 24.00 20 11/20 FACILITY ELECTRONIC OPERATION AND
MAINTENANCE SUPPORT INFORMATION(eOMSI)
01 91 00.15 20 02/21 TOTAL BUILDING COMMISSIONING
DIVISION 02 - EXISTING CONDITIONS
02 41 00.00 22 02/19 DEMOLITION AND DECONSTRUCTION
02 61 13 02/21 EXCAVATION AND HANDLING OF CONTAMINATED
MATERIAL
02 81 00 02/21 TRANSPORTATION AND DISPOSAL
OF HAZARDOUS MATERIALS
02 82 00.00 22 11/18 LEAD REMEDIATION
02 83 00.00 22 11/18 ASBESTOS REMEDIATION
02 84 16.00 22 05/20 HANDLING OF LIGHTING BALLASTS AND LAMPS
CONTAINING PCBS AND MERCURY
02 84 33.00 22 04/06 REMOVAL AND DISPOSAL OF POLYCHLORINATED
BIPHENYLS (PCBs)
DIVISION 03 - CONCRETE
03 30 00 05/21 CAST-IN-PLACE CONCRETE
03 31 30 02/19 MARINE CONCRETE
PROJECT TABLE OF CONTENTS Page 2
DIVISION 05 – METALS
05 05 20.00 27 02/21 POST-INSTALLED CONCRETE AND MASONRY
ANCHORS
05 12 00 11/18 STRUCTURAL STEEL
05 40 00 08/18 COLD-FORMED METAL FRAMING
05 50 13 08/18 MISCELLANEOUS METAL FABRICATIONS
05 51 33 02/18 METAL LADDERS
05 52 00 02/18 METAL RAILINGS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 11/18 ROUGH CARPENTRY
06 73 01 05/18 FIBERGLASS REINFORCED PLASTIC (FRP)
GRATING
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 92 00 11/18 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 08/20 STEEL DOORS AND FRAMES
08 71 00 08/20 DOOR HARDWARE
08 81 00 05/19 GLAZING
DIVISION 09 - FINISHES
09 22 00 08/18 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 02/20 GYPSUM BOARD
09 65 00 08/18 RESILIENT FLOORING
09 90 00.00 22 02/21 PAINTS AND COATINGS
09 90 50.00 22 11/05 PAINT REMOVAL AND CONTROLS
DIVISION 22 – PLUMBING
22 00 00 08/18 PLUMBING, GENERAL PURPOSE
22 14 29.00 40 05/17 SUMP PUMPS
22 15 14.00 40 11/17 GENERAL SERVICE COMPRESSED-AIR
SYSTEMS, LOW PRESSURE
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 05 48.19 08/20 SEISMIC BRACING FOR HVAC
23 05 93 11/15 TESTING, ADJUSTING, AND BALANCING FOR
HVAC
23 81 00 02/21 DECENTRALIZED UNITARY HVAC EQUIPMENT
DIVISION 25 – INTEGRATED AUTOMATION
25 05 11.01 05/21 CYBERSECURITY FOR FACILITY-RELATED
CONTROL SYSTEMS
25 05 11.02 05/21 CYBERSECURITY FOR PUMP STATION
MONITORING AND CONTROL SYSTEMS
25 05 11.03 05/21 CYBERSECURITY FOR ELECTRICAL
SUBSTATION CONTROL SYSTEMS
25 05 11.04 05/21 CYBERSECURITY FOR EMERGENCY GENERATOR
CONTROL SYSTEMS
PROJECT TABLE OF CONTENTS Page 3
DIVISION 26 - ELECTRICAL
26 05 48.00 10 10/07 SEISMIC PROTECTION FOR ELECTRICAL
EQUIPMENT
26 08 00 02/15 APPARATUS INSPECTION AND TESTING
26 13 26.00 25 11/16 MEDIUM-VOLTAGE SWITCHGEAR
26 20 00 11/19 INTERIOR DISTRIBUTION SYSTEM
26 20 01 11/19 EXTERIOR DISTRIBUTION SYSTEM
26 51 00 05/20 INTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 10 00 08/11 BUILDING TELECOMMUNICATIONS CABLING
SYSTEM
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 31 76.00 22 08/14 INTERIOR ADDRESSABLE FIRE ALARM
SYSTEMS
DIVISION 31 – EARTHWORK
31 09 13 01/22 GEOTECHNICAL AND SURVEY MONITORING
31 23 00.00 20 08/15 EXCAVATION AND FILL
31 62 16.13 11/20 STEEL PIPE PILES
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 19.61 11/19 SEALING OF JOINTS IN RIGID PAVEMENT
32 11 23 08/17 AGGREGATE BASE COURSES
32 12 16.16 11/20 ROAD-MIX ASPHALT PAVING
32 13 13.06 05/20 PORTLAND CEMENT CONCRETE PAVEMENT FOR
ROADS AND SITE FACILITIES
32 17 23 11/18 PAVEMENT MARKINGS
32 31 13 05/17 CHAIN LINK FENCES AND GATES
DIVISION 33 - UTILITIES
33 08 55 08/19 FUEL DISTRIBUTION SYSTEM START-UP
(NON-HYDRANT)
33 11 00.00 22 05/16 POTABLE WATER UTILITY DISTRIBUTION
PIPING
33 11 00.01 22 02/11 SALTWATER UTILITY DISTRIBUTION PIPING
33 30 00 05/18 SANITARY SEWERAGE
33 31 00 10/18 EXTERIOR OILY WASTE, WASTE OIL PIPING
33 40 00 02/19 STORM DRAINAGE UTILITIES
33 52 23.15 11/18 POL SERVICE PIPING WELDING
33 52 40 11/20 FUEL SYSTEMS PIPING (NON-HYDRANT)
33 56 10 11/20 FACTORY-FABRICATED FUEL STORAGE TANKS
33 57 55 11/20 FUEL SYSTEM COMPONENTS (NON-HYDRANT)
33 61 13.19 11/20 VALVES, PIPING, AND EQUIPMENT IN
VALVE MANHOLES
33 63 13 04/06 EXTERIOR UNDERGROUND STEAM
DISTRIBUTION SYSTEM
33 71 02 11/19 UNDERGROUND ELECTRICAL DISTRIBUTION
33 82 00 04/06 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
Kemp, Richard A.
26 20 00 and 26 51 00 have been updated to common specs. Please add them both in this section.
Kemp, Richard A.
26 51 00 has been updated to a common spec. Please remove.
Kemp, Richard A.
26 51 00 has been updated to a common spec. Please remove.
PROJECT TABLE OF CONTENTS Page 4
DIVISION 34 - TRANSPORTATION
34 11 00 04/08 RAILROAD TRACK AND ACCESSORIES
34 11 19.00 20 08/18 WELDING CRANE AND RAILROAD RAIL -
THERMITE METHOD
DIVISION 40 - PROCESS INTERCONNECTIONS
40 05 13 02/20 PIPELINES, LIQUID PROCESS PIPING
40 05 13.96 05/10 WELDING PROCESS PIPING
40 60 00 05/20 PROCESS CONTROL
DIVISION 41 - MATERIAL PROCESSING AND HANDLING EQUIPMENT
41 22 13.33 05/10 PORTAL CRANE TRACK INSTALLATION
41 22 23.19 05/20 MONORAIL HOISTS
PART 2 - COMMON TO PHASE 1
01 45 35 11/20 SPECIAL INSPECTIONS
07 21 16 08/18 MINERAL FIBER BLANKET INSULATION
DIVISION 26 – ELECTRICAL
26 11 13.00 20 11/21 PRIMARY UNIT SUBSTATION
23 13 00 11/14 SF6/HIGH-FIREPOINT FLUIDS INSULATED
PAD-MOUNTED SWITCHGEAR
26 29 01.00 10 11/08 ELECTRIC MOTORS, 3-PHASE VERTICAL
INDUCTION TYPE
26 32 15.00 05/20 ENGINE-GENERATOR SET STATIONARY, WITH
AUXILIARIES AND LOAD BANK
DIVISION 31 - EARTHWORK
31 63 33 01/19 MICROPILES
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 45 04.00 10 11/20 SUBMERSIBLE PUMP, CENTRIFUGAL TYPE
FOR DRY PIT APPLICATOIN
PROJECT TABLE OF CONTENTS Page 5
PART 3 – COMMON TO PHASE 2
01 45 35 11/20 SPECIAL INSPECTIONS
DIVISION 05 - METALS
05 30 00 05/15 STEEL DECKS
05 51 00 05/17 METAL STAIRS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 13 33 08/17 PIER TIMBERWORK
07 14 00 02/18 FLUID-APPLIED WATERPROOFING
07 21 13 08/20 BOARD AND BLOCK INSULATION
07 22 00 11/18 ROOF AND DECK INSULATION
07 27 10.00 10 02/20 BUILDING AIR BARRIER SYSTEM
07 27 19.01 08/20 SELF-ADHERING AIR BARRIERS
07 52 00 11/19 MODIFIED BITUMINOUS MEMBRANE ROOFING
07 60 00 11/18 FLASHING AND SHEET METAL
DIVISION 08 - OPENINGS
08 51 23 08/20 STEEL WINDOWS
DIVISION 10
- SPECIALTIES
10 14 00.10
11/18
EXTERIOR SIGNAGE
10 44 16 11/19 FIRE EXTINGUISHERS
DIVISION 21 - FIRE SUPPRESSION
21 13 13 08/20 WET PIPE SPRINKLER SYSTEMS, FIRE
PROTECTION
DIVISION 26 – ELECTRICAL
26 29 01.00 10 11/08 ELECTRIC MOTORS, 3-PHASE VERTICAL
INDUCTION TYPE
26 32 15.00 05/20 ENGINE-GENERATOR SET STATIONARY, WITH
AUXILIARIES
26 41 00 11/13 LIGHTNING PROTECTION SYSTEM
DIVISION 31 - EARTHWORK
31 41 16 01/22 STEEL SHEET PILE AND COMBINATION
PILE WALLS
31 52 00 01/22 TEMPORARY COFFERDAMS
31 62 19.13 08/17 TIMBER MARINE PILES
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 20 14 04/08 STOPLOGS
35 45 01 02/21 VERTICAL TURBINE PUMPS
35 59 35 01/22 MOORING FITTINGS
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 6
SPECIFICATION APPENDICES
TABLE OF CONTENTS
Appendix A – Reference Drawings A1 – 1941 Dry Dock 8 Discharge Header and Culvert A2 – 1942 Dry Dock 8 Pumpwell A3 - 1941 Quay Wall North of Entrance Pile Plan A4 – 1961 Dry Dock 8 Pump Stations A5 – 1961 Utilities Increment – Dry Dock 8 Sheets A6 – 2009 Dry Dock 8 Repair Walls and Floor – Typical Sections A7 – 2016 Dry Dock 8 Stop Log Seat Repair A8 – 1998 NNSY Drawings – Pumpwell 8 Schematic Flooding & Dewatering Isometric A9 – 2020 Pumpwell 8 – Replace MDP-2 A10- 1941 Berth 39 Appendix B – Historical Geotechnical Data Appendix C – Project Geotechnical Data Appendix D – Soils Chemical and Environmental Analytical Results Appendix E – HAZMAT Inspection Drawing and Laboratory Reports Appendix F – Utility Test Hole Logs Appendix G – Electric Manhole Survey Appendix H - Stormwater Management Plan Appendix I – Permits and Approvals Appendix J – NNSY Instructions P5090 Appendix K – Five-Year Site Management Plan Appendix L – 1941 Berth 39
P678 Dry Dock 8 Saltwater System for CVN-78 Work Order #: 1364315 Norfolk Naval Shipyard, Portsmouth, VA
SECTION 01 45 35
SPECIAL INSPECTIONS
11/20
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN SOCIETY OF CIVIL ENGINEERS (ASCE)
ASCE 7-16 (2017; Errata 2018; Supp 1 2018) Minimum Design Loads and Associated Criteria for Buildings and Other Structures
INTERNATIONAL CODE COUNCIL (ICC)
ICC IBC (2018) International Building Code
1.2 GENERAL REQUIREMENTS
Perform Special Inspections in accordance with the Statement of Special Inspections, Schedule of Special Inspections and Chapter 17 of ICC IBC .
The Statement of Special Inspections and Schedule of Special Inspections are included as an attachment to this specification. Special Inspections are to be performed by an independent third party and are intended to ensure that the work of the Prime Contractor is in accordance with the Contract Documents and applicable building codes. Special inspections do not take the place of the three phases of control inspections performed by the Contractor's QC Manager or any testing and inspections required by other sections of the specifications.
Structural observations will be performed separately by the Government .
The Contractor must provide notification to the Contracting Officer 14 days prior to the following points of construction to allow for structural observation:
a. Installation of Pump Station 6 and 8 Deep foundations
b. Placement of Pump Station 6 and 8 mezzanine level framing and concrete over metal deck
c. Installation of Pump Station 6 and 8 framing and roof deck
d. Placement of concrete for Pump Station 6 and 8 foundation and exterior walls.
1.3 DEFINITIONS
1.3.1 Continuous Special Inspections
Continuous Special Inspections is the constant monitoring of specific tasks by a special inspector. These inspections must be carried out continuously over the duration of the particular tasks.
SECTION 01 45 35 Page 1
1.3.2 Perform
Perform these Special Inspections tasks for each welded joint or member.
1.3.3 Observe
Observe these Special Inspections items on a periodic daily basis.
Operations need not be delayed pending these inspections.
1.3.4 Special Inspector (SI)
A qualified person retained by the Contractor and approved by the Contracting Officer as having the competence necessary to inspect a particular type of construction requiring Special Inspections. The SI must be an independent third party hired directly by the Prime Contractor.
1.3.5 Associate Special Inspector (ASI)
A qualified person who assists the SI in performing Special Inspections but must perform inspection under the direct supervision of the SI and cannot perform inspections without the SI on site.
1.3.6 Third Party
A Special inspector must not be an employee of the Contractor or of any Sub-Contractor performing the work to be inspected.
1.3.7 Special Inspector of Record (SIOR)
A licensed engineer in responsible charge of supervision of all special inspectors for the project and approved by the Contracting Officer. The SIOR must be an independent third party entity hired directly by the Prime Contractor.
1.3.8 Contracting Officer
The Government official having overall authority for administrative contracting actions. Certain contracting actions may be delegated to the Contracting Officer's Representative (COR).
1.3.9 Contractor's Quality Control (QC) Manager
An individual retained by the Prime Contractor and qualified in accordance with the Section 01 45 00.00 22 QUALITY CONTROL having the overall responsibility for the Contractor's QC organization.
1.3.10 Structural Engineer of Record (SER)
A registered design professional contracted by the Government as an A/E responsible for the overall design and review of submittal documents prepared by others. The SER is registered or licensed to practice their respective design profession as defined by the statutory requirements of the professional registration laws in the state in which the design professional works. The SER is also referred to as the Engineer of Record (EOR) in design code documents.
SECTION 01 45 35 Page 2
1.3.11 Statement of Special Inspections (SSI)
A document developed by the SER identifying the material, systems, components and work required to have Special Inspections. This statement is included at the end of this specification.
1.3.12 Schedule of Special Inspections (SSI)
A schedule which lists each of the required Special Inspections, the extent to which each Special Inspection is to be performed, and the required frequency for each in accordance with ICC IBC Chapter 17. This schedule is included at the end of this specification.
1.3.13 Designated Seismic Systems (DSS)
Those nonstructural components that require design in accordance with ASCE 7-16 Chapter 13 and for which the component importance factor, Ip, is greater than 1.0. This designation applies to systems that are required to be operational following the Design Earthquake for RC I - IV structures and following the MCER for RC V structures. Designated Seismic Systems will have an Importance Factor Ip = 1.5.
1.3.14 Definable Feature of Work (DFOW)
An inspection group that is separate and distinct from other inspection groups, having inspection requirements or inspectors that are unique.
1.4 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00.00 22 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
SIOR Letter of Acceptance; G
Special Inspections Project Manual; G
SD-06 Test Reports
Special Inspections Biweekly Reports
SD-07 Certificates
AISC Certified Steel Fabricator
Special Inspector of Record Qualifications; G
Special Inspector Qualifications; G
SD-11 Closeout Submittals
Interim Report of Special Inspections for Each DFOW; G
Comprehensive Final Report of Special Inspections; G
SECTION 01 45 35 Page 3
1.5 SPECIAL INSPECTOR QUALIFICATIONS
Submit qualifications for each special inspector and the special inspector of record.
1.5.1 Steel Construction and High Strength Bolting
1.5.1.1 Special Inspector
a. ICC Structural Steel and Bolting Special Inspector certificate with one year of related experience, or
b. Registered Professional Engineer with three years of related experience
1.5.1.2 Associate Special Inspector
Engineer-In-Training with one year of related experience.
1.5.2 Welding Structural Steel
1.5.2.1 Special Inspector
a. ICC Structural Welding Special Inspector certificate with one year of related experience, or
b. AWS Certified Welding Inspector
1.5.2.2 Associate Special Inspector
AWS Certified Associate Welding Inspector
1.5.3 Nondestructive Testing of Welds
1.5.3.1 Special Inspector
NDT Level III Certificate
1.5.3.2 Associate Special Inspector
NDT Level II Certificate plus one year of related experience
1.5.4 Concrete Construction
1.5.4.1 Special Inspector
a. ICC Reinforced Concrete Special Inspector Certificate with one year of related experience, or
b. ACI Concrete Construction Special Inspector, or
c. Registered Professional Engineer with three years of related experience
1.5.4.2 Associate Special Inspector
a. ACI Concrete Construction Special Inspector in Training, or
b. Engineer-In-Training with one year of related experience
SECTION 01 45 35 Page 4
1.5.5 Verification of Site Soil Condition, Fill Placement and Load-Bearing Requirements
1.5.5.1 Special Inspector
a. ICC Soils Special Inspector Certificate with one year of related experience, or
b. NICET Soils Technician Level II Certificate in Construction Material Testing, or
c. Geologist-In-Training with three years of related experience, or
d. Registered Professional Engineer with three years of related experience
1.5.5.2 Associate Special Inspector
a. NICET Soils Technician Level I Certificate in Construction Material Testing with one year of related experience, or
b. Engineer-In-Training with one year of related experience
1.5.6 Deep Foundations
1.5.6.1 Special Inspector
a. NICET Soils Technician Level II Certificate in Construction Material Testing, or
b. Geologist-In-Training with three years of related experience, or
c. Registered Professional Engineer with three years of related experience
1.5.6.2 Associate Special Inspector
a. NICET Soils Technician Level I Certificate in Construction Material Testing with one year of related experience, or
b. NICET Geotechnical Engineering Technician Level I Construction or Generalist Certificate with one year of related experience, or
c. Engineer-In-Training with one year of related experience
1.5.7 Special Inspector of Record (SIOR)
Registered Professional Engineer with five years of related experience.
PART 2 PRODUCTS
2.1 FABRICATOR SPECIAL INSPECTIONS
Special Inspections of fabricator's work performed in the fabricator's shop is required to be inspected in accordance with the Statement of Special Inspections and the Schedule of Special Inspections unless the fabricator is certified by the approved agency to perform such work without Special Inspections. Submit the following certification to the Contracting Officer for information to allow work performed in the fabricator's shop to not be subjected to Special Inspections.
SECTION 01 45 35 Page 5
AISC Certified Steel Fabricator.
At the completion of fabrication, provide a certificate of compliance, to be included with the comprehensive final report of Special Inspections, stating that the materials supplied and work performed by the fabricator are in accordance with the construction documents.
PART 3 EXECUTION
3.1 RESPONSIBILITIES
3.1.1 Special Inspector of Record
a. Supervise all Special Inspectors required by the Contract Documents and the IBC.
b. Submit a SIOR Letter of Acceptance to the Contracting Officer attesting to acceptance of the duties of SIOR, signed and sealed by the SIOR.
c. Verify the qualifications of all of the Special Inspectors.
d. Verify the qualifications of fabricators.
e. Prepare a Special Inspections Project Manual, which must cover the following:
(1) Roles and responsibilities of the following individuals during Special Inspections: SIOR, SI, ASI, General Contractor's QC Manager and SER.
(2) Organizational chart or communication plan, indicating lines of communication.
(3) Contractor's internal plan for scheduling inspections. Address items such as timeliness of inspection requests, who to contact for inspection requests, and availability of alternate inspectors.
(4) Indicate the Government reporting requirements.
(5) Propose forms or templates to be used by SI and SIOR to document inspections.
(6) Indicate procedures for tracking nonconforming work and verification that corrective work is complete.
(7) Indicate how the SIOR and SI will participate in weekly QC meetings.
(8) Indicate how Special Inspections of shop fabricated items will be handled when the fabricator's shop is not certified in accordance with paragraph FABRICATOR SPECIAL INSPECTIONS.
(9) Include a section in the manual that covers each specific item requiring Special Inspections that is indicated on the Schedule of Special Inspections. Provide names and qualifications of each special inspector who will be performing the Special Inspections for each specific item. Provide detail on how the Special Inspections are to be carried out for each item so that the
SECTION 01 45 35 Page 6 expectations are clear for the General Contractor and the Subcontractor performing the work.
Make a copy of the Special Inspections Project Manual available on the job site during construction. Submit a copy of the Special Inspections Project Manual for approval.
f. Attend coordination and mutual understanding meeting where the information in the Special Inspections Project Manual will be reviewed to verify that all parties have a clear understanding of the Special Inspections provisions and the individual duties and responsibilities of each party.
g. Maintain a 3-ring binder for the Special Inspector's daily and biweekly reports and the Special Inspections Project Manual. This file must be located in a conspicuous place in the project trailer/office to allow review by the Contracting Officer and the SER.
h. Provide a copy of the Special Inspector's daily reports to the QC Manager.
i. Discrepancies that are observed during Special Inspections must be reported to the QC Manager for correction. If discrepancies are not corrected before the special inspector leaves the site the observed discrepancies must be documented in the daily report.
j. Submit a biweekly Special Inspections report until all work requiring Special Inspections is complete. A report is required for each biweekly period in which Special Inspections activity occurs, and must include the following:
(1) A brief summary of the work performed during the reporting time frame.
(2) Changes and discrepancies with the drawings, specifications and mechanical or electrical component certification, that were observed during the reporting period.
(3) Discrepancies which were resolved or corrected.
(4) A list of nonconforming items requiring resolution.
(5) All applicable test results including nondestructive testing reports.
k. At the completion of each Definable Feature of Work (DFOW) requiring Special Inspections, submit an interim report that documents the Special Inspections completed for that DFOW including corrections of all discrepancies noted in the daily reports. Interim reports of Special Inspections must be signed and dated by the SIOR.
l. At the completion of the project submit a comprehensive final report of Special Inspections that documents the Special Inspections completed for the project including corrections of all discrepancies noted in the daily reports. The comprehensive final report of Special Inspections must be signed, dated and bear the seal of the SIOR.
SECTION 01 45 35 Page 7
3.1.2 Quality Control Manager
a. Maintain a rework items list that includes discrepancies noted on the Special Inspectors daily report.
3.1.3 Special Inspectors
a. Inspect all elements of the project for which the special inspector is qualified to inspect and are identified in the Schedule of Special Inspections.
b. Attend preparatory phase meetings related to the Definable Feature of Work (DFOW) for which the special inspector is qualified to inspect.
c. Provide a copy of the daily reports to the QC Manager.
d. Report discrepancies that are observed during Special Inspections to the QC Manager for correction. If discrepancies are not corrected before the special inspector leaves the site the observed discrepancies must be documented in the daily report.
e. Submit a biweekly Special Inspection Report until all inspections are complete. A report is required for each biweekly period in which Special Inspections activity occurs, and must include the following:
(1) A brief summary of the work performed during the reporting time frame.
(2) Changes and discrepancies with the drawings, specifications and mechanical or electrical component certification, that were observed during the reporting period.
(3) Discrepancies which were resolved or corrected.
(4) A list of nonconforming items requiring resolution.
(5) All applicable test result including nondestructive testing reports.
f. At the completion of each DFOW requiring Special Inspections, submit an interim report of Special Inspections that documents the Special Inspections completed for that DFOW. Identify the inspector responsible for each item inspected and corrections of all discrepancies noted in the daily reports. The interim report of Special Inspections must be signed, dated and indicate the certification of the special inspector qualifying them to conduct the inspection.
g. At the completion of the project submit a comprehensive final report of Special Inspections that documents the Special Inspections completed for the project and corrections of all discrepancies noted in the daily reports. The comprehensive final report of Special Inspections must be signed, dated and indicate the certification of the special inspector qualifying them to conduct the inspection.
h. Submit daily reports to the SIOR.
SECTION 01 45 35 Page 8
3.2 DEFECTIVE WORK
Check work as it progresses, but failure to detect any defective work or materials must in no way prevent later rejection if defective work or materials are discovered, nor obligate the Contracting Officer to accept such work.
-- End of Section --
SECTION 01 45 35 Page 9
THIS PAGE INTENTIONALLY LEFT BLANK
SECTION 01 45 35 Page 10
Project:
Location:
Project #:
Date:
C
IV
No
Statement of Special Inspections Page 1 of 2
Pump Stations - To framing and edge conditions Pump Stations - Horizontal flexible diaphragm Pump Stations - Horizontal rigid diaphragm
Horizontal LFRS Elements Notes Mezzanine level concrete filled metal deck Roof level metal deck Deck attachments
Pump Stations Pump Stations Pump Stations Pump Stations
Following is a listing of critical main wind/seismic force resisting systems for this structure. Carefully inspect these elements as part of the roles and responsiblities of the Special Inspector (reference the Schedule of Special Inspections for inspection checklists).
Lateral Force Resisting System (LFRS) 2018 IBC 1704.3.2 and 1704.3.3
Vertical LFRS Elements Notes Ordinary reinforced concrete shear walls Wall dowels into foundation Deep foundation placements Deep foundation embedment into mat foundation
Hazardous Occupancy or attached to such?
STATEMENT OF SPECIAL INSPECTIONS
Special Inspector of Record (SIOR) A Special Inspector of Record (SIOR)
SIOR Name (Registered Professional):
Professional Registration Number:
Consulting Firm Name (if any):
SIOR Office AND Mobile Phone Number:
IS
Group H Occupancies required (per UFGS 01 45 35, Section 1.3.8)
P678 - DD8 Saltwater System - Phase 2 Portsmouth, VA N4008518D1100 10/6/2021
Project Seismic Design Category:
Project Risk Category:
Project Design Wind Speed (mph):
Number of Stories:
Structure Height Above Grade (ft):
Project:
Location:
Project #:
Date:
1.
2.
3.
4.
5.
1.
2.
3.
4.
5.
6.
1.
2.
3.
4.
5.
6.
10/6/2021 N4008518D1100 Portsmouth, VA P678 - DD8 Saltwater System - Phase 2
Designated Seismic Systems (DSS)
Final Walk Down Inspection and Report
(UFC 3 301 01 SECTION 2-5.4)
Designated Seismic Systems shall receive a final walk-down inspection by the Registered Design Professional in Responsible Charge
Final Walk Down Report, Prepared by the Registered Design Professional in Responsible Charge, Must Include:
1. Record observations of Final Walk Down Inspection
2. Document that Inspections were performed in accordance with the Schedule of Special Inspections
3. Document that all Designated Seismic Systems are installed according to construction/manufacturer document requirements, and that Compliance Certificates have been collected (UFC 03 301 01, 3-6.2, 13.2.2.2).
Statement of Special Inspections Page 2 of 2
Saltwater Supply Pumps and Piping Systems Pump Instrumentation and Control Systems Surge Tanks Strainers Fuel tank and accessories
(2018 IBC 1705.13.3) (ASCE 7-16, 13.2.2, C13.2.2) (UFC 3-301-1, 2-5.3)
Non-structural 'Designated Seismic Systems' (DSS) must remain operable and contain hazardous substances following a design earthquake. Accordingly, all Designated Seismic Systems must be listed below and must be certified by the manufacturer to remain both operable and/or to contain hazardous substances after a design earthquake per UFC 3-301-01, Section 3-6.2. Submit said Certificates of Compliance to the Contracting Officer for each DSS after they have been reviewed and accepted by the EOR/DOR.
Additionally, the below listed Designated Seismic Systems must be carefully inspected by the Special Inspector according to the requirements noted in the Schedule of Special Inspections, Section AA.
ELECTRICAL Designated Seismic Systems (DSS) Requiring a Certificate of Compliance
If additional space is required, append an additional sheet listing the remaining DSS
If additional space is required, append an additional sheet listing the remaining DSS
Emergency Generator (Spec 26 32 15.00) Switchgears (Spec 26 13 26.00 25) Safety Switches (Spec 26 20 00) Motor Starters under 600V (Spec 26 29 23) Panelboards (Spec 26 20 00)
MECHANICAL/PLUMBING Designated Seismic Systems (DSS) Requiring a Certificate of Compliance
OTHER Designated Seismic Systems (DSS) Requiring a Certificate of Compliance Building egress stair systems Building fire sprinkler systems
Project P678 - DD8 Saltwater System - Phase 2 Location Portsmouth, VA Project # N4008518D1100
Date 10/6/2021
6 Transformers (Spec 26 20 00) 7 Lighting Fixtures (Spec 26 51 00) 8 SCADA Wall Cabinet (Spec 27 10 00) 9 Automatic Transfer Switch
Additional ELECTRICAL Designated Seismic Systems (DSS) requiring a Certificate of Compliance
SCHEDULE OF SPECIAL INSPECTIONS FOR UFGS 01 45 35 REVISED FOR IBC 2018 ON 03/01/20
SCHEDULE OF SPECIAL INSPECTIONS
Reference UFGS 01 45 35 for all requirements not noted as part of this schedule.
INSPECTION DEFINITIONS:
PERFORM: Perform these tasks for each weld, fastener or bolted connection, and noted verification.
OBSERVE: Observe these items randomly during the course of each work day to insure that applicable requirements are being met. Operations need not be delayed pending these inspections at contractor’s risk.
DOCUMENT: Document, with a report, that the work has been performed in accordance with the contract documents. This is in addition to any other reports required in the Special Inspections guide specification.
CONTINUOUS: Constant monitoring of identified tasks by a special inspector over the duration of performance of said tasks.
The Seismic Design Category for this project is: ☐ A, ☐ B, ☒ C, ☐ D, ☐ E, ☐ F (check appropriate box)
SCHEDULE OF SPECIAL INSPECTIONS FOR UFGS 01 45 35 REVISED FOR IBC 2018 ON 03/01/20
STRUCTURAL - STEEL – WELDING SECTION
ALL OR PORTIONS OF THIS SECTION ARE APPLICABLE IF BOX IS CHECKED: ☒
STEEL INSPECTION PRIOR TO WELDING – VERIFY THE FOLLOWING ARE IN COMPLIANCE
2018 IBC 1705.2.1, AISC 360-16: Table C-N5.4-1
TASK INSPECTION TYPE1 DESCRIPTION
1. Verify that the welding procedures specification (WPS) is available
PERFORM
2. Verify manufacturer certifications for welding consumables are available
PERFORM
3. Verify material identification PERFORM Type and grade.
4. Welder Identification
System PERFORM The fabricator or erector, as applicable, shall maintain a system by which a welder who has welded a joint or member can be identified. Stamps, if used, shall be the low-stress type.
5. Fit-up of groove welds (including joint geometry)
OBSERVE Joint preparation Dimensions (alignment, root opening, root face, bevel) Cleanliness (condition of steel surfaces) Tacking (tack weld quality and location) Backing type and fit (if applicable)
6. Configuration and finish of access holes
OBSERVE
7. Fit-up of fillet welds OBSERVE Dimensions (alignment, gaps at root) Cleanliness (condition of steel surfaces) Tacking (tack weld quality and location)
STEEL INSPECTION DURING WELDING – VERIFY THE FOLLOWING ARE IN COMPLIANCE
2018 IBC 1705.2.1, AISC 360-16: Table C-N5.4-2
TASK INSPECTION TYPE DESCRIPTION
8. Use of qualified welders PERFORM Welding by welders, welding operators, and tack welders who are qualified in conformance with requirements.
9. Control and handling of welding consumables OBSERVE Packaging
Electrode atmospheric exposure control
10. No welding over cracked tack welds
OBSERVE
11. Environmental conditions OBSERVE Wind speed within limits Precipitation and temperature
12. Welding Procedures Specification followed
OBSERVE Settings on welding equipment Travel speed Selected welding materials Shielding gas type/flow rate Preheat applied Interpass temperature maintained (min./max.)
Proper position (F, V, H, OH) Intermix of filler metals avoided
13. Welding techniques OBSERVE Interpass and final cleaning Each pass within profile limitations Each pass meets quality requirements
1 PERFORM: Perform these tasks for each weld, fastener or bolted connection, and required verification.
OBSERVE: Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need not be delayed pending these inspections at contractor’s risk.
SCHEDULE OF SPECIAL INSPECTIONS FOR UFGS 01 45 35 REVISED FOR IBC 2018 ON 03/01/20
STRUCTURAL - STEEL – WELDING SECTION (CONTINUED)
STEEL INSPECTION AFTER WELDING – VERIFY THE FOLLOWING ARE IN COMPLIANCE
2018 IBC 1705.2.1, AISC 360-16: Table C-N5.4-3
TASK INSPECTION TYPE 1 DESCRIPTION
14. Welds cleaned OBSERVE
15. Size, length, and location of all welds PERFORM Size, length, and location of all welds conform to the requirements of the detail drawings.
16. Welds meet visual acceptance criteria
PERFORM AND
DOCUMENT
Crack prohibition Weld/base-metal fusion Crater cross section Weld profiles Weld size Undercut Porosity
17. Arc strikes PERFORM
18. k-area PERFORM When welding of doubler plates, continuity plates or stiffeners has been performed in the k-area, visually inspect the web k-area for cracks.
19. Backing removed, weld tabs removed and finished, and fillet welds added where required
PERFORM
20. Repair activities PERFORM AND
DOCUMENT
21. Document acceptance or rejection of welded joint or member
PERFORM
END SECTION
1 PERFORM: Perform these tasks for each weld, fastener or bolted connection, and required verification.
DOCUMENT: Document in a report that the work has been performed as required. This is in addition to all other required reports.
SCHEDULE OF SPECIAL INSPECTIONS FOR UFGS 01 45 35 REVISED FOR IBC 2018 ON 03/01/20
STRUCTURAL - STEEL – BOLTING SECTION
STEEL INSPECTION TASKS PRIOR TO BOLTING – VERIFY THE FOLLOWING ARE IN COMPLIANCE
2018 IBC 1705.2.1, AISC 360-16: Table C-N5.6-1
TASK INSPECTION TYPE 1 DESCRIPTION
1. Manufacture’s certifications available for fastener materials
PERFORM
2. Fasteners marked in accordance with ASTM requirements
OBSERVE
3. Proper fasteners selected for joint detail (grade, type, bolt length if threads are to be excluded from shear plane)
OBSERVE
4. Proper bolting procedure selected for joint detail
OBSERVE
5. Connecting elements, including appropriate faying surface condition and hole preparation, if specified, meet applicable requirements
OBSERVE
6. Proper storage provided for bolts, nuts, washers, and other fastener components
OBSERVE
STEEL INSPECTION TASKS DURING BOLTING – VERIFY THE FOLLOWING ARE IN COMPLIANCE
2018 IBC 1705.2.1, AISC 360-16: Table C-N5.6-2
TASK INSPECTION TYPE 1 DESCRIPTION
7. Fastener assemblies of suitable condition, placed in all holes and washers (if required) are positioned as required
OBSERVE
8. Joint brought to the snug-tight condition prior to pretensioning operation
OBSERVE
9. Fastener component not turned by the wrench prevented from rotating
OBSERVE
10. Bolts are pretensioned in accordance with RCSC Specification, progressing systematically from the most rigid point toward the free edges
OBSERVE
STEEL INSPECTION TASKS AFTER BOLTING – VERIFY THE FOLLOWING ARE IN COMPLIANCE
IBC 1705.2.1, AISC 360-10: Table C-N5.6-3
TASK INSPECTION TYPE 1 DESCRIPTION
11. Document acceptance or rejection of all bolted connections
1 PERFORM: Perform these tasks for each weld, fastener or bolted connection, and required verification.
OBSERVE: Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need
DOCUMENT: Document in a report that the work has been performed as required. This is in addition to all other required reports.
SCHEDULE OF SPECIAL INSPECTIONS FOR UFGS 01 45 35 REVISED FOR IBC 2018 ON 03/01/20
STRUCTURAL - STEEL - NON DESTRUCTIVE TESTING SECTION
NONDESTRUCTIVE TESTING OF WELDED JOINTS – VERIFY THE FOLLOWING ARE IN COMPLIANCE
2018 IBC 1705.2.1, AISC 360-16: Section N5.5
TASK INSPECTION TYPE 1 DESCRIPTION
1. Use of qualified nondestructive testing personnel
PERFORM Visual weld inspection and nondestructive testing (NDT) shall be conducted by personnel qualified in accordance with AWS D1.8 clause 7.2
2. CJP groove welds OBSERVE [NOTE: DOR must delete this row if section D (SEISMIC PROVISIONS SECTION) is checked] Dye penetrant testing (DT) and ultrasonic testing (UT) shall be performed on 20% of CJP groove welds for materials greater than 5/16” (8mm) thick. Testing rate must be increased to 100% if greater than 5% of welds tested have unacceptable defects.
3. Welded joints subject to fatigue
OBSERVE Dye penetrant testing (DT) and Ultrasonic testing (UT) shall be performed on 100% of welded joints identified on contract drawings as being subject to fatigue.
4. Weld tab removal sites OBSERVE At the end of welds where weld tabs have been removed, magnetic particle testing shall be performed on the same beam-to-column joints receiving UT
1 PERFORM: Perform these tasks for each weld, fastener or bolted connection, and required verification.
OBSERVE: Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need
SCHEDULE OF SPECIAL INSPECTIONS FOR UFGS 01 45 35 REVISED FOR IBC 2018 ON 03/01/20
STRUCTURAL - STEEL – AISC 341 REQUIREMENTS (SEISMIC PROVISIONS) SECTION
ALL OR PORTIONS OF THIS SECTION ARE APPLICABLE IF BOX IS CHECKED: ☐
NONDESTRUCTIVE TESTING OF WELDED JOINTS – VERIFY THE FOLLOWING ARE IN COMPLIANCE
2018 IBC 1705.2.1, AISC 341-16: Section J6.2
TASK INSPECTION TYPE 1 DESCRIPTION
[NOTE: DOR may uncheck this section for projects NOT designed in accordance with AISC 341 (Seismic Provisions) or for projects designed according to AISC 341, but using an R value equal to 3]
5. CJP groove welds OBSERVE Dye penetrant testing (DT) and ultrasonic testing (UT) shall be performed on 100% of CJP groove welds for materials greater than 5/16” thick (8mm).
6. Beam cope and access hole.
OBSERVE At welded splices and connections, thermally cut surfaces of beam copes and access holes shall be tested using magnetic particle testing (MT) or dye penetrant testing (DT), when the flange thickness exceeds 1 1/2 in. for rolled shapes, or when the web thickness exceeds 1 1/2 in. for built-up shapes.
7. K-area NDT (AISC 341)
PERFORM Where welding of doubler plates, continuity plates or stiffeners has been performed in the k-area, the web shall be tested for cracks using magnetic particle testing (MT). The MT inspection area shall include the k-area base metal within 3-inches of the weld. The MT shall be performed no sooner than 48 hours following completion of the welding.
8. Placement of reinforcing or contouring fillet welds
1 PERFORM: Perform these tasks for each weld, fastener or bolted connection, and required verification.
OBSERVE: Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need
DOCUMENT: Document in a report that the work has been performed as required. This is in addition to all other required reports.
SCHEDULE OF SPECIAL INSPECTIONS FOR UFGS 01 45 35 REVISED FOR IBC 2018 ON 03/01/20
STRUCTURAL - STEEL - COMPOSITE CONSTRUCTION 1
COMPOSITE CONSTRUCTION PRIOR TO PLACING CONCRETE – VERIFY THE FOLLOWING ARE IN COMPLIANCE 2018 IBC 1705.2.1, AISC 360-16: Table N6.1, AISC 341-16: Table J9.1
TASK INSPECTION TYPE 2 DESCRIPTION
1. Placement and installation of steel headed stud anchors
PERFORM
2. Material identification of reinforcing steel (Type/Grade)
OBSERVE
3. Determination of carbon equivalent for reinforcing steel other than ASTM A706
OBSERVE
4. Proper reinforcing steel size, spacing, clearances, support, and orientation
OBSERVE
5. Reinforcing steel has not been re-bent in the field
OBSERVE
6. Reinforcing clearances have been provided
OBSERVE
7. Reinforcing steel has been tied and supported as required
OBSERVE
8. Composite member has required size
OBSERVE
STRUCTURAL - STEEL - OTHER INSPECTIONS
OTHER STEEL INSPECTIONS – VERIFY THE FOLLOWING ARE IN COMPLIANCE
2018 IBC 1705.2.1, AISC 341-16: Tables J8.1 & J10.1
TASK INSPECTION TYPE 2 DESCRIPTION
1. Anchor rods and other embedments supporting structural steel
PERFORM Verify the diameter, grade, type, and length of the anchor rod or embedded item, and the extent or depth of embedment prior to placement of concrete.
2. Fabricated steel or erected steel frame
OBSERVE Verify compliance with the details shown on the construction documents, such as braces, stiffeners, member locations and proper application of joint details at each connection.
3. Reduced beam sections (RBS) where/if occurs
DOCUMENT Contour and finish Dimensional tolerances
4. Protected zones DOCUMENT No holes or unapproved attachments made by fabricator or erector
5. H-piles where/if occurs DOCUMENT No holes or unapproved attachments made by the responsible contractor
1 See Concrete Construction Section for all concrete related inspection of composite steel construction.
2 PERFORM: Perform these tasks for each weld, fastener or bolted connection, and required verification.
OBSERVE: Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need
DOCUMENT: Document in a report that the work has been performed as required. This is in addition to all other required reports.
SCHEDULE OF SPECIAL INSPECTIONS FOR UFGS 01 45 35 REVISED FOR IBC 2018 ON 03/01/20
STRUCTURAL - COLD-FORMED METAL DECK - PLACEMENT SECTION
METAL DECK INSPECTION PRIOR TO DECK PLACEMENT – VERIFY THE FOLLOWING ARE IN COMPLIANCE SDI QA/QC-2011, Appendix 1, Table 1.1
TASK INSPECTION TYPE 1 DESCRIPTION
1. Verify compliance of materials
(deck and all deck accessories) with construction documents, including profiles, material properties, and base metal thickness
PERFORM
2. Document acceptance or rejection of deck and deck accessories
DOCUMENT
METAL DECK INSPECTION DURING DECK PLACEMENT – VERIFY THE FOLLOWING ARE IN COMPLIANCE SDI QA/QC-2011, Appendix 1, Table 1.2
TASK INSPECTION TYPE 1 DESCRIPTION
3. Verify compliance of deck and all deck accessories installation with construction documents
PERFORM
4. Verify deck materials are represented by the mill certifications that comply with the construction documents
PERFORM
5. Document acceptance or rejection of installation of deck and deck accessories
DOCUMENT
METAL DECK INSPECTION AFTER DECK PLACEMENT – VERIFY THE FOLLOWING ARE IN COMPLIANCE SDI QA/QC-2011, Appendix 1, Table 1.3
TASK INSPECTION TYPE 1 DESCRIPTION
6. Welding procedure specification
(WPS) available
PERFORM
7. Manufactures certifications for welding consumables available
OBSERVE
8. Material identification (type/grade)
OBSERVE
9. Check welding equipment OBSERVE
1 PERFORM: Perform these tasks for each weld, fastener or bolted connection, and required verification.
OBSERVE: Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need
DOCUMENT: Document in a report that the work has been performed as required. This is in addition to all other required reports.
SCHEDULE OF SPECIAL INSPECTIONS FOR UFGS 01 45 35 REVISED FOR IBC 2018 ON 03/01/20
STRUCTURAL - COLD-FORMED METAL DECK – WELDING SECTION
METAL DECK INSPECTION DURING WELDING – VERIFY THE FOLLOWING ARE IN COMPLIANCE
SDI QA/QC-2011, Appendix 1, Table 1.4
TASK INSPECTION TYPE 1 DESCRIPTION
1. Use of qualified welders OBSERVE
2. Control and handling of welding consumables
OBSERVE
3. Environmental conditions (wind speed, moisture, temperature)
OBSERVE
4. WPS followed OBSERVE
METAL DECK INSPECTION AFTER WELDING – VERIFY THE FOLLOWING ARE IN COMPLIANCE
SDI QA/QC-2011, Appendix 1, Table 1.5
TASK INSPECTION TYPE 1 DESCRIPTION
5. Verify size and location of welds, including support, sidelap, and perimeter welds.
PERFORM
6. Welds meet visual acceptance criteria
PERFORM
7. Verify repair activities PERFORM
8. Document acceptance or rejection of welds
1 PERFORM: Perform these tasks for each weld, fastener or bolted connection, and required verification.
OBSERVE: Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need
DOCUMENT: Document in a report that the work has been performed as required. This is in addition to all other required reports.
SCHEDULE OF SPECIAL INSPECTIONS FOR UFGS 01 45 35 REVISED FOR IBC 2018 ON 03/01/20
STRUCTURAL - COLD-FORMED METAL DECK – FASTENING SECTION
METAL DECK INSPECTION BEFORE MECHANICAL FASTENING – VERIFY THE FOLLOWING ARE IN COMPLIANCE SDI QA/QC-2011, Appendix 1, Table 1.6
TASK INSPECTION TYPE 1 DESCRIPTION
1. Manufacturer installation instructions available for mechanical fasteners
OBSERVE
2. Proper tools available for fastener installation
OBSERVE
METAL DECK INSPECTION DURING MECHANICAL FASTENING – VERIFY THE FOLLOWING ARE IN COMPLIANCE SDI QA/QC-2011, Appendix 1, Table 1.7
TASK INSPECTION TYPE 1 DESCRIPTION
3. Fasteners are positioned as required
OBSERVE
4. Fasteners are installed in accordance with manufacturer's instructions
OBSERVE
METAL DECK INSPECTION AFTER MECHANICAL FASTENING – VERIFY THE FOLLOWING ARE IN COMPLIANCE SDI QA/QC-2011, Appendix 1, Table 1.8
TASK INSPECTION TYPE 1 DESCRIPTION
5. Check spacing, type, and installation of support fasteners
PERFORM
6. Check spacing, type, and installation of sidelap fasteners
PERFORM
7. Check spacing, type, and installation of perimeter fasteners
PERFORM
8. Verify repair activities PERFORM
9. Document acceptance or rejection of mechanical fasteners
1 PERFORM: Perform these tasks for each weld, fastener or bolted connection, and required verification.
OBSERVE: Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need
DOCUMENT: Document in a report that the work has been performed as required. This is in addition to all other required reports.
SCHEDULE OF SPECIAL INSPECTIONS FOR UFGS 01 45 35 REVISED FOR IBC 2018 ON 03/01/20
STRUCTURAL - LIGHT GAUGE STEEL FRAMING AND/OR LIGHT GAUGE TRUSSES SECTION
LIGHT GAUGE STEEL CONSTRUCTION AND CONNECTIONS – VERIFY THE FOLLOWING ARE IN COMPLIANCE
IBC 1705.2.2, 1705.11.2, 1705.11.3, UFC 4 023 03
TASK INSPECTION TYPE1 DESCRIPTION
1. Trusses spanning 60-feet or greater where/if applies
PERFORM Verify that temporary and permanent truss restraint/bracing is installed in accordance with approved truss submittal package.
2. Welded connections (seismic and/or wind resisting system)
OBSERVE Visually inspect all welds composing part of the main wind or seismic force resisting system, including shearwalls, braces, collectors (drag struts), and hold-downs.
[NOTE: DOR must identify critical wind and/or seismic force resisting welds in the contract drawings so that the special inspector can confirm compliance.]
3. Connections (seismic and/or wind resisting system)
OBSERVE Visually inspect all screw attachment, bolting, anchoring and other fastening of components within the main wind or seismic force resisting system, including roof deck, roof framing, exterior wall covering, wall to roof/floor connections, braces, collectors (drag struts) and hold-downs.
[NOTE: DOR must identify critical wind and/or seismic force resisting connection/fastener components in the contract drawings so that the special inspector can confirm compliance.]
4. Cold-formed steel (progressive collapse resisting system where/if applies)
OBSERVE Verify proper welding operations, screw attachment, bolting, anchoring and other fastening of components within the progressive collapse resisting system, including horizontal tie force elements, vertical tie force elements and bridging elements (UFC 4 023 03).
[NOTE: DOR must identify critical progressive collapse resisting connection/fastener components in the contract drawings so that the special inspector can confirm compliance.]
STRUCTURAL - OPEN-WEB STEEL JOISTS SECTION
OPEN-WEB STEEL JOISTS AND JOIST GIRDERS – VERIFY THE FOLLOWING ARE IN COMPLIANCE
IBC TABLE 1705.2.3
TASK INSPECTION TYPE 1 DESCRIPTION
1. Installation of open-web steel joists and joist girders
OBSERVE End connections – welded or bolted Bridging – horizontal and diagonal
1 PERFORM: Perform these tasks for each weld, fastener or bolted connection, and required verification.
OBSERVE: Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need
SCHEDULE OF SPECIAL INSPECTIONS FOR UFGS 01 45 35 REVISED FOR IBC 2018 ON 03/01/20
STRUCTURAL - CONCRETE CONSTRUCTION SECTION
CONCRETE CONSTRUCTION, INCLUDING COMPOSITE DECK – VERIFY THE FOLLOWING ARE IN COMPLIANCE
IBC TABLE 1705.3 (ACI 318 REFERENCES NOTED IN IBC TABLE)
TASK INSPECTION TYPE 1 DESCRIPTION
1. Inspect reinforcement, including prestressing tendons, and verify placement.
OBSERVE Verify prior to placing concrete that reinforcing is of specified type, grade and size; that it is free of oil, dirt and unacceptable rust; that it is located and spaced properly; that hooks, bends, ties, stirrups and supplemental reinforcement are placed correctly; that lap lengths, stagger and offsets are provided; and that all mechanical connections are…