Outage List for Bidders.pdf
PDF 56 KB Posted
- Attached to
- 656-22-341 Conduct Substation Upgrade Federal contract opportunity
- Solicitation number
- 36C26326B0024-0002
About this file
This document is a transformer outage scheduling guide for a VA facility that establishes allowable outage timing requirements for 16 transformers based on current building usage and operational needs.
All transformer outages must be coordinated with the VA based on building use and requirements at the time of the outage, with the Contractor required to submit a work schedule for VA approval prior to execution. Outages affecting chillers require temperature consideration. Transformers serving Buildings 2, 5, 48, 50, and 51 require temporary power provision by the Contractor if outages exceed 8 hours. Specific timing restrictions apply to each transformer: TX1 and TX1C (which are interdependent) must occur before 8 a.m. or after 5 p.m. with 60-day advanced notice for surgery scheduling; TX2, TX2A, and TX4 have varying restrictions from normal business hours to daytime scheduling; TX5, TX48, TX50, and TX51A must occur outside normal business hours with temporary power required if exceeding 8 hours; TX8 and TX88 require 30-day minimum advanced notice and can be scheduled during business hours; TX9 (HPU) requires disconnection from the S&C switch prior to work; TX10 and TX57 must occur outside normal business hours; TX59 must be completed outside laundry business hours (closed Wednesdays); and TX94 has no scheduling restrictions.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C26326B0024 0002.pdf | ||
| Attachment Questions upgrade substation Final Answers.docx | DOCX document | |
| Site Visit Agenda 656 22 341 Conduct Substation Upgrade.docx | DOCX document | |
| Substation Pre_Bid Signin Sheet.pdf | ||
| 337300 UTILITY TRANSFORMERS 20260212 (1).pdf | ||
| Pictures.zip | ZIP file |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
656-22-341 Transformer Outage Table By Building/Location General comments:
All outages must be coordinated based on building use and requirements at the time of the outage.
The table below is a summary of the allowable outage timing based on current facility needs.
A schedule for the work shall be submitted by the Contractor as approved by VA so that arrangements can be made for all outages.
Many transformers will affect chillers, so temperatures are a consideration.
Buildings 2, 5, 48, 50, and 51 - outages exceeding 8 hours will require temporary power provided by the Contractor.
Transformer Allowable Outage Timing Per Current Building Usage ALTERNATE Provide adequate notice for surgery schedule - 60 day advanced notice with schedule approval.
PRIMARY Provide adequate notice for surgery schedule - 60 day advanced notice with schedule approval.
TX1
Must take place outside normal business hours including urgent care hours, before 8 a.m. or after 5:00 p.m. 7 days a week. This will also take down Transformer 1C.
TX1C
Must take place outside normal business hours including urgent care hours, before 8 a.m. or after 5:00 p.m. 7 days a week.
TX2
This outage can be during normal business hours. If exceeding 8 hours of outage, provide temporary power for the building.
TX2A This outage can be completed during normal business hours.
TX4 Must take place outside normal business hours.
TX5
This outage must be outside normal business hours. If exceeding 8 hours of outage, provide temporary power for the building.
TX8
Advanced notice (30 days minimum) required for shutdown that can be during normal business hours. Some flexibility needed to schedule a day without other uses.
TX9 (HPU)
Must take place outside normal business hours. Disconnection from S&C switch required prior to working on this transformer in order to return power to B111.
TX10
Must take place outside normal business hours
TX48
This outage must be outside normal business hours. If exceeding 8 hours of outage, provide temporary power for the building.
TX50 (deduct alternate) This outage must be outside normal business hours. If exceeding 8 hours of outage, provide temporary power for the building.
TX51A
This outage must be outside normal business hours. If exceeding 8 hours of outage, provide temporary power for the building.
TX57 Must take place outside normal business hours TX59 Laundry is closed on Wednesdays. This outage must be completed outside business hours for Laundry TX88 30 days advanced notice minimum and can work during business hours.
TX94 Can be scheduled without restrictions.
Answers to Bidders