About this file
This document presents preliminary Other Transaction (OT) terms and conditions for the USSPACECOM Headquarters Progressive Design-Build acquisition under 10 U.S.C. § 2808a. The document is a draft for industry awareness only and does not constitute an offer, agreement, or authorization to begin work. Final terms will be negotiated post-selection with the Design-Builder Contractor (DBC). The Government requests industry feedback on material concerns via John Cone at One Nation Innovation (john.cone@onenationinnovation.org), though responses are not guaranteed.
The acquisition structure includes multiple milestones implemented in phases. Phase 1 comprises a Validation Period and Design Development Period during which the Design-Builder validates Owner-provided information, establishes project feasibility, phasing, and schedules, and develops a Validation Period Report. The parties may then enter an Agreement Amendment to proceed with Design Development and subsequently negotiate a Guaranteed Maximum Price (GMP) Amendment for Phase 2. Early Work may occur during Phase 1 under an Early GMP Amendment. Phase 2 involves design completion, construction documents development, construction, startup, testing, commissioning, and closeout. The Design-Builder must provide submissions on an open-book, transparent basis with all underlying assumptions and pricing details disclosed. Material Differences discovered during Phase 1 must be reported; Design-Builder cannot claim Change Orders for Material Differences discovered after Phase 1 conclusion that could have been discovered with reasonable diligence during Phase 1. Key responsibilities include obtaining permits (unless identified on Owner's Permit List), performing construction services with requisite expertise, maintaining quality standards, exercising exclusive control over construction means and methods, assembling equipment per manufacturer instructions, properly storing materials, correcting nonconforming work within seven days or providing a correction schedule, maintaining the work area free of debris, and providing comprehensive facility data with Unlimited Rights granted to the Government. Design-Builder must comply with Davis-Bacon Act wage requirements, 29 CFR Parts 1926 and 1910 safety standards, U.S. Army Corps of Engineers Safety and Health Requirements Manual EM 385-1-1, and provide project insurance including Commercial General Liability, Builder's Risk, and other coverage negotiated per milestone. Design-Builder provides warranty that construction meets Agreement Documents requirements, is fit for stated purposes, and defects are corrected within one year of Substantial Completion. Design-Builder indemnifies and defends One Nation Innovation against claims arising from Design-Builder operations, including violations of law, injury or death, liens, intellectual property infringement, and Government non-compliance, with the duty to defend arising immediately upon notification regardless of indemnification applicability.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USSPACECOM Headquarters Progressive Design-Build
PRELIMINARY OTHER TRANSACTION TERMS AND CONDITIONS
DRAFT FOR INDUSTRY AWARENESS — SUBJECT TO POST-SELECTION NEGOTIATION
Purpose and Status These Preliminary Other Transaction Terms and Conditions communicate the Government’s anticipated agreement framework for the USSPACECOM Headquarters Progressive Design-Build acquisition under 10 U.S.C. § 2808a.
These provisions are provided for industry awareness and planning only. They do not constitute an offer, an executed agreement, authorization to begin work, or an obligation of Government funds. Final terms will be developed and negotiated with the selected Design-Builder (DBC), subject to applicable legal authorities, approvals, and available funding.
While industry is not being asked to review, redline, or negotiate a final agreement during the selection process, potential offerors are encouraged to identify any material concerns that could affect their willingness to participate in this challenge. Concerns can be sent to Mr. John Cone with One Nation Innovation (ONI) at john.cone@onenationinnovation.org for review with the Government. The Government is not obligated to provide responses but will consider them and incorporate them into the award process as necessary to ensure maximum participation in this challenge.
These preliminary terms are not incorporated into any agreement unless expressly adopted in an executed OT.
Material changes to acquisition expectations that could affect participation or selection will be communicated to industry through the Government’s applicable challenge procedures.
IMPORTANT NOTE: This does not represent an all-inclusive list of terms and conditions. This list represents the terms and conditions which the Government has identified as high interest for this acquisition for which the Government requests industry feedback. A comprehensive set of terms and conditions will be provided and negotiated after the downselect.
1) Agreement Milestones and Phases
Milestones
The Project scope will have one or more Milestones. Each Milestone will identify a specific scope and budget within the overall Project for which the Design-Builder authorized to proceed. In the Initial Milestone, Design Builder shall collaboratively determine with the Owner the phasing of the Project, including but not limited to whether there is one or multiple Milestones as part of the overall Project. If the Parties determine that there are multiple Milestones, the Initial Milestone scope will be discussed between the Parties but is anticipated to include but not be limited to the following:
1) Validation of the feasibility of the entire Project;
2) Establishment of the phasing, general scope, and schedule for the entire Project and the estimated general scope and schedule for each Milestone;
mailto:john.cone@onenationinnovation.org Robynne Thaxton Consider starting the document with this section, as it sets up the expectations for the PDB aspects of the project. Starting with construction is a little confusing for a PDB project.
3) Establishment of the Division of Responsibility between the Design-Build Scope and the C4IT Scope; and
4) Other tasks as set forth in the Initial Milestone.
Subsequent Milestones will be implemented in multiple phases as described below.
Phase 1.
Phase 1 shall commence upon Notice to Proceed from the Owner and shall end on the Phase 1 Completion Date as set forth in the Target Schedule, collaboratively established pursuant to the Agreement Documents.
Phase 1 shall consist of two periods: the Validation Period, and the Design Development Period. During the Validation Period and within the time period established in the Project Schedule, the Design-Builder shall perform such assessments, reviews, and investigations of the Owner Provided Information, as set forth in the Agreement and determined by Design Builder to be reasonably necessary to validate the Owner Provided Information, the Commercial Terms, and the Owner’s Project Criteria. At the conclusion of the initial Validation Period, the parties shall establish the feasibility of the Project, the phasing, general scope, and schedule for the Project, the Initial Project Scope, Target Budget, and Target Schedule, as well as other Submittals as described in the Agreement. Each Validation Period will conclude with a Validation Period Report that proposes terms for the Design Development Period. Provided the parties agree to the terms, the Parties shall enter into a Agreement Amendment to proceed with the Design Development Period to develop the final Agreement terms, including the Agreement Price, the Basis of Design Documents, and the Project Schedule. At the time set forth in the schedule, the Design-Builder will provide a Proposal to enter into Phase 2 for negotiation of a Guaranteed Maximum Price Amendment (“GMP Amendment”) with the Owner for the applicable Milestone.
The Design-Builder may not rely on information provided by the Owner and must validate all information provided by the Owner during Phase 1 as set forth in the Agreement Documents.
The Design-Builder shall provide the Submissions set forth in the Agreement Documents on an Open Book and transparent basis. Open Book basis means providing the Owner all underlying assumptions, price quotes and data associated with pricing or compensation (whether of the Design-Builder or the Owner) or adjustments thereto, including assumptions as to costs of the Work, schedule, composition of equipment spreads, equipment rates, labor rates, productivity, estimating factors, design and productivity allowance, contingency and indirect costs, risk pricing, discount rates, interest rates, and other items reasonably required by the Owner to satisfy itself as to the reasonableness of the amount. In addition, the Design-Builder and the Owner shall, consistent with any applicable provision of the Agreement Documents, agree upon the quantity and level of development for Submissions that the Owner may wish to review, which Submissions may include Milestone Submissions, design criteria, drawings, diagrams, and specifications setting forth the Project requirements.
Submissions shall be consistent with the Commercial Terms, as they may develop through the design process set forth in the Agreement Documents.
The Parties may also agree to construction work during Phase 1 (Early Work). Early Work will be established pursuant to an Early GMP Amendment that establishes the scope, schedule, price, and other commercial terms applicable to the Early Work.
If the Design-Builder discovers or should have discovered with reasonable diligence Material Differences from the actual conditions at the Site or the Owner Provided Information, Design-Builder shall, upon discovery but no later than at the conclusion of Phase 1, provide Owner with written notice of any such Material Differences. A “Material Difference” is defined as one that would either impact the Owner’s Project Criteria, the Initial Project Scope, or a Commercial Term or be considered a Differing Site Condition. Design- Builder shall not be entitled to a Change Order for any Material Difference during Phase 2, including but not limited to for Differing Site Conditions, pursuant to the Differing Site Conditions clause of the General
Robynne Thaxton Added a brief description of the periods in Phase 1, which will be important to the Offerors. All of the meetings I attended noted that the project needs to have a Validation Period.
Robynne Thaxton Given some of the Offerors I saw, it is important to be specific as to what we mean by being transparent.
Given the schedule requirements (a Presidential ground breaking), I want to let them know that Early Work is a possibility.
Conditions, if the Material Difference could have been discovered, with reasonable diligence, during Phase 1 and was not disclosed pursuant to this Section.
Phase 2.
Provided the Parties agree to the GMP Amendment that authorizes the Design-Builder to proceed with Phase 2, Phase 2 consists of the final phase of each Milestone where the Design-Builder: completes the design services and develops Construction Documents for the applicable Milestone, performs the construction, start-up, testing and commissioning and closeout of the applicable Milestone, undertakes any necessary warranty services for the applicable Milestone, and performs other services as set forth in the Agreement Documents, the GMP Amendment and any Early GMP Amendment.
2) Government Approvals and Permits.
Unless the parties have identified permits in an Owner’s Permit List attached either as an exhibit to the Agreement or as part of the Owner’s Project Criteria or Basis of Design Documents, Design-Builder shall obtain and pay for all necessary permits, approvals, licenses, government charges and inspection fees required for the prosecution of the Work by any government or quasi-government entity having jurisdiction over the Project.
Design-Builder shall provide reasonable assistance to Owner in obtaining those permits, approvals and licenses that are Owner’s responsibility.
3) Design-Builder’s Construction Phase Services.
Unless otherwise provided in the Agreement Documents to be the responsibility of Owner or a separate Agreementor, Design-Builder shall provide through itself or Subcontracts the necessary supervision, labor, inspection, testing, start-up, material, equipment, machinery, temporary utilities and other temporary facilities to permit Design-Builder to complete construction of the Project consistent with the Agreement Documents.
Design-Builder shall perform all construction activities efficiently and with the requisite expertise, skill and competence to satisfy the requirements of the Agreement Documents. Design-Builder shall at all times exercise complete and exclusive control over the means, methods, sequences and techniques of construction.
Prime Performer represents and warrants that all Services shall be performed by qualified personnel in a good and workmanlike fashion, in accordance with the Construction Documents, applicable building codes, the Unified Facilities Criteria (UFC) and other design and construction criteria designated in [Relevant Appendix], and good construction practice, and that all materials and equipment incorporated into the Project shall be new (unless otherwise specified), of good quality, and free from defects.
The Design-Builder shall assemble and install all equipment according to the applicable manufacturer’s installation instructions. Work that does not conform to the applicable instructions and/or any resulting errors in assembly or installation shall be corrected by the Design-Builder. If the Owner determines that the Design- Builder has incorrectly assembled, installed and/or damaged any such equipment, the Design-Builder shall, at its own expense, furnish a competent manufacturer’s representative to assist, instruct and approve the Design- Builder’s corrected work.
If any materials or equipment are stored by Design-Builder, they shall be stored so as to ensure the preservation of their quality and fitness. Materials and equipment shall be placed on platforms or other hard, clean surfaces, and not on the ground, and shall be placed undercover and heated adequately to prevent condensation, oxidation or freezing. Stored materials and equipment shall be located so as to facilitate observation. The Design-Builder shall be responsible for all damage or loss that occurs as a result of its fault or negligence in connection with the care and protection of all materials and equipment until completion and acceptance of the entire Work by the Owner.
There will likely be multiple Phase 2’s to meet the schedule requirements.
Design-Builder is responsible for verifying that any equipment supplied by the Owner is in working order, consistent with the applicable Performance Requirements, and sufficient for the purposes for which it was intended in the Project. If equipment furnished by Owner is not in working order or is not sufficient for the Project, Design-Builder shall notify Owner immediately, and Owner shall either repair or replace the equipment, at Owner’s sole discretion. Design-Builder is responsible for the proper installation of the equipment furnished by Owner.
Design-Builder shall be responsible for all damages to persons or property that occur as a result of the Design- Builder’s fault or negligence and shall provide appropriate security for the Site and shall take all reasonable precautions and provide protection to prevent damage, injury, vandalism, theft, and loss to the Work, equipment and materials used to perform the Work, real property within the Site, and other property at or on the Site, whether owned by Design-Builder, Owner, or any other third party.
Design-Builder shall maintain, rebuild, repair, restore or replace all Work (including plans and specifications, and materials, equipment, supplies and maintenance equipment which are purchased for permanent installation in, or for use during construction of, the Project, regardless of whether the Owner has title thereto) that is injured or damaged prior to Substantial Completion. Following Substantial Completion, Design-Builder shall continue to have responsibility to maintain, build, repair, restore or replace all Work not 100% completed at Substantial Completion, until Owner accepts maintenance responsibility with respect to such Work. Except as provided below, all remaining elements of the Project shall be considered accepted for maintenance purposes as of the Final Acceptance Date. Maintenance responsibility under this section includes rebuilding, repairing and restoring all other property at the Project Site whether owned by Design-Builder, Owner or any other Person.
With respect to Work on property not owned by Owner, Design-Builder’s obligations under this section shall terminate upon acceptance of such Work by the property owner and the Owner.
During the period after Substantial Completion until Final Acceptance, the Owner may issue a Change Order requiring Design-Builder to continue to have responsibility for maintaining, rebuilding, repairing, restoring and replacing Work accepted by Owner, provided, however, no Change Order is required in connection with direction to proceed with Warranty Work.
The Design-Builder shall at all times keep the work area, including storage areas, free from accumulations of waste materials. Before completing the work, the Design-Builder shall remove from the work and premises any rubbish, tools, scaffolding, equipment, and materials that are not the property of the Owner. Upon completing the work, the Design-Builder shall leave the work area in a clean, neat, and orderly condition satisfactory to the Owner or designated Representative. Upon Substantial Completion of the Work, or a portion of the Work, Design-Builder shall remove all debris, trash, construction wastes, materials, equipment, machinery and tools arising from the Work or applicable portions thereof to permit Owner to occupy the Project or a portion of the Project for its intended use.
4) Inspections.
Design-Builder shall inform Owner of any part of the Work which is about to be covered and offer a full and adequate opportunity to Owner to inspect and test such part of the Work before it is covered. At all times before Final Completion, Design-Builder shall remove or uncover such portions of the finished construction Work as directed by Owner. After examination by the Owner Representative and any other Persons designated by Owner, Design-Builder shall restore the Work to the standard required by the Agreement Documents.
The Design-Builder shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the agreement conforms to agreement requirements. The Design-Builder shall maintain complete inspection records and make them available to the Owner. All work shall be conducted under the general direction of the Owner and is subject to Owner inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the Agreement.
Owner inspections and tests are for the sole benefit of the Owner and do not-
• Relieve the Design-Builder of responsibility for providing adequate quality control measures;
• Relieve the Design-Builder of responsibility for damage to or loss of the material before acceptance;
• Constitute or imply acceptance; or
• Affect the continuing rights of the Owner after acceptance of the completed work.
The presence or absence of an Owner inspector does not relieve the Design-Builder from any Agreement requirement, nor is the inspector authorized to change any term or condition of the specification without the Owner’s written authorization.
The Design-Builder shall promptly furnish, at no increase in Agreement Price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Owner. The Owner may charge to the Design-Builder any additional cost of inspection or test when work is not ready at the time specified by the Design-Builder for inspection or test, or when prior rejection makes reinspection or retest necessary. The Owner shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the agreement.
The Design-Builder shall, without charge, replace or correct work found by the Owner not to conform to agreement requirements, unless in the public interest the Owner consents to accept the work with an appropriate adjustment in Agreement Price. The Design-Builder shall promptly segregate and remove rejected material from the premises.
If the Design-Builder does not promptly replace or correct rejected work, the Owner may-
• By Agreement or otherwise, replace or correct the work and charge the cost to the Design-Builder; or
• Terminate for default the Design-Builder’s right to proceed.
If, before acceptance of the entire work, the Owner decides to examine already completed work by removing it or tearing it out, the Design-Builder, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Design-Builder or its subcontracts, the Design-Builder shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet Agreement requirements, the Owner shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.
Unless otherwise specified in the agreement, the Owner shall accept, as promptly as practicable after completion and inspection, all work required by the agreement or that portion of the work the Owner determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Owner’s rights under any warranty or guarantee.
5) Title.
Design-Builder warrants that it owns, or will own, and has, or will have, good and marketable title to all materials, equipment, tools and supplies provided, or to be provided, by it and its subcontracts that become part of the Project or are purchased for Owner for the operation, maintenance, rebuild, repair or replacement thereof, free and clear of all Liens.
Title to all such materials, equipment, tools and supplies delivered to the Site shall pass to Owner, free and clear of all Liens, upon the sooner of incorporation into the Project, or payment by Owner to Design-Builder of invoiced amounts pertaining thereto.
Notwithstanding any such passage of title, Design-Builder shall retain sole care, custody, and control of, and risk of loss with respect to, such materials, equipment, tools and supplies and shall exercise due care with respect thereto until Final Acceptance or until Design-Builder is removed from the Project.
6) Operations and Storage Areas.
The Design-Builder shall confine all operations (including storage of materials) on Owner premises to areas authorized or approved by the Owner. The Design-Builder shall hold and save the Owner, its officers and agents, free and harmless from liability of any nature occasioned by the Design-Builder’s performance.
Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Design-Builder only with the approval of the Owner and shall be built with labor and materials furnished by the Design- Builder without expense to the Owner. The temporary buildings and utilities shall remain the property of the Design-Builder and shall be removed by the Design-Builder at its expense upon completion of the work.
The Design-Builder shall, under regulations prescribed by the Owner, use only established roadways, or use temporary roadways constructed by the Design-Builder when and as authorized by the Owner. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Design-Builder shall protect them from damage. The Design-Builder shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
7) Design-Builder’s Responsibility for Project Safety.
Design-Builder recognizes the importance of performing the Work in a safe manner so as to prevent damage, injury or loss to all individuals at the Site, whether working or visiting; the Work, including materials and equipment incorporated into the Work or stored on-Site or off-Site; and all other property at the Site or adjacent thereto. Design-Builder assumes responsibility for implementing and monitoring all safety precautions and programs related to the performance of the Work. Design-Builder shall, prior to commencing construction, designate a Safety Representative with the necessary qualifications and experience to supervise the implementation and monitoring of all safety precautions and programs related to the Work. Unless otherwise required by the Agreement Documents, Design-Builder’s Safety Representative shall be an individual stationed at the Site who may have responsibilities on the Project in addition to safety. The Safety Representative shall make routine daily inspections of the Site and shall hold weekly safety meetings with Design-Builder’s personnel, Subcontracts and others as applicable.
The Design-Builder shall provide and maintain work environments and procedures which will-
• Safeguard the public and Owner personnel, property, materials, supplies, and equipment exposed to Design-Builder operations and activities;
• Avoid interruptions of Owner operations and delays in project completion dates; and
• Control costs in the performance of this Agreement.
For these purposes on Agreements for construction or dismantling, demolition, or removal of improvements, the Design-Builder shall-
• Provide appropriate safety barricades, signs, and signal lights;
• Comply with the standards issued by the Secretary of Labor at 29 CFR Part 1926 and 29 CFR Part
1910 ; and
• Ensure that any additional measures the Owner determines to be reasonably necessary for the purposes are taken.
The Design-Builder shall comply with all pertinent provisions of the latest version of U.S. Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1, in effect on the date of the solicitation.
Whenever the Owner becomes aware of any noncompliance with these requirements or any condition which poses a serious or imminent danger to the health or safety of the public or Owner personnel, the Owner shall notify the Design-Builder orally, with written confirmation, and request immediate initiation of corrective action. This notice, when delivered to the Design-Builder or the Design-Builder’s representative at the work site, shall be deemed sufficient notice of the noncompliance and that corrective action is required. After receiving the notice, the Design-Builder shall immediately take corrective action. If the Design-Builder fails or refuses to promptly take corrective action, the Owner may issue an order stopping all or part of the work until satisfactory corrective action has been taken. The Design-Builder shall not be entitled to any equitable adjustment of the Agreement price or extension of the performance schedule on any stop work order issued under this clause.
Design-Builder and Subcontracts shall comply with all Legal Requirements relating to safety, as well as any Owner-specific safety requirements set forth in the Agreement Documents, provided that such Owner-specific requirements do not violate any applicable Legal Requirement. Design-Builder will immediately report in writing any safety-related injury, loss, damage or accident arising from the Work to Owner’s Representative and, to the extent mandated by Legal Requirements, to all government or quasi-government authorities having jurisdiction over safety-related matters involving the Project or the Work.
Design-Builder’s responsibility for safety under this section is not intended in any way to relieve Subcontracts and Sub-Subcontracts of their own contractual and legal obligations and responsibility for complying with all Legal Requirements, including those related to health and safety matters; and taking all necessary measures to implement and monitor all safety precautions and programs to guard against injuries, losses, damages or accidents resulting from their performance of the Work.
The Design-Builder shall insert this section, with appropriate changes in the designation of the parties, in all subcontracts.
8) Design Responsibility.
Design-Builder shall cause all design and engineering services to be performed by architects and engineers licensed in the jurisdiction in which the Site is located (or as otherwise permitted for federal work), in accordance with the professional standard of care and the codes and criteria designated in [Relevant Appendix], and shall be responsible for the professional quality, technical accuracy, and coordination of all designs, drawings, and specifications it furnishes. Design-Builder shall correct any errors or deficiencies in its design without additional compensation. Review or approval of design submittals by One Nation Innovation or the Government shall not relieve Design-Builder of responsibility for its design. To the extent the Government furnishes the design, Design-Builder shall promptly report any error, omission, or inconsistency it discovers and shall not proceed with affected work until directed in writing.
By submitting Design Submissions, Design-Builder represents to the Owner that the Work depicted and otherwise shown, contained, or reflected in Design Submissions may be constructed in compliance with the then current Agreement Price and Agreement Time and are consistent with the Technical and Safety requirements. Further, during the design process, the Design-Builder shall review the designs to incorporate constructability and means and methods, including but not limited to use of equipment, materials procurement, labor availability, and efficient construction techniques.
9) Design-Builder’s Warranty.
Design-Builder warrants to Owner that the construction, including all materials and equipment furnished as part of the construction, shall be new unless otherwise specified in the Agreement Documents, of good quality, in conformance with the Agreement Documents and free of defects in materials and workmanship, the Project shall be fit for use for the purposes, objectives, functions, uses and requirements set out in or reasonably
Consider starting with design prior to construction. I find that putting the provisions in chronological order is better received.
inferred from this Agreement, and the Work shall meet all of the requirements of the Agreement Documents.
Design-Builder’s warranty obligation excludes defects caused by abuse, alterations, or failure to maintain the Work in a commercially reasonable manner. Nothing in this warranty is intended to limit any manufacturer’s warranty which provides Owner with greater warranty rights than set forth in this section or the Agreement Documents. Design-Builder will provide Owner with all manufacturers’ warranties upon Substantial Completion.
With respect to the Project Performance Requirements, Design-Builder shall be responsible for meeting the performance requirements of the Project established in the applicable Agreement Amendment, including but not limited to the requirements that the Project meet the Technical and Safety requirements as well as all applicable Legal Requirements.
10) Correction of Defective Work.
Design-Builder agrees to correct any Work that is found to not be in conformance with the Agreement Documents (“Nonconforming Work”), including that part of the Work subject to the Design-Builders’ Warranty hereof, within a period of one year from the date of Substantial Completion of the Work or any portion of the Work, or within such longer period to the extent required by any specific warranty included in the Agreement Documents.
Nonconforming Work rejected by Owner shall be revised, removed and replaced so as to conform to the requirements of the Agreement Documents, at Design-Builder’s cost and without any adjustment to the Agreement Price or time extension or any other relief; and Design-Builder shall promptly take all action necessary to prevent similar deficiencies from occurring in the future. The fact that Owner may not have discovered the Nonconforming Work shall not constitute an acceptance of such Nonconforming Work.
Design-Builder shall, within seven (7) days of receipt of written notice from Owner of Nonconforming Work, take meaningful steps to commence correction of such Nonconforming Work, including the correction, removal or replacement of the Nonconforming Work and any damage caused to other parts of the Work affected by the Nonconforming Work. If the correction of Nonconforming Work cannot be completed within such seven (7) day period, Design-Builder must provide a schedule for correcting the Nonconforming Work and commence and diligently prosecute such correction in accordance with the approved schedule to completion. If Design-Builder fails to commence the necessary steps within such seven (7) day period, Owner, in addition to any other remedies provided under the Agreement Documents, may provide Design-Builder with written notice that Owner will commence correction of such Nonconforming Work with its own forces. If Owner does perform such corrective Work, Design-Builder shall be responsible for all reasonable costs incurred by Owner in performing such correction. If the Nonconforming Work creates an emergency requiring an immediate response, the seven (7) day period identified herein shall be deemed inapplicable.
Owner may agree to accept any Nonconforming Work without requiring it to be fully corrected. In such event, Owner shall be entitled to reimbursement of a portion of the Agreement Price (which shall also reduce the GMP) in an amount equal to the greater of: the amount deemed appropriate by Owner to provide compensation for future maintenance and/or other costs relating to the Nonconforming Work, or 100% of Design-Builder’s cost savings associated with its failure to perform the Work in accordance with Agreement requirements. Such reimbursement (plus an administrative charge equal to 10% of the costs and expenses) shall be payable to Owner within ten days after Design-Builder’s receipt of an invoice therefor. Alternatively, Owner may deduct the amount of such costs and expenses (plus an administrative charge equal to 10% of the costs and expenses) from any sums owed by Owner to Design-Builder pursuant to this Agreement. Design- Builder acknowledges and agrees that Owner shall have sole discretion regarding acceptance or rejection of Nonconforming Work and the amount payable in connection therewith. Payment, reimbursement or deduction of the amounts owing to Owner under this section shall be a condition precedent to the acceptance of the applicable Nonconforming Work.
Defective Work includes designs
The one-year period referenced above applies only to Design-Builder’s obligation to correct Nonconforming Work and is not intended to constitute a period of limitations for any other rights or remedies Owner may have regarding Design-Builder’s other obligations under the Agreement Documents.
11) Differing Site Conditions.
Concealed or latent physical conditions or subsurface conditions at the Site that materially differ from the conditions indicated in the Owner Provided Information in the Agreement Documents or are of an unusual nature, differing materially from the conditions ordinarily encountered and generally recognized as inherent in the Work, are collectively referred to herein as “Differing Site Conditions.” If Design-Builder encounters a Differing Site Condition, Design-Builder will be entitled to an adjustment in the Agreement Price and/or Agreement Time(s) to the extent Design-Builder’s cost and/or time of performance are adversely impacted by the Differing Site Condition. Notwithstanding the preceding, provided the parties sign the applicable GMP Amendment, Design-Builder shall not be entitled to a Change Order for Differing Site Conditions if the Differing Site Condition was discovered or could have been discovered, with reasonable diligence, during Phase 1.
Upon encountering a Differing Site Condition, Design-Builder then Design-Builder shall immediately notify Owner thereof telephonically or in person, to be followed by written notification within five days. The Owner shall investigate the Differing Site Conditions promptly after receiving the notice. Design-Builder shall, to the extent reasonably possible, provide such notice before the Differing Site Condition has been substantially disturbed or altered. Design-Builder shall immediately stop Work in and secure the area pending further instructions.
If directed by Owner, Design-Builder shall promptly conduct such further investigation. If Design-Builder continues to believe that the material or condition falls within the scope of Differing Site Conditions, Design- Builder shall at that time also advise Owner of any action recommended to be taken regarding the situation.
Owner then will determine whether Design-Builder’s findings and proposed actions are acceptable and either approve, or require modification of, Design-Builder’s proposed actions. If the condition involves discovery of Hazardous Materials that are Owner’s responsibility under the Agreement, Owner shall advise Design-Builder regarding its plans for Hazardous Materials Remediation and shall coordinate with Design-Builder in performance of such activities, in accordance with the Hazardous Materials clause
Owner shall have the right to require Design-Builder to recommence work in the area at any time, even though an investigation or other work may still be ongoing, so long as recommencing work would not violate any Legal Requirements. Design-Builder shall promptly recommence Work in the area upon receipt of notification from Owner to do so. On recommencing Work, Design-Builder shall follow all applicable procedures contained in the Agreement Documents and all other Legal Requirements with respect to such work, consistent with Owner’s determination or preliminary determination regarding the nature of the material or condition.
No request by the Design-Builder for an adjustment pursuant to the above paragraphs shall be allowed unless the Design-Builder has given the written notice required, such time frame may be extended by the Owner.
No request by the Design-Builder for an adjustment pursuant to the above paragraphs shall be allowed if made after Final Payment under this Agreement.
12) Archaeological Resources In the event the Design-Builder or any of its Subcontracts inadvertently discover any archaeological, paleontological, biological, cultural, or other resources at any time during the project, Design-Builder shall immediately notify the Owner telephonically and suspend all excavation activities at the site.
Design-Builder shall follow the procedures set forth in the Differing Site Conditions section with respect to addressing the discovery of and shall be entitled to a Change Order as set forth therein, provided, however, that the Design-Builder shall not be entitled to a Change Order if the archaeological, paleontological, biological, cultural, or other resource was discovered or could have been discovered, with reasonable diligence, during Phase 1.
"Archaeological Resource" shall mean any material remains of human life or activities which are of interest.
This shall include all sites, objects, structures, artifacts, implements, and locations of prehistoric or archaeological interest, whether previously recorded or still unrecognized, including, but not limited to objects pertaining to prehistoric and historic American Indian or aboriginal burials, campsites, dwellings, and their habitation sites, including rock shelters and caves, their artifacts and implements of culture such as projectile points, arrowheads, skeletal remains, grave goods, basketry, pestles, mauls and grinding stones, knives scrapers, rock carvings and paintings, and other implements and artifacts of any material or form.
Any Archaeological Resources that may be discovered during progress of the Work shall, at Owner’s sole discretion, be the property of Owner.
13) Design-Builder’s Insurance Requirements.
Design-Builder is responsible for procuring and maintaining the insurance for the coverage amounts all as set forth in the Agreement Documents, which shall be negotiated for each Milestone. Coverage shall be secured from insurance companies authorized to do business in the state in which the Project is located, and with a minimum rating set forth in the Agreement.
Design-Builder’s insurance shall specifically delete any design-build or similar exclusions that could compromise coverages because of the design-build delivery of the Project.
Upon signing and returning the signed Agreement to the Owner, and in any event, prior to performing any Work under this Agreement, Design-Builder shall provide Owner with certificates evidencing that all insurance obligations required by the Agreement Documents are in full force and in effect and will remain in effect for the duration required by the Agreement Documents; and no insurance coverage will be canceled, renewal refused, or materially changed unless at least thirty (30) days’ prior written notice is given to Owner.
If any of the foregoing insurance coverages are required to remain in force after final payment is reasonably available, an additional certificate evidencing continuation of such coverage shall be submitted with the Final Application for Payment. If any information concerning reduction of coverage is not furnished by the insurer, it shall be furnished by Design-Builder with reasonable promptness according to Design-Builder’s information and belief.
The Design-Builder’s maintenance of insurance, its scope of coverage, and limits as required herein shall not be construed to limit the liability of the Design-Builder to the coverage provided by such insurance or otherwise limit the Owner’s recourse to any remedy available at law or in equity. Design-Builder shall be financially responsible for all pertinent deductibles, self-insured retentions, and/or self-insurance.
If Design-Builder maintains higher insurance limits than the minimums shown above, Owner shall be insured for the full available limits of commercial general and excess or umbrella liability maintained by Design- Builder, irrespective of whether such limits maintained by Design-Builder are greater than those required by this Agreement or whether any certificate of insurance furnished to the Owner evidences limits of liability lower than those maintained by Design-Builder.
Design-Builder’s insurance coverage shall be primary insurance with respect to Owner. Any insurance, self-insurance, or insurance pool coverage maintained by Owner shall be excess of Design-Builder’s insurance and shall not contribute with it.
I took out all references to any additional exhibit
Design-Builder shall cause each and every Subcontractor to provide insurance coverage that complies with all applicable requirements of Design-Builder-provided insurance as set forth herein, except Design-Builder shall have sole responsibility for determining the limits of coverage required to be obtained by subcontracts.
Design-Builder shall ensure that the Owner is an additional insured on each Subcontractor’s Commercial General liability insurance policy using an endorsement as least as broad as ISO CG 20 10 10 01 for ongoing operations and CG 20 37 10 01 for completed operations.
Failure on the part of the Design-Builder to maintain the insurance as required shall constitute a material breach of Agreement, upon which the Owner may, after giving as least five business days’ notice to Design- Builder to correct the breach, immediately terminate the Agreement or, at its discretion, procure or renew such insurance and pay any and all premiums in connection therewith, with any sums so expended to be repaid to the Owner on demand, or at the sole discretion of the Owner, offset against funds due Design-Builder from the Owner.
14) Owner’s Liability Insurance.
Owner shall procure and maintain from insurance companies authorized to do business in the state in which the Project is located such liability insurance to protect Owner from claims which may arise from the performance of Owner’s obligations under the Agreement Documents or Owner’s conduct during the course of the Project.
15) Builder’s Risk Insurance.
Unless otherwise provided in the Agreement Documents, Design-Builder shall procure and maintain from insurance companies authorized to do business in the state in which the Project is located builder’s risk insurance on an “all risk” or equivalent policy form upon the entire Project to the full insurable value of the Project, including professional fees, overtime premiums and all other expenses incurred to replace or repair the insured property. The property insurance obtained by Design-Builder shall be the broadest coverage commercially available and shall include as additional insureds the interests of Owner, Design-Builder, Design Consultants and Subcontracts of any tier. Such insurance shall include but not be limited to the perils of fire and extended coverage, theft, vandalism, malicious mischief, collapse, flood, earthquake, debris removal and other perils or causes of loss as called for in the Agreement Documents. A copy of the builder’s risk policy shall be made available to the Owner. The builder’s risk insurance shall include physical loss or damage to the Work, including temporary buildings, debris removal, and damage to materials and equipment in transit, at the Site or at another location as may be indicated in Design-Builder’s Application for Payment and approved by Owner. Design-Builder is responsible for the payment of any deductibles under the insurance required by this section.
Unless the Agreement Documents provide otherwise, Owner shall procure and maintain boiler and machinery insurance that will include the interests of Owner, Design-Builder, Design Consultants, and Subcontracts of any tier. Owner is responsible for the payment of any deductibles under the insurance required by this Section.
Prior to Design-Builder commencing any Work, Owner shall provide Design-Builder with certificates evidencing that all Owner’s insurance obligations required by the Agreement Documents are in full force and in effect and will remain in effect until Design-Builder has completed all of the Work and has received final payment from Owner; and no insurance coverage will be canceled, renewal refused, or materially changed unless at least thirty (30) days’ prior written notice is given to Design-Builder. Owner’s property insurance shall not lapse or be canceled if Owner occupies a portion of the Work pursuant to Substantial Completion clauses hereof. Owner shall provide Design-Builder with the necessary endorsements from the insurance company prior to occupying a portion of the Work.
Any loss covered under the builder’s risk insurance shall be adjusted with Owner and Design-Builder and made payable to both of them as trustees for the insureds as their interests may appear, subject to any applicable mortgage clause. All insurance proceeds received as a result of any loss will be placed in a separate account and distributed in accordance with such agreement as the interested parties may reach. Any disagreement concerning the distribution of any proceeds will be resolved in accordance with Agreement Adjustments and Disputes hereof.
Owner and Design-Builder waive against each other and Owner’s separate contractors, Design Consultants, Subcontracts, agents and employees of each and all of them, all damages covered by property insurance provided herein, except such rights as they may have to the proceeds of such insurance. Design-Builder and Owner shall, where appropriate, require similar waivers of subrogation from Owner’s separate contractors, Design Consultants and Subcontracts and shall require each of them to include similar waivers in their Agreements. These waivers of subrogation shall not contain any restriction or limitation that will impair the full and complete extent of its applicability to any person or entity unless agreed to in writing prior to the execution of this Agreement.
16) Labor Standards.
Whether or not the Government determines that such laws apply of their own force to the Agreement, the Services shall be performed in compliance with the Davis-Bacon Act (40 U.S.C. §§ 3141-3148), the Copeland “Anti-Kickback” Act (40 U.S.C. § 3145 and 18 U.S.C. § 874), the Agreement Work Hours and Safety Standards Act (40 U.S.C. §§ 3701-3708), and the U.S. Department of Labor regulations at 29 C.F.R. Parts 1, 3, and 5, as if this Agreement were a covered federal construction Agreement, and the Agreement clauses set forth at 29 C.F.R. § 5.5(a) and (b) are incorporated by reference. Without limitation, Design-Builder shall, and shall require its lower-tier performers to: (a) pay all laborers and mechanics employed at the Site not less than the wages and fringe benefits in the Wage Determination; (b) post the Wage Determination and required notices at the Site; (c) submit weekly certified payrolls (Form WH-347 or an equivalent format) to One Nation Innovation or directly to the Government, as directed; (d) pay overtime as required by the Agreement Work Hours and Safety Standards Act; (e) maintain payroll records as required by 29 C.F.R. § 5.5; and (f) cooperate with any Government or Department of Labor review or investigation. One Nation Innovation may withhold, or pass through any Government withholding of, amounts necessary to satisfy unpaid wages or liquidated damages for labor-standards violations. Prime Performer shall insert the substance of this Section 10.5 in all lower-tier agreements for work at the Site.
17) Bonds and Other Performance Security.
If Owner requires Design-Builder to obtain performance and labor and material payment bonds, or other forms of performance security, the amount, form and other conditions of such security shall be as set forth in the Agreement.
All bonds furnished by Design-Builder shall be in a form satisfactory to Owner. The surety shall be a company qualified and registered to conduct business in the state in which the Project is located.
18) Construction Documents and Facility Data.
The Government shall have Unlimited Rights in all drawings, specifications, design calculations, building information models, as-built drawings, operation and maintenance manuals, test and commissioning reports, and other Data delivered under Appendix C that are necessary to construct, operate, maintain, repair, modify, or reconstruct the Facility, and Prime Performer shall obtain from its design professionals and lower-tier performers all rights necessary to grant such rights. Prime Performer may retain and reuse its standard details, typical designs, and pre-existing intellectual property, other than Project-specific Data, provided that such reuse does not disclose Confidential Information of the Government.
19) Role of One Nation Innovation.
One Nation Innovation serves as consortium manager and administrative intermediary. Its responsibilities under this Agreement are limited to: (a) invoicing, including receiving and reviewing Design-Builder invoices and submitting corresponding invoices to the Government; (b) disbursing to the Design-Builder payments received from the Government; (c) Agreement administration, including serving as a point of contact, flowing down Government requirements, and maintaining agreement records; (d) preparing and processing modifications; and (e) facilitating communication among the Government, the Design-Builder, and other parties. One Nation Innovation does not perform the technical work, does not warrant the Design-Builder’s technical performance or deliverables, and is not responsible for the Government’s failures or alleged failures under the Agreement.
20) Indemnification and Duty to Defend One Nation Innovation.
(a) To the fullest extent permitted by law, Design-Builder specifically obligates itself to protect, immediately defend, indemnify and hold One Nation Innovation and its respective officers, directors, employees, agents and representatives (hereinafter referred to as the “Indemnitees”) harmless against claims,…