OTA 2 DBC Challenge Questions and Answers Updated 11_23_2026.pdf
PDF 88 KB Posted
- Attached to
- USSPACECOM Command and Control Facility (C2F): Design-Build Contractor (DBC) for Collaborative Delivery
- Solicitation number
- Not on record
- Issued by
-
Department of Defense
About this file
This file is a Questions and Answers (Q&A) document for the USSPACECOM Command & Control Facility (C2F) Progressive Design-Build (PDB) project, addressing industry inquiries regarding the solicitation requirements and evaluation criteria.
The project will follow the DBIA PDB Best Practices framework with phases including Validation, Design and Preconstruction, and Final Design and Construction, culminating in a negotiated Guaranteed Maximum Price (GMP) arrangement. The contract will be awarded as a fixed-price agreement with a designated consortium manager under Other Transaction Agreement authority. All applicable Unified Facilities Criteria (UFCs) will govern design and construction, with the Government committing to release a redacted Planning Charrette Report (PCR) dated June 25, 2026, to all offerors for equal access. Building Information Modeling (BIM) is required at LOD 400 prior to fabrication and LOD 500 as field-verified, as-constructed documentation. The Buy America Act will apply to materials, though specific applicability will be discussed post-award. The Government is willing to consider alternative labor sourcing options beyond U.S. citizen-only requirements, subject to Site Security Plan approval. Offerors and core team members must possess verified CMMC Level 2 (Self) compliance at Challenge Statement submission. Davis-Bacon Act wage determinations apply. Key Personnel requirements have been increased to allow submission of five individuals. The proposal narrative is limited to 15 pages (excluding attachments and project profiles), with five required reference project profiles limited to two pages each. The bonding requirement is anticipated not to exceed approximately $2.5 billion. Alabama licensure requirements for key personnel have been modified per an accompanying amendment. The Government does not require CAS-compliant accounting systems but mandates open-book cost transparency and auditable reporting throughout performance.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Reference # Industry Questions Government Response
1 Please provide the stages of design where BIM at L400 or L500 is required. BIM L400 - Model elements designated for LOD 400 shall be developed and coordinated by the responsible Model Element Author prior to fabrication, prefabrication, or installation of the associated work. Required delivery dates shall be established in the BIM Execution Plan and coordinated with the project schedule, submittal schedule, procurement activities, and construction sequencing.
BIM L500 - Model elements designated for LOD 500 shall be developed as field-verified, as-constructed representations following installation, testing, and commissioning of the associated work. The responsible Model Element Author shall update the model to reflect actual installed conditions, equipment, locations, dimensions, and applicable asset information. Model elements shall identify the basis and level of accuracy of field verification and shall be delivered as part of the project closeout and owner turnover documentation, coordinated with the record documents, operation and maintenance materials, commissioning records, and facility management requirements.
2 Which specific Unified Facilities Criteria (UFC), Department of Defense directives, and installation-specific engineering standards will govern the design, construction, and physical security of the USSPACECOM C2F?
All applicable UFCs will apply. Offerors should review updated UFCs on the Whole Building Design Guide Website at wbdg.org for applicable criteria and updates. Any specific, additional directives and installation-specific engineering standards will apply and any requests for exceptions will be discussed with the selected design builder post award.
3 Please clarify whether the contracting and award process for the USSPACECOM C2F project will follow a specific framework or Progressive Design-Build Playbook, including validation, preconstruction, negotiation of a Guaranteed Maximum Price (GMP), and authorization to proceed with construction, or whether the Government intends to implement an alternative process under the Other Transaction Authority (OTA). If an alternative process is anticipated, please provide an overview of the proposed contracting structure, award phases, and procedures for transitioning from preconstruction to construction.
Yes, the contract will follow the process outlined in the DBIA PDB Best Practices and Progressive Design-Build Deeper Dive, including Validation, Design and Preconstruction, and Final Design and Construction after negotiation of the project's terms. The Government anticipates awarding a fixed-price arrangement with the designated consortium manager for authorized phases of performance under the Other Transaction Agreement.
The consortium manager, working with the PDB, shall establish a business-to-business (B2B) agreement with pricing arrangements that maximize the incentives for the PDB to achieve agreement milestones. Design and construction activities are anticipated to be performed under a negotiated Guaranteed Maximum Price (GMP), subject to mutually agreed terms, authorized funding, and Government approval to proceed. Detailed pricing and payment provisions will be established during post-selection negotiations.
4 Data Center Experience – Would the Government consider removing the “DOW” and “C4IT” qualifiers from the data center experience requirements under Projects of Similar Scope and Complexity? The Minimum Qualifications Form references Tier 3/4 data centers, which are commonly delivered commercially with comparable technical complexity, redundancy, and reliability requirements. Allowing commercial data center experience would broaden competition without compromising the Government’s technical objectives.
Yes, the Government is removing the “DOW” and “C4IT” qualifiers from the data center experience requirements under Projects of Similar Scope and Complexity. Please refer the updated requirement in the Amended Challenge statement.
5 Site Security Plan and Construction Security Plan - Factor 2(b) of the Challenge Statement requires Offerors to provide “a fully compliant approach to the project's site security plan that complies with all applicable ICD 705 requirements and consistent with the CSP.” Additionally, Attachment 4 – Minimum Qualifications Form requires all on-site Construction Surveillance Technicians (CSTs) to possess active Top Secret (TS) and Sensitive Compartmented Information (SCI) clearances prior to deployment. Please provide the project's Site Security Plan and/or Construction Security Plan (CSP) to allow Offerors to develop a project-specific approach addressing these requirements. Alternatively, please confirm that, in the absence of these documents, the Government is seeking a general narrative describing the Offeror's proposed approach to construction security, personnel clearances, site access controls, and compliance with applicable ICD 705 requirements.
The Government will not provide a sanitized Tier 1 CSP. In the absence of the final SSP (which is a living document developed post award), offerors must submit a general narrative in their proposal detailing their approach to meeting the requirements, including personnel vetting, site access control, and compliance with ICD 705.
6 Please provide the CSP for the DBC to utilize to help develop the Site Security Plan. Please see response to question 5
7 Is there a FCA requirement for the entire DB team, or just the TS/SCI requirement for construction inspectors? TS cleared individuals will be needed as part of the integrated project. The DBC will be required to provide a plan for how they will provide TS cleared individuals. The Challenge Statement does not state that every member of the Design-Build team must hold an individual TS/SCI clearance. All applicable personnel clearance and access requirements will be based on assigned duties and Government security requirements.
BIM, UFCs & Project Framework
Site, Personnel Security
What are the specific personnel security clearance levels (e.g., Secret, Top Secret/SCI, Special Access Program eligibility) required for designated Key Personnel and on-site supervisory staff?
Please see response to question 7.
9 American Materials – The Challenge Statement appears to require exclusively American-made materials. Would the Government clarify whether the intent is to apply the Buy American Act (BAA), including applicable Trade Agreements Act (TAA) provisions and exceptions, rather than impose an absolute domestic-only requirement?
Allowing materials from designated countries under applicable trade agreements would preserve competition, improve material availability, and reduce unnecessary cost and schedule impacts without compromising the Government's objectives. In the absence of BAA under trade agreements, significant uncertainty exists regarding the viability of the project.
The Buy America Act will apply to this Project. The Parties will discuss the extent to which specific materials will be subject to the Buy America Act post award.
10 US Citizen Requirement – The requirement for all construction workers to be U.S. citizens will significantly limit trade partner competition, increase costs, and complicate workforce availability and scheduling. Would the Government consider allowing legally authorized non-U.S. citizen workers during general construction, with U.S.
citizenship requirements taking effect during later stages of fit-out when sensitive systems, equipment, and secure spaces are introduced? This approach would maintain appropriate security controls while reducing unnecessary cost and schedule impacts.
Yes, the government is willing to consider alternative ways to provide labor sources, to include the options described here. We recognize the impact of requiring U.S. Citizens has on labor availability, and are open to options to provide labor, mitigate security risks, and enable the schedule. As always, the SSO must approve recommended solutions that will be codified in the CSP.
11 The solicitation requires the Design Build Contractor to comply with applicable personnel access, security, and citizenship requirements. The current Challenge Statement specifically states that the DBC must use U.S. citizens from U.S. companies for all general construction work, and further requires compliance with the Government approved Site Security Plan (SSP), Construction Security Plan (CSP), ICD 705, and Government furnished security requirements. Please confirm the citizenship and security requirements applicable to design and construction personnel, including the following: 1. Are all design personnel, including architects, engineers, consultants, and subconsultants, required to be U.S. citizens? 2. Are all construction personnel, including subcontractors, trade personnel, vendors, and other individuals requiring project site access, required to be U.S. citizens? 3. Are security clearances or other personnel security screening requirements applicable to design or construction personnel? If so, please identify the required clearance or screening level and when it must be obtained. 4. If requirements vary based on access to secure areas, CUI, classified information, project documents, or Government information systems, please clarify the applicable requirements for each category of personnel.
Please confirm whether any exceptions or waiver processes are available for non-U.S. citizen personnel.
Please see response to Question 10.
12 Please confirm that to qualify as a "U.S. company", an entity must be ultimately owned and controlled by U.S.
citizens. Please explicitly confirm that a company’s U.S. incorporation, U.S. headquarters, or domestic operations alone will not satisfy this requirement if the entity is subject to Foreign Ownership, Control, or Influence (FOCI), or is ultimately owned or controlled by a foreign parent corporation or other foreign entity.
The Government confirms that to qualify offerors must be a "U.S. company" but does not preclude companies subject to FOCI. A U.S. incorporation, a U.S.-based headquarters, or domestic operations may be considered sufficient when the entity is subject to FOCI and the Government has reviewed and formally accepted its Statement of Affiliation and associated Risk Mitigation Plan. The Government may consider alternate means proposed to achieve the intent of this requirement such as a FOCI Mitigation Agreement approved by the Defense Counterintelligence and Security Agency. Offerors subject to FOCI may provide their plan to meet the intent of this requirement as an attachment to the Narrative due December 3, 2026, for review by the Government.
13 Attachment 4, Offeror’s Minimum Qualifications, states: “Offeror and core Team Members possess verified CMMC Level 2 compliance per 32 C.F.R. §170.3 to handle Controlled Unclassified Information (CUI).” Please confirm that the Offeror and all core Team Members must possess verified CMMC Level 2 compliance at the time of Challenge Statement submission, rather than achieving compliance prior to award or commencement of work involving CUI.
The Government confirms that, in accordance with Section 4 of the Challenge Statement and Attachment 4, Minimum Qualification Form, the Offeror and its core team members must possess verified CMMC Level 2 (Self) compliance at the time of the Challenge Statement Submission. This is a minimum corporate eligibility requirement evaluated on a pass/fail basis. An intent or plan to achieve compliance afar submission, whether prior to award or before commencing work involving CUI, does not satisfy the stated requirement.
14 PCR Report – Please provide the Planning Charrette Report (PCR - draft if necessary) and/or Program of Requirements (POR) immediately to allow Offerors to begin familiarizing themselves with the project requirements, technical challenges, and opportunities for schedule acceleration. Given the size, complexity, and accelerated acquisition schedule, immediate access to this information is essential for meaningful, informed discussions during the collaborative meetings. If document control is a concern, the Government could consider requiring NDAs or providing controlled access to Offerors that have demonstrated minimum qualifications such as CMMC and bonding.
It is the Government's intent and commitment that all offerors to the upcoming Command & Control Facility (C2F) Progressive Design Build project have equal access to documentation relevant to the project.
USSPACECOM is therefore releasing the redacted Planning Charrette Report (PCR), dated 25 Jun 2026, that was used for MILCON authorization and appropriation requests. This PCR does not represent Owner’s Project Requirements (OPR), as the OPRs are currently being revised to remove specific design solutions and allow for increased innovation. Any cost estimates in the PCR are not current, and the author of the PCR is not involved in development of the OPR. All offerors are encouraged to develop creative approaches and solutions that they believe best address the Work Focus Areas cited in the Challenge Statement. Evaluation of responses will be based upon the Evaluation Factors listed in the Challenge Statement; any alignment or misalignment of responses to the PCR will have no effect upon evaluation. Please see Attachment 5 for specific instructions to request a copy of the 25 Jun 2026 PCR.
15 Will the Government provide all prospective Offerors access to the HDR Planning Charrette Report (PCR), associated programming documentation, existing design drawings, studies, and other supporting project documentation developed for the USSPACECOM C2F during the solicitation period? It is our understanding that HDR developed or has access to these materials and is also seeking to engage, or may already be engaged, as a team member with an Offeror pursuing this opportunity. Given the relevance of this information to development of the Basis of Design (BOD) and preparation of responsive technical proposals, we respectfully request that the Government make these documents available to all prospective Offerors. Providing equal access to these materials would help establish a level playing field among prospective Offerors, ensuring that all competing teams have the same opportunity to review and incorporate existing project information into their technical approaches. This would establish a consistent technical baseline, minimize potential competitive advantages associated with prior access to project-specific information, and promote fairness, transparency, and meaningful competition throughout the procurement process. Please confirm whether these materials will be made available and, if so, when and through what mechanism they will be distributed to prospective Offerors.
Please see response to Question 14.
16 Will the Government provide all prospective Offerors access to the Owner's Project Requirements (OPR), developed for the USSPACECOM C2F during the solicitation period? It is our understanding that HDR developed or has access to these materials and is also seeking to engage, or may already be engaged, as a team member with an Offeror pursuing this opportunity. Given the relevance of this information to development of the Basis of Design (BOD) and preparation of responsive technical proposals, we respectfully request that the Government make these documents available to all prospective Offerors. Providing equal access to these materials would help establish a level playing field among prospective Offerors, ensuring that all competing teams have the same opportunity to review and incorporate existing project information into their technical approaches. This would establish a consistent technical baseline, minimize potential competitive advantages associated with prior access to project-specific information, and promote fairness, transparency, and meaningful competition throughout the procurement process. Please confirm whether these materials will be made available and, if so, when and through what mechanism they will be distributed to prospective Offerors.
Please see response to Question 14.
17 Page Limit / Relevant Reference Projects - The Challenge Statement requires detailed profiles of five (5) relevant reference projects demonstrating experience with projects of similar scope and complexity. Section 6, Proposal Submission Instructions, subsection (b), limits the narrative to 15 pages, excluding attachments. However, the reference project profiles are not specifically identified as an attachment under Item 10, Checklist for Submission (Page 20). Please confirm that the five (5) required reference project profiles are excluded from the 15-page narrative limit.
The Challenge Statement requires five (5) relevant reference-project profiles demonstrating experience with projects of similar scope and complexity. For clarification, the profiles may be submitted as a separate attachment and are excluded from the 15-page narrative limit in Section 6(b), Proposal Submission Instructions.
Each profile is limited to two (2) pages, for a maximum of ten (10) pages total for all five profiles.
18 Section 6.b limits the Narrative to 15 pages, excluding Attachments. Evaluation Factor 1(b) requests detailed profiles of five relevant reference projects but does not identify those profiles as an attachment. Please confirm whether the Project Profiles under Factor 1(b) may be submitted separately and excluded from the 15-page Narrative limit. This would allow sufficient space to present the requested detail for all five projects.
Please refer to Government's Response to Question 17 .
PCR Release
Administrative
19 Project Profile Page Limit - Section 6.b limits the Narrative to 15 pages, excluding attachments. Section 6.b also requests five detailed project profiles under Factor 1, but does not identify the profiles as an attachment or state whether they count toward the narrative limit. Other supporting materials, including the Identification of Projects Table, resumes, and organizational chart, are submitted as attachments. Will the Government consider allowing the five project profiles to be submitted as a separate attachment and excluded from the 15-page narrative limit, consistent with the treatment of the other supporting materials? This would allow Offerors to provide meaningful project-specific information while preserving the page limit for the evaluation-factor narrative.
Please refer to Government's Response to Question 17.
20 The Challenge Statement states that Attachment 1 has no page limit and may be submitted in an 8.5 × 14-inch format. Please confirm whether the provided Identification of Projects Table may instead be submitted on 11 × 17-inch pages to maintain readability when completing the required project information.
Please refer to the Government's Response to Question 17. The Government confirms that Attachment 1 be submitted in the stated 8.5 × 14-inch format.
21 We respectfully request that the Government increase the proposal narrative page limit from 15 to 25 pages, excluding attachments and project profiles. Given the complexity, technical requirements, and multiple evaluation factors associated with the USSPACECOM C2F project, the additional pages would allow Offerors to provide more comprehensive and informative responses that adequately address their qualifications, technical approach, design and construction methodology, and project controls. Please confirm whether the Government will consider amending the Challenge Statement to allow a 25-page narrative, with project profiles and required attachments excluded from the page limitation.
The 15-page limit for the proposal narrative remains unchanged. As clarified in the Government’s response to Question 17, the required Project Profiles are excluded from—and do not count toward—that limit. Each Project Profile is limited to two pages.
22 We respectfully request that the Government permit the use of a legible font size smaller than 10-point for graphics, tables, figure captions, and reproduced Challenge Statement text within the proposal. Allowing reduced font sizes for these elements would enable Offerors to present detailed technical information efficiently while maintaining readability and maximizing the available page space for substantive narrative responses. Please confirm whether the Government will consider amending the submission requirements to allow font sizes smaller than 10-point for these elements, provided the text remains clearly legible.
Font size will remain at 10-point.
23 Attachment 3 states that the organizational chart shall be one page and may be submitted in an 11-inch by 14-inch format. Please confirm that Offerors may submit the organizational chart on an 11-inch by 17-inch sheet. The chart must also show each Key Personnel member’s estimated time commitment for each Project period:
Validation, Design and Preconstruction, and Final Design and Construction. Please confirm whether Offerors may submit separate, phase-specific organizational charts on multiple sheets when that format better communicates the reporting relationships, team structure, and personnel commitments for each period.
The Government concurs that Offerors may submit the organizational chart on an 11-inch by 17-inch sheet.
Offerors may also submit separate, phase-specific organizational charts on multiple sheets when needed to clearly show reporting relationships, team structure, and each Key Personnel member’s estimated time commitment for the Validation, Design and Preconstruction, and Final Design and Construction periods. Each chart should be clearly labeled for the applicable project period. Offerors may show additional team members above and beyond those identified Key Personnel.
24 RFI Question 5 references the draft Governance Structure (Exhibit A); however, Exhibit A does not appear to be included in the available RFI or Challenge Statement attachments. Could the Government please provide Exhibit A so industry can review the proposed governance structure and offer informed recommendations?
The Government is working to simplify the project's Governance Structure, so that our team can facilitate efficient and streamlined decision making. As we understand the importance of this structure, we have adjusted our original planning in this area and now expect to build this structure with input from the selected DBC after award.
25 Section 7(c) of the Challenge Statement identifies pricing deliverables required during the post-downselection phase but does not specify the required submission formats or identify standardized pricing forms. Will the Government provide supplemental submission instructions and standardized pricing templates or forms to downselected Offerors, or are Offerors expected to develop their own formats for the required pricing deliverables?
Yes, The Gov't will provide additional instructions and all applicable forms to those offerors who are downselected.
Pricing, Bonding, etc.
26 Home Office Overhead – The Pricing Deliverables request a lump-sum Home Office Overhead (HOOH) percentage but do not clearly address other insurance and project-related costs, including but not limited to Builders Risk Insurance, Professional Liability Insurance, and Subcontractor Default Protection (SDP). Please confirm that these customary project costs are allowable and may be separately identified, negotiated, and incorporated during the GMP/FFP development and reconciliation process, given their project-specific nature and variability.
The Government acknowledges that insurance and other project-related costs may vary based on project-specific requirements and the allocation of risk. For the current Challenge Statement submission, Offerors shall provide the Home Office Overhead (HOOH) percentage and all other pricing information requested in the Challenge Statement. Any additional cost-breakout requirements, including the identification of project-specific insurance and risk-related costs, will be provided in subsequent downselect instructions, as applicable. The treatment and allocation of these costs will be addressed during subsequent pricing development and negotiations, as appropriate.
27 Bonding - Please confirm the value of the Design-Build Contractor's (DBC) bonded obligation to the Government is anticipated to be a maximum of approximately $2.5 billion. If a greater value is anticipated, please indicate.
The Government does not anticipate the bonding requirement to be greater than the approximately $2.5 billion identified in the challenge statement.
28 Applicability of the Davis Bacon Act (DBA) - Are offerors on the USSPACECOM C2F Project subject to Davis-Bacon Act (DBA) labor standards?
Yes. A Davis-Bacon Wage Determination exception cannot be requested for this project. 10 U.S.C. § 2808a provides non-FAR flexibility but does not grant statutory relief from federal prevailing wage requirements under 40 U.S.C. § 3141. The project agreement must incorporate applicable Department of Labor wage determinations to maintain statutory compliance and avoid operational delays.
29 Project Controls and Collaboration – Factor 4 references familiarity with Federal Cost Accounting Standards (CAS) and auditable, open-book cost reporting. As a clarification, would the Government consider evaluating each Offeror's proposed approach to cost transparency, accountability, and control across the design and pricing gates? Offerors should be permitted to demonstrate their approach through established estimating practices, competitive procurement, open-book pricing, and certified cost or pricing data, as applicable, without requiring a CAS-compliant accounting system. This would preserve the Government's cost oversight objectives while avoiding unnecessary administrative burden and maximize schedule efficiency.
The Government does not require a CAS-compliant accounting system under the 10 U.S.C. 2808a OTA. This requirement has been removed and is formally reflected in Amendment 2 to the Challenge Statement. The Government requires open-book transparency, full accountability of costs, and auditable cost reporting throughout the entire period of performance. Offerors may demonstrate this capability through established estimating systems, competitive lower-tier trade procurement, transparent cost-buildup methodologies, and verifiable financial records across all design and pricing gates.
30 Confirm whether the proposed overhead and fee percentages will apply throughout the full contract, including afar FFP conversion, and whether the fee will apply to all project costs, including general conditions, insurance, bonds, indirect costs, and other applicable expense consistent with typical contracting practices, rather than only self-perform and subcontractual work as currently described.
For the current Challenge Statement submission, offerors shall provide the overhead and fee percentages as requested. This information is only due with the Deliverables for One-on-One Collaborative Interviews.
31 Alabama Licensure Requirements - The Challenge Statement requires several key personnel, including the Lead Architect, to be licensed in Alabama. Given that state-specific licensure is not typically required for Federal projects, would the Government consider accepting licensure in any U.S. state or, alternatively, allowing personnel to demonstrate eligibility for Alabama licensure through reciprocity?
The Government confirms that the Alabama Licensure requirements for the Lead Architect and Lead Electrical Engineer are being modified through the accompanying amendment to Section 9.c of the Challenge Statement.
Offerors shall refer to the amended Challenge Statement for the revised licensure requirements and applicable timing.
32 Please clarify the requirement that the Lead Architect and Lead Electrical Engineer be professionally licensed in the State of Alabama. Would the Government consider amending this requirement to allow individuals holding active professional licenses in any U.S. state, provided they obtain Alabama licensure through reciprocity or comity prior to performing services requiring state-specific licensure? This approach would expand the pool of qualified professionals while ensuring compliance with applicable Alabama licensing requirements.
See response to Question 31.
33 Please clarify the Government's requirement regarding Professional Engineer (PE) and Registered Architect (RA) licensure within the State of Alabama.
See response to Question 31.
34 Additional Key Personnel - Section 9 allows Offerors to identify up to three additional Key Personnel. Given the project’s scale and the need to integrate design, construction, C4IT, security, accreditation, and commissioning, would the Government consider increasing the limit to five? This would allow Offerors to identify the additional personnel needed to support successful delivery.
The Government agrees to allow offerors to submit 5 Key Personnel in their submission.
Key Personnel, Licensing
C4IT Related
35 During the one-on-one discussion, the Government advised that the C4IT scope may be separated from the overall Progressive Design-Build (PDB) contract. This change raises a significant integration concern between the facility design and construction scope and the C4IT scope. Specifically, successful facility design is dependent upon timely definition and integration of C4IT requirements that may affect room configurations, infrastructure, cabling, structural and mechanical systems, and other building systems. Separating these scopes without clearly defined integration responsibilities and timely C4IT involvement may create challenges to achieving the Project’s stated schedule, performance, and technology objectives. Given the significance of this interface, we recommend that the Government consider adding a dedicated C4IT Integration Challenge to the amended Challenge Statement requiring each Offeror to present its proposed approach for addressing the integration of the PDB and C4IT scopes. This additional challenge would provide the Government an opportunity to evaluate each Offeror’s innovation aptitude and ability to successfully manage the technical, design, construction, schedule, testing, commissioning, accreditation, and systems integration interfaces created by the proposed separation of these scopes.
The Government is continuing to address the necessary coordination and integration between these efforts through subsequent design development, acquisition planning, and execution activities that will ultimately support a cohesive, fully integrated mission-capable facility. The government appreciates the recommendation and recognizes the importance of effective collaboration and integration between the PDB and C4IT efforts. The government welcomes industry responses to this concern through the optional inclusion of Attachment 6.