OT Attachment 2 Schedule of Milestones and Payments - Template.docx
DOCX document 36 KB Posted
- Attached to
- SDA Tranche 1 Tracking Layer
- Solicitation number
- SDA-PS-22-02
- Issued by
-
Space Development Agency
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 2 Schedule of Milestones and Payments HQ0850229XXXX 17 March 2022
Solicitation Number: SDA-PS-22-02
| Mile stone |
| CLIN |
| Task |
| Estimated Date |
| Payment |
| Funding |
| 1 |
| 0001 |
| Kickoff |
| 2 |
| 0001 |
| SRR/SDR |
| 3 |
| 0001 |
| PDR |
| 4 |
| 0001 |
| OCT Interoperability Test Success |
| 5 |
| 0001 |
| CDR |
| 6 |
| 0001 |
| S-Band and Ka-Band |
Compatibility Test Success
| 7 |
| 0001 |
| Networking and Encryption Interoperability Test Success |
| 8 |
| 0001 |
| System TRR |
| 9 |
| 0001 |
| PSR (First Plane) |
| 10 |
| 0001 |
| PSR (Second Plane) |
| 11 |
| 0001 |
| OPAR (First Plane) |
| 12 |
| 0001 |
| OPAR (Second Plane) |
| 13 |
| 0002 |
| Launch 1 – Kickoff EIS |
| 14 |
| 0002 |
| Launch 1 – Finalize ICDs |
| 15 |
| 0002 |
| Launch 1 – Integrated Stack PSR |
| 16 |
| 0002 |
| Launch 1 – Flight Readiness Review |
| 17 |
| 0002 |
| Launch 1 – SVs Deployed |
| 18 |
| 0003 |
| Launch 2 – Kickoff EIS |
| 19 |
| 0003 |
| Launch 2 – Finalize ICDs |
| 20 |
| 0003 |
| Launch 2 – Integrated Stack PSR |
| 21 |
| 0003 |
| Launch 2 – Flight Readiness Review |
| 22 |
| 0003 |
| Launch 2 – SVs Deployed |
| 23 |
| 0004 |
| Ground Element CDR |
| 24 |
| 0004 |
| NOVA Beta Version Delivery |
| 25 |
| 0004 |
| LEORR Complete |
| 26 |
| 0004 |
| OPAR (First Plane) |
| 27 |
| 0005 |
| OPAR (First Plane) & IR Calibration |
| 28 |
| 0005 |
| OPAR (Second Plane) & IR Calibration |
| 29 |
| 0005 |
| O&S Year 1 Q3 |
| 30 |
| 0005 |
| O&S Year 1 Q4 |
| 31 |
| 0005 |
| O&S Year 2 Q1 |
| 32 |
| 0005 |
| O&S Year 2 Q2 |
| 33 |
| 0005 |
| O&S Year 2 Q3 |
| 34 |
| 0005 |
| O&S Year 2 Q4 |
| 35 |
| 0006 |
| O&S Year 3 Q1 (Unexercised) |
| 36 |
| 0006 |
| O&S Year 3 Q2 (Unexercised) |
| 37 |
| 0006 |
| O&S Year 3 Q3 (Unexercised) |
| 38 |
| 0006 |
| O&S Year 3 Q4 (Unexercised) |
| 39 |
| 0007 |
| O&S Year 4 Q1 (Unexercised) |
| 40 |
| 0007 |
| O&S Year 4 Q2 (Unexercised) |
| 41 |
| 0007 |
| O&S Year 4 Q3 (Unexercised) |
| 42 |
| 0007 |
| O&S Year 4 Q4 (Unexercised) |
| 43 |
| 0008 |
| O&S Year 5 Q1 (Unexercised) |
| 44 |
| 0008 |
| O&S Year 5 Q2 (Unexercised) |
| 45 |
| 0008 |
| O&S Year 5 Q3 (Unexercised) |
| 46 |
| 0008 |
| O&S Year 5 Q4 (Unexercised) |
| Totals |
| $0 |
| $0 |
| Exercised |
| $0 |
| Unexercised |
| $0 |
Note 1: This is a notional document and the proposed milestones may vary in accordance with the program solicitation.
Note 2: Operations and Sustainment Milestones for years 3, 4, and 5 are not exercised. The parties agree to the milestone payment amounts in the table above should the effort be necessary.
Note 3: The dates in the table are best estimates. The Performer is still eligible for payment if a milestone is completed after the estimated date. O&S milestone estimated dates will be updated following launch of Plane 1, at which point they will represent the end of the respective milestone period of performance.
Note 4: The Government is not obligated to pay any milestone before the estimated date, regardless of when the milestone completion criteria are met.
Note 5: Consistent with standard Systems Engineering processes, each Milestone is subject to Lien(s), Major Action Items(s), and Minor Action Item(s) as identified in coordination between the Government and Contractor.
· A Lien is defined as a substantial item coming out of the review that does not show sufficient evidence of a path to delivery of the system in compliance with the contract. A lien prevents payment of a milestone until closed or converted into a Major Action Item.
· A Major Action Item is defined as an item that presents a substantial risk to the system if no action is taken prior to the next review. A Major Action Item prevents payment of a milestone until either the action item is closed, a closure plan is agreed to with the Government, or the Government agrees to track the item as a program risk.
· A Minor Action Item is defined as no threat to the system, administrative in nature, or a recommendation for change. Milestones can be paid with outstanding Minor Action Items.
Milestone Exit Criteria are outlined in accordance with the SOW. Each Milestone is subject to liens, major action items, and minor action items as identified in coordination between the Government and Performer:
1 Kickoff
Exit Criteria: Kickoff meeting conducted. All applicable requirements from the SOW are completed and approved by the Government, inclusive of those contained in Section 2.1 but not limited to that section.
2 SRR/SDR
Exit Criteria: SRR/SDR meeting conducted. All applicable requirements from the SOW are completed and approved by the Government, inclusive of those contained in Section 2.1 but not limited to that section.
3 PDR
Exit Criteria: PDR meeting conducted. All applicable requirements from the SOW are completed and approved by the Government, inclusive of those contained in Section 2.1 but not limited to that section.
4 OCT Interoperability Test Success
Exit Criteria: Test executed in accordance with the approved test plan, test procedures, and all applicable requirements in the SOW and the Government has provided written notification of the test completion.
The milestone will be considered complete when any one of the following conditions is met:
· The Government provides written and signed documentation indicating that either:
· The Contractor successfully completed the full test, or
· The Contractor has successfully completed the test with exceptions for which the Contractor is clearly and defensibly not at fault
· The Government fails to provide written and signed documentation indicating unsuccessful completion of the test within 30 days following the written notification of the test completion.
If the Government provides written and signed documentation indicating that the Contractor did not successfully complete the test, then they shall coordinate a retest with the Government as defined in INT_CTR_1. The milestone will not be considered completed until the Contractor successfully completes the retest as identified above.
5 CDR
Exit Criteria: CDR meeting conducted. All applicable requirements from the SOW are completed and approved by the Government, inclusive of those contained in Section 2.1 but not limited to that section.
6 S Band and Ka Band Compatibility Test Success
Exit Criteria: Test was executed in accordance with Government approved test plan, test procedures, and all applicable requirements in the SOW. All success criteria in the test plan have been satisfied.
7 Networking and Encryption Interoperability Test Success
Exit Criteria: Test executed in accordance with the approved test plan, test procedures, and all applicable requirements in the SOW and the Government has provided written notification of the test completion.
The milestone will be considered complete when either:
· The Government provides written and signed documentation indicating that either:
· The Contractor successfully completed the full test, or
· The Contractor has successfully completed the test with exceptions for which the Contractor is clearly and defensibly not at fault, or
· The Government fails to provide written and signed documentation indicating unsuccessful completion of the test within 30 days following the written notification of the test completion.
If the Government provides written and signed documentation indicating that the Contractor did not successfully complete the test, then they shall coordinate a retest with the Government as defined in INT_CTR_1. The milestone will not be considered completed until the Contractor successfully completes the retest as identified above.
8 System TRR
Exit Criteria: TRR meeting conducted. All applicable requirements from the SOW are completed and approved by the Government, inclusive of those contained in Section 2.1 but not limited to that section.
9 PSR (First Plane)
Exit Criteria: PSR meeting for the first plane conducted. All applicable requirements from the SOW are completed and approved by the Government, inclusive of those contained in Section 2.1 but not limited to that section.
10 PSR (Second Plane)
Exit Criteria: PSR meeting for the integrated stack for the second launch conducted. All applicable requirements from the SOW are completed and approved by the Government, inclusive of those contained in Section 2.1 but not limited to that section.
11 OPAR (First Plane)
Exit Criteria: OPAR meeting for the first plane conducted. All applicable requirements from the SOW are completed and approved by the Government, inclusive of those contained in Section 2.1 but not limited to that section.
12 OPAR (Second Plane)
Exit Criteria: OPAR meeting for the second plane conducted. All applicable requirements from the SOW are completed and approved by the Government, inclusive of those contained in Section 2.1 but not limited to that section.
13 Launch 1 – Kickoff Early Integration Studies
Exit Criteria: Kickoff meeting completed with no liens.
14 Launch 1 – Finalize ICDs
Exit Criteria: ICDs between spacecraft vendor and launch vehicle vendor for Launch 1 are finalized, approved by the Government, and released for signature.
15 Launch 1 – Integrated Stack PSR
Exit Criteria: PSR meeting for the integrated stack for the first launch conducted. All applicable requirements from the SOW are completed and approved by the Government, inclusive of those contained in Section 2.1 but not limited to that section.
16 Launch 1 – Flight Readiness Review
Exit Criteria: FRR meeting for the first launch conducted. All applicable requirements from the SOW are completed and approved by the Government, inclusive of those contained in Section 2.1 but not limited to that section.
17 Launch 1 – SVs Deployed
Exit Criteria: The Contractor provides written confirmation of SV launch vehicle separation for all SVs, as received from the Launch Service Provider, to the Government or provides documentation confirming first contact with all SVs by the Contractor, whichever comes first.
18 Launch 2 – Kickoff Early Integration Studies
Exit Criteria: Kickoff meeting completed with no liens.
19 Launch 2 – Finalize ICDs
Exit Criteria: ICDs between spacecraft vendor and launch vehicle vendor for Launch 2 are finalized, approved by the Government, and released for signature.
20 Launch 2 – Integrated Stack PSR
Exit Criteria: PSR meeting for the integrated stack for the second launch conducted. All applicable requirements from the SOW are completed and approved by the Government, inclusive of those contained in Section 2.1 but not limited to that section.
21 Launch 2 – Flight Readiness Review
Exit Criteria: FRR meeting for the second launch conducted. All applicable requirements from the SOW are completed and approved by the Government, inclusive of those contained in Section 2.1 but not limited to that section.
22 Launch 2 – SVs Deployed
Exit Criteria: The Contractor provides written confirmation of SV launch vehicle separation for all SVs, as received from the Launch Service Provider, to the Government or provides documentation confirming first contact with all SVs by the Contractor, whichever comes first.
23 Ground Element CDR
Exit Criteria: Ground Element CDR conducted, either separately or in conjunction with program CDR. All applicable requirements from the SOW are completed and approved by the Government, inclusive of those contained in Section 2.1 but not limited to that section.
24 NOVA Beta Version Delivery
Exit Criteria: Beta version of the NOVA software delivered to and installed at the Government-specified facility. A successful functional test of the software has been executed, with no liens, and the software is approved by the Government.
25 LEORR Complete
Exit Criteria: LEORR meeting for the first plane conducted. All applicable requirements from the SOW are completed and approved by the Government, inclusive of those contained in Section 2.1 but not limited to that section.
26 OPAR (First Plane) Ground Element
Exit Criteria: OPAR meeting for the first plane conducted. All applicable requirements from the SOW are completed and approved by the Government, inclusive of those contained in Section 2.1 but not limited to that section.
27 OPAR (First Plane) & IR Calibration
Exit Criteria: OPAR meeting and IR Calibration for the first plane conducted. All applicable requirements from the SOW are completed and approved by the Government, inclusive of those contained in Section 2.1 but not limited to that section.
28 OPAR (Second Plane) & IR Calibration
Exit Criteria: OPAR meeting and IR Calibration for the second plane conducted. All applicable requirements from the SOW are completed and approved by the Government, inclusive of those contained in Section 2.1 but not limited to that section.
29 O&S Year 1 Q3
Exit Criteria: Provide Operations and Sustainment support planning and execution in accordance with the SOW.
30 O&S Year 1 Q4
Exit Criteria: Provide Operations and Sustainment support planning and execution in accordance with the SOW.
31 O&S Year 2 Q1
Exit Criteria: Provide Operations and Sustainment support planning and execution in accordance with the SOW.
32 O&S Year 2 Q2
Exit Criteria: Provide Operations and Sustainment support planning and execution in accordance with the SOW.
33 O&S Year 2 Q3
Exit Criteria: Provide Operations and Sustainment support planning and execution in accordance with the SOW.
34 O&S Year 2 Q4
Exit Criteria: Provide Operations and Sustainment support planning and execution in accordance with the SOW.
35 O&S Year 3 Q1 (Unexercised)
Exit Criteria: Provide Operations and Sustainment support planning and execution in accordance with the SOW.
36 O&S Year 3 Q2 (Unexercised)
Exit Criteria: Provide Operations and Sustainment support planning and execution in accordance with the SOW.
37 O&S Year 3 Q2 (Unexercised)
Exit Criteria: Provide Operations and Sustainment support planning and execution in accordance with the SOW.
38 O&S Year 3 Q2 (Unexercised)
Exit Criteria: Provide Operations and Sustainment support planning and execution in accordance with the SOW.
39 O&S Year 3 Q2 (Unexercised)
Exit Criteria: Provide Operations and Sustainment support planning and execution in accordance with the SOW.
40 O&S Year 3 Q2 (Unexercised)
Exit Criteria: Provide Operations and Sustainment support planning and execution in accordance with the SOW.
41 O&S Year 3 Q2 (Unexercised)
Exit Criteria: Provide Operations and Sustainment support planning and execution in accordance with the SOW.
42 O&S Year 3 Q2 (Unexercised)
Exit Criteria: Provide Operations and Sustainment support planning and execution in accordance with the SOW.
43 O&S Year 3 Q2 (Unexercised)
Exit Criteria: Provide Operations and Sustainment support planning and execution in accordance with the SOW.
44 O&S Year 3 Q2 (Unexercised)
Exit Criteria: Provide Operations and Sustainment support planning and execution in accordance with the SOW.
45 O&S Year 3 Q2 (Unexercised)
Exit Criteria: Provide Operations and Sustainment support planning and execution in accordance with the SOW.
46 O&S Year 5 Q4 (Unexercised)
Exit Criteria: Provide Operations and Sustainment support planning and execution in accordance with the SOW.
File details come from the government source that posted it. Updated .