About this file

This document is a wasteload allocation transmittal from the Georgia Environmental Protection Division (EPD) to the Spalding County Water Authority regarding a new discharge of treated domestic wastewater into Cabin Creek in the Ocmulgee River Basin. The EPD has provided recommended effluent permit limits for parameters such as flow rate, biochemical oxygen demand, total suspended solids, ammonia, total phosphorus, dissolved oxygen, Escherichia coli, and pH. The Spalding County Water Authority will be required to submit an Antidegradation Analysis, an Environmental Information Document, and a Design Development Report for EPD's review and concurrence before a draft NPDES permit can be issued. The Authority will also need to prepare a Watershed Assessment and Watershed Protection Plan if they have not already done so.

The related state and local contract opportunity is for Progressive Design-Build Services for the 2024 Sewer Implementation project in Spalding County, Georgia. The scope includes Phase 1 Preconstruction Services and Phase 2 Final Design, Construction, and Commissioning Services. The Phase 1 services are professional in nature and involve planning, surveying, assessment, alternatives analysis, permitting, detailed design, constructability reviews, value engineering, and cost estimating to allow the Design-Builder to develop a Proposal and Guaranteed Maximum Price for the Phase 2 services.

View the file

Other files

File Type Posted
Exhibit Q BABA_Special_Conditions.pdf PDF
Cert G Regarding Lobbying.docx DOCX document
Exhibit N EEO Certification.docx DOCX document
Exhibit O Certification Regarding Debarment S.docx DOCX document
Exhibit K Certification Regarding Lobbying.docx DOCX document
Aff B Non Collusion Affidavit.docx DOCX document
Sewer Feasibility Study _ Final Published 080.pdf PDF
Add 01 04042024 Cert F Regarding EEO 1.pdf PDF
Exhibit A Owner_s Project Criteria.docx DOCX document
Exhibit I Subcontractor Affidavit.docx DOCX document
Exhibit B Scope of Services.docx DOCX document
Draft Agreement (PDF) _ Owner Modified DBIA 5.pdf PDF
Updated_WLArequest_Exhibit_Feb2024.pdf PDF
Exhibit D Performance Incentives.docx DOCX document
Aff C Prime E_verify.docx DOCX document
Exhibit M DBE Compliance Form.docx DOCX document
HypotheticalSchedule_03092024.pdf PDF
Exhibit P American_Iron_Steel_Special_Conditi.pdf PDF
Aff A SCWSFA Proposal Certification Form.docx DOCX document
Draft General Conditions (PDF) _ Owner Modifi.pdf PDF
Exhibit F Insurance Requirements.docx DOCX document
Aff D Sub E_verify.docx DOCX document
Cert F Regarding EEO.docx DOCX document
Cert H Cost Proposal Form.docx DOCX document
Addendum 01 _ 04042024 1.pdf PDF
Exhibit G Payment and Performance Bonds.docx DOCX document
Exhibit J Grant Related Requirements.docx DOCX document
RFP 2024_022 issued 03092024.pdf PDF
Exhibit E Forms of Waiver and Release _ Progr.docx DOCX document
Exhibit C Contract Pricing Basis.docx DOCX document
Proposer Question and Response 01 _ 04042024 .pdf PDF
PDB Scope Scenarios.pdf PDF
Cert E Regarding Debarment.docx DOCX document
Exhibit H Contractor Affidavit.docx DOCX document
Exhibit L SRF_Supplemental_General_Conditions.pdf PDF
Updated_WLA000257request_Feb2024.pdf PDF
PROCUREMENT POLICY_12_21_2022.pdf PDF
Show all 37

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Jeffrey W. Cown, Director

Watershed Protection Branch 2 Martin Luther King, Jr. Drive Suite 1470A, East Tower Atlanta, Georgia 30334 404-463-1511

August 18, 2023

Joseph Johnson, P.E., General Manager Spalding County Water Authority 119 East Solomon St Griffin, Georgia 30223

RE: Wasteload Allocation Transmittal

New Discharge to Cabin Creek

EPD # WLA000257

Spalding County, Ocmulgee River Basin

Dear Mr. Johnson:

The Georgia Environmental Protection Division (EPD) has completed the evaluation of the wasteload allocation request for a new discharge of 0.05 and 0.10 MGD of treated domestic wastewater into Cabin Creek in the Ocmulgee River Basin. The following wasteload allocation is valid for one year from the date of this letter unless a written extension is requested and granted. The wasteload is provided for planning purposes only.

Recommended effluent permit limits – Discharge to Cabin Creek:

Constituent/Parameter (1) Limits

Effluent Flow Rate (MGD) 0.05 0.10

Five-Day Biochemical Oxygen Demand (mg/L) 25.0 20.0

Total Suspended Solids (mg/L) 20 20

Ammonia, as N (mg/L) 10.0 5.0

Total Phosphorus, as P (mg/L) 5.0 5.0

Dissolved Oxygen, Minimum (mg/L) 5.0 5.0

Escherichia Coli (#/100 mL) 126 126 pH, Minimum – Maximum (Standard Units) 6.0 – 9.0 6.0 – 9.0

Total Residual Chlorine, Daily Maximum (mg/L) (2) 0.31 0.16

(1) Values are maximum monthly averages except as noted.

(2) If an ultra-violet light or ozone system is used to treat bacteria, the TRC limit will only apply when chlorine is in use at the facility.

Mr. Johnson August 18, 2023

Recommended effluent permit limits (continued):

Constituent/Parameter Limit

Orthophosphate, as P (mg/L) Monitor

Organic Nitrogen, as N (mg/L) Monitor

Nitrate-Nitrite, as N (mg/L) Monitor

Total Kjeldahl Nitrogen, as N (mg/L) Monitor

Priority pollutant limitations and aquatic toxicity testing requirements will be determined at a later date. Please also be aware that EPD will be developing a Nutrient Permitting Strategy in the upcoming months that may result in a total nitrogen limit and/or reduced total phosphorus limit.

Spalding County Water Authority (Authority) will also be required to submit an Antidegradation

Analysis justifying the proposed discharge, an Environmental Information Document to evaluate the direct and indirect environmental impacts of the project, and a Design Development Report to describe any process modifications. EPD must concur with all the documents before a draft NPDES permit for the requested flow rates can be issued. Please submit the reports for review to the Wastewater Regulatory Program.

Communities requesting a new or increased surface water discharge permit are also required to prepare a Watershed Assessment (WA) and Watershed Protection Plan (WPP) for watersheds in their jurisdiction if they have not already done so. Prior to conducting the WA, a Watershed Monitoring Plan (WMP) describing the field study proposal for the WA should be submitted for review and approval. We strongly recommend that a pre-submittal meeting be held with our TMDL Modeling and Development Unit prior to submitting the WMP. Guidance for preparation of the WMP, WA, and WPP can be found at: www.gaepd.org.

If you should have any questions, please contact me at (470) 524-0657 or alex.gramling@dnr.ga.gov.

Sincerely, Alex Gramling Municipal Permitting Unit Wastewater Regulatory Program cc: Rick Jeffares, Turnipseed Engineers (RJeffares@turnipseed.com)

Eric Armstrong, Falcon Design Consultants, LLC (earmstrong@fdc-llc.com) Joseph Johnson, Spalding County Water Authority (Josephjohnson@spaldingcounty.com) Rebecca Lindsey, Lindsay Engineering & Consulting, LLC (rebecca@lindsay-engineering.com) Josh Welte, EPD Water Quality Modeling Unit (josh.welte@dnr.ga.gov)