OldsmarESAddendum17126ss.pdf

PDF 559 KB Posted

Attached to
Chiller Replacement
Solicitation number
26-CD-027
Issued by
Pinellas County, Florida

About this file

This addendum to the Oldsmar Elementary School Chiller Replacement project, issued by the Pinellas County School District on July 1, 2026, provides electrical specifications and revisions for the removal and replacement of chillers CH-1 and CH-2. The addendum, prepared by Edward J. Wolanin, PE Principal Electrical Engineer, specifies that existing chillers must be disconnected and removed with associated conductors returned to the switchboard, while maintaining existing conduits and breakers for reuse. The scope requires terminating existing conduits into a new stainless steel weathertight junction box, providing new conduits from the junction box to the new chiller entry point, and ensuring the junction box placement does not block access panels on the new equipment. The feeder specifications require two runs of three #350 KCM copper conductors and one #1 THWN copper equipment ground in each existing conduit from the switchboard to each chiller, utilizing the junction box as a pull-box. This addendum was issued prior to the sealed electronic bid deadline of July 8, 2026, at 4:00 p.m. via the District's e-Procurement Portal.

The addendum addresses specific electrical design modifications necessary for the chiller replacement installation and serves as a binding revision to the original bid documents. Prospective bidders were required to obtain all bid documents through the OpenGov procurement portal at https://procurement.opengov.com/portal/PCSB to ensure automatic notification of all addenda and subsequent modifications. The District indicated consideration of pricing established through the State of Florida Department of Management Services, Division of Purchasing contracts, and all bidders were required to comply with specified insurance requirements and the District's formal bid protest procedures. No specific contract award date, term duration, or renewal options are detailed in this addendum document.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDUM #1

Date: July 1, 2026 To: Doug Schoel Project: Oldsmar Elementary School – Chiller Replacement MPS Job #: 25102

The following revisions have been made to the scope related to the electrical plans and specs:

SHEET E1.0

DEMO KEYED NOTES

1. CHILLERS CH-1 & CH-2 ARE TO BE REMOVED. DISCONNECT CHILLERS AND REMOVE

ASSOCIATED CONDUCTORS BACK TO THE SWITCHBOARD BUT MAINTAIN EXISTING

CONDUITS AND BREAKERS FOR REUSE WITH NEW CHILLERS.

ELECTRICAL KEYED NOTES

1. EXISTING CONDUIT STUB-UP LOCATION MAINTAINED FROM DEMOLITION OF OLD CHILLER.

TERMINATE EXISTING CONDUITS INTO NEW STAINLESS STEEL WEATHERTIGHT JUNCTION

BOX REWORK AS NECESSARY. PROVIDE NEW CONDUITS FROM JUNCTION BOX TO NEW

CHILLER CONDUIT ENTRY POINT. AVOID BLOCKING ANY ACCESS PANELS ON NEW CHILLER

WITH THE PLACEMENT OF THE NEW JUNCTION BOX. PROVIDE NEW UNSPLICED FEEDER

FROM THE SWITCHBOARD TO THE CHILLER USING THE NEW JUNCTION BOX AS A PULL-BOX.

FEEDER TO EACH CHILLER SHALL BE – TWO RUNS OF (3) #350 KCM CU AND (1) #1 THWN CU

EQUIPMENT GROUND IN EACH IN EXISTING CONDUITS.

If you have any questions regarding the above mentioned, please call for clarification.

Sincerely, Edward J. Wolanin PE Principal Electrical Engineer

2026-07-01T09:37:49-0400
Edward J Wolanin

File details come from the government source that posted it. Updated .