The document is a Fire Protection System Protocol for Capital Planning Projects developed by the Orange County Convention Center (OCCC), detailing comprehensive procedures for Fire Alarm Company technicians performing various technical tasks within the facility. The protocol outlines specific step-by-step procedures for four primary activities: system installation, program downloading, pretesting, and final testing with the Authority Having Jurisdiction (AHJ). Each procedure requires prior approval from the OCCC Project Management Team, mandates at least two technicians be present, involves coordination with OCCC Capital Planning and Security/Life Safety teams, and necessitates detailed documentation through a debrief report that confirms system status before and after work completion.

While the document does not provide specific pricing or funding details, it establishes a rigorous operational framework for Fire Alarm Company technicians working on capital planning projects at the Orange County Convention Center. The protocol emphasizes safety, systematic documentation, and precise communication protocols, requiring technicians to check in with prime contract holders, notify OCCC Capital Planning and Security before work begins, manage system test modes, document all system changes, and ensure the fire protection system remains stable throughout interventions. The document is version 1, dated 8/19/2024, and appears to be a standardized procedure to maintain consistent technical and safety standards during fire protection system modifications and testing.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

V e r s i o n 1 - 8 / 1 9 / 2 0 2 4 P a g e 1 | 3

OCCC Fire Protection System Protocol for Capital Planning Projects

Location: Orange County Convention Center

Procedure for installing:

1. After approval from OCCC Project Management Team, the OCCC designated Fire Alarm

Company technicians arrive onsite.

2. The OCCC designated Fire Alarm Company technician checks in with prime contract holder.

3. The prime contract holder is to notify OCCC Capital Planning prior to the work being performed. Capital Planning staff will inform OCCC Security/Life safety.

4. The OCCC Designated Fire Alarm Company technician arrives at the TSW in command and confirms number of existing alarms, troubles, supervisory, and bypasses on the system and documents in a debrief report.

5. The OCCC Designated Fire Alarm Company technician notifies OCCC Security to put the system in test until X:XX as needed.

6. The OCCC Designated Fire Alarm Company technician disables any points needed and document disabled points.

7. The OCCC Designated Fire Alarm Company technician starts installation of scope.

8. The OCCC Designated Fire Alarm Company technician will reenable any disabled points disabled by

The OCCC Designated Fire Alarm Company.

9. Once the scope of work is complete The OCCC Designated Fire Alarm Company technician will verify the system is left with the same or lesser number of alarms, troubles, supervisory, or bypasses on the system then when started and documents them on a debrief report.

10. The OCCC Designated Fire Alarm Company technician notifies OCCC Security to take the system off test prior to leaving site.

11. A debrief report that includes the system status will be signed and a copy left with the prime contract holder to be submitted to OCCC Capital Planning.

12. The Prime contract holder is responsible for notifying OCCC Capital Planning that the work is complete.

Procedure for downloading a program:

1. After approval from OCCC Project Management Team, the OCCC designated Fire Alarm Company technicians arrive onsite.

2. The OCCC Designated Fire Alarm Company must provide at least two technicians, one technician must remain at the TSW and one or more technician(s) performing the download at the specific node(s).

3. The OCCC Designated Fire Alarm Company technician checks in with prime contract holder.

4. The prime contract holder is to notify OCCC Capital Planning prior to the work being performed.

Capital Planning staff will inform OCCC Security/Life safety.

5. The OCCC Designated Fire Alarm Company technician arrives at the TSW in command and confirms number of existing alarms, troubles, supervisory, and bypasses on the system and documents on a debrief report.

6. The OCCC Designated Fire Alarm Company technician also confirms all panels being downloaded are communicating with the network and no known troubles are found that will hinder the ability to download.

7. The OCCC Designated Fire Alarm Company technician notifies OCCC Security to put the system in test until X;XX as needed.

8. The OCCC Designated Firm Alarm Company technician turns on any bypasses as needed.

V e r s i o n 1 - 8 / 1 9 / 2 0 2 4 P a g e 2 | 3

9. The OCCC Designated Fire Alarm Company technician completes the download at each panel and does not move on to the next until the panel is completely back up on the network.

10. Once the scope of work is complete The OCCC Designated Fire Alarm Company technician will check the system is left with the same or lesser number of alarms, troubles, supervisory, or bypasses on the system then when started and documents them on a debrief report.

11. The OCCC Designated Fire Alarm Company technician will turn off any bypasses.

12. The OCCC Designated Fire Alarm Company technician notifies OCCC Security to take the system off test prior to leaving site.

13. A debrief report that includes the system status will be signed and a copy left with the prime contract

14. The Prime contract holder is responsible for notifying OCCC Capital Planning that the work is complete.

Procedure for the OCCC Designated Fire Alarm Company pretesting:

Company technicians arrive onsite.

2. The OCCC Designated Fire Alarm Company must provide at least two technicians, one technician must remain at the TSW and one or more technician(s) performing the testing of the device(s).

3. The OCCC Designated Fire Alarm Company technician checks in with prime contract holder.

4. The prime contract holder is to notify OCCC Capital Planning prior to the work being performed. Capital

Planning staff will inform OCCC Security/Life safety.

5. The OCCC Designated Fire Alarm Company technicians arrive at the TSW in command and confirm the number of existing alarms, troubles, supervisory, and bypasses on the system and documents on a debrief report.

6. The OCCC Designated Fire Alarm Company technician notifies OCCC Security to put the system in test until X:XX as needed.

7. The OCCC Designated Fire Alarm Company technician turns on any bypasses as needed.

8. The OCCC Designated Fire Alarm Company technician starts required testing.

9. When testing the OCCC Designated Fire Alarm Company technician confirms points triggered are received at the TSW in command center.

10. Once the scope of work is complete the OCCC Designated Fire Alarm Company technician will check the system is left with the same or lesser number of alarms, troubles, supervisory, or bypasses on the system then when started and documents them on a debrief report.

11. The OCCC Designated Fire Alarm Company technician will turn off any bypasses.

12. The OCCC Designated Fire Alarm Company technician notifies OCCC Security to take the system off test prior to leaving site.

13. A debrief report that includes the system status will be signed and a copy left with the prime contract

14. The Prime contract holder is responsible for notifying OCCC Capital Planning that the work is complete.

Procedure for final testing with the AHJ:

Company technicians arrive onsite.

2. The OCCC Designated Fire Alarm Company must provide at least two technicians, one technician must remain at the TSW and one or more technician(s) performing the testing of the device(s).

3. The OCCC Designated Fire Alarm Company technician checks in with prime contract holder.

4. The prime contract holder is to notify OCCC Capital Planning prior to the work being performed. Capital

Planning staff will inform OCCC Security/Life safety.

5. The OCCC Designated Fire Alarm Company technicians arrive at the TSW in command and confirm the number of existing alarms, troubles, supervisory, and bypasses on the system and documents on a debrief report.

6. The OCCC Designated Fire Alarm Company technician notifies OCCC Security to put the system in test until X:XX as needed.

7. The OCCC Designated Fire Alarm Company technician turns on any bypasses as needed.

8. The OCCC Designated Fire Alarm Company technician starts required testing with AHJ.

9. When testing the OCCC Designated Fire Alarm Company technician confirms points triggered are received at the TSW in command center.

10. Once the scope of work is complete the OCCC Designated Fire Alarm Company technician will check

V e r s i o n 1 - 8 / 1 9 / 2 0 2 4 P a g e 3 | 3 the system is left with the same or lesser number of alarms, troubles, supervisory, or bypasses on the system then when started and documents them on a debrief report.

11. The OCCC Designated Fire Alarm Company technician will turn off any bypasses.

12. The OCCC Designated Fire Alarm Company technician notifies OCCC Security to take the system off test prior to leaving site.

13. A debrief report that includes the system status will be signed and a copy left with the prime contract

14. The Prime contract holder is responsible for notifying OCCC Capital Planning that the work is complete.

Location: Orange County Convention Center
Procedure for installing:
Procedure for downloading a program:
Procedure for final testing with the AHJ: