NVPS Athletics (Balance) - Bid Clarification 01.pdf
PDF 269 KB Posted
- Solicitation number
- RFP NVP 260000002718 7
- Issued by
- Michigan
About this file
This is a Bid Clarification document issued by Rockford Construction for the Northview High School Athletic Stadium Addition & Renovation project located in Grand Rapids, Michigan. The clarification, issued on October 14, 2026, addresses questions raised by subcontractors and suppliers during the bidding process and notes that all Bid RFIs must be submitted by October 15, 2026, to allow for incorporation into future addenda. The project involves multiple bid packages addressing various scope items including soccer and lacrosse goals, bleacher installation with concrete slabs, turf drain tile systems, concrete work with curb turf anchors, netting replacement, turf specifications, demo and removal of existing turf and shock pads, track edge sawcutting, and storm drainage installation.
Key scope clarifications specify that BP 6 soccer and lacrosse goals will be furnished and installed by the owner and are excluded from this bid package; BP 13 is responsible for providing concrete slabs under proposed bleachers; BP 32D assumes responsibility for turf drain tile under the turf system specification; and BP 31 is responsible for sawcutting track edges and demo work to prevent damage while preparing areas for new aggregate base and drainage systems. The document includes multiple alternates with pricing lines for BP 3, BP 31, and BP 32C and BP 32D, though specific pricing guidance or contract value information is not provided in this clarification. No set-asides, funding sources, or contract award dates are mentioned in the document.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1 | P a g e
601 First Street NW Grand Rapids, Michigan 49504
(616) 285-6933 www.rockford.com
BID CLARIFICATION NO. 1
TO: All Subcontractors / Suppliers
FROM: Dan Korcek, Senior Project Manager; Morgan Gross, Assistant Project Manager
DATE: October 14, 2026
RE: NVPS Athletics Addition and Renovation
This Bid Clarification No.1 is being sent to all bidders to address questions raised at bid time.
1. Bid RFIs have been generated; no responses have been received from design team as of this clarification. Responses will be provided in future bid clarifications. AS A REMINDER ALL BID
RFIS ARE DUE BY 10/15/2026 TO ALLOW TIME FOR RESPONSE AND INCORPORATION INTO
ADDENDUM.
2. Scope Clarifications
a. BP 6; Soccer and Lacrosse goals previously listed to be included shall not be included in this bid package. Soccer and Lacrosse Goals will be furnished and installed by owner.
b. BP 13 Bleacher Contractor is responsible for providing concrete slabs under proposed bleachers. Reference sheets LD1.09, L5.01, L5.02, LD5.01, LD5.02, LD5.03, LD5.04, LD 5.05.
c. BP 32D shall be responsible for Specification section 33 4615 Turf Drain Tile under their turf system.
d. Revised Alternate 3 for BP 3 Concrete to provide alternate to furnish and install curb turf anchors at 2 Bullpens. Reference LD1.07
e. BP 32C Alternate 1 provide Alternate for Netting replacement at Quad which is not currently specified to be replaced. $__________
f. BP 32D Alternate 4 Provide Alternate to provide 52 oz turf in lieu of 46 oz turf. This will also be issued in the addendum.
g. BP 31 Provide revised Alternate 5 Demo, Removal and Off Site Disposal of Existing Turf and Shock pad. $___________
h. BP 31 ALTERNATE 6 Include Complete removal of Existing Turf base, drain tiles, flat drains at band field. Dispose of offsite A $_____________ B. This material can be used as access roads $________
i. South D Zone Demo. BP 31 shall sawcut edge of track as required to prevent damage to track and allow for Demo all weather surface in D zone, asphalt surface, aggregate, trench train etc. to allow for new Aggregate Base and drainage system to be installed by
BP 32D.
j. North D Zone Demo. BP 31 shall sawcut edge of track as required to demo items as specified in D zone to allow for new storm drainage aggregate base by BP 31.
k. BP 3 Alternate 3 Disregard Alternate 3 as this is provided by BP 13.
End of Clarification https://protect.checkpoint.com/v2/r01/___http:/www.rockford.com___.YzJ1OnJvY2tmb3JkMTpjOm9mZmljZTM2NV9lbWFpbHNfYXR0YWNobWVudDo5M2QwMjI2MWQxMmRhNzdlYmEzMzkzODgzYTMyNTAwMDo3OmE1OGI6NWEyYTg3YTcwZmI4OWM3M2VlNmEzNjAzOGZhZGM4YzE5NDE3ODNlY2Q3Y2YwOWZiNGUzYWY2Y2NiZmQ2YjRmOTpwOlQ6Rg