The document is a project map for the Michigan Ditch Wildfire Mitigation Forest Service Project, prepared by Colorado State Forest Service in collaboration with the US Forest Service. The map specifically details the North Crossing element of the project, which involves installing a 40-foot culvert near the northern boundary of Unit 1, to be installed by the City of Fort Collins. The project requires minimal temporary road construction, approximately 100 feet in length, which will be installed by the contractor. The map includes detailed geographic information such as culvert locations, landing zones, truck turn-around areas, and percent slope indicators across the project area.
The map provides technical planning details for a wildfire mitigation effort in the upper Michigan Ditch watershed in Jackson County, Colorado. While specific pricing and funding sources are not directly outlined in this document, the map suggests a collaborative approach involving multiple agencies including the Colorado State Forest Service, US Forest Service, and City of Fort Collins. The project appears focused on forest management and wildfire risk reduction, with careful consideration of terrain, access routes, and environmental management zones. The graphic includes a scale of 0-250 feet and a comprehensive legend detailing project-specific geographic features and management zones.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
0 125 250
Feet
Legend
Culverts
Landing
Truck Turn Around
Temporary Road
Michigan Ditch Road
Tributaries
Unit 1
Stream Management Zones
US Forest Service
Percent Slope
Michigan Ditch Wildfire Mitigation Forest Service Project North Crossing
The north crossing will occur close to the northern boundary of Unit 1.
The culvert will be installed by the City of Fort Collins and be 40 feet in length.
Expectation is a minimal amount of temporary road will be necessary beyond the culvert; the layer on the map is ~100'.
All temporary roads are to be installed by the contractor.