SOLICITATION NO. NNK16577535R

PROJECT TITLE/LOCATION: Deconstruct Facilities and Structures, HQ (M6-0399) CIF Group

GOVERNMENT PRE AWARD INQUIRY FORM

5/27/2016

1 Pricing Volume Can please provide the bonding requirements since this project is in several different task orders with additional options.

Please see FAR 52.228-15 and 52.228-1. Bonds are based on the total awarded amount.

Performance Bonds (Standard Form 25). The penal amount of performance bonds at the time of contract award shall be 100 percent of the original contract price.

Payment Bonds (Standard Form 25-A). The penal amount of payment bonds at the time of contract award shall be 100 percent of the original contract price.

The amount of the bid guarantee shall be 20% of the bid price or $3M, whichever is less.

2 Section L.9(d)(7). _Pg. 69 of RFP___ Section L.9(d)(7) requests 2 copies of Past Performance Data from Prior Customers in accordance with

Article L.10(b), however L.10(b) only discusses the Past Performance Questionnaire requirements.

Please advise what is to be supplied by the Offeror for the “Past Performance Data from Prior

Customers” section

Offerors will provide the first page of the completed questionnaire in their Technical proposal. The offeror will send the entire questionnaire to their customer contact to complete. The customer is to send the completed questionnaire to the contract specialist stefania.i.wanzie@nasa.gov. See L.10.(b)(e) and

(ii) for further details.

3 Pricing Volume Data required for the pricing volume is not listed out in Section L, Instructions to Offerors, of this RFP.

Please confirm that the only documents required for the separate pricing volume is Section B –

Supplies or Services and Prices/Costs (page 4 of the RFP). Additionally, please advise how many copies of this form must be provided to NASA._

The Pricing volume consist of items described in section L.9 (d), items (1), (2), (3), (8), (9), (10), (11), (12).

4 SF-1442 Since Page 2 of the SF-1442 contains cost data, Should the 1 Original and 2 Copies of this form be provided in the separate Price Proposal?

Yes

5 Section L.10(a) Is relevant experience to be provided for the prime Offeror only, or will relevant experience for team members be considered as well? Will prime and subcontractor experience be evaluated equally?

Please see Amendment 0006 changes to Section M.1 (b)(1)(ii). In addition, relevant experience , in accordance with M.1.(b)(2) second paragraph, will be considered. This includes using PPQs that refer directly to a major subcontractor.

6 General Is the prime 8(a) Offeror required to perform 25% of the fully burdened cost of direct labor using their own forces?

Please see FAR 52.219-14 (c) (4) Construction by special trade contractors. The concern will perform at least 25 percent of the cost of the contract, not including the cost of materials, with its own employees.

7 Technical We assume that a State of Florida Contractors License is not a requirement for this project and have not seen it stated in the solicitation.

No. A Florida Contractors License isn't required.

8 2. Reference: Section L.10 (b)

Can an established CPARS be submitted instead of a PPQ?

No, the PPQ must be provided.

9 Solcitiation Can a team comprised as follows be awarded this project: A JV between two companies with an approved mentor protégé relationship - where the protégé is an approved 8(a) and the mentor is not.

Please refer to RFP L.9 (d) (13) from Amendment 0002; 13 CFR 124.513; and your local SBA office to obtain guidance on the proper JV requirements.

10 Solicitation Does the JV have to be comprised both of an 8(a) and does the JV have to be approved at bid submission?

Both member of the JV do not have to be 8(a), however, an 8(a) JV must follow the guidelines set forth in 13 CFR 124.513. Please see Amendment 0002.

11 SOLICITATION, SECTION L,

PARAGRAPH 5 & 6, PAGE 69

Please verify Appendix 2 is the PPQ form beginning on Page 74 of the Solicitation. We see no reference to “Appendix 2” on that document.

The PPQ document begins on page 74 of the RFP. The RFP heading that should have said "Appendix

2 " seems to have been inadvertently deleted.

12 SOLICITATION, SECTION L,

PARAGRAPH 5 & 6, PAGE 69

Please verify the PPQ document beginning on Page 74 of the Solicitation is the correct document to be used for both “Past Performance” and “Safety Past Performance”.

Yes. The PPQ questions are #6 through # 11.

13 Statement of Work, C-2 (a) CONTRACT

DRAWINGS, MAPS, SPECIFICATIONS,

AND/OR STATEMENTS OF WORK

QUESTION:

Please provide copy of Drawing/Maps 79K39838 and 79K39839; and Kennedy Space Center Diverted

Aggregate Reclamation and Collection Yard (DARCY) site located at the Schwartz Road Landfill.

Please provide any associated Contract Drawings, Maps and Specifications.

Drawings and specifications were provided upon request in accordance with section L.9. A Google view of the DARCY area is attached.

Amend No.No. QUESTION Reference

(Section Paragraph/Page)

GOVERNMENT RESPONSE

GOVERNMENT PRE AWARD INQUIRY FORM

5/27/2016

Amend No.No. QUESTION Reference

(Section Paragraph/Page)

GOVERNMENT RESPONSE

14 Statement of Work, C. 2 CONTRACT

DRAWINGS, MAPS, SPECIFICATIONS,

AND/OR STATEMENTS OF (c) Addenda to Specifications, Drawings, Maps, and/or

Statements of Work.

Please provide copy of Drawing 79K39839 D3 (sheet 9). Please provide any associated Contract

Drawings, Maps and Specifications.

Drawings and specifications were provided upon request in accordance with section L.9.

15 Section L.10 (b) Past Performance Factor, PDF p. 72 of 146.

Section L.10 (b) Past Performance Factor (PDF p. 72 of 146) states that “Past Performance

Questionnaires will not be accepted directly from offerors.” In order to prevent reference fatigue, may we utilize Past Performance Questionnaires which were submitted with previous solicitations. If so, may we include them with our proposal?

No, the PPQ must be provided.

16 Section L.8, Communications Regarding this Solicitation; Appendix 1, Question/Comment Form

Section L.8 states that questions shall be submitted by 12 May 2016; the Question/Comment Form lists the cutoff date and time for receipt of questions as 25 May 2016. Please confirm that questions shall be submitted by 12 May 2016.

Please see Amendment 0004 which corrected the question cutoff at May 12, 2016. 0004

17 Section L.10 (a) Technical Experience &

(b) Past Performance Factor, PDF p. 71-72 of 146.

For Technical Experience and the corresponding Past Performance, please confirm that highly relevant projects performed by the offeror as a subcontractor will be considered.

Yes

18 Section L.5 (a) Proposal Page Limitations, PDF p. 67 of 146; Section L.9 (d), PDF p.

Section L.5 and Section L.9 (d), mention “Past Performance Data from Prior Customers.” Although inclusion of Past Performance Data from Prior Customers is optional, please define what type of data this section might include.

Section L.5 reference to the optional past performance data was removed via amendment 0006. The optional data differs from the requirements in L.9(d)(5) and L.10(b).

19 Section L – Instructions, Conditions, and

Notice to Offerors or Respondents

Please confirm that no electronic (CD) submittal is required. A CD is not required with the submittal.

20 Specification 79K39837_REV_A, Appendix, Asbestos Schedules

Specification 79K39837_REV_A, Appendix, Asbestos Schedules contains a spreadsheet which lists materials, locations, and whether or not the materials are suspected of containing asbestos. Reference is made to specific reports which were used to compile the Asbestos Schedules. In order to ensure that our proposal and estimate is as accurate as possible, we respectfully request that the complete surveys for each building be provided.

Refer to Data Manual Appendix B (Attachment KSC-TA-13017 App B)

21 Solicitation, various sections Given that each offeror was only allowed to have a total of 3 attendees at the site visit held on 06 May

2016, we respectfully request that an additional site visit be scheduled.

No additional site visits will be scheduled.

22 Solicitation, I. 13 NFS 1852.219-11 Special

8(a) Contract Conditions.

This is an 8(a) set-aside procurement. Please clarify whether, in order to be eligible for award, 8(a) offerors must have an SBA Bona Fide office in North Florida.

Although this solicitation is not restricted to an area, please refer to SBA requirements found in 13

CFR 124.507

23 Specification Section 02 41 00 Page 55 Specification Section 02 41 00 Page 55 paragraph 3.1.8 references removing, stacking, palletizing, and covering in shrink wrap acoustical ceiling tiles. Will the contractor be responsible for storing the palletized and wrapped ceiling tiles for the duration of demolition activities, or will they be turned over immediately to the Government for storage?

Ceiling Tiles will not be palletized and recycled. There are Heavy Metals found above the ceiling tile, therefore, tiles can't be recycled. They can be disposed of at the KSC landfill. Dispose of them as

C&D debris. This overrides 79K39837 Section 02 41 00 paragraph 3.1.8 Acoustical Ceiling Tile.

(This does not pertain to Carpet Tile. )

Amendment 0007 will incorporate these changes.

GOVERNMENT PRE AWARD INQUIRY FORM

5/27/2016

Amend No.No. QUESTION Reference

(Section Paragraph/Page)

GOVERNMENT RESPONSE

24 Solicitation Section L.9 (d) (12) Solicitation Section L.9 (d) (12) states that offerors are to include “one (1) properly executed bid bond in accordance with NFS 1852.228-73.” Please confirm that this is the same as 48 CFR 1852.228-73 which states that “each bidder shall submit with its bid a bid bond (Standard Form 24) with good and sufficient surety or sureties acceptable to the Government, or other security as provided in Federal

Acquisition Regulation clause 52.228-1, in the amount of twenty percent (20%) of the bid price, or $3 million, whichever is the lower amount.”

NFS 1852.228-73 has been removed from the NFS. Amendment 0006 removed the reference from the solicitation.

Please refer to FAR 52.228-1 in section L.2 of the solicitation for bonding requirements.

25 Drawing No. 79K39838 Drawing No. 79K39838, Note 2. Sequence of Demolition Activities indicates that due to possible PCB-contaminated soils, the contractor may be required to turn over work areas to the Government for up to six months. Will the Government extend the Contract Completion Date accordingly for any delays caused by the discovery of PCB-contaminated soils?

The contract duration includes a 6 month window where the Contractor will not be able to perform work inside the potential PCB contaminated areas and setback boundary as indicated on Drawing No.

79K39838 Sheet EN 2. Demolition work can be performed in all other areas during this time. The 6 months are embedded in the whole contract performance period, including the time period between completion of CIF building (M6-0342) and turnover of the Headquarters building (M6-0399).

26 Solicitation p. 14, Section F.1 and F.2, RE:

Option 1 – DARCY Operations

F.1 Site Availability Date is listed as, “Concurrent with period of performance of Task 1 and Task 2.”

F.2 – Work Period is listed as 7:00 AM to 3:30 PM, Monday through Friday. However, it was indicated at the site visit that the current contractor only operates the DARCY two days per week. Is it the intent of the RFP for the contractor to fully manage and operate the DARCY for the full Work

Period listed in F.2 with the contractor’s own personnel and equipment for the duration of the project?

If the option is awarded, the contractor will operate the DARCY Monday thru Friday per the hours indicated at clause F.2. This would only be while the demolition operations are on-going. You're to bid per the description of CLINs 0003A and 0003B.

27 J-B-34 RECYCLING AND SALVAGING

MATERIALS (MAR 2014)

What is the recycling goal that has to be met under this contract? KSC has a center-wide recycling goal which this project will support. The Contractor shall recycle and salvage all materials indicated in this contract clause, and throughout the contract drawings and specifications. As a project we're pursuing a 51% recycling or salvaging goal by weight. This goal is not imposed upon the contractor, though the contractor is expected to identify and implement any means within contract scope to support this goal.

28 J-B-37 SCHWARTZ ROAD LANDFILL

OPERATIONS (OCT 2015)

Given the limited time that the KSC landfill/DARCY is operational, how many loads of debris can the landfill/DARCY process in a day?

Truck loads of material go through a weighing in at the single monitoring station. If properly identified

(a placard indicating project, site number and name, and contents is to be displayed on the windshield) it should take no more than 5 minutes for processing. The remainder of the time is transportation time.

You can assume 90% of the loads going into the DARCY, while demolition is on-going, will be from this project's demolition activities. The contractor is expected to manage the logistics of this activity accordingly in order to prevent a funnel effect at the landfill/DARCY.

29 H. 6 SAFETY AND HEALTH (MAY

2014)

Do we have to have a Site Safety Officer? The contractor is to provide a project safety officer to handle the multiple safety requirements on this contract.

30 E. 2 BASIC INSPECTION SYSTEM

(MAR 2016)

Do we have to have a Contractors Quality Control Manager? Yes, although it does not need to be a full time discipline. This function shall be addressed in the submitted contractor's quality control plan (a deliverable). Specifications, Part 1, Summary 4th paragraph states Contractor's Quality Control (CQC) System Manager and the Designer of Record, if applicable, to check and approve all items prior to submittal and stamp, sign, and date indicating action taken.

31 J-B-34 RECYCLING AND SALVAGING

MATERIALS (MAR 2014)

Are there any restrictions on the size of the concrete to be recycled? No.

32 J-B-34 RECYCLING AND SALVAGING

MATERIALS (MAR 2014)

Are there any restrictions on rebar in the concrete to be recycled? No. Rebar removal is a normal activity for a project of this size. An unquantifiable amount of rebar will still be embedded in the clean concrete deposited at the DARCY.

33 H. 6 SAFETY AND HEALTH (MAY

2014)

Do the contractors have to perform a pre-demolition engineering survey? Yes, refer to 79K39837 Specification section 02 41 00 paragraph 1.3.1, 1.7 and 1.11.

GOVERNMENT PRE AWARD INQUIRY FORM

5/27/2016

Amend No.No. QUESTION Reference

(Section Paragraph/Page)

GOVERNMENT RESPONSE

34 H. 6 SAFETY AND HEALTH (MAY

2014)

Is there a requirement for erecting a construction fence around the buildings? A construction fence will be absolutely necessary at the HQ, M6-0399, site, eastern area, due to the immediate vicinity of the new Central Campus, which will be fully operational prior to the demolition activities. The contractor should expect to have personnel walking near that fence at any time of the day. In other areas there may be wide open expanses where no traffic or personnel is expected and in these areas a fence may not be required.

35 J-B-34 RECYCLING AND SALVAGING

MATERIALS (MAR 2014)

What are the dumping procedures at the landfill and DARCY? Do the contractors have to wait till all the debris have been covered?

Dumping procedures require the driver to follow the monitor's directions to the desired dumping area.

There's no expected wait time for covering debris.

36 J-B-37 SCHWARTZ ROAD LANDFILL

OPERATIONS (OCT 2015)

Does the non friable ACM (Cat II) have to be abated prior to demolition? If we can demolish the building using wet methods with non friable Cat II ACM in place, will the KSC landfill accept the debris?

No, only RACM and materials that will become RACM during demolition require abatement. The contract drawings also require selective abatement of non-friable materials. Refer to 79K39838 Sheet

EN1 Asbestos Abatement Note 2 and Sheet EN2 Environmental Notes 1-3, 79K39839 Sheet EN1

Asbestos Abatement Note 2 and Sheet EN2 Environmental Notes 1-3 and 79K39837 Specification 02

82 13.00 98.

37 SECTION L, (1) Past Performance

Questionnaires

Due to the time of the year, most of the contracting personnel are busy. Following up on a question that was previously asked, can we submit final CPARS or PPQ from another project in lieu of new

PPQs?

No, the PPQ must be provided.

38 015720 page 40 3.3.5 Waste Water Do we have to test every truck load? If we have to dispose the residue offsite, why test it? No, though 79K39837 specification section 01 57 20.00 10 paragraph 3.3.5 required one test for asbestos and one test for RCRA 8 metals per truckload. The government has decided to only require one sample at the beginning, one during the middle of the demolition operations and one at the end.

39 Spec Section 028213 Is the contractor responsible for any air monitoring (other than OSHA)? Yes, the contractor is required for all air monitoring per 79K39837 specifications sections 02 82 13.00

98, 02 82 33.13 20 and 02 84 33.

40 028213 page 62 NESHAPS Will a pre-demolition hazardous waste (ACM, ORM, LBP) survey to include wiring, roof testing results and NESHAPS Categories I or II per ACM be available?

Yes, refer to Data Manual Appendix B (Attachment KSC-TA-13017 App B)

41 028213 page 62 NESHAPS Will the floor tiles require removal in order to increase the amount of clean concrete? Yes, refer to 79K39838 Sheet EN2 Environmental Notes 1-2 and 79K39839 Sheet EN2 Environmental

Notes 1-2.

42 Asbestos Schedule notes Is the mastic under the floor tiles asbestos? No, refer to 79K39838 Sheet EN2 Environmental Note 2 and 79K39839 Sheet EN2 Environmental

Note 2 and the 79K39837 Specification Appendix.

43 Asbestos Schedule notes page 290 Number 3 addresses Appendix D. Have these items been tested since the building is vacated? Drawing 79K39839 (CIF) has completed testing as is shown in the Specifications Appendix. Drawing

79K39838 (HQ) is still occupied and therefore testing has not been completed (mainly for the 4th

Floor). For bidding purposes, all suspect items are shown as assumed in the Specification Appendix.

Testing will be completed by the government after award of contract. A determination as to any impact to the scope of the contract will be made at that time.

44 028233 Lead Based Paint Will a Lead Based Paint Pre demolition survey be available for review? No. Refer to 79K39838 Sheet EN1 Environmental Note 7 and 79K39839 Sheet EN1 Environmental

Note 6 and 79K39837 Specification section 02 82 33.13 20 paragraph 1.3.1.

45 028433 PCB Will a PCB Pre demolition survey be available for review? Yes, refer to Data Manual Appendix B (Attachment KSC-TA-13017 App B)

46 028433 PCB page 101 1.7.1 What are the training certificates required for PCB removal? Refer to OSHA 29 CFR 1910.1000 and 79K39837 Specification section 02 84 33 paragraph 1.4.1, 1.4.2, competent person

47 028433 PCB Will the government supply the waste containers for PCB disposal? Yes, the contractor is only responsible for handling, containerizing and labeling of containers. Waste disposal will be submitted by your KSC environmental point of contact and disposal through KSC waste management.

GOVERNMENT PRE AWARD INQUIRY FORM

5/27/2016

Amend No.No. QUESTION Reference

(Section Paragraph/Page)

GOVERNMENT RESPONSE

48 J-B-37 SCHWARTZ ROAD LANDFILL

OPERATIONS (OCT 2015)

Who will be responsible for wastes when the TCLP results are above the allowable limits? Will KSC landfill accept these waste?

The contractor is responsible to transport all waste that can't be salvaged or recycled to the KSC landfill. Refer to 79K39838 Sheet EN1 Environmental Note 7 and 79K39839 Sheet EN1

Environmental Note 6. Contractor is responsible for all wastes.

49 J-B-37 SCHWARTZ ROAD LANDFILL

OPERATIONS (OCT 2015)

Are there any restrictions on the size of the debris that the landfill can handle? No.

50 Spec Section 028213 Does the ACM plan have to be prepared and stamped by a CIH? No, refer to 79K39837 Specification section 02 82 13.00 98, which requires the ACM plan to be signed by a Florida Licensed Asbestos Consultant.

51 Do all the personnel working onsite have to be US citizens? Can foreign nationals work onsite? Personnel must meet NASA badging requirements. Personnel who are US citizens, naturalized US

Citizens and US legal residents with green cards should meet badging requirements. Please contact

321-867-7763 for specific badging questions for any foreign nationals and the escort requirements that it may entail.

52 Is there a burrow pit for fill and top soil materials Contractor is to assume materials will be obtained off site for base bid.

53 Are all the salvageable and recyclable materials property of the contractor? See J-B-34 RECYCLING AND SALVAGING MATERIALS (MAR 2014) . No. Salvageable and recyclable materials are specifically called out in the contract clauses, contract drawings and

Specification 02 41 00. Generally, salvageable materials are turned over to the Government, while recyclable materials are given to the Contractor, with some exceptions as indicated in the contract documents. J-B-34 is being amended to include asphalt materials as salvage to the government. Also amended to include all metal as recycle material to be the property of the contractor. Amendment to follow making these changes.

54 Appendix “Asbestos Schedules (HQ and

CIF)”

This appendix includes a lot of data that needs to be transferred to estimating programs. Can we get these data in excel format? We understand we are responsible for data contained in the original NASA provided format.

No, this data is only available in pdf format. The Contractor is solely responsible for determining all quantities and estimations.

55 Temporary Electrical Service Are specifications available for provision of temporary electrical service? There are no specifications available. The government will not provide temporary electrical service.

Any means of temporary electrical service put in place by the contractor will need to follow OSHA

Standards.

56 Drawing D1 (79K39838) Note 2 under

Sequence of Demolition Activities due to possible PCB Contaminated Soils.

The Note states that the Contractor shall turn over PCB Contamination Areas for up to 6 months, however, at the site walk it was stated that the KSC Headquarters Building (M6-0399) was not going to be released to the Contractor until August 31, 2017, and the required Contract Completion date was stated to be March 30, 2018. This is only a 7 month period and does not leave any time to perform work required at the KSC Headquarters Building. Is the Government going to revise the Contract

Completion Deadline to allow for the required 6 month Government PCB Remediation?

The 6 months are embedded in the whole contract performance period, including the time period between completion of CIF building (M6-0342) and turnover of the Headquarters building (M6-0399).

57 Secftion C.2 Item (b) DARCY Operations It was indicated at the site walk that DARCY and the KSC Class III landfill standard operating hours are Tuesdays and Thursdays only. This does not appear to be sufficient to meet the work requirements in the 16 week CLIN 0003 Option 1 description. Will the Government extend the operating hours at the landfill and DARCY to accommodate a 5 or 6 day per week working schedule?

The 16 weeks is a minimum time for the Option. This is why Sub CLIN 0003B is there. For the baseline, assume the same 2 days of operation as the landfill per clause J-B-37.

58 Attachment J-E Appendix Will the Government provide the asbestos surveys for both the KSC Headquarters Building (M6-0399) and the Central Instrumentation Facility (CIF) M6-0342, Hazardous Waste Shelter M6-0342B, GN2

Storage Area M6-0342C, Generator Enclosure M6-0342D and the Toxic Hazard Lab M6-0392?

Yes, refer to Data Manual Appendix B (Attachment KSC-TA-13017 App B)

GOVERNMENT PRE AWARD INQUIRY FORM

5/27/2016

Amend No.No. QUESTION Reference

(Section Paragraph/Page)

GOVERNMENT RESPONSE

59 Secftion C.2 Item (b) DARCY Operations The Government bid item for CLIN 0003, SUBCLIN 0003A contemplates 16 weeks of DARCY

Operations Services. It appears that these 16 weeks contemplated by the Government appear to be consecutive 16 week period, however, as stated at the site visit there is a long period of time between release of the CIF buildings and the Headquarters Building, not to mention the required up to 6 month period for PCB remediation at the Headquarters Building. Therefore the DARCY Operations Services might have to be broken up into several discreet operations periods, with mobilization and demobilization built in to accommodate Government project timing. Will the Government consider revising the CLIN 0003, SUBCLIN 0003A to accommodate the Governments scheduling requirements?

CLIN 0003A may cover only a portion of the HQ demolition period. CLIN 0003B will be providing any additional time required during the performance of demolition activities including CIF operations.

60 Solicitation - Bid Due Date Will the Government consider extending the due date an additional 2 to 3 weeks to accommodate answering of the questions, bidder review of any additional information provided by the Government in answer to questions, and to allow bidders to coordinate and receive the past performance questionnaires from customers?

See Amendment 0005 0005

61 (b) Statement of Work for CLIN 3 –

OPTION 1 – DARCY OPERATIONS

Statement of Work Item 2 states that the Demolition Contractor’s proposed stockpiling methodology must accommodate the storage of 80,000 tons of material and include adequate room (as determined by NASA) for a future crushing operation and associated processed material lay down area(s) and Item 3 states The Demolition

Contractor will be responsible for processing the incoming materials and loads that are a result of this contract for Deconstruct Facilities and Structures, HQ (M6-0399) & CIF

Group as well as materials and loads that are incoming from other active NASA construction sites herein referred to as NASA construction contractors. Where did the Government derive the quantity of

80,000 tons, what are the processing requirements for incoming materials (i.e. sorting, crushing, rebar removal, screening, stockpiling, etc.), what is the footprint of the NASA future crushing operations, and how many other loads of concrete are expected from other NASA construction contractors?

The estimated tonnage of 80,000 tons is a storage capacity goal. It's not the estimated number of tons to be deposited at the DARCY. The estimate going into the landfill and DARCY combined would be close to 1,000 tons/day if no additional days are available. This is approximately 7 trucks per hour, if the driver has all the required identification of the load and the material has been segregated properly.

Processing means, weighing, verifying load content as acceptable for the DARCY, directing where loads are to be deposited (i.e. to segregate concrete from fines (sub-base material), densifying by accommodation material that may have been improperly scattered, or piling material higher as needed for meeting capacity goal as well as accessibility for accepting additional loads. This doesn't include any crushing or screening. The footprint of a crusher and screening equipment is approximately 1/4 acre including the pile it creates. Accessibility for future deposits of raw material must also be considered. Other NASA construction contractor and tenants will deposit approximately 20 tons a year at the DARCY. The demolition contractor will deposit the majority of material at the DARCY.

62 (b) EVALUATION OF NON-PRICE

FACTORS (1) TECHNICAL

EXPERIENCE (i-vi), p. 84

The experience requirements are a bit stringent for many 8(a) companies to meet. We have two projects valued at $500,000 and $900,000 which fit well with the scope and nature of work and other requirements. Would the government consider reducing the contract dollar value of $1,000,000 and the building size requirement of 50,000 square feet?

No the dollar value will not be reduced. Please see Amendment 0006 changes to Section M.1 (b)(1)(ii) which reduces the number of projects that must fit that parameter.

63 (b) EVALUATION OF NON-PRICE

FACTORS (1) TECHNICAL

EXPERIENCE (i-vi), p. 84

Can prime contractors use the technical experience of non 8(a) subcontractors which meet the requirements for acceptability in this section?

Please see Amendment 0006 changes to Section M.1 (b)(1)(ii). In addition, relevant experience , in accordance with M.1.(b)(2) second paragraph, will be considered. This includes the possibility of using PPQs that refer directly to a major subcontractor.

64 (b) EVALUATION OF NON-PRICE

FACTORS (1) TECHNICAL

EXPERIENCE (i-vi), p. 84

We are an 8(a) company with successful and recent demolition experience; some of this occurred under multiple contracts which add up to the required value. Would the government allow 8(a) companies use a combined value and square footage under these contracts?

Please see Amendment 0006 changes to Section M.1 (b)(1)(ii). In addition, Section (No

Suggestions).(b)(1)(v) states that the demolished square feet of all contract/projects shall collectively total a minimum of 50,000 square feet. Several projects can collectively total 50,000. However, the offeror must submit projects in accordance with changes found in Section M.1 (b)(1)(ii)

65 (b) EVALUATION OF NON-PRICE

FACTORS (1) TECHNICAL

EXPERIENCE (i-vi), p. 84

With the specificity of non-price technical experience evaluation factors, is there an incumbent 8(a) performer in consideration for this opportunity?

No.

66 SF 1442, #13A Will the government consider granting a time extension for the response to allow more time for question and answer review and appropriate response adjustments?

See Amendment 0005 0005

GOVERNMENT PRE AWARD INQUIRY FORM

5/27/2016

Amend No.No. QUESTION Reference

(Section Paragraph/Page)

GOVERNMENT RESPONSE

67 SF 1442, #11; F.1(c) p. 14 The PoP is listed as 750 days from NTP (SF 1442, #11). Also listed on page 14 is a completion date of

March 31, 2018, and finally on page 14, award is expected between July 2016 and March 2017. Is the

PoP 750 days from NTP or March 2018?

The 1442 was amended to remove the POP of 750 days.

68 (b) EVALUATION OF NON-PRICE

FACTORS (1) TECHNICAL

EXPERIENCE (i-vi), p. 84

We have performed non-building site removals on significant and complex multi-million dollar projects. Would projects of this nature be acceptable in meeting the requirement of 50,000 square feet?

No. The 50,000 sq. foot requirement is for buildings.

69 Drawing number 79K39839 & 79K39839

Electrical General Notes on sheet E1 note

10 states “

1) Drawing number 79K39839 & 79K39839 Electrical General Notes on sheet E1 note 10 states

“Before beginning work, all electrical equipment and systems designated as being saved shall be operated in the presence of representatives of the contractor and the contracting officer in order to establish that all systems are in proper working order at the start of demolition. Upon completion of the above test, the contractor shall submit a detailed listing of any items which are not in fully operational condition”

Please confirm that “all” electrical equipment are only those indicated on the drawings. Please provide details of how extensive the “operational test” needs to be; such as visual inspection, VLF, Transformer

Testing or other specialized testing requiring test equipment or PPE or additional sub-contract specialist to perform these test.

All electrical equipment designated as being saved includes equipment identified in any of the contract documents. Operational testing will include demonstrating the devices operate as originally intended by the manufacturer.

70 2) Assuming all electrical items to be removed that contain hazards contaminants such as PCB’s, Asbestos, Lead Paint, lamps, ballast, ect. will be identified by the Government prior to removal. Will the electrical contractor be responsible to remove any of the containments or submit any paperwork or provide testing/services prior to air gapping and turning it over to the Demo Contractor.

Yes. These items are identified in the drawings. Please see the environmental notes as well on both drawings. In addition, gapping, being a physical cut, will be witnessed by a government representative.

Request for Outages may be required. Contractor is to verify no power on any electrical circuits being affected prior to any operation per contract requirements and OSHA.

71 Are fire hydrants around the buildings available for a water source for dust control? The government will not provide utilities or utility hookups directly to the contractor. The Contractor may use water from nearby hydrants without being charged. Amendment 0007 will make this change to clause I.16

72 How much furnishings should we expect to remain inside at turnover to us? Should we give you a unit price per dump truck load to include labor and hauling to landfill?

Expect minimal to no furniture remaining at turnover to contractor. No unit price is required.

73 In base bid, if DARCY option is NOT exercised, then is the DARCY only available to us on Tuesday

& Thursday?

For baseline assume that DARCY would be available only Tuesdays and Thursdays per clause J-B-37.

74 Can we pay to have the landfill operated 5 days a week instead of 2 days per week? If not, can we operate the landfill the other 3 days per week as an option like the DARCY?

Yes, the contractor may opt to pay the landfill operator for additional operating days.

75 Can we work Saturday’s? Yes. The contractor will need to submit an extended work hours request to the Contracting Officer for hours beyond those specified at clause F.2.

76 For badging requirement, can individuals with work permits or green cards be badged for the access to

JFK NASA facility.

Personnel must meet NASA badging requirements. Personnel who are US citizens, naturalized US

Citizens and US legal residents with green cards should meet badging requirements. Please contact

321-867-7763 for specific badging questions for any foreign nationals and the escort requirements that it may entail.

77 Section F For Building M6-0399 the start date is Aug 31st 2017, with a completion date of March 31st 2018.

This duration is not sufficient to abate and deconstruct the building. We request the government to extend the time for completion of this task by 4 months.

The period of performance is being extended to July 31, 2018 per this modification to the solicitation.

78 Drawing # EN2 - BLDG M6-0399 Requirement for sediment and erosion control. What is the approval process / requirement for Erosion and Sediment control on the project site. Do we need to get a county or state permit or the federal government will approve the plan. If we need to go to the state will the government pay the permit fee.

Does the contractor need to engage an expeditor for the permit?

Refer to clause J-B-26 Stormwater Pollution Prevention. The Contractor is solely responsible for obtaining the permit.

GOVERNMENT PRE AWARD INQUIRY FORM

5/27/2016

Amend No.No. QUESTION Reference

(Section Paragraph/Page)

GOVERNMENT RESPONSE

79 Drawing # EN2 - BLDG M6-0399 Possible PCB contamination area- Does the government plan on abating / remediating the PCB area? Yes, the Government is responsible for remediating the possible PCB contamination area and will do

so. Refer to 79K39838 Sheet EN3 General Notes and Specific Note.

80 Please provide all survey documents for ACMs, lead, PCBs, and any other hazardous materials conducted in the past.

Refer to Data Manual Appendix B (Attachment KSC-TA-13017 App B)

81 Drywall was noted to contain less than 1% asbestos. Please provide further documentation for that conclusion. (Aside comment: contractors are still required to protect workers and others with less than

1%, so it ends up being designed similar to abatement)

Refer to Data Manual Appendix B (Attachment KSC-TA-13017 App B)

82 Will further PCB sampling of building materials be required? No. Further sampling is not required. Materials not sampled were assumed to contain PCBs as indicated in 79K39837 Specification section 02 84 33 paragraph 1.2.

83 Are bidders required to utilize the landfills specified? Yes for controlled/hazardous substances. Contractor can submit proof of equivalent landfills for approval by the CO for non hazardous/controlled substances.

84 What is the quantity of asbestos cement water pipe to capped and remain in place vs removed? Refer to 79K39838 Sheet EN1 Asbestos Abatement Note 8 and 79K39839 Sheet EN1 Asbestos

Abatement Note 8.

85 Solicitation Will there be required to have an superintendent, quality control personal, and site safety personal? If so, can any of these be the same person?

A full time superintendent is required per clause J-B-17. Other personnel shall be provided by the contractor to ensure the function and responsibilities are fully and duly executed. It could be one person fulfills multiple roles.

86 Solicitation - Section C It is stated in the Solicitation that a price for the contractor to run the DARCY Monday through Friday for 16 weeks shall be included. Will the equipment used in the DARCY be provided or will the contractor need to provide the equipment? Also, during the site visit it was stated that the DARCY is only accessible Tuesday and Thursday now. If Option 1 is not selected will the DARCY be able to be accessed Monday through Friday?

The contractor shall provide all equipment for operations at the DARCY. Should option 1 not be exercised the base bid consists of access to the DARCY according to those hours described at clause J-

B-37, landfill operations. The DARCY will be available only Tuesdays and Thursdays, under the base bid.

87 Solicitation - Page 45 Missing Attachment J-I - Site Specific Safety & Occupational Health Plan (referenced on pg. 45 of

Solicitation)

The Site Specific Safety & Occupational Health Plan is submitted by the winning bidder after award.

It's then incorporated by the contracting officer through a modification to the contract upon approval by the government. This reference is a place holder.

88 Solicitation - Section E During the pre-bid there was mention of section E.4 which I do not see or can find? The section pointed out in the pre-bid was section F.4. Section E.4 is not a part of this solicitation.

89 Solicitation - Section L pg. 69 and 71 Was the Attachment for Appendix 2 to Section L, the Past Performance Questionnaire, included in the package? We do not find it.

Yes, the PPQ form begins on page 74. The header that was supposed to read Appendix 2 was inadvertently deleted.

90 Pre Bid Meeting Discussion &

Solicitation - Section C.2 (b) 1. pg. 6

Demolition completion per pre-bid comments on duration of job end date/completion to be August of

2018. It was stated that the CIF building NASA estimated 6-weeks for demolition. Also Headquarters building was 3-months. Demolition only. Please clarify dates and duration. 6 weeks and 3 months or till completion dates of August 2018?

The deconstruction of facilities is not circumscribed to physical demolition. There are abatement, site clearing, landscaping, shop drawing submittals, etc. The completion dates for this project shall be per the solicitation as changed by this amendment to clause F.1, changing the period of performance to July

31, 2018.

91 Drawings for Building M6-0342 AS-Built

Sheet 45

When foundation piles are encountered at what elevation are they to be removed at? Refer to 79K39839 Sheet D3, Flag Note R and Sheet D1 Demolition Note 1. The term demolish includes removal and disposal.

92 Solicitation - Attachment J-B, Contractor

Property, pg. 26.

Are all recyclable metals, i.e. copper etc. property of the demolition contractor? Yes, per clause J-B-34, as amended in amendment 0007, unless otherwise specifically indicated for an item in the contract drawings or specifications, or these bidder's questions answers.

93 Solicitation Is there a spec on the portable scale needed at the CIF and Headquarters site? No. Any calibrated scale that can weigh the loading vehicles the contractor will have on site is sufficient. Contractor is to keep the calibration records on site should the government want to inspect them.

94 Solicitation Is NASA looking for a printed ticket for each load? Yes, the contractor is to keep an electronic log of all truck loads and weights leaving the site and their destination. The printed ticket should be kept at the contractor's office for backup should the government require evidence. A weekly electronic report (Excel spreadsheet) will be required to be turned over to the government. This allows the government to measure compliance with its goals and metrics.

GOVERNMENT PRE AWARD INQUIRY FORM

5/27/2016

Amend No.No. QUESTION Reference

(Section Paragraph/Page)

GOVERNMENT RESPONSE

95 Solicitation When we control the DARCY will it be up to us the working hours of the DARCY M-F? Yes. Any extended hours beyond those stated in clause F.2 must be requested and approved by the contracting officer.

96 Solicitation Will NASA be supplying a borrow area for backfill dirt needed? Contractor is to assume materials will be obtained off site.

97 As part of removing the asphalt and piping as depicted on the drawings, will we need to replace the asphalt back in these areas?

Utilities are to be abandoned and capped under pavement. If asphalt is removed for this task, it will have to be replaced.

98 Please confirm that the electrical and plumbing disconnects are by others or is this part of our scope. The facilities will be turned over to the contractor dark and cold. Contractor is to safely verify such condition. Should it not be so, contractor is to stop operations and notify the contracting officer.

99 Will the Freon recovery be done by others? No, refer to 79K39387 Specification section 02 41 00 paragraphs 3.1.9 and 3.3.3.

100 Will there be any fees associated with dumping at the landfill and in the concrete dump. No, there are no fees for dumping at the KSC Class III Landfill or DARCY.

101 Is there is any replacement of dirt and sod as part of this work. Yes, refer to 79K39838 Sheet D1 Demolition Note 20 and Sheet D79 and 79K39839 Sheet D1

Demolition Note 20.

102 Will we have to fence off the demolition area? A construction fence will be absolutely necessary at the HQ, M6-0399, site, eastern area, due to the immediate vicinity of the new Central Campus, which will be fully operational prior to demolition activities. The contractor should expect to have personnel walking near that fence at any time of the day. In other areas there may be wide open expanses where no traffic or personnel is expected and in these areas a fence may not be required.

103 Is there an onsite location to dispose of the asphalt? Yes, asphalt shall be disposed of at the KSC Class III Landfill per clause J-B-35 Solid Waste, and J-B-

34 RECYCLING AND SALVAGING MATERIALS (MAR 2014) per Amendment 0007. Asphalt shall be transported in segregated loads. Identify those asphalt loads to the landfill monitor to receive directions as to where in the landfill they need to be deposited.

104 Please advise who is responsible for the relocation of the trees Relocation of trees is the responsibility of the Contractor awarded the project.

105 The floor plan dimensions do not match the site plan dimension. For example sheet floor plan shows

290 x 152, site shows 250x132. Which is correct. I would assume that the larger building has the same issue.

Refer to 79K39838 Sheet D1 Demolition Note 4 and 79K39839 Sheet D1 Demolition Note 4.

106 SF1442 Would the Govt consider requesting the P & P Bond when the options are exercised? We are requesting this because the HQ Building is not anticipated to start Aug 2017 and that is a long time to have a bond out for work that will not be performed until that time.

No. Please follow requirements found in FAR 52.228-15 and 52.228-1

107 If the DARCY Operations option is not exercised will the Govt extend the days and times that the

DARCY will be open or will it continue to run only two days a week?

Base bid is only 2 days per clause J-B-37.

GOVERNMENT PRE AWARD INQUIRY FORM

5/27/2016

Amend No.No. QUESTION Reference

(Section Paragraph/Page)

GOVERNMENT RESPONSE

108 How may days in the week is the waste disposal site open? See clause J-B-37.

109 Will we have to manage the DARCY between the two task orders? No.

110 Will we be provided water/power hookup? If not can we use the Fire Hydrants or are we going to be required to brink water tanks?

The government will not provide utilities or utility hookups directly to the contractor. The Contractor may use water from nearby hydrants without being charged. Amendment 0007 will make this change to clause I.16

111 Can we use the technical experience of our teaming partner or major subcontractor? Technical experience of teaming partners or major subcontractors can be used. Please also see

Amendment 0006 changes to Section M.1 (b)(1)(ii).

112 Will the land fill will be open 5 days a week No. Per J-B-45, the landfill hours of operations are restricted to Tuesdays and Thursdays from 0715 to

1500.

113 Under the base bid will the DARCY be open 5 days a week or just 2 unless the option 1 DARCY operations is utilized

The DARCY will be available only Tuesdays and Thursdays, under the base bid.

114 Specifications 3.1.5 Miscellaneous Metal Some as-built drawings were not supplied, please confirm interior wall of building M6-0399 and M6-

0342 are mainly steel studs and not wood 2x4's , and if so will the landfill take construction debris that contain steel studs? Or will the contractor be made to remove all metals from construction debris and salvage as scrap even though it is not cost efficient?

Generally both buildings have both steel and wood studs, depending on period of construction. The landfill will take construction debris that contains steel studs. However, the government requests that the contractor make an effort to reduce the amount of steel going into the landfill to support the government's recycling goals.

115 Will water be made available from fire hydrants in the vicinity and at no cost to the contractor? The government will not provide utilities or utility hookups directly to the contractor. The Contractor may use water from nearby hydrants without being charged. Amendment 0007 will make this change to clause I.16

116 Please confirm that NASA will not provide any utilities directly to the Contractor The government will not provide utilities or utility hookups directly to the contractor. The Contractor may use water from nearby hydrants without being charged. Amendment 0007 will make this change to clause I.16

117 Seven months is far too short a duration for the abatement and dismantlement of the Headquarters building, given the astronomical quantities of asbestos that must be removed prior to demolition. Will

NASA consider a longer duration for this evolution of the project?

The government will extend the period of performance by 4 months.

118 Please confirm that no work can be performed outside during Phase II lightning warnings [typical in the summer].

That is correct.

119 How long does NASA Shops have to respond to a utility outage request? Two weeks. See clause J-B-1.

120 Is ECATTS training required for all workers on site? No.

121 What are the restrictions for bringing in large [over-sized] equipment, such as track-hoes, etc.? Are there special permits required? Due to the massive traffic influx in the a.m. and outflow during certain hours in the p.m. are there time restrictions as well?

See clause J-B-5. In addition, all oversized vehicle entrance to KSC must be preceded by coordination with KSC security services at least 2 days prior. There are no special permits.

122 Please confirm that all the asbestos greater than 1% must be removed from the buildings prior to demolition and that it cannot be demolished in place with the buildings.

No, all Asbestos greater than 1% does not have to be removed from the buildings prior to demolition.

Only RACM and materials that will become RACM during demolition require abatement. The contract drawings also require selective abatement of non-friable materials. Refer to 79K39838 Sheet EN1

Asbestos Abatement Note 2 and Sheet EN2 Environmental Notes 1-3, 79K39839 Sheet EN1 Asbestos

Abatement Note 2 and Sheet EN2 Environmental Notes 1-3 and Specification 02 82 13.00 98.

GOVERNMENT PRE AWARD INQUIRY FORM

5/27/2016

Amend No.No. QUESTION Reference

(Section Paragraph/Page)

GOVERNMENT RESPONSE

123 The blue paint on the exterior columns of Headquarters is identified as containing 1,174 ppm PCB's, which is well above the 500 parts per million threshold for PCB Bulk Product Waste. Will this paint have to be removed and turned over to NASA as hazardous waste prior to demolition?

These concrete columns may not be recycled at DARCY. Therefore, the paint may remain on the concrete columns and shall be disposed of as C&D waste at the KSC Class III Landfill. If the contractor removes the paint, the waste stream shall be considered hazardous PCB waste and shall be turned over to NASA following the PWQ/TRP process. However, if the paint is removed, the concrete columns will still not be allowed to be recycled at the DARCY.

124 RFP p. 6, Section C.2 (b) The RFP p. 6, Section C.2 (b) 3 states that “the Demolition Contractor will be responsible for processing the incoming materials and loads.” Can the Government more clearly specify what is intended by “processing”? Does the Government mean to say that the Demolition Contractor will be responsible for “handling” the incoming materials and loads?

Processing means, weighing, verifying load content as acceptable for the DARCY, directing where loads are to be deposited (i.e. to segregate concrete from fines (sub-base material), densifying by accommodation material that may have been improperly scattered, or piling material higher as needed for meeting capacity goal as well as accessibility for accepting additional loads.

125 RFP p. 6, Section C.2 (b) With the Landfill and DARCY operation only open 2 days a week, the demolition process will most likely move faster than KSC can receive the material.