Pathfinder Technology Demonstrator
Operational Concept
Small Spacecraft Technology Program Office
NASA Ames Research Center
February 9, 2016
1st Flight Demonstration
• Fly Busek MEP Thruster Payload (3 thrusters)
• Perform a thorough Spacecraft Checkout
• Perform Thrust Demo (Orbit Raise/Lower)
• Thrusters will be fired in velocity or anti-velocity vector to raise or lower orbit by accelerating or decelerating spacecraft.
Option: Globalstar Duplex Radio Tech Demo
• Fly (1) GSP-1720 Duplex Modem and Related Hardware as a Secondary
Communication System
• Exercise Globalstar to Characterize Communication System Performance
(Non-Interference to the Primary Communication System)
MEP DEMONSTRATION OPTIONS
Operational Concept (1/5)
Launch
•Powered off
•Battery capacity to survive launch delays, eclipse
•“Lazarus” mode
•ISS inhibit switch requirements (3min) and battery bypass
Deploy into
LEO
•350-800 km, any RAAN or Beta angle, (98 or 51 or 45) degree inclinations cover most available launch scenarios
•No critical event coverage assumed. Best effort to be over a station
•Wait for 45 minutes before PTD can “radiate”. Bus powers up. Survival heating available.
•If tumbling…need a mode to charge batteries (could require array deploy if no power stowed). After threshold charge reached…turn on.
Safe-Hold
•Stabilize spacecraft in a power positive “safe” mode until ground commanded. Ability to communicate.
Ground Station Contact
•Contacts scheduled with JSOC TLE’s (at least initially)
•Launch provider to provide insertion state vector.
•Assume a “beacon mode” for primary comm system. CW unmodulated tone.
Operational Concept (2/5)
Commissioning
•BUS COMMISSIONING: One week bus system commissioning. Prop system powered off. Survival power available.
•SOLAR: Auto deploy panels or cmd open.
•COMM: Step thru transceiver configurations/rates.
•ACS: HW thru attitude control scenarios to validate/calibrate control gains
•THERMAL: Monitor thermal stability, potentially adjust controls
•PROP CHECKOUT: After one week, prop system power up/checkout. Melt plug. Test communications. Measure temps, run thru voltages.
• Short duration firing to ensure no affects on other systems
• Check measurement systems – IMU, prop system measurements
System
Characterization
•Up to 23 days of propulsion system characterization (30 days total on orbit time)
• Success criteria could be met in less time
•200 hours total firing time per engine
•One monitored pass per weekday (minimum)
• 10 passes/day at 32kbps TLM (min), 2 kbps CMD (min)
• MOC staffed 4 hours/weekday= 20 hours/week
• One CMD upload/weekday
•Lights out passes everyday, remote alert notification
•Ground stations to provide data within 3 hours.
•Ground command to initiate demo
•Propulsion system to operate (at times) w/o ground contact.
Operational Concept (3/5)
Thrust Demo
Orbit
Raise/Lower
• NADIR point spacecraft
• Fire all three thrusters in the velocity/anti-velocity direction to raise/lower the orbit
• Off-Pulse the outer thrusters to counter any delta-v thrust torque bias
• Spacecraft tracks velocity vector autonomously based on GPS measurements
• GPS processed on-board (position and velocity)
• Thrust in eclipse
• Use GPS to measure orbit and characterize thrust by post processing on the ground
• NASA responsible for thrust post processing
Operational Concept (4/5)
Data
Processing
•Prop system to estimate total propellant mass usage using look up tables on the ground.
•Use mass usage w/ DV and thrust duration to estimate “effective” Isp (includes effects of pointing errors, etc.) and force.
Data
Handling
•POC (Payload Operations Center) @ GRC
•PI at Ames for commissioning, then at GRC for remainder of the mission.
•FTP or direct access to data files
•MOC / POC on the IONET
•MOC security standards met
Command
Planning
•30 day operations plan maintained
•PI to compare measure results against ground test results on a daily basis
•PI to adjust science plan as needed
•Command approval meetings to be held
Optional:
Globalstar Demo
•Power on GSP1720
•Health check of communication system
•Execute command set from MOC
•Collect Telemetry
•Note: Characterization to be performed by NASA operations personnel
Operational Concept (5/5)
Repeat - up to 23 days performance Characterization
• Burn fuel until empty or run until a thruster fails
• Option: Complete Globalstar Testing
• Exercise EOM commands Decommissioning
Deorbit 25 year maximum requirement
30 Days Total Mission Duration
Conops Big Picture – NEN Option
PTD MOC
Ames Research Center
Moffett Field, CA
GSFC
NIC
AS1
AS3
Voice
TLM / CMD / UPD
NISN
Mission Networks
IONet
- Closed
- Restricted
- Open
CMD / Acq Data
Voice
WGS
SG1
SG2
SG3
MG1 Real-Time and Stored TLM
NASA/GSFC
Ames Res Ctr
NASA/MSFC
CMD, TLM & Voice
Real-Time TLM / Redistributed Stored TLM
S-Band
Uplink:
4 kbps BPSK
Downlink:
1-2 Mbps BPSK
SC Vendor I&T Facility
S-Band
WOTIS
Sched Reqs / Acq Data
Scheds / Acq Data
TLEs
GRC
POC
TLM – Archived
USSTRATCOM
Real-Time and Stored TLM
Real-Time and Stored TLM
Real-Time and Stored TLM
Glenn Res Ctr
Activity Requests
CSAFS
Stored TLM
Redistributed Stored TLM
CMD / Acq Data
Voice
WS1
USHI01
USHI02
Real-Time TLM
AUWA01
USSTRATCOM
JSpOC
Real-Time TLM
Real-Time and Stored TLM
Voice.
CMD / Acq Data.
Internet
Stored TLM
Stored TLM
High Inclination Orbit
Low Inclination Orbit
Navigation:
TLM includes Onboard GPS Data
Spacecraft Vendor
Conops Big Picture – Vendor GDS Option
PTD MOC
Ames Research Center
Moffett Field, CA
Voice
NISN
Mission Networks
IONet
- Closed
- Restricted
- Open
Ames Res Ctr
CMD, TLM & Voice
Real-Time TLM / Redistributed Stored TLM
S-Band
Uplink:
Vendor chosen Rate
Downlink:
SC Vendor I&T Facility
RF Link
Sched Reqs / Acq Data
Scheds / Acq Data
TLEs
GRC
POC
TLM – Archived
USSTRATCOM
Real-Time and Stored TLM
Glenn Res Ctr
Activity Requests
CMD / Acq Data
Voice
USSTRATCOM
JSpOC
Any Inclination Orbit
Navigation:
TLM includes Onboard GPS Data
Spacecraft Vendor
Vendor Antenna(s)
Control Facilities
Secure Internet
(VPN, SFTP, etc)
CMD / Acq Data
Sched Reqs / Acq Data
Scheds / Acq Data
Vendor chosen Rate
Note: For Vendor supplied GDS solution, RF capabilities and GDS ground components must meet daily PTD data volume and response time requirements. Vendor is responsible for meeting FISMA security requirements and securing Spectrum authorization.
Vendor chosen
Conops Big Picture – Globalstar Option
PTD MOC
Ames Research Center
Moffett Field, CA
Voice
NISN
Mission Networks
IONet
- Closed
- Restricted
- Open
Ames Res Ctr
CMD, TLM & Voice
Real-Time TLM / Redistributed Stored TLM
S-Band
Uplink:
Vendor chosen Rate
Downlink:
SC Vendor I&T Facility
RF Link
Sched Reqs / Acq Data
Scheds / Acq Data
TLEs
GRC
POC
TLM – Archived
USSTRATCOM
Real-Time and Stored TLM
Glenn Res Ctr
Activity Requests
CMD / Acq Data
Voice
USSTRATCOM
JSpOC
Any Inclination Orbit
Navigation:
TLM includes Onboard GPS Data
Spacecraft Vendor
Vendor Antenna(s)
Control Facilities
Secure Internet
(VPN, SFTP, etc)
CMD / Acq Data
Sched Reqs / Acq Data
Scheds / Acq Data
Vendor chosen Rate
Note: For Vendor supplied GDS solution, RF capabilities and GDS ground components must meet daily PTD data volume and response time requirements. Vendor is responsible for meeting FISMA security requirements and securing Spectrum authorization.
Vendor chosen
PTD MEP Thrust Measurement Approach
Thrust Measurement Approach
Thrust in anti-velocity or velocity
• GPS update to set thrust direction (as specified by s/c)
Thrust during eclipse
Change in orbit period (semi-major axis) and argument of perigee observed
Depending on orbit altitude, on-off thrusting required to measure drag force independently
Thruster performance metrics will be determined by observing the change in the orbit parameters after extended firing.
Simulated Orbit
0 2 4 6 8 10 12 14 16 18 398.8
399.2
399.4
399.6
399.8
Time (hr)
A lt it u d e k m
• 100 uN force
• 10 kg spacecraft mass
• Initial orbit – circular, 400 km
• 1.2 km change in altitude after 16 hours
Orbit Determination Monte Carlo
Monte Carlo Simulation run to characterize orbit modeling
• GPS position/velocity measurements every minute
• 26 m 1 s, Gaussian
• Thruster on, lowering orbit
• Atmosphere known
• Harris Preister Model
• Orbit: 500 km Sun-synch
• Least squared error fit of orbit to GPS data over an orbit
• Includes thrust force and initial conditions as parameters
Thruster error over 100 cases: < 1%
Thruster characterization dominated by uncertainty in atmospheric drag