This is a Schedule of Values (SOV) template spreadsheet for a Fiber Optic Transmitting System (FOTS) duct bank installation project at Newark Liberty International Airport (EWR). The SOV template includes line items for mobilization/badging/transportation, materials (cables/grounding/infrastructure/hardware), and miscellaneous costs (waste/environmental/sanitation), with columns for subtotal, profit, and bond amounts, though no actual values are filled in.
The associated contract opportunity is a small business set-aside solicitation under NAICS 238210 with an estimated value between $100,000-$250,000. The work involves installing two new duct bank sections with 2-4" concrete encased PVC conduit and inner ducts at EWR. Quotes are due February 27, 2025, by 5:00 PM CT, with a site visit request deadline of February 13, 2025, and questions due by February 20, 2025. The project requires 51% self-performance, has a 30-day completion timeline, and will be awarded as Lowest Price Technically Acceptable. Davis-Bacon Act wages apply, and bonding is required as the project exceeds $150,000.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Communications Construction Install Schedule of Values | ||
| Project: EWR FOTS | ||
| Location: Newark, NJ | ||
| Scope: Duct Bank Installation | ||
| Notes: | ||
| Mobilization | Badging, Transportation | $0.00 |
Materials Cables, Grounding, Infrastructure, Hardware $0.00
| Miscellaneous | Waste, Environmental, Sanitation | $0.00 |
| Subtotal | $0.00 | |
| Profit | $0.00 | |
| Bond | $0.00 | |
| Total Cost of Project | $0.00 |