This is a Questions and Answers document for a fiber optic installation project at Newark Airport (SIR #25-19006839). The document addresses technical specifications and logistics for installing a Fiber Optic Transmitting System (FOTS), confirming that the project requires installation of a 24-strand single-mode fiber cable that is government-furnished material (GFM) and currently looped in manholes.
Key details include: work hours are typically 12:00am-5:00am subject to airport operations and runway closures; contractors must obtain Newark Airport badges and hire escorts at their expense; no pre-bid survey is possible due to access restrictions; the contractor is responsible for duct bank installation and pulling the GFM fiber cable, while the FAA will handle terminations; weekend work can be approved if needed; and bids are due by January 27, 2025. The project involves installation at two sites, with fiber originating from MH 10-24 at Site 1 and HH COM 13-28 at Site 2, with no splicing required at either location as the fiber cable is already looped and ready to be pulled once duct banks are installed.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Newark NJ RFI 03.04.25.pdf | ||
| 00002 Amendment - Newark NJ rfi.pdf | ||
| 00001 Amendment - Newark NJ ext rfi nosite.pdf | ||
| EWR FOTS Drawings 19006839.pdf | ||
| EWR FOTS Duct Bank Specifications.pdf | ||
| Newark NJ SOV.xlsx | XLSX spreadsheet | |
| Wage Determination NJ20250031 01.03.2025.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Install (FOTS) Fiber Optic Transmitting System in Newark, NJ
SIR # 25-19006839
Questions
1. Can the appropriate party please define Night Work Hours?
Typically, it is 12:00a-5a. Work times will be subject to airport Ops, runway closures, and air traffic release due to the area of work. Upon award, work schedule will need to be coordinated with local airport and FAA based on monthly schedules.
2. We understand the spec sections state no weekend work is needed or approved. Since this is a night job will Friday
Nights be considered a weekend?
Yes, weekend work can be requested and approved if there is a need.
3. What are the special Access requirements?
Newark Airport badging and hiring of escorting personnel. Newark airport will not badge movement area, so appropriately badged escorts will need to be hired at contractor expense, and access badges will need to be acquired for workers at contractor expense.
4. Is it possible to survey the work areas to collect information to put our proposal together?
Due to access restrictions, we cannot to a pre-bid survey in the area.
5. Is the fiber to be installed to be Single Mode?
Yes
6. How many strands is the fiber cable?
24 strand single mode
7. The Site 1 drawing calls for fiber by sections (Site 1 Notes: 1). Is there just 1 fiber cable being installed from MH
10-24 to 22R GS Shelter, or are these each separate fiber runs?
1 fiber cable that is looped in the manhole waiting to be pulled. Termination to be performed by FAA.
8. How many total fiber runs, and what size and type are each fiber for the project?
Cable is GFM currently looped in the manholes waiting to be pulled through one of the contractor supplied and installed innerduct. Single cable to be pulled. 24 strand single mode fiber.
9. Site 1 fiber originates in MH 10-24. Does the new fiber get spliced to an existing fiber in the manholes? Is there an existing splice case and splice slack in these manholes? If slack is needed, where would it need to be pulled from to be able to do the splices?
No splice needed. Fiber cable is looped and ready to be pulled once duct banks are installed.
10. What type of fiber termination shelf is needed at each termination point? Rack mount, wall mount?
Termination shall be performed by FAA. Contractor responsible for duct bank installation and pulling of GFM fiber cable that is currently looped in manholes.
11. Site 2 drawing shows conduit starting in HH COM 13-28. Does the new fiber get spliced to an existing fiber in the
HH? Is there an existing splice case and splice slack in this HH? If slack is needed, where would it need to be pulled from to be able to do the splices?
No splice needed. Fiber cable is looped and ready to be pulled once duct banks are installed.
12. Can additional questions be asked at a later date?
Bids are due 01/27/25, please have all questions before this date.