This is a Cost Proposal template from the Nebraska Department of Natural Resources (NeDNR) for RFP Number CTP2401, focused on 2D BLE for the Cheyenne, White, and Niobrara (Phase 1) HUC-6 Watersheds. The template provides a structured format for bidders to submit their cost estimates across five main tasks: Project Management, Develop Hydrologic Data, Develop Hydraulic Data, Perform Floodplain Mapping, and DFIRM Database. The spreadsheet includes columns for up to five labor classes (with the option to add more if needed) and requires bidders to input estimated hours per task for each labor class.
The template requires bidders to fill in their company information, specify labor class titles, estimate hours per task, and provide fixed hourly rates for each labor class. The spreadsheet is designed to automatically calculate total estimated hours per task, total hours per labor class, and total estimated costs through built-in formulas. The document emphasizes that certain totals should populate automatically and not be manually filled. The template appears to be part of a larger procurement package, though specific pricing parameters or budget constraints are not indicated in the cost proposal form itself.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| NeDNR_RFP_CTP2401_2DBLE.pdf | ||
| Form-42_SolicitationIntenttoAwardNotice.pdf | ||
| Form-34_SolicitationListofRespondents.pdf | ||
| NeDNR_CTP2401_2DBLE_EvaluationCriteria.pdf | ||
| NeDNR_RFP_CTP2401_2DBLE.docx | DOCX document | |
| NeDNR_CTP2401_2DBLE_EvaluationCriteria.docx | DOCX document | |
| SolicitationAddendumQ&A.pdf | ||
| NeDNR_RFP_CTP2401_CostProposal.xlsx | XLSX spreadsheet | |
| NeDNR_CTP2401_2DBLE_EvaluationCriteria.pdf | ||
| NeDNR_CTP2401_2DBLE_EvaluationCriteria.docx | DOCX document | |
| NeDNR_RFP_CTP2401_2DBLE.pdf | ||
| NeDNR_RFP_CTP2401_CostProposal.xlsx | XLSX spreadsheet | |
| SolicitationAddendumQ&A.pdf | ||
| NeDNR_RFP_CTP2401_CostProposal.pdf | ||
| NeDNR_RFP_CTP2401_2DBLE.docx | DOCX document | |
| NeDNR_RFP_CTP2401_CostProposal.xlsx | XLSX spreadsheet | |
| NeDNR_RFP_CTP2401_2DBLE.pdf | ||
| NeDNR_RFP_CTP2401_2DBLE.docx | DOCX document | |
| NeDNR_CTP2401_2DBLE_EvaluationCriteria.pdf | ||
| NeDNR_RFP_CTP2401_CostProposal.pdf | ||
| NeDNR_CTP2401_2DBLE_EvaluationCriteria.docx | DOCX document |
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Labor Class #1 Labor Class #2 Labor Class #3 Labor Class #4 Labor Class #XX Labor Class Title [PLEASE FILL] [PLEASE FILL] [PLEASE FILL] [PLEASE FILL] [PLEASE FILL]
Cost Proposal 2D BLE for the Cheyenne, White, and Niobrara (Phase 1) HUC-6 Watersheds
RFP Number CTP2401
Bidder Name:
Bidder Address:
Telephone Number:
Contact Person:
Task # Task Name
Lab or C las s #
1 - Esti mate d Hours/
Tas k
Lab or C las s #
2 - Esti mate d Hours/
Tas k
Lab or C las s #
3 - Esti mate d Hours/
Tas k
Lab or C las s #
4 - Esti mate d Hours/
Tas k
Lab or C las s #
XX - E
sti mate d Hours/
Tas k
Total Esti mate d Hours/
Tas k
Total Esti mate d Cost/
Tas k
1 Project Management 0.00 0.00 0.00 0.00 0.00 0.00 -$ 2 Develop Hydrologic Data 0.00 0.00 0.00 0.00 0.00 0.00 -$ 3 Develop Hydraulic Data 0.00 0.00 0.00 0.00 0.00 0.00 -$ 4 Perform Floodplain Mapping 0.00 0.00 0.00 0.00 0.00 0.00 -$ 5 DFIRM Database 0.00 0.00 0.00 0.00 0.00 0.00 -$
0.00 0.00 0.00 0.00 0.00 0.00 Total Estimated Project Hours -$ -$ -$ -$ -$ -$ Total Estimated Project Cost
Total Hours/Labor Class Hourly Rate/Labor Class
Total Estimated Cost/Labor Class
Instruction:
1. Fill each Labor class title expected to work on this project. If less than five labor classes are expected, please leave the remaining labor class information columns blank.
If more than five classes are expected, please add a column for each additional labor class to each respective chart.
2. Estimate and fill the number of hours needed to complete each task per each respective labor class in the chart below. 'Total Estimate Hours/Task' & 'Total Estimate Hours/Labor Class' should automatically populate via formula and shall not be manually filled.
3. Fill the fixed hourly rate for each respective Labor Class in Row 29. 'Total Estimated Cost/Task', 'Total Estimated Cost/Labor', and 'Total Estimated Project Cost' should