NeDNR_CTP2401_2DBLE_EvaluationCriteria.docx
DOCX document 23 KB Posted
- Solicitation number
- CTP2401
- Issued by
- Lancaster County, Nebraska
About this file
This document outlines the solicitation evaluation criteria for a contract opportunity related to the Cheyenne, White, and Niobrara (Phase 1) HUC 6 Watersheds project. The solicitation, numbered CTP2401, is for 2D BLE services. Responses must address mandatory requirements such as a signed Contractual Agreement Form, Corporate Overview, Technical Approach, Project Schedule, and Cost Sheet. The evaluation criteria include scoring for Corporate Overview (15 points), Technical Approach (50 points), Project Schedule (25 points), and Cost Sheet (10 points) for a total of 100 possible points without oral interviews. The Cost Sheet points will be awarded based on the formula of lowest cost submitted receiving the maximum points, with other submissions scored proportionally. The solicitation opens on December 6, 2024 at 2:00 PM Central Time.
The document provides details on how the Cost Sheet points will be calculated, including samples of the formula to be used. No further information is provided about pricing terms, set asides, incumbents, funding requirements or sources, or other salient details.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| NeDNR_RFP_CTP2401_2DBLE.pdf | ||
| NeDNR_RFP_CTP2401_CostProposal.pdf | ||
| Form-42_SolicitationIntenttoAwardNotice.pdf | ||
| Form-34_SolicitationListofRespondents.pdf | ||
| NeDNR_CTP2401_2DBLE_EvaluationCriteria.pdf | ||
| NeDNR_RFP_CTP2401_2DBLE.docx | DOCX document | |
| NeDNR_CTP2401_2DBLE_EvaluationCriteria.docx | DOCX document | |
| SolicitationAddendumQ&A.pdf | ||
| NeDNR_RFP_CTP2401_CostProposal.xlsx | XLSX spreadsheet | |
| NeDNR_CTP2401_2DBLE_EvaluationCriteria.pdf | ||
| NeDNR_CTP2401_2DBLE_EvaluationCriteria.docx | DOCX document | |
| NeDNR_RFP_CTP2401_2DBLE.pdf | ||
| NeDNR_RFP_CTP2401_CostProposal.xlsx | XLSX spreadsheet | |
| SolicitationAddendumQ&A.pdf | ||
| NeDNR_RFP_CTP2401_CostProposal.pdf | ||
| NeDNR_RFP_CTP2401_2DBLE.docx | DOCX document | |
| NeDNR_RFP_CTP2401_CostProposal.xlsx | XLSX spreadsheet | |
| NeDNR_RFP_CTP2401_2DBLE.pdf | ||
| NeDNR_RFP_CTP2401_2DBLE.docx | DOCX document | |
| NeDNR_CTP2401_2DBLE_EvaluationCriteria.pdf | ||
| NeDNR_RFP_CTP2401_CostProposal.pdf |
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION EVALUATION CRITERIA
SOLICITATION NUMBER: CTP2401, 2D BLE for the Cheyenne, White, and Niobrara (Phase 1) HUC 6 Watersheds Opening Date: December 6, 2024; 2:00 PM (Central Time)
Mandatory Requirements The solicitation responses will first be examined to determine if all mandatory requirements listed below have been addressed to warrant further evaluation. Responses not meeting mandatory requirements will be excluded from further evaluation. The mandatory requirement items are as follows:
Contractual Agreement Form, must be signed manually in ink or by DocuSign;
Corporate Overview;
Technical Approach;
Project Schedule; and Cost Sheet.
Evaluation Criteria All responses to this solicitation, which fulfill all mandatory requirements, will be evaluated. Each category will have a maximum possible point potential. Areas that will be addressed and scored during the evaluation include:
| Evaluation Criteria |
| Possible Points |
| Part 1 Corporate Overview |
| 15 |
| Part 2 Technical Approach |
| 50 |
| Part 3 Project Schedule Points |
| 25 |
| Part 4 Cost Sheet Points |
| 10 |
| Total Points without Oral Interviews |
| 100 |
Part 4 – Cost Sheet Points Cost Sheet points should be calculated as follows:
0. Establish lowest cost submitted – lowest cost submitted receives the maximum points.
0. To assign points to all others, the following formula should be followed:
Lowest Cost Submitted Cost Submitted x Maximum Possible Cost Points = Cost Points to Award (see samples below)
Formula
Sample
Sample
Sample
Lowest Cost Submitted
$100,000
$100,000
$100,000
Cost Submitted
$100,000
$200,000
$150,000 x Maximum Possible Cost Points
= Points To Award
20.00
10.00
13.33