FBOAmendment001.pdf
PDF 125 KB Posted
- Attached to
- NOS/OCS Hydrographic Surveying Services Federal contract opportunity
- Solicitation number
- NCNJ3000-18-00238
About this file
This document provides an amendment to a Federal Business Opportunities notice seeking hydrographic surveying services. The National Oceanic and Atmospheric Administration is requesting statements of qualifications from firms to provide hydrographic surveying services in support of NOAA's mission to acquire survey data for nautical charts. The amendment answers seven questions received regarding the solicitation and clarifies that the required labor categories and personnel may be met by the prime contractor or assembled team as a whole. Interested parties should submit SF330 responses by March 12, 2019 for the agency to award up to seven contracts total, with a 2:1 small business set-aside ratio of two contracts for large businesses for every one for a small business.
Please find the attached Amendment 0001 that provides answers to questions received to date for NCNJ3000-18-00238 (NOS/OCS Hydrographic Surveying Services) posted to FBO on February 8, 2019.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FBOAmendment002.pdf | ||
| Attachment_B_LaborCategories.pdf | ||
| SOW_Hydrographic_Services_Contract.pdf | ||
| RequestforSF330s.pdf | ||
| AttachmentA_PPQ.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Amendment to Federal Business Opportunities (FBO) Notice
Amendment No.: 0001
Identification No.: NCNJ3000-18-00238
Title: NOS/OCS Hydrographic Surveying Services
Amendment Purpose: This amendment is issued to provide answers to questions received to date for NCNJ3000-18-00238 (NOS/OCS Hydrographic Surveying Services) posted to FBO on
February 8, 2019.
The following questions with respective answers are provided herein:
Question 1: The solicitation mentions, under “Professional Qualifications”, “In order to be qualified, firms will need to have personnel on payroll for all of the labor categories identified in
Attachment B, Labor Category Descriptions”. It then goes on to define “Key Personnel”.
Regarding having personnel “on payroll”, is this meant to apply to just the prime contractor, or to the assembled team as a whole? What about “key personnel” – is the prime expected to have at least these personnel on staff or is this also applicable to the team as a whole?
Answer: The team as a whole must have all of the labor categories identified in
Attachment B, Labor Category Descriptions, (including Key Personnel) on payroll.
Question 2: Will PPQs count against the page count?
Answer: PPQs will not count against the page count.
Question 3: Is a PPQ (or other assessment mechanism) required for each past performance project?
Answer: As stated in the Past Performance evaluation factor, a minimum of three (3) past performance references must be provided. Part I, Section F of the SF330 for example projects requires the Project Owner’s point of contact information be provided. As stated in the Past Performance Selection Criteria, The Government will evaluate past performance based on information submitted in the PPQ, Contractor Performance
Assessment Reporting System (CPARS) for projects provided in the SF330, Part I, Section F and may include customer inquiries, Government databases, and other information available to the Government including contact with points of contact provided in the SF330.
Question 4: The RFP states “In order to be qualified, firms will need to have personnel on payroll for all of the labor categories identified in Attachment B, Labor Category Descriptions.”
“Firms must also have at least two (2) certified hydrographers and availability through ownership or lease of a range of equipment such as seaworthy vessels with specially calibrated equipment and suitable aircraft” Are the qualified personnel required to be employed directly by the prime firm or can the required qualified personnel be drawn from a combination of the teaming firms’ staff?
Answer: The team as a whole must have all of the labor categories identified in
Attachment B, Labor Category Descriptions, (including Key Personnel) on payroll. The qualified personnel are not required to be employed directly by the prime firm.
Question 5: “Front and back side use of a single page will count as 2 pages. The overall submission package (Part I and Part II of SF330) shall not exceed 100 pages. Each side of a single sheet of paper is considered a page, such that a single sheet of 8 ½ X 11, is two pages of the 100 page total….” Would a SF330 page (or piece of paper) that’s only printed on one side count as one page or two pages?
Answer: The SF330 page that is only printed on one side counts as one page. If the
SF330 page is printed on two sides (double-sided), then it counts as two pages.
Question 6: A Past Performance Questionnaire (PPQ) form is included. In the request for
SF330 document, Section 4 “Past Performance”, it mentions PPQs are one item that will be used to evaluate past performance. Could you please clarify what action we are to take with this document concerning our SF330 response -- is the PPQ form included simply for reference, or are we expected to provide completed PPQ forms with the SF330 response? If so where in the
SF330 document and do they count toward the total page count, and do they need to correspond to example projects listed in Section F?
Answer: The PPQ is an optional form. The PPQ can be utilized for example projects listed in SF330, Part I, Section F or for other projects that demonstrate past performance with
Government agencies and private industry completing hydrographic data collection and processing to support routine activities and emergency incidents (relevant in size and scope to this acquisition) with respect to cost control, quality of work, compliance with performance schedules, stakeholder/customer satisfaction, and regulatory compliance, as stated in the Past
Performance Selection Criteria. If a PPQ is utilized, the Contractor is to complete blocks 1 through 4 and the Client (the agency, private firm that the Contractor completed work for) is to compete blocks 5 through 8. The Client shall provide the completed PPQ via email to the
Contract Specialist, Stacy Dohse at Stacy.Dohse@noaa.gov and cc Contracting Officer, Tiffany
Squyres at Tiffany.Squyres@noaa.gov. The PPQ does not count towards the total page count.
Question 7: In the “Past Performance” section, it mentions a minimum of three references must be provided. In what format are these references expected to be provided? Is a “reference” considered the Project Owner Information for example projects (box 23 in section F)?
mailto:Stacy.Dohse@noaa.gov
Answer: There is not a specific required format for references. A reference can be the
Project Owner Information included in SF330, Part I, Section F.
File details come from the government source that posted it. Updated .