N69450-21-R-0041-0001.pdf

PDF 201 KB Posted

Attached to
WEAPONS GENERATION FACILITY B EARLY START SITE Federal contract opportunity
Solicitation number
N69450-21-R-0041
Issued by
Department of the Navy Naval Facilities Engineering Command

About this file

This document contains an amendment to a solicitation for early start site work at Barksdale Air Force Base, Louisiana. The amendment provides updated specifications, drawings, and evaluation factors. Key details include site work across 53 acres to prepare for construction of a weapons generation facility, including clearing, grading, drainage, environmental remediation, building demolition, utility relocation, fencing installation, and road construction. Technical specifications are updated for various sections. Evaluation factors are revised to remove pricing submittal requirements and modify experience requirements to accept relevant experience from subcontractors for aqueous film forming foam remediation and unexploded ordnance clearance. The response due date of August 12, 2021 remains unchanged. The soliciting agency is the Department of the Navy Naval Facilities Engineering Command.

View the file

Other files for this federal contract opportunity

Other files attached to WEAPONS GENERATION FACILITY B EARLY START SITE, newest first.
File Type Posted
N69450-21-R-0041-0002.pdf PDF
SF-312 (Classified Information Nondisclosure Agreement).pdf PDF
NEW Safety_Data_Sheet.docx DOCX document
Exhibit B Past Performance Questionnaire.docx DOCX document
Exhibit E SB Participation Commitment Doc.docx DOCX document
Exhibit C Safety Data Sheet.docx DOCX document
Exhibit F Small Business Subcontracting Plan.doc DOC document
N6945021R0041.pdf PDF
Exhibit A Construction Experience Project Data Sheet.docx DOCX document
Exhibit D Historical SB Utilization.docx DOCX document
Attachment A ProjNet How To Guide.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

N69450-21-R-0041 - WEAPONS GENERATION FACILITY B EARLY START SITE WORK AT BARKSDALE AIR FORCE BASE, LA

1. Post IFIO Specifications and Draw ings

2. Technical updates

3. Factor updates

4. Provide an updated Attachment C, Safety Data Sheet.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 6

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 19-Jul-2021

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N6945021R0041

X 9B. DATED (SEE ITEM 11)

12-Jul-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

19-Jul-2021

CODE

NAVFAC ENGINEERING SYSTEMS COMMAND SE

ROICC BARKSDALE

334 DAVIS AVE WEST STE 103

BARKSDALE LA 71110

N69450 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N6945021R0041

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 1

1. 1. The purpose of this amendment is to: (1) Provide Weapons Generation Facility Early Start “Issued for Information Only” Specifications, (2) Provide “Issued for Information Only” Weapons Generation Facility Early Start Drawings, (3) Provide Technical updates to specifications, (2) provide Factor updates, (3) Provide an updated Attachment C, Safety Data Sheet.

2. Proposal due date remains unchanged at Thursday, 12 August 2021 at 3 pm Eastern Time.

TECHNICAL UPDATES

SECTION 01 11 00.00 25 SUMMARY OF WORK

1.6 SALVAGE MATERIAL AND EQUIPMENT

Delete the second sentence of this section and replace with “See drawings 0A-ED121, 0A- ED122, 0A-ED123, 0A-ED124, 0A-ED125, 0A-ED134, 0A-ED135, and 0A-ED136 for specific locations and corresponding notes.

SECTION 30 00 00 EARTHWORK

3.2.7 STRUCTURAL EXCAVATION

Delete this paragraph in its entirety.

3.7 FINAL GRADE OF SURFACES TO SUPPORT CONCRETE

Delete this paragraph in its entirety.

3.9 UTILIZATION OF EXCAVATED MATERIALS

Replace the first sentence in this paragraph with “Unsatisfactory materials shall be removed from the installation.”

SECTION 01 45 00

1.4 QC PROGRAM REQUIREMENTS

Remove “Commissioning” from the second sentence.

1.5.1.2 QUALIFICATIONS

Replace paragraphs with “An individual with a minimum of 10 years combined experience in the following positions: Project Superintendent, QC Manager, Project Manager, Project Engineer or Construction Manager on similar size and type construction contracts which included the major trades that are part of this Contract. The individual must have at least five years experience as a QC Manager. The individual must be familiar with the requirements of EM 385-1-1, and have experience in the areas of hazard identification, safety compliance, and sustainability.

Or, a graduate of a four year accredited college or university program in one of the following disciplines: Engineering, Architecture, Construction Management, Engineering Technology, Building Construction, or Building Science, with a minimum of 5 years experience as a Project Superintendent, QC Manager, Project Manager, Project Engineer or Construction Manager on similar size and type construction contracts which included the major trades that are part of this Contract. The individual must have at least two years experience as a QC Manager. The individual must be familiar with the requirements of EM 385-1-1, and have experience in the areas of hazard identification, safety compliance, and sustainability.”

1.6.1.1 REQUIREMENTS

Remove “commissioning” from the first sentence.

1.7.1 PURPOSE

Delete “Cx” from the first sentence.

1.7.3 ATTENDEES

Remove “Assistant QC Manger” from the first sentence.

1.10.1 PREPARATORY PHASE

Remove “Assistant QC Manager” from the second sentence.

1.10.2 INITIAL PHASE

Remove “Assistant QC Manager” from the second sentence and replace with “QC Manager”.

Remove “Cx” from item e.

SECTION 03 30 53 MISCELLANEOUS CAST-IN-PLACE CONCRETE

3.1.3.3 BATCHING AND MIXING EQUIPMENT

Delete this paragraph in its entirety.

SECTION 01 50 00.00 25 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

3.5.1 GOVERNMENT CONSTRUCTION MANAGER RECORDS AND FIELD OFFICE

3.5. ADD: h. Prior to demobilization, the contractor will prepay Internet/WiFi to provide continuous and uninterrupted service throughout all the trailer spaces through 29 FEB 2024, which is anticipated to be six (6) months after completion of the work in this contract.

SECTION 02 41 00 DEMOLITION

3.1.5 STRUCTURAL STEEL

Replace entire paragraph with “All structural steel material will be removed from site and will become the Contractor’s property.”

3.1.8 MECHANICAL EQUIPMENT AND FIXTURES

Replace entire paragraph with “All mechanical equipment and fixtures will be removed from site and will become the Contractor’s property.”

SECTION 30 01 00 MUNITIONS AND EXPLOSIVES OF CONCERNS (MEC)

REMEDIATION

1.2.1 Design RequirementsReplace entire paragraph with “Design requirements shall comply with the Department of Defense Explosives Safety Board (DDESB) approved Explosives Safety Submission (ESS) and be included in the UXO Construction Support Contractor's Work Plan.”

SECTION 01 14 00.00 25 WORK RESTRICTIONS

1.3.1 ACTIVITY REGULATIONS

Replace paragraph four with “During the initial fencing installation of the CFZ, the Contractor personnel will be required to access the work area through the MSA Control Point. Contractor personnel will be escorted to the demarcated work area and are not allowed to exit this demarcation without Government escort. Government escorts are not available during the weekend or during off-shift hours without prior coordination with the Contracting Officer. Upon establishment of the temporary CFZ fencing and the permanent Type II MSA fence, including the tie-in of this fence to the existing MSA fence (see drawings 0A_CS121 and 0A-CS136 for tie-in locations), the Contractor shall request an inspection by the Contracting Officer to determine that the boundary is secure. Once Contracting Officer approval is obtained, the jobsite can be accessed through the CFZ and not the MSA.”

01 50 00.00 25 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

2.3 FENCING

Replace entire paragraph with “Provide fencing along the construction site and at all open excavations and tunnels to control access by unauthorized personnel. Reference drawing 0A- C021 for the overall fence plan, and drawings 0C-C510, 0A-C511, and 0A-C512 for MSA Type

II

and Construction Free Zone fence details. Safety fencing must be highly visible to be seen by pedestrians and vehicular traffic. Specific fencing requirements for fencing other than that noted in the drawings referenced are described herein. All fencing will meet the requirements of EM 385-1-1. All fencing other than that noted in the drawings referenced will be removed upon completion of the contract.”

FACTOR UPDATES

1) Revise Section 00 21 00, EVALUATION FACTORS, (a) Price (Part I), (1) Solicitation Submittal Requirements, as follows:

DELETE paragraph ii, “SF 1442 Schedule of Prices for Contract Line Items Numbers.

Complete the Section 00 10 00 CLIN SF 1442 Schedule of Prices.” and re-number accordingly.

2) Revise Section 00 21 00, EVALUATION FACTORS, (b) Non-Price Factors (Part I), (2) Factor 2 – Experience (change is in blue colored font):

FROM:

(1) Construction Experience:

Submit a minimum of 3 (three) and a maximum of five (5) relevant construction projects for the Offeror that best demonstrates your experience as the prime contractor on relevant projects that are similar in size, scope, and complexity to the RFP. For purposes of this evaluation, a relevant project is further defined as includes building demolition, rough grading, installation of site features and utilities within a secure area, and with a contract value of $10,000,000, or greater.

In addition to the above, submit a minimum of one (1) and a maximum of three (3) construction projects that demonstrate relevant experience with environmental remediation of Aqueous Fill Forming Foam (AFFF) in groundwater and unexploded ordnance (UXO) or Munitions and Explosives of Concern (MEC). If the Offeror does not have relevant experience in both AFFF remediation and UXO clearance within the same project, the Offeror may submit relevant experience in two separate projects, but experience in both environmental remediation must be demonstrated. If the Offeror does not have relevant experience installing active vehicle barriers, the Offeror may submit relevant experience from a subcontractor they plan to use. The project(s) that demonstrate experience with AFFF and UXO experience is not required to meet the minimum contract value stated above.

TO:

Submit a minimum of 3 (three) and a maximum of five (5) relevant construction projects for the Offeror that best demonstrates your experience as the prime contractor on relevant projects that are similar in size, scope, and complexity to the RFP. For purposes of this evaluation, a relevant project is further defined as includes building demolition, rough grading, installation of site features and utilities within a secure area, and with a contract value of $10,000,000, or greater.

In addition to the above, submit a minimum of one (1) and a maximum of three (3) construction projects that demonstrate relevant experience with environmental remediation of Aqueous Fill Forming Foam (AFFF) in groundwater and unexploded ordnance (UXO) or Munitions and Explosives of Concern (MEC). If the Offeror does not have relevant experience in both AFFF remediation and UXO clearance within the same project, the Offeror may submit relevant experience in two separate projects, but experience in both environmental remediation must be demonstrated. If the Offeror does not have relevant experience with AFFF and UXO, the Offeror may submit relevant experience from a subcontractor they plan to use. The project(s) that demonstrate experience with AFFF and UXO experience is not required to meet the minimum contract value stated above.

3) Revise Section 00 21 00, EVALUATION FACTORS, (d) Price (Part II), (i) Solicitation Submittal Requirements, as follows:

DELETE paragraph (1), “The executed DD1155. Offerors shall insert their company name and address in Block 9, signature, date signed, and name and title of person authorized to sign in Block 16, and the price proposed on Page 2 of the DD1155.”

REPLACE WITH: “(1) SF 1442 Schedule of Prices for Contract Line Items Numbers. Complete the Section 00 10 00 CLIN SF 1442 Schedule of Prices.”

(End of Summary of Changes)

File details come from the government source that posted it. Updated .