WEAPONS GENERATION FACILITY B EARLY START SITE Federal contract opportunity
Solicitation number
N69450-21-R-0041
Issued by
Department of the Navy Naval Facilities Engineering Command

About this file

This is a request for proposal for early start site work at Barksdale Air Force Base in Louisiana. The solicitation seeks offers for clearing, grading, drainage, environmental remediation, building demolition, utility relocation, fencing installation, and road construction across 53 acres to prepare for a new industrial facility. Proposals will be evaluated based on technical approach, experience, past performance, safety, technical solution, and small business utilization. Offerors must submit pricing by August 12, 2021. The work is to be completed within 648 calendar days of award. A minimum of 20% small business participation is required.

View the file

Other files for this federal contract opportunity

Other files attached to WEAPONS GENERATION FACILITY B EARLY START SITE, newest first.
File Type Posted
N69450-21-R-0041-0001.pdf PDF
N69450-21-R-0041-0002.pdf PDF
SF-312 (Classified Information Nondisclosure Agreement).pdf PDF
NEW Safety_Data_Sheet.docx DOCX document
Exhibit B Past Performance Questionnaire.docx DOCX document
Exhibit E SB Participation Commitment Doc.docx DOCX document
Exhibit C Safety Data Sheet.docx DOCX document
Exhibit F Small Business Subcontracting Plan.doc DOC document
Exhibit A Construction Experience Project Data Sheet.docx DOCX document
Exhibit D Historical SB Utilization.docx DOCX document
Attachment A ProjNet How To Guide.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N69450-21-R-0041, WEAPONS GENERATION FACILITY B EARLY START SITE WORK AT BARKSDALE AIR FORCE BASE, LA

This acquisition w ill be solicited on a unrestricted basis w ith full and open competition.

This solicitation w ill result in a Firm Fixed Price , Design-Bid-Build Construction contract issued as a Tw o Part DBB procurement.

In accordance w ith Defense Federal Acquisition Regulation Supplement (DFARS) 236.204, the total project magnitude is betw een $25,000,000 and $100,000,000.

NAICS Code: 236220 – Commercial and Institutional Building Construction

All correspondence regarding this solicitation shall be directed via email to Herbert Fusilier at herbert.l.fusilier.civ@us.navy.mil and Rebecca Jones at rebecca.m.jones75.civ@us.navy.mil

NOTE: SPECIFICATIONS, DRAWINGS AND ALL AMENDMENTS WILL BE POSTED ON SAM.GOV. IT IS THE RESPONSIBILTIY OF ALL POTENTIAL

OFFERORS TO CHECK SAM.GOV. PERIODICALLY.

HERBERT L. FUSILIER 318-456-2704

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

12-Jul-2021

(RFP)

(IFB)

X

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

X

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______15 calendar days and complete it w ithin ________648 calendar days after receiving aw ard, notice to proceed. This performance period is X mandatory, negotiable. (See _________________________FAR 52.211-10

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________12 Aug 2021 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee X is, is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______120 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

NAVFAC ENGINEERING SYSTEMS COMMAND SE

ROICC BARKSDALE

334 DAVIS AVE WEST STE 103

BARKSDALE LA 71110

N69450

PAGE OF PAGES

1 OF

CODE N69450

(Title, identifying no., date):

12B. CALENDAR DAYS

03:00 PM (hour)

Sealed envelopes containing offers

NAVFAC ENGINEERING SYSTEMS COMMAND SE

CORE CONSTRUCTION

BLDG 903 YORKTOWN

PO BOX 0030

JACKSONVILLE FL 32212-0030

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

FAX:TEL: TEL: FAX:

N6945021R0041 72

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

N6945021R0041

Section 00 10 00 - Solicitation

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Project

WEAPONS GENERATION FACILITY B EARLY STAR

FFP

Early start site work across 53 acres to prepare for the construction of a large industrial project at Barksdale Air Force Base, LA including the ability to perform:

clearing, grading, and drainage, environmental remediation, building demolition, demolition / relocation of existing utilities, secure fencing, and roadway construction in the Munitions Storage Area (MSA).

FOB: Destination

PSC CD: Y1EC

NET AMT

0002 1 Project OPTION Domestic Water

FFP

0003 1 Project OPTION Natural Gas

FFP

0004 1 Project OPTION Electrical

FFP

0005 1 Project OPTION MEC Removal and Disposal

FFP

Removal and disposal of a Munition of Explosive Concern (MEC) item discovered during the course of UXO Construction Support per the Explosive Safety Submission

0006 1 Project OPTION Underground Utility Removal

FFP

Removal of 200 feet of designed underground utility, 0007 1 Project OPTION Underground Utility Addition

FFP

Addition of 200 feet of underground utility.

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

0001 648 dys. ADC 1 NAVFAC ENGINEERING SYSTEMS

COMMAND SE

HERBERT L. FUSILIER

ROICC BARKSDALE

334 DAVIS AVE WEST STE 103

BARKSDALE LA 71110

318-456-2704

N69450

0002 648 dys. ADC 1 (SAME AS PREVIOUS LOCATION)

0003 648 dys. ADC 1 (SAME AS PREVIOUS LOCATION)

0004 648 dys. ADC 1 (SAME AS PREVIOUS LOCATION)

0005 648 dys. ADC 1 (SAME AS PREVIOUS LOCATION)

0006 648 dys. ADC 1 (SAME AS PREVIOUS LOCATION)

0007 648 dys. ADC 1 (SAME AS PREVIOUS LOCATION)

CLAUSES INCORPORATED BY REFERENCE

52.236-15 Schedules for Construction Contracts APR 1984 52.242-14 Suspension of Work APR 1984 52.246-12 Inspection of Construction AUG 1996

CLAUSES INCORPORATED BY FULL TEXT

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 15 calendar days after the date the Contractor receives the award, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 648 calendar days. The time stated for completion shall include final cleanup of the premises.

(End of clause)

52.211-13 TIME EXTENSIONS (SEP 2000)

Time extensions for contract changes will depend upon the extent, if any, by which the changes cause delay in the completion of the various elements of construction. The change order granting the time extension may provide that the contract completion date will be extended only for those specific elements related to the changed work and that the remaining contract completion dates for all other portions of the work will not be altered. The change order also may provide an equitable readjustment of liquidated damages under the new completion schedule.

(End of clause)

Section 00 21 00 - Instructions

52.204-7 System for Award Management OCT 2018 52.204-16 Commercial and Government Entity Code Reporting AUG 2020 52.204-22 Alternative Line Item Proposal JAN 2017 52.215-1 Instructions to Offerors--Competitive Acquisition JAN 2017 52.215-1 Alt I Instructions to Offerors--Competitive Acquisition (Jan 2017) -

Alternate I

OCT 1997

52.219-4 Notice of Price Evaluation Preference for HUBZone Small Business Concerns

MAR 2020

52.222-5 Construction Wage Rate Requirements--Secondary Site of the Work

MAY 2014

52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction

FEB 1999

52.222-56 Certification Regarding Trafficking in Persons Compliance Plan.

OCT 2020

52.225-12 Notice of Buy American Requirement - Construction Materials Under Trade Agreements

MAY 2014

52.225-12 Alt I Notice of Buy American Requirement - Construction Materials Under Trade Trade Agreements (Feb 2009) - Alternate I

MAY 2014

52.236-28 Preparation of Proposals--Construction OCT 1997 252.215-7010 Requirements for Certified Cost or Pricing Data and Data

Other Than Certified Cost or Pricing Data

JUL 2019

52.211-14 NOTICE OF PRIORITY RATING FOR NATIONAL DEFENSE, EMERGENCY PREPAREDNESS, AND ENERGY PROGRAM USE (APR 2008)

Any contract awarded as a result of this solicitation will be; DO-C2 rated order certified for national defense, emergency preparedness, and energy program use under the Defense Priorities and Allocations System (DPAS) (15 CFR 700), and the Contractor will be required to follow all of the requirements of this regulation. [Contracting Officer check appropriate box.]

(End of provision)

52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a FIRM-FIXED-PRICE contract resulting from this solicitation.

52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States.

The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.-

(c) (c) The amount of the bid guarantee shall be 20% percent of the bid price or $3,000,000, whichever is less.-

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.-

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

52.233-2 SERVICE OF PROTEST (SEP 2006)

(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from:

NAVFAC Southeast CORE Construction Attention: Rebecca Jones Bldg 903 PO Box 30 NAS Jacksonville FL 32212

Herbert Fusilier at herbert.l.fusilier.civ@us.navy.mil Rebecca Jones at rebecca.m.jones75.civ@us.navy.mil

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for-- Site Visit will be conducted during Part II RFP

(c) Participants will meet at--

TBD

52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

https://www.acquisition.gov/browse/index/far

52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (NOV 2020)

(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the provision.

(b) The use in this solicitation of any Defense Federal Acquisition Regulation (48 CFR 2) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.

INSTRUCTIONS TO OFFERORS

The full design for this project will not be completed until the issuance of the Part II amendment. Therefore, proposals will be solicited in a two-part submission for a single solicitation. The submissions will be divided into "Part I" and "Part II" of the solicitation, as follows: The first submission ("Part I") will require Offerors to submit proposals for Factor 1 (Technical Approach), Factor 2 (Experience), Factor 3 (Past Performance) and Factor 4 (Safety). Once the full design of AWUB 14-5001 Weapons Generation Facility Hybrid Early Start Site Work is completed, the solicitation will be amended and proposals from Offerors who submitted proposals for Part I will be requested to provide proposals for Factor 5 (Technical Solution), Factor 6 (Small Business Utilization) and Price (this second submission is hereby referred to as "Part II"). As this is not a two-phase procurement, there will be no down selection between Part I and Part II of the solicitation. In order to be eligible to submit for Part II of the solicitation (Factors5 and 6), the Offeror must have submitted a proposal for Part I of the solicitation (Factors 1, 2, 3 and 4). Any changes to an Offeror's submission for Part I of the solicitation will NOT be permitted after submission of Part I proposals. For further clarity, there will be no opportunity for an Offeror to amend its Part I submission as part of the Part II submission and/or review process.

List of Exhibits & Attachments

Exhibit A – Construction Experience Project Data Sheet

Exhibit B – Past Performance Questionnaire (PPQ)

Exhibit C – Safety Data Sheet

Exhibit D – Small Business Participation and Commitment Strategy (Historical SB Utilization)

Exhibit E – Small Business Participation Commitment Strategy Document

Exhibit F – Small Business Subcontracting Plan Template

Attachment A – ProjNet How To Guide

Beta.SAM.gov Amendments will be posted directly to beta.SAM.gov. The drawings and specifications will be available on beta.SAM.gov under the Attachments/Links section of this solicitation. Additionally, other postings will be made to beta.SAM.gov, such as revised drawings, etc., under the Attachments/Links section of the solicitation. Postings to the Attachments/Links section of beta.SAM.gov do not generate an automated email to Offerors. It is recommended Offerors periodically check the beta.SAM.gov Attachments/Links section of the solicitation to see if additional postings have been made. It is the Offeror’s responsibility to check beta.SAM.gov for all postings.

Additional Information for Offerors

1. Contractor’s performance will be evaluated using the respective contractor performance evaluation report entry system located on the website http://www.cpars.gov/. Prior to commencement of work the contractor is required to provide the government with the name, phone number and e-mail address of the “Contractor’s Representative” that will be responsible for receipt and review of draft performance evaluations prepared by the government in the appropriate system. It is the contractor’s responsibility to keep this contact information current.

2. Information to Offerors: This procurement is solicited on an unrestricted basis with full and open competition.

This acquisition will result in a FIRM-FIXED PRICE (FFP), Design-Bid-Build construction contract for Weapons Generation Facility Early Start Site work.

3. Project magnitude: Between $25,000,000 and $100,000,000

4. Pre-Proposal Inquiries (PPIs): All pre-proposal inquiries (PPIs) must be submitted in writing via the “Bidder Inquiry” in ProjNet at www.projnet.org/projnet <http://www.projnet.org/projnet>. The bidder inquiry key for this solicitation is S7AAYD-47DBEG. All questions shall be submitted at least ten (10) calendar days prior to the closing date of the solicitation in order to permit adequate time to reply to the inquiry. Answers will be made via ProjNet, however, answers do not change the solicitation, any changes to the solicitation will be made via an amendment to the RFP and will be posted https://SAM.gov.

All Offerors are encouraged to register on ProjNet for alerts and to stay abreast of bidder inquiries and Government responses that are posted in reference to this solicitation. Only self-registered users on ProjNet can submit and review inquiries. A “how to” guide has been provided via Attachment A and provided under additional documents in beta.SAM.gov. Those submitting inquiries will receive a system generated e-mail notification when their inquiry has been processed and responded to. It is the Offeror's responsibility to monitor for inquiries and responses.

5. Proposal Delivery Information: Proposal Acceptance Period: 120 calendar days from receipt of final offers.

Part I Proposal Submission Due Date/Time: 12 August 2021; 3:00 PM (Eastern Time)

Electronic Submission:

The Price Proposal and the Non-Price Proposal shall be e-mailed to herbert.l.fusilier.civ@us.navy.mil with copy to rebecca.m.jones75.civ@us.navy.mil and contain “N69450-21-R-0041” in the subject line no later than 3:00 PM Eastern 12 August 2021. The Contract Specialist will try to acknowledge proposal receipt by return e-mail the same day. However, if e-mail acknowledgement is not received, it is the offeror’s responsibility to follow-up to ensure proposal receipt. Proposal file(s) shall be Adobe PDF formatted and under 10MB; the size of an e-mail cannot exceed 10MB. Proposals must be received by electronic mail (e-mail) no later than the date and time stated above.

PROPOSALS SUBMITTED IN RESPONSE TO THIS REQUEST FOR PROPOSAL MUST BE RECEIVED NO

LATER THAN THE DATE AND TIME SPECIFIED. Proposals not received by the time and date specified shall be treated in accordance with FAR 52.215-1 "Instructions to Offerors – Competitive Acquisitions" and may be rejected.

You are highly advised to submit at least one day prior to avoid late submission (See FAR 15.208(b)(1)(i)). The Offeror’s proposal must include all data and information required and must be submitted in accordance with these instructions. LATE SUBMITTALS WILL NOT BE CONSIDERED.

6. Pre-Proposal Conference: See FAR clause 52.236-27 Alt I. Information will be provided in Part II.

4. Reserved: N/A

5. Subcontracting Information: SMALL BUSINESS SUBCONTRACTING PLAN shall be provided with the Factor 6 submission as stated in the “Evaluation Factors” section herein.

6. System for Award Management (SAM): The System for Award Management (SAM) is a Federal Government owned and operated free web site that consolidates the capabilities in Central Contractor Registry (CCR),/Federal Registration(FedReg), Online Representations and Certifications Application (ORCA), and Excluded Parties List System (EPLS). Contractors must be registered in SAM prior to award of a Department of Defense (DoD) contract.

For more information and to complete the electronic representations and certifications, see the SAM website at https://www.sam.gov. A contract cannot be awarded to a contractor that is not registered in SAM. Remember to review the NAICS codes listed in your SAM record and make sure that you have listed the NAICS code for this procurement: NAICS 236220, Commercial and Institutional Building Construction

7. Federal Contractor Program: In accordance with Federal Acquisition Regulation (FAR) 22.1303, any contractor or subcontractor with a contract of $150,000 or more with the Federal Government must take affirmative action to hire and promote qualified targeted veterans which includes, special disabled veterans, veterans of the Vietnam-era, recently separated veterans, and any other veterans who served on active duty during a war or in a campaign or expedition for which a campaign badge has been authorized. Companies MUST file an annual VETS-4212 report, which shows the number of targeted veterans in their work force by job category, hiring location, and number of new hires, including targeted veterans hired during the reporting period and the maximum number and minimum number of employees of such contractor during the period covered by the report. Instructions, information and follow-up assistance is provided at VETS-4212 Internet site athttps://www.dol.gov/vets/vets4212.htm or employers may contact the VETS_4212 Processing Center at (866) 237-0275 or e-mail at VETS4212-customersupport@dol.gov.

8. Women Owned Small Business Program Repository: In accordance with the Small Business Administration’s (SBA) WOSB Federal Contract program regulations, EDWOSBs are required to upload and categorize all required documents in the SBA’s General Login System (GLS) at https://eweb.sba.gov/gls.

9. Incurred Expenses: The Government is not responsible for any costs incurred or associated with preparation and submission of a proposal in response to this solicitation.

10. No Alternate or Multiple Proposals: Neither multiple proposals, nor proposal variations or options, nor alternate or alternative proposals will be considered in the evaluation.

11. Intent to Incorporate Contractor’s Non-Cost/Price (Technical) Proposal

(a) All or part of the successful offeror's Non-cost/price (technical) proposal may be incorporated in any contract resulting from this solicitation. The successful offeror's technical proposal may be incorporated by reference.

Nothing contained in the successful offeror's technical proposal shall constitute a waiver to any other requirement of the contract. In the event of any conflict between the successful offeror's technical proposal and any other requirement of the contract, the conflict shall be resolved in accordance with the Order of Precedence clause.

(b) The successful offeror will provide an updated technical proposal which reflects the results/responses to all exchanges and/or Evaluation Notices (ENs) issued during the negotiation process for incorporation in the contract.

If, after contract award, it is discovered that changes made during negotiations were not incorporated in the SOW and/or technical proposal, such changes to the Contractor's documents shall be considered administrative in nature and shall be made by unilateral modification to the contract, at no change in contract cost or price or other terms and conditions.

BASIS FOR AWARD

1. The Government reserves the right to eliminate from consideration for award any or all offers atany time prior to award of the contract; to negotiate with offerors in the competitive range; and to awardthe contract to the offeror submitting the proposal determined to represent the best value—the proposal most advantageous to the Government, price and other factors considered.

2. The Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)). The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary. In addition, if the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals.

3. The tradeoff process is selected as appropriate for this acquisition. The Government considers it to be in its best interest to allow consideration of award to other than the lowest priced offeror or other than the highest technically rated offeror.

4. As stated in the solicitation, all technical factors when combined are of equal importance to the performance confidence assessment (past performance) rating; and all technical factors and the performance confidence assessment (past performance) rating, when combined approximately equal to price.

5. Any proposal found to have a deficiency in meeting the stated solicitation requirements or performance objectives will be considered ineligible for award, unless the deficiency is corrected through discussions. Proposals may be found to have either a significant weakness or multiple weaknesses that impact either the individual factor rating or the overall rating for the proposal.

EVALUATION FACTORS

1. For Two-Part DBB procurements, Factors 1-4 will be evaluated in Part I, Factors 5-6 will be evaluated in Part II.

Factor 1 will only be rated Acceptable or Unacceptable. In making the best value award decision after Part II, the Government will consider Factors 2-6 and price. The solicitation requires the evaluation of price and the following non-cost/price factors:

Part I:

Factor 1 – Technical Approach Factor 2 – Experience Factor 3 – Past Performance Factor 4 – Safety

Part II:

Factor 5 – Technical Solution Factor 6 – Small Business Utilization

The distinction between experience and past performance is experience pertains to the types of work and volume of work completed by a contractor that are comparable to the types of work covered by this requirement, in terms of size, scope, and complexity. Past performance pertains to both the relevance of recent efforts and how well a contractor has performed on the contracts.

2. The relative order of importance of the non-cost/price evaluation factors is that technical factors (2, 4, 5, and 6) are equal to each other and when combined are equal importance to the performance confidence assessment (Factor 3 – Past Performance). When the proposal is evaluated as a whole, the technical factors and past performance/performance confidence assessment factor combined (i.e., the non-cost/price evaluation factors) are approximately equal to price.

The importance of price will increase if the Offerors’ non-price proposals are considered essentially equal in terms of overall quality, or if price is so high as to significantly diminish the value of a non-price proposal’s superiority to the Government. Award will be made to the responsible Offeror(s) whose offer conforms to the solicitation and represents the best value to the Government, price and nonprice factors considered.

3. Basis of Evaluation and Submittal Requirements for Each Factor.

(a) Price (Part I):

Price proposals shall be submitted separately from the technical proposals. Provide one (1) electronic copy as an Adobe PDF file of the solicitation submittal requirements for the pricing identified below.

(1) Solicitation Submittal Requirements:

i. Cover letter with the following information:

Authorized negotiator’s (POC) name POC telephone number POC email address CAGE code DUNS number TIN (taxpayer ID number) Business Size (Large or Small Business)

ii. Executed Standard Form (SF) 1442. Offeror shall insert its company name, address, DUNS Number, CAGE Code, and Federal Tax ID number in Block #14, telephone number in Block #15, acknowledge all amendments (if applicable) in Block #19, name and title of person authorized to sign in Block #20A, signature in Block #20B, and offer date in Block #20C of the SF 1442. If proposing as a joint venture, Offeror shall provide the DUNS number for all members of the joint venture.

iii. SF 1442 Schedule of Prices for Contract Line Items Numbers. Complete the Section 00 10 00 CLIN SF 1442 Schedule of Prices.

iv . Bonding Letter. Offeror shall submit a letter from its Bonding Company indicating the offeror’s bonding limit for a single project and aggregate bonding capacity. Offerors must have a single award bonding capacity of $25,000,000 and the ability to bond multiple projects.

v. SAM registration. Offeror shall ensure current registration on the SAM Website, www.sam.gov, including Annual Representations and Certifications are complete and updated for this procurement.

If a Representation or Certification required by Section 00600 of the RFP is not provided in SAM, include the representation or certification in your price proposal.

vi. FAPIIS Certification. Offeror shall ensure Federal Awardee Performance and Integrity Information System (FAPIIS) Certification as required by FAR 52.209-7, Information Regarding Responsibility Matters.

vii. Veteran’s Employment & Training Service (VETS). Offeror shall ensure a current VETS- 4212 (previously VETS-100 and/or VETS-100-A) report has been submitted to the Department of Labor website, http://www.dol.gov/vets/vets4212.htm, if the Offeror is required to submit. An email confirmation of submission can be requested and received by the Offeror from the DOL website and is to be submitted in the price proposal. If the Offeror is not required to submit a report to VETS-4212, include a brief statement stating that the Offeror is not required to submit a report and state the reason. Visit the VETS-4212 website for details concerning if your company is required to submit a VETS-4212 report and to request an email confirmation of submission.

Note: The SAM, FAPIIS and VETS-4212 registrations must be in the name and address, CAGE, and DUNS of the offeror identified on the SF1442.

(2) Basis of Evaluation: Offerors will be evaluated on the information required to be submitted in the solicitation submittal requirements identified above.

(b) Non-Price Factors (Part I):

Provide one (1) electronic copy as an Adobe PDF file of the solicitation submittal requirements for Factors 1-4 identified below. Entire proposal shall not exceed 50 pages in length (front side only) utilizing a minimum Arial Font of 12 or comparable size font for Factors 1-5 unless otherwise specified in the factor. Title page, table of contents, dividers, and any pages specifically excluded under each factor do not count towards the total page count and should not be numbered. Any pages beyond the first 50 pages submitted will not be evaluated. The 50 page limitation does not include Joint Venture Agreement, CPARS evaluations, and/or past performance questionnaires.

(1) Factor 1 – Technical Approach:

(a) Solicitation Submittal Requirements:

The composition and management of the firms proposed as the construction team for this contract will be evaluated in this factor.

The Offeror shall submit the following information:

(1) Provide a narrative describing the proposed primary firms for this contract and the rationale for proposing this arrangement. Provide the role, responsibilities, and contractual relationships between the various firms (see FAR Subpart 9.6). The narrative shall also include a simple organizational chart that clearly identifies the lines of authority between the entities. If the experience of an entity is being claimed in Factor 2, that entity must be named in the above narrative and organizational chart.

The technical approach narrative shall be limited to one (1) double-sided page (or two (2) single-sided pages) including the organizational chart. The information requested in item #2 below is not included in this page limitation.

(2) In addition to the narrative, the Offeror shall submit a signed copy of a joint venture agreement, partnership agreement, teaming agreement, approved mentor protégé agreement (MPA), or letter of commitment for each member of the Offeror’s team identified above (e.g., joint venture member, partner, team member, subcontractor, parent company, subsidiary, or other affiliated company, etc.).

(b) Basis of Evaluation:

The assessment of the Offeror’s technical approach will be used as a means to evaluate the organizational structure and teaming relationships proposed by the Offeror. This factor will be rated on an Acceptable or Unacceptable basis.

(2) Factor 2 – Experience:

(a) Solicitation Submittal Requirements: The Offeror shall submit the following information:

(1) Construction Experience:

Submit a minimum of 3 (three) and a maximum of five (5) relevant construction projects for the Offeror that best demonstrates your experience as the prime contractor on relevant projects that are similar in size, scope, and complexity to the RFP. For purposes of this evaluation, a relevant project is further defined as includes building demolition, rough grading, installation of site features and utilities within a secure area, and with a contract value of $10,000,000, or greater.

In addition to the above, submit a minimum of one (1) and a maximum of three (3) construction projects that demonstrate relevant experience with environmental remediation of Aqueous Fill Forming Foam (AFFF) in groundwater and unexploded ordnance (UXO) or Munitions and Explosives of Concern (MEC). If the Offeror does not have relevant experience in both AFFF remediation and UXO clearance within the same project, the Offeror may submit relevant experience in two separate projects, but experience in both environmental remediation must be demonstrated. If the Offeror does not have relevant experience installing active vehicle barriers, the Offeror may submit relevant experience from a subcontractor they plan to use. The project(s) that demonstrate experience with AFFF and UXO experience is not required to meet the minimum contract value stated above.

Projects submitted for the Offeror to meet either relevancy, shall be completed within the past five (5) years of the date of issuance of this RFP.

A project is defined as a construction project performed under a single task order or contract. For multiple award and indefinite delivery/indefinite quantity type contracts, the contract as a whole shall not be submitted as a project;

rather Offerors shall submit the work performed under a task order as a project.

The attached Construction Experience Project Data Sheet (Attachment A) is MANDATORY and SHALL be used to submit project information. If the same project is being used to demonstrate construction experience, submit separate Project Data Sheets for construction. Except as specifically requested, the Government will not consider information submitted in addition to this form. Individual blocks on this form may be expanded; however, total length for each project data sheet shall not exceed one (1) double-sided page (or two (2) single-sided pages).

For all submitted projects, the description of the project shall clearly describe the scope of work performed and the relevancy to the project requirements of this RFP (i.e., unique features, area, construction methods).

If the Offeror is a Joint Venture (JV), relevant project experience should be submitted for projects completed by the Joint Venture entity. If the Joint Venture does not have shared experience, projects may be submitted for the Joint Venture members. Offerors who fail to submit experience for all Joint Venture members may be rated lower.

Offerors are still limited to a total of five (5) projects combined.

If an Offeror is utilizing experience information of affiliates/subsidiaries/parent/LLC/LTD member companies (name is not exactly as stated on the SF1442), the proposal shall clearly demonstrate that the affiliate/subsidiary/parent firm will have meaningful involvement in the performance of the contract.

The Offeror may utilize experience of a subcontractor that will perform major or critical aspects of the requirement to demonstrate construction experience under this evaluation factor. The Offer must provide a letter of commitment and an explanation of the meaningful involvement that the subcontractor will have in performance of this contract.

The basis of evaluation will include the Offeror’s demonstrated experience and depth of experience in performing relevant construction projects as defined in the solicitation submittal requirements. The assessment of the Offeror’s relevant experience will be used as a means of evaluating the capability of the Offeror to successfully meet the requirements of the RFP. Offerors clearly demonstrating relevant experience in a single project for construction and both remediation types may be rated higher. The Government will only review eight projects for construction. Any projects submitted in excess of the five (5) for Construction Experience and three (3) for Remediation Experience will not be considered.

(3) Factor 3 – Past Performance:

If a completed Contractor Performance Assessment Reporting System (CPARS) evaluation is available, it shall be submitted with the proposal for each project included in Factor 2 for construction experience and remediation experience. If there is not a completed CPARS evaluation then submit Past Performance Questionnaires (Attachment B) for each project included in Factor 2 for Construction Experience and Remediation Experience. The Offeror should provide completed Past Performance Questionnaires (PPQ) in the proposal. Offerors shall not incorporate by reference into their proposal PPQs previously submitted for other RFPs. However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation.

If the Offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the Offeror shall complete and submit with the proposal the first page of the PPQ, which will provide contract and client information for the respective project(s). The Government may make reasonable attempts to contact the client noted for that project(s) to obtain the PPQ information. However, Offerors should follow-up with clients/references to help ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government’s point of contact, Herb Fusilier at herbert.l.fusilier.civ@us.navy.mil.

Offerors may provide any information on problems encountered and the corrective actions taken on projects submitted under Factor 2 – Experience. Offerors may also address any adverse past performance issues.

Explanations shall not exceed two (2) double-sided pages (or four (4) single-sided pages) in total.

The Government reserves the right to contact references for verification or additional information. The Government’s inability to contact any of the Offeror’s references or the references unwillingness to provide the information requested may affect the Government’s evaluation of this factor.

Performance award or additional information submitted will not be considered.

This evaluation will consider how well the Offeror’s team performed on relevant projects submitted under Factor 2 – Experience and may also consider past performance on other projects currently documented in known sources.

The Government will consider the recency and relevance of the information, the source of the information, context of the data, and general trends in the Contractor’s performance. This evaluation is separate and distinct from the Contracting Officer’s responsibility determination. The assessment of the Offeror’s team’s past performance will be used as a means of evaluating the Offeror’s team’s probability to successfully meet the requirements of the RFP.

Offerors lacking relevant past performance history will receive a NEUTRAL Confidence rating.

(4) Factor 4 – Safety

The Offeror shall submit the following information on Exhibit C: The Days Away from Work, Restricted Duty, or Job Transfer (DART) Rate; and Total Case Rate (TCR) for the specified five (5) Calendar Years (CY), as well as a safety narrative, as described further below. For a partnership or joint venture, the Offeror shall submit separate DART rates and TCR for the specified five (5) CY for each contractor who is part of the partnership/joint venture;

however, only one safety narrative is required. Any fatalities experienced within this 5-year timeframe must be explained in detail, to include root cause and corrective actions.

NOTE: DART and TCR shall not be submitted for subcontractors.

1. DART Rate: Submit five (5) previous complete calendar years’ [CY2020, CY2019, CY2018, CY2017, and CY2016] worth of data (not an overall average). If the Offeror has no DART rate, for any year, affirmatively state so and explain why. Should a negative trend occur above moderate risk levels, an acceptable/detailed explanation is required that includes any corrective actions taken for improvement.

a. DART cases include injuries or illnesses resulting in death, days away from work, and/or restricted work or transfer to another job days beyond the day of injury/illness.

b. Calculation of DART rate: Multiply the total number of DART cases by 200,000, and then divide by the number of employee labor hours worked.

DART RATE = Number of DART Incidents x 200,000 Total Number of Employee Labor Hours Worked

2. TCR Rate: Submit five (5) previous complete calendar years’ [CY2020, 2019, 2018, 2017, and 2016] worth of data (not an overall average). If the Offeror has no TCR rate, for any year, affirmatively state so and explain why.

Should a negative trend occur above moderate risk levels, an acceptable/detailed explanation is required that includes any corrective actions taken for improvement.

a. TCR cases include injuries or illnesses resulting in death, days away from work, restricted work or transfer to another job days beyond the day of injury/illness, medical treatment beyond first aid, or loss of consciousness.

b. Calculation of TCR rate: Multiply the total number of TCR incidents by 200,000, and then divide by the number of employee labor hours worked.

TCR RATE = Number of TCR Incidents x 200,000 Total Number of Employee Labor Hours Worked

3. Technical Approach to Safety: Submit a narrative that addresses the following:

a. Describe the Offeror’ s approach to implementing and executing a Safety Management System (SMS) including Management/Leadership involvement, Employee involvement, Hazard prevention, Hazard control, Worksite analysis, and Safety and health training, to include the standard(s) used to benchmark the SMS.

b. Describe the evaluation process used to select potential subcontractors.

c. Describe the processes of how the Offeror will oversee safety compliance of subcontractors at all levels throughout performance of the contract (to include the Offeror’s own in-house workforce).

d. The Technical Approach to Safety narrative shall be limited to two (2) single-sided pages or one (1) double-sided page.

4. The Government reserves the right to review other available sources (public/Government internal) of information.

These may include but are not limited to OSHA data, NAVFAC’s Contractor Incident Reporting System (CIRS), Contractor Performance Assessment Reporting System (CPARS), Electronic Contract Management System (eCMS), etc.

The Government is seeking to determine that the Offeror has consistently demonstrated a commitment to safety and that the Offeror plans to properly manage and implement safety procedures for itself and its subcontractors. The evaluation will collectively consider the DART rate, TCR, Technical Approach to Safety, and other sources of information available to the Government as part of such collective evaluation. The board will evaluate the DART rates and TCR to determine if the Offeror has demonstrated a history of safe work practices taking into account any negative trends and extenuating circumstances that impact the rating.

1. DART Rate: The board will evaluate trends over the last five years considering changes that take it from one risk level (or more) to the next up or down. Negative trends occurring above moderate risk levels require the offeror to provide a detailed explanation that includes any corrective actions taken for improvement.

a. Missing data without an explanation is considered a deficiency.

b. Declining trends that push the risk levels from Moderate Risk (MR) or higher to Low Risk (LR) or Very Low Risk (VLR) would indicate a strength.

c. An increasing DART rate trend could be considered a weakness (i.e. MR or better to High Risk (HR) or Extremely High Risk EHR)) if an acceptable explanation is not provided for any trends that rise above Moderate.

d. This chart correlates the DART rate to the level of risk:

Risk DART Rate Very Low Risk Less Than 1.0 Low Risk From 1.0 to 1.99 Moderate Risk From 2.0 to 2.99 High Risk From 3.0 to 4.0 Extremely High Risk Greater than 4.0

2. TCR Rate: The board will evaluate trends over the last five years considering changes that take it from one risk level (or more) to the next up or down. Negative trends occurring above moderate risk levels require the offeror to provide a detailed explanation that includes any corrective actions taken for improvement.

a. Missing data without an explanation is considered a deficiency.

b. Declining trends that push the risk levels from Moderate Risk (MR) or higher to Low Risk (LR) or Very Low Risk (VLR) would indicate a strength.

c. An increasing TCR rate trend could be considered a weakness (i.e. MR or better to High Risk (HR) or Extremely High Risk EHR)) if an acceptable explanation is not provided for any trends that rise above Moderate.

d. This chart correlates the TCR rate to the level of risk:

Risk TCR Rate Very Low Risk Less Than 2.49 Low Risk From 2.5 to 3.49 Moderate Risk From 3.5 to 4.49 High Risk From 4.5 to 5.99 Extremely High Risk Greater than 6.0

3. The Technical Approach to Safety Narrative. To determine the degree to which the Offeror:

a. Describes a viable SMS that addresses elements; such as Management/Leadership involvement, Employee involvement, Hazard prevention, Hazard control, Worksite analysis, and Safety and health training, to include the standard(s) used to benchmark the SMS.

b. Describes a methodical process of evaluating subcontractor’s safety performance in their selection process.

c. Describes a logical management plan to hold themselves and their subcontractors accountable for adhering to the safety requirements of the contract.

d. The Technical Approach to Safety narrative shall be limited to two (2) single-sided pages or one (1) double-sided page. Information on pages beyond this will not be considered.

4. The Government reserves the right to review other available sources (public/Government internal) of information.

These may include but are not limited to OSHA data, NAVFAC’s Contractor Incident Reporting System (CIRS), Contractor Performance Assessment Reporting System (CPARS), Electronic Contract Management System (eCMS), etc.

(c) Non-Price Factors (Part II):

All ratings from Part I will be carried over into Part II.

(5) Factor 5 – Technical Solution

(a) Solicitation Submittal Requirements:

A. Provide a detailed narrative describing the technical solution to the project that meets the requirements of the RFP and that demonstrates the Offeror’s ability to successfully perform this contract at Barksdale AFB, Barksdale, MS. Include the following:

1. A project execution plan that the Offeror will implement to develop the pre-construction storm water control system(s), as required to facilitate the grading and fill activities. The narrative shall include description of:

a) The development new and use of the existing permanent stormwater features and piped storm water discharge system to maintain stormwater controls until site grading is complete;

b) Dewatering activities;

c) The process for moisture conditioning of the fill material required, whether at the borrow source or on site;

d) Proposed utilization and maintenance of the existing adjacent roadways;

e) The process to be used to verify the grades indicated on the drawings are accomplished; and,

f) The plan for managing the required testing of the embankments.

The Site Fill, Grading and Stormwater Management narrative shall be limited to three (3) pages.

2. Describe the plan the Offerer will implement to ensure the proper security protocols are met and base operations are not impacted during the fence relocation and construction period. The narrative shall include description of:

a) The proposed plan to manage the initial construction of…