ACQR5361737

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Solcitation Number N69450-18-R-0905 Explosive Handling Wharf 1 Repairs Phases 2 and 3 Design-Bid-Build at Naval Submarine Base Kings Bay, Georgia

The purpose of this amendment is to provide and incorporates the follow ing:

1. Various changes to Division 00 PROPOSAL FORMS & DOCUMENTS.

2. Changes to the specifications.

Amendment No. 0008 is continued on Page 2

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 14-Aug-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X N6945018R0905

X 9B. DATED (SEE ITEM 11)

28-Jun-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

14-Aug-2018

CODE

NAVFAC SOUTHEAST

SOUTH ATLANTIC

BLDG 903, PO BOX 30

NAS JACKSONVILLE

JACKSONVILLE FL 32212-0030

N69450 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N6945018R0905

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

The following items are applicable to this modification:

SUMARRY OF CHANGES (REVISED)

SUMMARY OF CHANGES

The following have been added by full text:

AMENDMENT NO. 0008

Solcitation Number N69450-18-R-0905 Explosive Handling Wharf 1 Repairs Phases 2 and 3 Design-Bid-Build at Naval Submarine Base Kings Bay, Georgia

Amendment No. 0008 has been uploaded 14 August 2018 to this solicitation (N6945018R0905) on NECO, accessible at https://www.neco.navy.mil/ and is hereby incorporated into this solicitation.

The purpose of this amendment is to provide and incorporates the following:

1. Various changes to Division 00 PROPOSAL FORMS & DOCUMENTS.

2. Changes to the specifications.

1. CHANGES TO DIVISION 00 PROCUREMENT AND CONTRACTING REQUIREMENTS

SECTION 00010 – SOLICITATION CONTRACT FORM (SF 1442)

Block 11. Revised to add “1270”.

SECTION 00202 – SUBMISSION REQUIREMENTS AND EVALUATION FACTORS FOR AWARD

I. INTRODUCTION

B. DESCRIPTION OF ACQUISITION

Change from:

4. The contract completion schedule is as follows:

CLIN 0001 (Phase 2) - 730 calendar days from date of contract award CLIN 0002 (Phase 3 Option 1) - 540 calendar days from date of contract option award

To:

4. The contract completion schedule is a total of 1270 calendar days as shown below. Upon award of CLIN 0002 (Phase 3) the CLIN 0002 completion date will be established as 540 calendar days from the completion date of CLIN 0001 (Phase 2) for a total completion schedule of 1270 calendar days.

CLIN 0002 (Phase 3 Option 1) - 540 calendar days from date of contract option award

SECTION 00700 – CONTRACT CLAUSES

FAR 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) is revised.

FAR 52.222-62 is added.

2. CHANGES TO THE SPECIFICATIONS

SECTION 01 14 00.00 25 WORK RESTRICTIONS

1.2 Special Scheduling Requirements

N6945018R0905

Delete paragraph c. in its entirety and replace it with the following:

c. "The Contractor shall submit a detailed work sequencing plan to the Contracting Officer for approval before work begins. This sequencing plan shall consist of a detailed description of the sequence of work to successfully accomplish the awarded scope with ongoing repairs to Phase 1 and the scope of work for Phases 2 and Phase 3, if awarded. The plan shall also include details of blasting, preparation, and coating operations of structural steel members."

3. The hour and date specified for receipt of offers remains unchanged.

4. All other terms and conditions of the solicitation are unchanged and remain in effect.

5. Acknowledgement of Amendment No. 0008 is required with your proposal.

SECTION 00010 - SOLICITATION CONTRACT FORM

The contractor period of performance end 1270 has been added.

SECTION 00700 - CONTRACT CLAUSES

The following have been added by reference:

52.222-62

The following have been modified:

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 1270 days from date of contract award. The contract completion schedule for each CLIN is as follows:

CLIN 0002 (Phase 3 Option 1) - 540 calendar CLIN 0002 days from date of contract option award

Upon award of CLIN 0002 (Phase 3) the CLIN 0002 completion date will be established as 540 calendar days from the completion date of CLIN 0001 (Phase 2) for a total completion schedule of 1270 calendar days.

The time stated for completion shall include final cleanup of the premises.

Note: Contract award or contract option award is notice to proceed.