Document 3 Amendment No. 0004

View the file

Other files

File Type Posted
_1_Amendment_0006_PPI_Log_.pdf PDF
_N6945014R1261_Amendment_0006_.pdf PDF
_1_Amendment_0005_PPI_Log_.pdf PDF
_N6945014R1261_Amendment_0005_.pdf PDF
_1_Amendment_0004_PPI_Log_.pdf PDF
_5_Amendment_0004_Drawings_Vol_1of3_AD101_.pdf PDF
_4_Amendment_0004_Drawings_Vol_1of3_5-GEOTECHNICAL_.pdf PDF
_10_Amendment_0004_BLDG_856_SOUTH_ELEVATION_.JPG JPG image
_8_Amendment_0004_Drawings_Vol_2of3_V2_C702_.pdf PDF
_6_Amendment_0004_Drawings_Vol_1of3_ED014_.pdf PDF
_11_Amendment_0004_BLDG_856_WEST_ELEVATION_.JPG JPG image
_7_Amendment_0004_Drawings_Vol_2of3_V2_T103_.pdf PDF
_N6945014R1261_Amendment_0004_.pdf PDF
_2_Amendment_0004_Vol_1of3_Specs_Section_01_32_17_00_25_.pdf PDF
_9_Amendment_0004_BLDG_856_NORTH_ELEVATION_.JPG JPG image
_N6945014R1261_Amendment_No_0003_.pdf PDF
_1_Amendment_0003_PPI_Log_.pdf PDF
_N6945014R1261_Amendment_0002_.pdf PDF
_1_Amendment_0002_PPI_Log_.pdf PDF
_3_Amendment_0002_Section_01_50_00.00_25_Dwg_PH100_Hydrants_.pdf PDF
_2_Amendment_0002_Section_01_32_17.00_25_.pdf PDF
_4_Amendment_0002_Section_02_41.00_Attachment_.pdf PDF
_N6945014R1261_1_Pre_Proposal_Conf_SiteVisit_Agenda_wMap_.pdf PDF
_N6945014R1261_3_Airfield_Attendance_Roster_.pdf PDF
_N6945014R1261_Amendment_0001_.pdf PDF
_N6945014R1261_2_Pre_Proposal_Conf_SiteVisit_Mins_.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

P-8A Airfield & Lighting Rprs (Vol 1 of 3) Work Order No. 1174318 NAS Jacksonville, FL

SECTION 01 50 00.00 25

TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

10/11

NAVFAC SE VERSION

PART 1 GENERAL

1.1 SUMMARY

Requirements of this Section apply to, and are a component of, each section of the specifications.

1.2 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN WATER WORKS ASSOCIATION (AWWA)

AWWA C511 (2007) Standard for Reduced-Pressure Principle Backflow Prevention Assembly

FOUNDATION FOR CROSS-CONNECTION CONTROL AND HYDRAULIC RESEARCH

(FCCCHR)

FCCCHR List (continuously updated) List of Approved Backflow Prevention Assemblies

FCCCHR Manual (1988e9) Manual of Cross-Connection Control

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 241 (2009) Standard for Safeguarding Construction,Alteration, and Demolition Operations

NFPA 70 (2011; Errata 2 2012) National Electrical Code

U.S. FEDERAL AVIATION ADMINISTRATION (FAA)

FAA AC 70/7460-1 (2007; Rev K) Obstruction Marking and Lighting

U.S. FEDERAL HIGHWAY ADMINISTRATION (FHWA)

MUTCD (2009) Manual of Uniform Traffic Control Devices

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.

SECTION 01 50 00.00 25 Page 1

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

Construction site plan; G

Traffic control plan; G

SD-03 Product Data

Backflow preventers; G

SD-06 Test Reports

Backflow Preventer Tests; G

SD-07 Certificates

Backflow Tester Certification; G

Backflow Preventers Certificate of Full Approval

1.4 CONSTRUCTION SITE PLAN

Prior to the start of work, submit a site plan showing the locations and dimensions of temporary facilities (including layouts and details, equipment and material storage area (onsite and offsite), and access and haul routes, avenues of ingress/egress to the fenced area and details of the fence installation. Identify any areas which may have to be graveled to prevent the tracking of mud. Indicate if the use of a supplemental or other staging area is desired. Show locations of safety and construction fences, site trailers, construction entrances, trash dumpsters, temporary sanitary facilities, and worker parking areas.

1.5 BACKFLOW PREVENTERS CERTIFICATE

Certificate of Full Approval from FCCCHR List, University of Southern California, attesting that the design, size and make of each backflow preventer has satisfactorily passed the complete sequence of performance testing and evaluation for the respective level of approval. Certificate of Provisional Approval will not be acceptable.

1.5.1 Backflow Tester Certificate

Prior to testing, submit to the Contracting Officer certification issued by the State or local regulatory agency attesting that the backflow tester has successfully completed a certification course sponsored by the regulatory agency. Tester must not be affiliated with any company participating in any other phase of this Contract.

1.5.2 Backflow Prevention Training Certificate

Submit a certificate recognized by the State or local authority that states the Contractor has completed at least 10 hours of training in backflow preventer installations. The certificate must be current.

SECTION 01 50 00.00 25 Page 2

PART 2 PRODUCTS

2.1 TEMPORARY SIGNAGE

2.1.1 Bulletin Board

Immediately upon beginning of work, provide a weatherproof glass-covered bulletin board not less than 36 by 48 inches in size for displaying the Equal Employment Opportunity poster, a copy of the wage decision contained in the contract, Wage Rate Information poster, and other information approved by the Contracting Officer. Locate the bulletin board at the project site in a conspicuous place easily accessible to all employees, as approved by the Contracting Officer.

2.1.2 Project and Safety Signs

The requirements for the signs, their content, and location are as specified in Section 01 58 00.00 25 PROJECT IDENTIFICATION.. Erect signs within 15 days after receipt of the notice to proceed. Correct the data required by the safety sign daily, with light colored metallic or non-metallic numerals.

2.2 TEMPORARY TRAFFIC CONTROL

2.2.1 Haul Roads

At contractors expense construct access and haul roads necessary for proper prosecution of the work under this contract. Construct with suitable grades and widths; sharp curves, blind corners, and dangerous cross traffic are be avoided. Provide necessary lighting, signs, barricades, and distinctive markings for the safe movement of traffic. The method of dust control, although optional, must be adequate to ensure safe operation at all times. Location, grade, width, and alignment of construction and hauling roads are subject to approval by the Contracting Officer. Lighting must be adequate to assure full and clear visibility for full width of haul road and work areas during any night work operations.

2.2.2 Barricades

Erect and maintain temporary barricades to limit public access to hazardous areas. Whenever safe public access to paved areas such as roads, parking areas or sidewalks is prevented by construction activities or as otherwise necessary to ensure the safety of both pedestrian and vehicular traffic barricades will be required. Securely place barricades clearly visible with adequate illumination to provide sufficient visual warning of the hazard during both day and night.

2.2.3 Fencing and Barricades

2.2.3.1 Fencing

Fencing will be required at various locations on the project site during the various phases of work associated with this project.

Aircraft and aircraft engines are subject to FOD from debris and waste material lying on airfield pavements. Remove all such material that may appear on operational aircraft pavements due to the Contractor's operations. The Contractor shall install and maintain a temporary fencing at the Contractor's expense to control the spread of FOD potential debris.

SECTION 01 50 00.00 25 Page 3

The fencing shall consist of a 6-foot fence covered with a 8-foot fabric designed to stop the debris; anchor the fence and fabric with sandbags to prevent displacement by winds or jet/prop blasts. Use 8-foot wide fabric and put 2 feet of fabric under sandbags. The fabric shall be located inside the fence. The fence shall be located on the airfield side of the project area and 20 feet past the airfield perimeter. The obstruction fence shall be erected using frangible construction methods.

One acceptable method is to drive pipes in the grassed areas 2 feet and to use base plates on pavement and securing them with sand bags. The obstruction fence shall have self-powered obstruction lights (Contractor supplied and maintained generator or battery - these lights will not be connected to the airfield lighting system) with red lenses spaced every 20 feet. Use 60W bulbs minimum or LEDs that are at least equal to 60W bulbs in brightness.

The Contractor shall have the lights turned on during the hours between sunset and sunrise and anytime the airfield lighting is on (i.e., cloudy or foggy weather). Remove barricade when no longer required.

This type of fencing is required at the Contractor's laydown/storage area(s) and on the east and west sides of hangar 1000 as detailed on the drawings. The contractor, at their discretion, may install security fencing on the airfield, which shall meet the requirements described above.

Fencing shall be removed by the contractor upon completion of the requirement.

2.2.3.2 Barricades

During phases 2B and 3 the Contractor shall provide and maintain orange barricades to delineate portions of the airfield being closed at the phase transition from 2A to 2B and 2B to 3. This requirement is in addition to requirements put forth by the Federal Aviation Authority and NAVAIR

51-50AAA-2.

Barricades shall be low-profile, water filled and placed with a 6-foot space between barricades. The barricades will be mounted with red obstruction lights (as described above) and spaced so that a single light is on each barricade. Lights will be self-powered as described above and set as flashing beacons.

Barricades shall be removed by the contractor upon completion of the requirement.

2.2.4 Temporary Wiring

Provide temporary wiring in accordance with NFPA 241 and NFPA 70, Article 305-6(b), Assured Equipment Grounding Conductor Program. Include frequent inspection of all equipment and apparatus.

2.2.5 Backflow Preventers

Reduced pressure principle type conforming to the applicable requirements AWWA C511. Provide backflow preventers complete with 150 pound flanged cast iron, bronze or brass mounted gate valve and strainer, 304 stainless steel or bronze, internal parts. The particular make, model/design, and size of backflow preventers to be installed must be included in the latest edition of the List of Approved Backflow Prevention Assemblies issued by

SECTION 01 50 00.00 25 Page 4 the FCCCHR List and be accompanied by a Certificate of Full Approval from FCCCHR List. After installation conduct Backflow Preventer Tests and provide test reports verifing that the installation meets the FCCCHR Manual Standards.

PART 3 EXECUTION

3.1 EMPLOYEE PARKING

Contractor employees will park privately owned vehicles in an area designated by the Contracting Officer. This area will be within reasonable walking distance of the construction site. Contractor employee parking must not interfere with existing and established parking requirements of the government installation.

3.2 AVAILABILITY AND USE OF UTILITY SERVICES

3.2.1 Temporary Utilities

a. Utility Connection Permit

1. In order to receive temporary utility service, the customer must first complete a Utility Connection Permit provided by the Government.

No utilities will be provided until this permit has been completed and approved.

b. Electrical

1. For overhead temporary service, the Government will provide installation and removal of an overhead secondary service and meter, at an existing secondary source. For an underground service, the Government will connect and disconnect the customer's service cable to the Government's existing underground facilities, including installation and removal of the meter.

2. Service may be single phase or three phase, 60 hertz, at the available standard secondary distribution voltage. This service is available only when the Government has existing capacity in lines, transformers, and other equipment at the requested point of delivery.

3. For overhead temporary service, the customer shall provide a sturdy and adequate service drop support, complete with service entrance and approved meter enclosure, to accommodate the Government's service drop and meter in accordance with the NESC. In an underground area, a pedestal with approved meter socket shall be provided by the customer to accommodate the meter, and the customer's service cable shall be installed up to the Government provided facilities. An adequate amount of service cable shall be left available for the Government to pull into the hand hole or transformer for connection. Please refer to form PWD-UEM-2000 for guidance.

4. If specific electrical service other than that stated above is required, the Government, at the customer's request, will determine its feasibility and may provide such service based on the estimated cost of purchasing, installing, and removing such electrical equipment. This estimated cost is payable in advance to the Government and will be subject to adjustment or refund based on actual costs.

5. The customer's installation shall satisfy all the requirements of

SECTION 01 50 00.00 25 Page 5 the National Electrical Code. Customer materials may be new or used, must be adequate for the required usage, not create unsafe conditions, and not violate applicable codes and standards.

c. Water

1. If the Contractor needs temporary water service, he will have to provide his own water meter and backflow preventer for said service.

The preferred method for obtaining temporary water is connecting to the nearest fire hydrant. If a hydrant is not available, the Contractor can wet tap or tee into an existing potable water main or service line to obtain temporary water and is responsible for all costs associated with tapping and piping the service to his facility. The Contractor will be responsible for properly capping the connection and removing all equipment and piping at the end of the contract. All plumbing work will be compliant with all local, state, and federal plumbing codes.

d. Sewer

1. The preferred method for temporary sewer service is an above ground self contained holding tank as tapping into an existing sewer line can be cost prohibitive based on availability and distance to a connecting point. All equipment, piping, and installation will be at the Contractor's expense, as well as the periodic pumping and disposing of the holding tank contents.

3.2.2 Payment for Utility Services

a. Unless otherwise provided in the contract, the amount of each utility service consumed will be charged to or paid for by the Contractor at prevailing rates charged to the Government or, where the utility is produced by the Government, at reasonable rates determined by the Contracting Officer. Carefully conserve any utilities furnished without charge.

b. Reasonable amounts of the above stated utilities will be made available to the Contractor at the prevailing rates. The customer must complete the Private Party Set Up Account Form provided by the Government to establish a billing account for utility consumption.

3.2.3 Advance Deposit

An advance deposit for utilities consisting of an estimated month's usage or a minimum of $50.00 will be required. The last monthly bills for the fiscal year will normally be offset by the deposit and adjustments will be billed or returned as appropriate. Services to be rendered for the next fiscal year, beginning 1 October, will require a new deposit. Notification of the due date for this deposit will be mailed to the Contractor prior to the end of the current fiscal year.

3.2.4 Final Meter Reading

Before completion of the work and final acceptance of the work by the Government, notify the Contracting Officer, in writing, 5 working days before termination is desired. The Government will take a final meter reading, disconnect service, and remove the meters. Then remove all the temporary distribution lines, meter bases, and associated paraphernalia.

Pay all outstanding utility bills before final acceptance of the work by the Government.

SECTION 01 50 00.00 25 Page 6

3.2.5 Telephone

Make arrangements and pay all costs for telephone facilities desired.

3.2.6 Obstruction Lighting of Cranes

Provide a minimum of 2 aviation red or high intensity white obstruction lights on temporary structures (including cranes) over 100 feet above ground level. Light construction and installation must comply with FAA AC 70/7460-1. Lights must be operational during periods of reduced visibility, darkness, and as directed by the Contracting Officer.

3.2.7 Fire Protection

Provide temporary fire protection equipment for the protection of personnel and property during construction. Remove debris and flammable materials daily to minimize potential hazards.

3.3 TRAFFIC PROVISIONS

3.3.1 Maintenance of Traffic

a. Conduct operations in a manner that will not close any thoroughfare or interfere in any way with traffic on railways or highways except with written permission of the Contracting Officer at least 15 calendar days prior to the proposed modification date, and provide a Traffic Control Plan detailing the proposed controls to traffic movement for approval.

The plan must be in accordance with State and local regulations and the MUTCD, Part VI. Make all notifications and obtain any permits required for modification to traffic movements outside Station's jurisdiction.

Contractor may move oversized and slow-moving vehicles to the worksite provided requirements of the highway authority have been met.

b. Conduct work so as to minimize obstruction of traffic, and maintain traffic on at least half of the roadway width at all times. Obtain approval from the Contracting Officer prior to starting any activity that will obstruct traffic.

c. Provide, erect, and maintain, at Contractor's expense, lights, barriers, signals, passageways, detours, and other items, that may be required by the Life Safety Signage, overhead protection authority having jurisdiction.

3.3.2 Protection of Traffic

Maintain and protect traffic on all affected roads during the construction period except as otherwise specifically directed by the Contracting Officer. Measures for the protection and diversion of traffic, including the provision of watchmen and flagmen, erection of barricades, placing of lights around and in front of equipment the work, and the erection and maintenance of adequate warning, danger, and direction signs, will be as required by the State and local authorities having jurisdiction. Protect the traveling public from damage to person and property. Minimize the interference with public traffic on roads selected for hauling material to and from the site. Investigate the adequacy of existing roads and their allowable load limit. Contractor is responsible for the repair of any damage to roads caused by construction operations.

SECTION 01 50 00.00 25 Page 7

3.3.3 Rush Hour Restrictions

Do not interfere with the peak traffic flows preceding and during normal operations without notification to and approval by the Contracting Officer.

3.3.4 Dust Control

Dust control methods and procedures must be approved by the Contracting Officer. Treat dust abatement on access roads with applications of calcium chloride, water sprinklers, or similar methods or treatment.

3.4 CONTRACTOR'S TEMPORARY FACILITIES

3.4.1 Safety

Protect the integrity of any installed safety systems or personnel safety devices. If entrance into systems serving safety devices is required, the Contractor must obtain prior approval from the Contracting Officer. If it is temporarily necessary to remove or disable personnel safety devices in order to accomplish contract requirements, provide alternative means of protection prior to removing or disabling any permanently installed safety devices or equipment and obtain approval from the Contracting Officer.

3.4.2 Administrative Field Offices

Provide and maintain administrative field office facilities within the construction area at the designated site. Government office and warehouse facilities will not be available to the Contractor's personnel.

3.4.3 Storage Area

Construct a temporary 6 foot high chain link fence around trailers and materials. Include plastic strip inserts, colored green, so that visibility through the fence is obstructed. Fence posts may be driven, in lieu of concrete bases, where soil conditions permit. Do not place or store Trailers, materials, or equipment outside the fenced area unless such trailers, materials, or equipment are assigned a separate and distinct storage area by the Contracting Officer away from the vicinity of the construction site but within the installation boundaries. Trailers, equipment, or materials must not be open to public view with the exception of those items which are in support of ongoing work on any given day. Do not stockpile materials outside the fence in preparation for the next day's work. Park mobile equipment, such as tractors, wheeled lifting equipment, cranes, trucks, and like equipment within the fenced area at the end of each work day.

3.4.4 Supplemental Storage Area

Upon Contractor's request, the Contracting Officer will designate another or supplemental area for the Contractor's use and storage of trailers, equipment, and materials. This area may not be in close proximity of the construction site but will be within the installation boundaries. Fencing of materials or equipment will not be required at this site; however, the Contractor is responsible for cleanliness and orderliness of the area used and for the security of any material or equipment stored in this area.

Utilities will not be provided to this area by the Government.

SECTION 01 50 00.00 25 Page 8

3.4.5 Appearance of Trailers

a. Trailers utilized by the Contractor for administrative or material storage purposes must present a clean and neat exterior appearance and be in a state of good repair. Trailers which, in the opinion of the Contracting Officer, require exterior painting or maintenance will not be allowed on installation property.

b. Paint in accordance with facility standards and maintain the temporary facilities. Failure to do so will be sufficient reason to require their removal.

3.4.6 Maintenance of Storage Area

a. Keep fencing in a state of good repair and proper alignment. Grassed or unpaved areas, which are not established roadways, will be covered with a layer of gravel as necessary to prevent rutting and the tracking of mud onto paved or established roadways, should the Contractor elect to traverse them with construction equipment or other vehicles; gravel gradation will be at the Contractor's discretion. Mow and maintain grass located within the boundaries of the construction site for the duration of the project. Grass and vegetation along fences, buildings, under trailers, and in areas not accessible to mowers will be edged or trimmed neatly.

b. Cut grass (or annual weeds) within the construction and storage sites to a maximum 4 inch height at least once a week during the growing season unless the grass area is not visible to the public. Trim the grass around fences at time of grass cutting. Maintain grass or weeds on stockpiled earth as descried above.

3.4.7 Security Provisions

Provide adequate outside security lighting at the Contractor's temporary facilities. The Contractor will be responsible for the security of its own equipment; in addition, the Contractor will notify the appropriate law enforcement agency requesting periodic security checks of the temporary project field office.

3.4.8 Storage Size and Location

The open site available for storage must be confined to the indicated operations area.

3.4.9 Storage in Existing Buildings

The Contractor will be working around existing buildings; the storage of material will not be allowed in the buildings.

3.4.10 Weather Protection of Temporary Facilities and Stored Materials

Take necessary precautions to ensure that roof openings and other critical openings in the building are monitored carefully. Take immediate actions required to seal off such openings when rain or other detrimental weather is imminent, and at the end of each workday. Ensure that the openings are completely sealed off to protect materials and equipment in the building from damage.

SECTION 01 50 00.00 25 Page 9

3.4.10.1 Building and Site Storm Protection

When a warning of gale force winds is issued, take precautions to minimize danger to persons, and protect the work and nearby Government property.

Precautions must include, but are not limited to, closing openings;

removing loose materials, tools and equipment from exposed locations; and removing or securing scaffolding and other temporary work. Close openings in the work when storms of lesser intensity pose a threat to the work or any nearby Government property.

3.4.10.2 Hurricane Condition of Readiness

Unless directed otherwise, comply with:

a. Condition FOUR (Sustained winds of 50 knots or greater expected within 72 hours): Normal daily jobsite cleanup and good housekeeping practices. Collect and store in piles or containers scrap lumber, waste material, and rubbish for removal and disposal at the close of each work day. Maintain the construction site including storage areas, free of accumulation of debris. Stack form lumber in neat piles less than 4 feet high. Remove all debris, trash, or objects that could become missile hazards. Contact Contracting Officer for Condition of Readiness (COR) updates and completion of required actions.

b. Condition THREE (Sustained winds of 50 knots or greater expected within 48 hours): Maintain "Condition FOUR" requirements and commence securing operations necessary for "Condition ONE" which cannot be completed within 18 hours. Cease all routine activities which might interfere with securing operations. Commence securing and stow all gear and portable equipment. Make preparations for securing buildings. Review requirements pertaining to "Condition TWO" and continue action as necessary to attain "Condition THREE" readiness.

Contact Contracting Officer for weather and COR updates and completion of required actions.

c. Condition TWO (Sustained winds of 50 knots or greater expected within 24 hours): Curtail or cease routine activities until securing operation is complete. Reinforce or remove form work and scaffolding.

Secure machinery, tools, equipment, materials, or remove from the jobsite. Expend every effort to clear all missile hazards and loose equipment from general base areas. Contact Contracting Officer for weather and Condition of Readiness (COR) updates and completion of required actions.

d. Condition ONE. (Sustained winds of 50 knots or greater expected within 12 hours): Secure the jobsite, and leave Government premises.

3.5 PLANT COMMUNICATION

Whenever the Contractor has the individual elements of its plant so located that operation by normal voice between these elements is not satisfactory, the Contractor must install a satisfactory means of communication, such as telephone or other suitable devices and made available for use by Government personnel.

3.6 TEMPORARY PROJECT SAFETY FENCING

As soon as practicable, but not later than 15 days after the date established for commencement of work, furnish and erect temporary project

SECTION 01 50 00.00 25 Page 10 safety fencing at the work site. The safety fencing must be a high visibility orange colored, high density polyethylene grid or approved equal, a minimum of 42 inches high, supported and tightly secured to steel posts located on maximum 10 foot centers, constructed at the approved location. Maintain the safety fencing during the life of the contract and, upon completion and acceptance of the work, will become the property of the Contractor and be removed from the work site.

3.7 CLEANUP

Remove construction debris, waste materials, packaging material and the like from the work site daily. Any dirt or mud which is tracked onto paved or surfaced roadways must be cleaned away. Store within the fenced area described above or at the supplemental storage area any materials resulting from demolition activities which are salvageable. Neatly stacked stored materials not in trailers, whether new or salvaged.

3.8 RESTORATION OF STORAGE AREA

Upon completion of the project remove the bulletinboard, signs, barricades, haulroads, and any other temporary products from the site. After removal of trailers, materials, and equipment from within the fenced area, remove the fence that will become the property of the Contractor. Restore to the original or better condition, areas used by the Contractor for the storage of equipment or material, or other use. Gravel used to traverse grassed areas must be removed and the area restored to its original condition, including top soil and seeding as necessary.

-- End of Section --