23Q0254 Amendment 1.docx

DOCX document 31 KB Posted

Attached to
Hanger Light Replacements Federal contract opportunity
Solicitation number
N6893623Q0254
Issued by
Department of the Navy Naval Air Systems Command Naval Air Warfare Center

About this file

This document is an amendment to the solicitation for the hangar light replacements project under opportunity number N6893623Q0254 from the Department of the Navy Naval Air Systems Command Naval Air Warfare Center. The amendment provides answers to contractor questions about the project specifications, including confirmation that the hangar ceiling height is 28 feet 1 inch, that the government will work with tenants to clear the work area as needed, that the lighting panel wiring should be 4 number 4/0 cables, and clarification that the proposal needs a full-time superintendent and part-time quality control manager.

View the file

Other files for this federal contract opportunity

Other files attached to Hanger Light Replacements, newest first.
File Type Posted
Current Wage Determination.pdf PDF
Hardware Specs Part 5.pdf PDF
General Requirements Part 2.docx DOCX document
Technical Specifications Part 4.pdf PDF
Construction Solicitation.docx DOCX document
Updated SOW Part 3 Rev C.pdf PDF
Updated Specific Requirements Part 2a Rev 2.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N6893623Q0254

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

The Table of Contents has changed from:

Exhibit/Attachment Table of Contents

DOCUMENT TYPE
DESCRIPTION
PAGES
DATE
Attachment 1
Wage Determination
Attachment 2
Updated Specific Requirements Part 2a Rev 2
Attachment 3
Technical Specifications Part 4
Attachment 4
Hardware Specs Part 5

to:

Exhibit/Attachment Table of Contents

DOCUMENT TYPE
DESCRIPTION
PAGES
DATE
Attachment 1
Current Wage Determination 9.15.23
Attachment 2
Updated Specific Requirements Part 2a Rev 2
Attachment 3
Technical Specifications Part 4
Attachment 4
Hardware Specs Part 5

SECTION L - INSTRUCTIONS, CONDITIONS AND NOTICES TO BIDDERS

The following have been added by full text:

52.252-3ALTERATIONS IN SOLICITATION (APR 1984)
Portions of this solicitation are altered as follows:

Specifications Questions and Answers:

1 . What is the height from finished floor to highest point in Hangar?

Answer: The height from floor to the interior hangar ceiling 28’01”.

2. Is the hangar clear of obstacles or is Contractor to put into price, moving of objects to get lifts in to complete work?

Answer: The hangar is occupied with jets and drones. The government representatives (Rodney and Nick) will work with the tenants to move equipment around the work area and man-lift during this construction.

3. What size wire is currently feeding Lighting panel “LPA”?

Answer: The actual wire size from the main switchboard to panel LP is unknown. However, it is 225A panel so it should be 4#4/0 under 75C.

4. It states that the Site Safety and Health Officer may also serve as the Site Superintendent. It than states that the Quality Control can be a “Roving Project Manager” Does this mean that the SSHO and Superintendent are one hat and to be on-site at ALL times and the QCM does NOT have to be on-site at all times but as needed? This would mean the contractor is to put one hat into proposal?

Answer:The Part 2a required a full time Superintendent and a part time (roving) QC manager. So just a superintendent will not meet the requirements of Part 2a. The QC position (second Hat) will need to be proposed, but it will not need be a full time position.

(End of Summary of Changes) image1.wmf