Contractor Surveillance Plan (CSP)
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 17-R-0015_RFP_Amendment_2.docx | DOCX document | |
| 17-R-0015_RFP_Amendment.docx | DOCX document | |
| Enclosure_1_-_Q's_and_A's.doc | DOC document | |
| Cost_Summary.xls | XLS spreadsheet | |
| Contract_Data_Requirements_List.pdf | ||
| INSTRUCTIONS_FOR_COMPLETING_THE_CONTRACTOR_PERFORMANCE.doc | DOC document | |
| PAST_PERFORMANCE_QUESTIONNAIRE.doc | DOC document | |
| PAST_PERFORMANCE_INFORMATION_FORM.pdf | ||
| WORKFORCE_QUALIFICATIONS.xls | XLS spreadsheet | |
| 17-R-0015_RFP.docx | DOCX document | |
| DD254.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
N68936-17-R-0015
CONTRACTOR SURVEILLANCE PLAN (CSP)
FOR DEPOT LEVEL MAINTENANCE FLEET READINESS CENTER SOUTHWEST (FRCSW) PRODUCTION SUPPORT SERVICES (PSS)
1. Purpose This Contractor Surveillance Plan (CSP) is a Government developed and applied document used to ensure systematic quality assurance methods in the administration of the Level of Effort (LOE) services under the planned contract. The intent is to ensure that the Contractor performs in accordance with the performance metrics and the Government receives the quality of services called for in the contract.
This contract requirement as defined in the Performance Work Statement for the Fleet Readiness Center Southwest (FRCSW), San Diego, CA, requires Production Support Services (PSS) for Depot Level Maintenance to include all maintenance support functions provided through the Industrial Production Support Department (IPSD) which provides engineering, planning and maintenance of FRCSW’s industrial plant equipment. The objective of the PSS for Depot Level Maintenance FRCSW is to provide fleet readiness support to the naval aviator.
This requirement will be met by issuing task orders with PWS’s. The contract will be for a five year ordering period. A properly executed CSP will assist the Government in achieving the objectives of this procurement.
2. Authority Authority for issuance of this CSP is provided by Section E - Inspection and Acceptance, which provides for inspection and acceptance of the services and documentation called for in Task Orders, to be executed by the Contracting Officer or a duly authorized representative.
3. Scope To fully understand the roles and responsibilities of the parties, it is important to first define the distinction in terminology between Quality Management Plan and the CSP. The Contractor, and not the Government, is responsible for management and quality control actions necessary to meet the quality standards set forth by the contract.
The CSP on the other hand, is put in place to provide Government surveillance oversight of the Contractor’s efforts to ensure that they are timely, effective and are delivering the results specified in the contract and documented in the Quality Management Plan.
4. Government Resources The following definitions for Government resources are applicable to this plan:
Contracting Officer - A person duly appointed with the authority to enter into (Procuring Contracting Officer) (PCO) or administer (Administrative Contracting Officer) (ACO) contracts and makes related determination and findings on behalf of the Government. The PCO for this contract is Ms. Debra Zamarron, NAVAIR Code 254330D. The ACO will be designated upon award of the resulting contract. Contracting Officers are designated via a written warrant, which sets forth limitations of authority.
Contracting Officer’s Representative (COR) - An individual appointed in writing by the PCO to act as their authorized representative to assist in administering the contract. The COR will be appointed upon award of the resulting contract. The limitations of authority are contained in a written letter of appointment.
Alternate Contracting Officer’s Representative (ACOR) – An individual appointed in writing by the PCO to act as their authorized representative, in the absence of the COR, to assist in administering the contract. The ACOR will be appointed in the resulting contract. The limitations of authority are contained in a written letter of appointment.
5. Responsibilities The following Government resources shall have responsibility for the implementation of this CSP:
Contracting Officer – The Contracting Officer ensures performance of all necessary actions for effective contracting, ensures compliance with the terms of the contract and safeguards the interests of the United States in the contractual relationship. It is the Contracting Officer that ensures the Contractor receives impartial, fair and equitable treatment under the contract. The Contracting Officer is ultimately responsible for the final determination of the adequacy of the Contractor’s performance.
Contracting Officer’s Representative (COR) – The COR is responsible for technical administration of the contract and ensures proper Government surveillance of the Contractor’s performance. The COR is not empowered to make any contractual commitments or to authorize any changes on the Government’s behalf. Any changes that the Contractor deems may affect contract price, terms or conditions shall be referred to the Contracting Officer for action.
Alternate Contracting Officer’s Representative (ACOR) – The ACOR is responsible for technical surveillance of the contractor’s performance in the absence of the COR. The ACOR is not empowered to make any contractual commitments or to authorize any changes on the Government’s behalf. Any changes that the contractor deems may affect task order price, terms or conditions shall be referred to the Contracting Officer for action.
6. Methods of QA Surveillance Enclosure (1), shall be used by the COR in the execution of this CSP. In addition to the below instructions, the form to be used for documentation of quality assurance surveillance for the Semi-annual reviews is the Surveillance Activity Checklist provided herein.
7. Surveillance The Surveillance Activity Checklist will be provided to the Contractor on a semi-annual basis, as feedback on their performance of the services provided under this contract.
8. Documentation In addition to providing semiannual reports to the Contracting Officer, the COR will maintain a complete Quality Assurance file. The file will contain copies of all reports, evaluations, recommendations, and any actions related to the Government’s performance of the quality assurance function, including the originals of the Quality Assurance Checklist. All such records will be maintained for the life of the contract. The COR shall forward these records to the Contracting Officer semi-annually to ensure surveillance is occurring and performance is satisfactory. The COR shall forward all records to the Contracting Officer at termination or completion of the contract.
9. Enclosures Enclosure (1) Surveillance Activity Checklist Surveillance Activity Checklist All tasks will be assessed on the following:
Cost – Assess the contractor’s effectiveness in forecasting, managing, and controlling contract cost. Is the contractor experiencing cost growth or under run? If so, discuss the causes and contractor-proposed solutions for the cost overruns. In addition, the extent to which the contractor demonstrates a sense of cost responsibility, through the efficient use of resources in each work effort will be assessed.
Schedule – Assess the contractor’s adherence to the required delivery schedule by assessing the contractor’s efforts during the assessment period that contribute to or effect the schedule variance. Also address significance of scheduled events, discuss the causes of any delays, and assess the effectiveness of contractor corrective actions.
Quality – Assess the contractor’s effort to transform operational requirements into an integrated solution. Areas of focus may include the planning and management of program tasks, the quality of support provided throughout all phases of contract execution, the integration of program management specialties, management of interfaces, and the management of a totally integrated effort of all program management concerns to meet cost, performance, and schedule objectives. Assess how successfully the contractor meets the program quality.
Management – Assess the timeliness, completeness and quality of problem identification, corrective action plans, proposal submittals (especially responses to change orders, Engineering Change Proposals or undefinitized contract actions), the contractor's history of reasonable and cooperative behavior, effective business relations, and customer satisfaction. Consider the contractor’s responsiveness to the program as it relates to meeting contract requirements during the period covered by the report.
Data Standards – Assess the contractor’s accuracy and timeliness of each data deliverable. Assess the contractor’s adherence with respect to following the applicable DID and format cited in each CDRL.
The evaluation ratings are as follows:
Exceptional – Performance meets contractual requirements and exceeds many to the Government’s benefit. The contractual performance of the tasks being assessed was accomplished with few minor problems for which corrective actions taken by the contractor were highly effective.
Satisfactory – Performance meets contractual requirements. The contractual performance of the tasks contains some minor problems for which corrective actions taken by the contractor were satisfactory.
Unsatisfactory – Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the tasks contains a serious problem(s) for which the contractor’s actions appear or were ineffective.
Enclosure (1)
Surveillance Activity Checklist
| Task Description |
| Surveillance Method/ Measure |
| Date Planned |
| Date Completed |
| Cost |
| Quality |
| Schedule |
| Management |
| Labor Qualifications IAW PWS 3.1 |
| 100% inspected by COR/ ACOR and customer feedback |
| Industrial Production Support Department IAW PWS Para 3.2 provide install, remove, repair, maintain, overhaul and perform preventative maintenance on a periodic or scheduled basis on a large variety of industrial plant equipment. |
| 100% inspected by COR/ ACOR and customer feedback |
| TBD |
| Support Eqmt planned maintenance IAW PWS 3.2.9.1: Provide support to 6.3.1 and N42 IAW 4790.2B CH-1 (NAMP) |
| 100% inspected by COR/ ACOR and customer feedback |
| TBD |
| Tool Room Support IAW PWS Para 3.3: perform Tool Control/Support Services has the responsibility for keeping the Central Tool Room and Satellite Tool Crib Centers in compliance with COMNAVAIRFORINST 4790.2B, Section 10.12, Positive Tool Control Program and keeping databases related to tool use and replenishment current and up to date |
| 100% inspected by COR/ ACOR and customer feedback |
| TBD |
| ISO-14001 Environmental Management System (EMS) Support IAW PWS Para 3.4: including 2nd Party Auditor support. |
| 100% inspected by COR/ ACOR and customer feedback |
| TBD |
| OHSAS-18001:2007 Safety Mgmt System Support IAW PWS Para 3.5: Day to day support service of OHSAS to support Code 7.10 |
| 100% inspected by COR/ ACOR and customer feedback |
| TBD |
| Bill of Material (BOM) Development for all depot level aircraft IAW PWS Para 3.6: including development, verification and performing sustainability/obsolescence assessment |
| 100% inspected by COR/ ACOR and customer feedback |
| Security Requirements IAW PWS 7.0 |
| 100% inspected by COR/ ACOR and customer feedback |
| Mobilization and Transition IAW PWS 11.0 |
| 100% inspected by COR/ ACOR and customer feedback |
Data Products
| Task Description |
| Surveillance Method/ Measure |
| Date Planned |
| Date Completed |
| Cost |
| Quality |
| Schedule |
| Management |
| Contractor’s Progress and Status Report, CDRL A001 |
| 100% Inspection by COR or as designated by COR |
| TBD |
| Quality Audit Finding and Response Record, CDRL A002 |
| 100% Inspection by COR or as designated by COR |
| TBD |
| Technical Report - Study/Services, CDRL A003 |
| 100% Inspection by COR or as designated by COR |
| TBD |
| Personnel Report, CDRL A004 |
| 100% Inspection by COR or as designated by COR |
| TBD |
| Trip/Travel Report, CDRL A005 |
| 100% Inspection by COR or as designated by COR |
| TBD |