Text version
DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 1 of 9 Pages
Adobe Professional 8.0
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT
B
C. CATEGORY:
TDP TM OTHER
D. SYSTEM/ITEM
JAPAN F-35 TSST SERVICES
E. CONTRACT/PR NO. F. CONTRACTOR
1. DATA ITEM NO.
A001
2. TITLE OF DATA ITEM
PRESENTATION MATERIALS
3. SUBTITLE
KICK-OFF MEETING PRESENTATION
MATERIALS
4. AUTHORITY (Data Acquisition Document No.)
DI-ADMIN-81373/T
5. CONTRACT REFERENCE
SOW Section 4.1.1
6. REQUIRING OFFICE
F-35 JPO
7. DD 250 REQ
N/A
9. DIST STATEMENT
REQUIRED
C
10. FREQUENCY
ONCE
12. DATE OF FIRST SUBMISSION
See Blk 16
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
8. APP CODE
D
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT
SUBMISSION
N/A
Draft
Final
Reg Repro
16. REMARKS
BLOCK 4: Electronic submission shall be made using Microsoft Office Products in Contractor’s chosen format. The Government will consolidate the input into the Kick-Off Presentation. The contractor shall provide the following information to facilitate the Kick- Off: 1) Introduction of Program Manager and key personnel; 2) Overview of project tasks;
3) Contractor POCs; 4) Roles and responsibilities; 5) Schedule showing major tasks; 6) Security requirements/issues/facility access procedures; 7) Reporting requirements; 8) Travel notification and procedures; 9) Invoice Procedures; 10) Other logistical issues; 11) Additional issues of concern; 12) Any other information the contractor deems pertinent.
BLOCK 9: Distribution authorized to U.S. Government agencies and their contractors.
BLOCK 12: The Contractor shall provide Kick-off Presentation Materials NLT ten (10) calendar days after contract award to support a Kick-Off Meeting NLT fifteen (15) calendar days after contract award.
BLOCK 14: Electronic submission required. Hard copies will be made available upon request. Electronic submissions authorized to the Primary COR (email address to be provided by the Government upon contract award and upon update), Alternate COR (email address to be provided by the Government upon contract award and upon update), TPOC, PCO (upon request) and JSFSupportContracts@jsf.mil.
The Contractor shall label each electronic delivery with the contract number and project title in the subject line of the e-mail transmittal. The contractor shall include a transmittal cover letter that defines the content of the data shipment, including item number, CAGE code, contract number, CDRL number and submittal type.
Primary COR 1 1 Alternate COR 1 1
TPOC 1 1
JSF Support Contracts 1 1
15. TOTAL 4 4 0
G. PREPARED BY
ANDERSON, CATHERINE E
H. DATE
4/2/2019
I. APPROVED BY
ANDERSON, CATHERINE E
J. DATE
4/2/2019 mailto:JSFSupportContracts@jsf.mil
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT
B
C. CATEGORY:
TDP TM OTHER
D. SYSTEM/ITEM
JAPAN F-35 TSST SERVICES
A002
MANAGEMENT PLAN
3. SUBTITLE
PROGRAM MANAGEMENT PLAN (PMP)
4. AUTHORITY (Data Acquisition Document No.)
DI-MGMT-80004A/T
5. CONTRACT REFERENCE
SOW Section 4.1.4
6. REQUIRING OFFICE
F-35 JPO
7. DD 250 REQ
N/A
ONE/R
12. DATE OF FIRST SUBMISSION
8. APP CODE
D
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT
Reg Repro
16. REMARKS
BLOCK 4: Contractor devised and Government approved format. Electronic submission shall be made using Microsoft Office Products. As part of the PMP, the Contractor shall provide a Transition-in-Plan (TIP). The TIP shall describe the process, details, and schedule for facilitating the inception of activities from the start of the Period of Performance, in accordance with the guidance herein for all elements of the SOW. The objectives of the TIP are: to minimize the impacts on JPO and JMoD while maintaining communication with all affected parties; identify key risks and issues; and overcome barriers to facilitating the effort. The activities performed during the TIP shall begin on the effective date of the contract and continue until all personnel are in place. The PMP shall also include an overall schedule for the TSST program and shall be updated every six (6) months. Milestones and measurable commitments will be included in the schedule. The Contractor must regularly report status to the TPOC and COR at periodic meetings and via regular written reports.
BLOCK 12: The Contractor shall provide a draft plan no later than (NLT) 30 calendar days after contract award, and a final plan incorporating any Government comments NLT 60 calendar days after contract award. Updates shall be provided every six (6) months.
provided by the Government upon contract award and upon update), Alternate COR (email cover letter that defines the content of the data shipment, including item number, CAGE code, contract number, CDRL number and submittal type.
Primary COR 1 1 Alternate COR 1 1
I. APPROVED BY
ANDERSON, CATHERINE E
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT
B
C. CATEGORY:
TDP TM OTHER
D. SYSTEM/ITEM
JAPAN F-35 TSST SERVICES
A003
STATUS REPORT
3. SUBTITLE
MONTHLY STATUS REPORT (MSR)
4. AUTHORITY (Data Acquisition Document No.)
DI-MGMT-80368 A/T
5. CONTRACT REFERENCE
SOW Section 4.1.2.1
6. REQUIRING OFFICE
F-35 JPO
7. DD 250 REQ
N/A
MTHLY
12. DATE OF FIRST SUBMISSION
8. APP CODE
D
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT
Reg Repro
16. REMARKS
BLOCK 4: Contractor devised and Government approved format. Electronic submission shall be made using Microsoft Office Products. The MSR shall summarize, by task area, the management and technical work conducted during the month as well as current financial information, including: activities during reporting period by task and subtask; ongoing, new and completed activities and progress of each; deliverables; schedule from the PMP;
problems and corrective actions; risks/issues that might affect project milestones and corresponding analysis and handling plans; summary of personnel gains, losses and status changes; Government actions required; summary of trips and conferences/meetings attended; financial status including total billed hours for the period and cumulative to date, projected, actual and cumulative actual cost by CLIN, and remaining labor and travel balances for both incremental funding and ceiling; and recommendations for change, modifications or improvements in task or process. The Contractor shall reconcile the MSR with each monthly invoice.
BLOCK 12: The initial report shall cover the period to the end of the first full month following contract award.
BLOCK 13: Subsequent reports are due NLT the 10th calendar day of each month.
provided by the Government upon contract award and upon update), Alternate COR (email cover letter that defines the content of the data shipment, including item number, CAGE code, contract number, CDRL number and submittal type.
Primary COR 1 1 Alternate COR 1 1
I. APPROVED BY
ANDERSON, CATHERINE E
J. DATE
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT
B
C. CATEGORY:
TDP TM OTHER
D. SYSTEM/ITEM
JAPAN F-35 TSST SERVICES
A004
FUNDS AND MAN-HOURS EXPENDITURE REPORT
3. SUBTITLE
MONTHLY EXPENDITURE REPORT (MER)
4. AUTHORITY (Data Acquisition Document No.)
DI-FNCL-80331 A/T
5. CONTRACT REFERENCE
SOW Section 4.1.2.2
6. REQUIRING OFFICE
F-35 JPO
7. DD 250 REQ
N/A
MTHLY
12. DATE OF FIRST SUBMISSION
8. APP CODE
D
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT
Reg Repro
16. REMARKS
**Draft invoices and supporting documentation must be submitted five (5) business days prior to submission in Wide Area Work Flow (WAWF).**
BLOCK 4: Contractor devised and Government approved format. Electronic submission shall be made using Microsoft Office Products. The MER must include the following data for labor: employee name; labor category; monthly and cumulative hours worked; fully burdened rates by labor category, fee and hourly rate; contract ceiling total; monthly total and cumulative amount billed per employee; CLIN and total cumulative amounts invoiced and funds remaining on the contract for each CLIN; time periods of hours billed if different than the invoiced period. The MER must include the following data for travel and Other Direct Costs (ODCs): purpose; dates and monthly, cumulative and remaining balance by CLIN; any cost incurred not billed; contract ceiling total.
BLOCK 12: The initial report shall cover the period to the end of the first full month following contract award.
BLOCK 13: Subsequent reports are due NLT the 10th calendar day of each month. If this date falls on a non-working day, the report is due the next business day.
provided by the Government upon contract award and upon update), Alternate COR (email cover letter that defines the content of the data shipment, including item number, CAGE code, contract number, CDRL number and submittal type.
Primary COR 1 1 Alternate COR 1 1
ANDERSON, CATHERINE E
H. DATE
4/2/2019
I. APPROVED BY
ANDERSON, CATHERINE E
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT
B
C. CATEGORY:
TDP TM OTHER
D. SYSTEM/ITEM
JAPAN F-35 TSST SERVICES
A005
PRESENTATION MATERIALS
3. SUBTITLE
PROGRAM MANAGEMENT REVIEW (PMR)
AGENDA AND PRESENTATION MATERIALS
4. AUTHORITY (Data Acquisition Document No.)
DI-ADMIN-81373/T
5. CONTRACT REFERENCE
SOW Section 4.1.5
6. REQUIRING OFFICE
F-35 JPO
7. DD 250 REQ
N/A
SEMIA
12. DATE OF FIRST SUBMISSION
8. APP CODE
D
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT
Reg Repro
16. REMARKS
BLOCK 4: Contractor devised and Government approved format. Electronic submission shall be made using Microsoft Office Products. The Contractor shall use the PMP in discussion of contract activities. PMR Agenda and Presentation Materials shall include:
• Introduction
• Schedule by task
• Previous six-months' activities by task
• Personnel overview and status
• Planned activities for the next six months by task
• Issues/actions required by either the U.S. Government or the Government of Japan
• Review of action items from previous PMRs
BLOCK 12: The Contractor shall provide a PMR Agenda and Presentation Materials no later than (NLT) ten (10) calendar days prior to the PMR, and shall incorporate any Government comments NLT two (2) business days following receipt of comments.
provided by the Government upon contract award and upon update), Alternate COR (email cover letter that defines the content of the data shipment, including item number, CAGE code, contract number, CDRL number and submittal type.
Primary COR 1 1 Alternate COR 1 1
TPOC 1 1
PCO 1 1
15. TOTAL 5 5 0
ANDERSON, CATHERINE E
H. DATE
4/2/2019
I. APPROVED BY
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT
B
C. CATEGORY:
TDP TM OTHER
D. SYSTEM/ITEM
JAPAN F-35 TSST SERVICES
A006
REPORT, RECORD OF MEETING/MINUTES
3. SUBTITLE
MEETING MINUTES
4. AUTHORITY (Data Acquisition Document No.)
DI-ADMIN-81505/T
5. CONTRACT REFERENCE
SOW Sections 4.1.1, 4.1.2.1, 4.1.5
6. REQUIRING OFFICE
F-35 JPO
7. DD 250 REQ
N/A
AS REQ
12. DATE OF FIRST SUBMISSION
8. APP CODE
D
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT
Reg Repro
16. REMARKS
BLOCK 4: Contractor devised and Government approved format. Electronic submission shall be made using Microsoft Office Products. The contractor shall provide:
• Meeting attendees and their contact information
• Meeting date
• Meeting location
• Purpose of meeting
• Summary of events
• Action items including responsible party and suspense date
• Any other information the contractor deems pertinent
BLOCK 12: The Contractor shall provide minutes no later than (NLT) ten (10) calendar following the meeting, and shall incorporate any Government comments NLT five (5) calendar days following receipt of comments.
provided by the Government upon contract award and upon update), Alternate COR (email cover letter that defines the content of the data shipment, including item number, CAGE code, contract number, CDRL number and submittal type.
Primary COR 1 1 Alternate COR 1 1
I. APPROVED BY
ANDERSON, CATHERINE E
J. DATE
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT
B
C. CATEGORY:
TDP TM OTHER
D. SYSTEM/ITEM
JAPAN F-35 TSST SERVICES
A007
TECHNICAL REPORT - STUDY/SERVICES
3. SUBTITLE
PROBLEM NOTIFICATION REPORTS (PNR)
4. AUTHORITY (Data Acquisition Document No.)
DI-MGMT-80508B/T
5. CONTRACT REFERENCE
SOW Section 4.1.2.1
6. REQUIRING OFFICE
F-35 JPO
7. DD 250 REQ
N/A
ASREQ
12. DATE OF FIRST SUBMISSION
8. APP CODE
D
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT
Reg Repro
16. REMARKS
BLOCK 4: Contractor devised and Government approved format. Electronic submission shall be made using Microsoft Office Products. The Contractor shall file a PNR to notify the Government of any issues such as potential cost/schedule overruns/impacts, delay to delivery, assumptions upon which tasks were based that have changed or were incorrect, and any other issues that require immediate Government attention.
BLOCK 12: The Contractor shall provide a PNR no later than (NLT) one (1) business day after the problem is identified.
provided by the Government upon contract award and upon update), Alternate COR (email cover letter that defines the content of the data shipment, including item number, CAGE code, contract number, CDRL number and submittal type.
Primary COR 1 1 Alternate COR 1 1
I. APPROVED BY
ANDERSON, CATHERINE E
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT
B
C. CATEGORY:
TDP TM OTHER
D. SYSTEM/ITEM
JAPAN F-35 TSST SERVICES
A008
TRANSITION PLAN
3. SUBTITLE
TRANSITION-OUT PLAN
4. AUTHORITY (Data Acquisition Document No.)
DI-MGMT-80790/T
5. CONTRACT REFERENCE
SOW Section 4.1.3
6. REQUIRING OFFICE
F-35 JPO
7. DD 250 REQ
N/A
ONE/R
12. DATE OF FIRST SUBMISSION
8. APP CODE
D
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT
Reg Repro
16. REMARKS
BLOCK 4: Contractor devised and Government approved format. Electronic submission shall be made using Microsoft Office Products. The Transition-Out Plan must include how the Contractor will coordinate with the incoming Contractor/Government personnel to transfer knowledge and GFE; project management processes; points of contact at all locations; location of technical/project management documentation; status of ongoing initiatives; transition of key personnel; schedule/milestones; Government actions requested;
a continuity plan for all processes and procedures; billet and position plans; status of security clearances; schedule turnover; and technical documentation and expectations.
BLOCK 12: No later than (NLT) 60 calendar following request by the Procuring Contracting Officer (PCO). Government comments must be incorporated NLT ten
(10) calendar days after receipt.
provided by the Government upon contract award and upon update), Alternate COR (email cover letter that defines the content of the data shipment, including item number, CAGE code, contract number, CDRL number and submittal type.
Primary COR 1 1 Alternate COR 1 1
I. APPROVED BY
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT
B
C. CATEGORY:
TDP TM OTHER
D. SYSTEM/ITEM
JAPAN F-35 TSST SERVICES
A009
TRAINING PROGRAM STRUCTURE DOCUMENT
3. SUBTITLE
TRAINING SYLLABI
4. AUTHORITY (Data Acquisition Document No.)
DI-SESS-81521B/T
5. CONTRACT REFERENCE
SOW Section 4.2.2
6. REQUIRING OFFICE
F-35 JPO
7. DD 250 REQ
N/A
AS REQ
12. DATE OF FIRST SUBMISSION
8. APP CODE
D
11. AS OF DATE
N/A
13. DATE OF SUBSEQUENT
Reg Repro
16. REMARKS
BLOCK 4: Contractor devised and Government approved format. Electronic submission shall be made using Microsoft Office Products. Each training syllabus must include an outline of planned training material including agenda, audience, proposed items to train and proposed synopsis of each area to be trained.
BLOCK 12: Training syllabi will be provided no later than (NLT) ten (10) business days prior to training conduct. Any changes provided by the Government will be incorporated NLT five (5) business days prior to the training.
provided by the Government upon contract award and upon update), Alternate COR (email cover letter that defines the content of the data shipment, including item number, CAGE code, contract number, CDRL number and submittal type.
Primary COR 1 1 Alternate COR 1 1
I. APPROVED BY
ANDERSON, CATHERINE E
J. DATE
INSTRUCTIONS FOR COMPLETING DD FORM 1423
(See DoD 5010.12-M for detailed instructions.)
FOR GOVERNMENT PERSONNEL
Item A. Self-explanatory.
Item B. Self-explanatory.
Item C. Mark (X) appropriate category: TDP - Technical Data Package; TM
- Technical Manual; Other - other category of data, such as "Provisioning,""Configuration Management," etc.
Item D. Enter name of system/item being acquired that data will support.
Item E. Self-explanatory (to be filled in after contract award).
Item F. Self-explanatory (to be filled in after contract award).
Item G. Signature of preparer of CDRL.
Item H. Date CDRL was prepared.
Item I. Signature of CDRL approval authority.
Item J. Date CDRL was approved.
Item 1. See DoD FAR Supplement Subpart 4.71 for proper numbering.
Item 2. Enter title as it appears on data acquisition document cited in Item 4.
Item 3. Enter subtitle of data item for further definition of data item (optional entry).
Item 4. Enter Data Item Description (DID) number, military specification number, or military standard number listed in DoD 5010.12-L (AMSDL), or one-time DID number, that defines data content and format requirements.
Item 5. Enter reference to tasking in contract that generates requirement for the data item (e.g., Statement of Work paragraph number).
Item 6. Enter technical office responsible for ensuring adequacy of the data item.
Item 7. Specify requirement for inspection/acceptance of the data item by the Government.
Item 8. Specify requirement for approval of a draft before preparation of the final data item.
Item 9. For technical data, specify requirement for contractor to mark the appropriate distribution statement on the data (ref. DoDD 5230.24).
Item 10. Specify number of times data items are to be delivered.
Item 11. Specify as-of date of data item, when applicable.
Item 12. Specify when first submittal is required.
Item 13. Specify when subsequent submittals are required, when applicable.
Item 14. Enter addressees and number of draft/final copies to be delivered to each addressee. Explain reproducible copies in Item 16.
Item 15. Enter total number of draft/final copies to be delivered.
Item 16. Use for additional/clarifying information for Items 1 through 15.
Examples are: Tailoring of documents cited in Item 4; Clarification of submittal dates in Items 12 and 13; Explanation of reproducible copies in Item 14.; Desired medium for delivery of the data item.
FOR THE CONTRACTOR
Item 17. Specify appropriate price group from one of the following groups of effort in developing estimated prices for each data item listed on the DD Form 1423.
a. Group I. Definition - Data which is not otherwise essential to the contractor's performance of the primary contracted effort (production, development, testing, and administration) but which is required by DD Form 1423.
Estimated Price - Costs to be included under Group I are those applicable to preparing and assembling the data item in conformance with Government requirements, and the administration and other expenses related to reproducing and delivering such data items to the Government.
b. Group II. Definition - Data which is essential to the performance of the primary contracted effort but the contractor is required to perform additional work to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, or quality of the data item.
Estimated Price - Costs to be included under Group II are those incurred over and above the cost of the essential data item without conforming to Government requirements, and the administrative and other expenses related to reproducing and delivering such data item to the Government.
c. Group III. Definition - Data which the contractor must develop for his internal use in performance of the primary contracted effort and does not require any substantial change to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, and quality of the data item.
Estimated Price - Costs to be included under Group III are the administrative and other expenses related to reproducing and delivering such data item to the Government.
d. Group IV. Definition - Data which is developed by the contractor as part of his normal operating procedures and his effort in supplying these data to the Government is minimal.
Estimated Price - Group IV items should normally be shown on the DD Form 1423 at no cost.
Item 18. For each data item, enter an amount equal to that portion of the total price which is estimated to be attributable to the production or development for the Government of that item of data.
These estimated data prices shall be developed only from those costs which will be incurred as a direct result of the requirement to supply the data, over and above those costs which would otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not include any amount for rights in data.
The Government's right to use the data shall be governed by the pertinent provisions of the contract.