This document is a solicitation for a five-year indefinite delivery/indefinite quantity contract to produce and deliver Mobile Facilities units in accordance with government drawings. The Naval Air Warfare Center Aircraft Division intends to award a single-award contract for the production of six First Article Test units and up to 560 production units over five years. Proposals are due by the date specified in Block 9 of the Standard Form 33. The contract will have a minimum guarantee of six FAT units or one production unit if FAT is waived. Pricing shall be fixed for the contract period. Offerors must submit pricing for all line items and quantities specified. The contract will incorporate FAR provisions including First Article Testing and Additional Cost or Pricing Data clauses. The Technical Data Package is export controlled and offerors must have a valid DD Form 2345 on file to receive it.

Solicitation Amendment

View the file

Other files for this federal contract opportunity

Other files attached to Mobile Facilities, newest first.
File Type Posted
MF_SOW.doc DOC document
N68335-18-R-0141_(RFP)_Solicitation_Amendment_002.docx DOCX document
MF_CDRL_L001_RD.pdf PDF
MF_CDRL_L002_RD.pdf PDF
Questions_Solicitation_N68335-18-R-0141.docx DOCX document
MF_SOW.doc DOC document
MF_Logistics_Statement_of_Work.doc DOC document
CDRLs.zip ZIP file
MF_SOW_2018_RD.doc DOC document
1339AS_Addenda_October_26_2018.pdf PDF
N68335-18-R-0141_(RFP).docx DOCX document
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this solicitation is to revise conflicting information as applicable.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 38

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 20-Dec-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N6833518R0141

X 9B. DATED (SEE ITEM 11)

19-Nov-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 2 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

20-Dec-2018

CODE

NAVAIR LAKEHURST

NAVAL AIR WARFARE CENTER AD (LKE)

HWY 547, BLDG 562-3, ROOM 306

JOINT BASE MDL NJ 08733-5082

N68335 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

X 1

N6833518R0141

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION A - SOLICITATION/CONTRACT FORM

The required response date/time has changed from 20-Dec-2018 03:00 PM to 15-Jan-

2019 03:00 PM.

The following have been modified:

SECTION A NARRATIVE

Procurement Office Point of Contact (POC) Kalil O’Neal Phone: 732-323-7491 Email: kalil.oneal@navy.mil

Technical Points of Contact Rodney Davis Phone: 732-323-2770 Email: rodney.davis@navy.mil

1) This will be a Fixed-Price Indefinite Delivery/ Indefinite Quantity (IDIQ) Contract for the procurement of six (6) First Article Test (FAT) Mobile Facility (MF) units, technical data items, and up to 554 MF Production units in accordance with Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)" dated January 2018; Attachment 2: "NAVAIR 1339AS Series Drawings"; Attachment 3: “1339AS Addenda”, Attachment 4: “Integrated Logistics Support SOW”; and Exhibit A "DD Form 1423, Contract Data Requirements List".

2) A Single-Award contract is intended to be issued for this requirement.

3) The guaranteed minimum for this contract is six (6) total FAT MF units (CLINs 0001-0006). However, if First Article Testing is waived in accordance with FAR 52.209-3(h), “First Article Approval- Contractor Testing”, then the guaranteed minimum for this contract is one (1) MF Production Unit, configuration to be determined. The guaranteed minimum will be met upon D.O. 0001 upon award of the basic contract.

4) The maximum quantity that may be ordered under this contract is six (6) FAT MF units and up to 560 MF Production units.

5) Delivery Orders may be placed as follows:

Year 1: CLINs 0001-0006: Delivery Order 0001 will be placed upon award of the basic contract.

Year 1: CLINs 0007-0012 and 0037-0048: May be ordered from the date of contract award through 365 days after Government Release for Production.

mailto:kalil.oneal@navy.mil mailto:rodney.davis@navy.mil

Year 2: CLINs 0013-0018 and 0037-0048: May be ordered from the date of contract award through 730 days after Government Release for Production.

Year 3: CLINs 0019-0024 and 0037-0048: May be ordered from the date of contract award through 1,095 days after Government Release for Production.

Year 4: CLINs 0025-0030 and 0037-0048: May be ordered from the date of contract award through 1,460

Year 5: CLINs 0031-0036 and 0037-0048: May be ordered from the date of contract award through 1,825

6) THE ISSUANCE OF PRODUCTION DELIVERY ORDERS AND RELEASE FOR

PRODUCTION ARE SEPARATE EVENTS. BOTH MUST HAVE OCCURRED BEFORE

PRODUCTION MAY COMMENCE. IN NO CASE WILL RELEASE FOR PRODUCTION

BE GRANTED PRIOR TO SUCCESSFUL COMPLETION OF FIRST ARTICLE TEST (FAT)

UNIT TESTING AND ACCEPTANCE OF THE FAT REPORT (CDRL A003A).

7) UPON APPROVAL, FAT UNITS WILL BE COUNTED AS PRODUCTION UNITS.

8) Proposal validity shall be for 180 days or longer as annotated by the offeror in Block 12 of the cover page of the SF33.

9) RELEASE OF TECHNICAL DATA PACKAGE INFORMATION: The specifications associated with this solicitation will NOT be posted with the Request for Proposal and must be obtained through this office.

The specifications associated with this procurement have been marked with Distribution Statement D, which authorizes distribution of the document to Department of Defense (DOD) and U.S. DOD contractors, because data contains critical technology and export controlled information. In order to receive a copy of the specifications, all vendors must provide a current and active Cage Code to confirm their status as a U.S.

Government contractor. Cage code status will be confirmed via the System for Award Management (SAM) at www.SAM.gov. For assistance in registering your company, please engage the SAM help desk at https://fsd.gov/fsd-govthome.do. Additionally, contractors shall also provide evidence demonstrating an active role as a contractor supporting DOD contracts/requirements and a certified copy of DD Form 2345, Militarily Critical Technical Data Agreement. The DD Form 2345 must be on file with the United States/Canada Joint Certification Office. For DD2345 information call DLIS in Battle Creek, at 800-352- 3572 or visit the Internet at http://www.dlis.dla.mil/jcp.

Interested Firms shall submit a written request for a copy of the Specification through Mr. Kalil O’Neal at:

kalil.oneal@navy.mil and cc, Mrs. Laurie Jiavaras at: laurie.jiavaras@navy.mil . The written request must include the name of your company, mailing address, phone number, email address, current CAGE number and a copy of current, approved DD Form 2345.

SECTION B - SUPPLIES OR SERVICES AND PRICES

CLIN 0001

The CLIN extended description has changed from:

Mobile Facility, Type A P/N 1339AS700-1, for functional testing in accordance with Section J, Attachment 1, "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2, "Drawing Package 1339AS463"; and Exhibit A http://www.dlis.dla.mil/jcp mailto:laurie.jiavaras@navy.mil

"DD Form 1423, Contract Data Requirements List"

To:

Mobile Facility, Type A P/N 1339AS700-1, for functional testing in accordance with Section J, Attachment 1, "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "NAVAIR 1339AS Series Drawings";

Attachment 3: “1339AS Addenda”; Attachment 4: "Integrated Logistics Support SOW"; and Exhibit A "DD Form 1423, Contract Data Requirements List"

CLIN 0002

Mobile Facility, Side Opening Type A P/N 1339AS500-1, for functional testing in accordance with Section J, Attachment 1, "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2, "Drawing Package 1339AS463";

and Exhibit A "DD Form 1423, Contract Data Requirements List"

Mobile Facility, Side Opening Type A P/N 1339AS500-1, for functional testing in accordance with Section J, Attachment 1, "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2, "NAVAIR 1339AS Series Drawings"; Attachment 3: “1339AS Addenda”; Attachment 4: "Integrated Logistics Support SOW"; and Exhibit A

CLIN 0003

Mobile Facility, Side Opening Type B P/N 1339AS501-1, for functional testing in accordance with Section J, Attachment 1, "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2, "Drawing Package 1339AS463";

Mobile Facility, Side Opening Type B P/N 1339AS501-1, for functional testing in accordance with Section J, Attachment 1, "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2, "NAVAIR 1339AS Series Drawings"; Attachment 3: “1339AS Addenda”; Attachment 4: "Integrated Logistics Support SOW"; and Exhibit A

CLIN 0004

Mobile Facility, Integration unit P/N 1339AS900-2, for functional testing in accordance with Section J, Attachment 1, "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2, "Drawing Package 1339AS463"; and Exhibit A "DD Form 1423, Contract Data Requirements List"

Mobile Facility, Integration unit P/N 1339AS900-2, for functional testing in accordance with Section J, Attachment 1, "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2, "NAVAIR 1339AS Series Drawings";

Attachment 3: “1339AS Addenda”; Attachment 4: "Integrated Logistics Support SOW"; and Exhibit A "DD Form 1423, Contract Data Requirements List"

CLIN 0005

Mobile Facility, Side Opening w/ Double Doors P/N 1339AS1000-1, for functional testing in accordance with Section J, Attachment 1, "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2, "Drawing Package 1339AS463"; and Exhibit A "DD Form 1423, Contract Data Requirements List"

Mobile Facility, Side Opening w/ Double Doors P/N 1339AS1000-1, for functional testing in accordance with Section J, Attachment 1, "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2, "NAVAIR 1339AS Series Drawings"; Attachment 3: “1339AS Addenda”; Attachment 4: "Integrated Logistics Support SOW"; and Exhibit A "DD Form 1423, Contract Data Requirements List"

CLIN 0006

Mobile Facility, Side Opening Type C P/N 1339AS1101-1, for functional testing in accordance with Section J, Attachment 1, "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2, "Drawing Package 1339AS463";

Mobile Facility, Side Opening Type C P/N 1339AS1101-1, for functional testing in accordance with Section J, Attachment 1, "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2, "NAVAIR 1339AS Series Drawings"; Attachment 3: “1339AS Addenda”; Attachment 4: "Integrated Logistics Support SOW"; and Exhibit A

CLIN 0007

Production Year One (1) for Mobile Facility Type A P/N 1339AS700-1 in accordance with Section J, Attachment 1:

"Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "Drawing Package 1339AS463"; Attachment 3:

“1339AS Addenda”, and Exhibit A "DD Form 1423, Contract Data Requirements List".

The total maximum ordering quantity that can be ordered under this CLIN is 112 each.

Production Year One (1) for Mobile Facility Type A P/N 1339AS700-1 in accordance with Section J, Attachment 1:

"Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "NAVAIR 1339AS Series Drawings";

Attachment 3: “1339AS Addenda”, Attachment 4: "Integrated Logistics Support SOW"; and Exhibit A "DD Form 1423, Contract Data Requirements List".

CLIN 0008

Production Year One (1) for Mobile Facility Type A P/N 1339AS500-1 in accordance with Section J, Attachment 1:

"Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "Drawing Package 1339AS463"; Attachment 3:

Production Year One (1) for Mobile Facility Type A P/N 1339AS500-1 in accordance with Section J, Attachment 1:

"Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "NAVAIR 1339AS Series Drawings";

Attachment 3: “1339AS Addenda”; Attachment 4: "Integrated Logistics Support SOW"; and Exhibit A "DD Form

CLIN 0009

Production Year One (1) for Mobile Facility Side Opening Type B P/N 1339AS501-1 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "Drawing Package 1339AS463";

Attachment 3: “1339AS Addenda”, and Exhibit A "DD Form 1423, Contract Data Requirements List".

Production Year One (1) for Mobile Facility Side Opening Type B P/N 1339AS501-1 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "NAVAIR 1339AS Series Drawings"; Attachment 3: “1339AS Addenda”; Attachment 4: "Integrated Logistics Support SOW"; and Exhibit A "DD Form 1423, Contract Data Requirements List".

CLIN 0010

Production Year One (1) for Mobile Facility Integration unit P/N 1339AS900-2 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "Drawing Package 1339AS463";

Production Year One (1) for Mobile Facility Integration unit P/N 1339AS900-2 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "NAVAIR 1339AS Series Drawings"; Attachment 3: “1339AS Addenda”; Attachment 4: "Integrated Logistics Support SOW"; and Exhibit A

CLIN 0011

Production Year One (1) for Mobile Facility Side Opening with Double Doors P/N 1339AS1000-1 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "Drawing Package 1339AS463"; Attachment 3: “1339AS Addenda”, and Exhibit A "DD Form 1423, Contract Data Requirements List". The total maximum ordering quantity that can be ordered under this CLIN is 112 each.

Production Year One (1) for Mobile Facility Side Opening with Double Doors P/N 1339AS1000-1 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "NAVAIR 1339AS Series Drawings"; Attachment 3: “1339AS Addenda”; Attachment 4: "Integrated Logistics Support SOW";

and Exhibit A "DD Form 1423, Contract Data Requirements List".

CLIN 0012

Production Year One (1) for Mobile Facility Side Opening Type C P/N 1339AS1101-1 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "Drawing Package 1339AS463"; Attachment 3: “1339AS Addenda”, and Exhibit A "DD Form 1423, Contract Data Requirements List". The total maximum ordering quantity that can be ordered under this CLIN is 112 each.

Production Year One (1) for Mobile Facility Side Opening Type C P/N 1339AS1101-1 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "NAVAIR 1339AS Series Drawings"; Attachment 3: “1339AS Addenda”; Attachment 4: "Integrated Logistics Support SOW"; and Exhibit A

CLIN 0013

Production Year Two (2) for Mobile Facility Type A P/N 1339AS700-1 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "Drawing Package 1339AS463"; Attachment 3: “1339AS Addenda”, and Exhibit A "DD Form 1423, Contract Data Requirements List".

Production Year Two (2) for Mobile Facility Type A P/N 1339AS700-1 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "NAVAIR 1339AS Series Drawings";

Attachment 3: “1339AS Addenda”; Attachment 4: "Integrated Logistics Support SOW"; and Exhibit A "DD Form

CLIN 0014

Production Year Two (2) for Mobile Facility Type A P/N 1339AS500-1 in accordance with Section J, Attachment 1:

"Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "Drawing Package 1339AS463"; Attachment 3:

Production Year Two (2) for Mobile Facility Type A P/N 1339AS500-1 in accordance with Section J, Attachment 1:

"Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "NAVAIR 1339AS Series Drawings";

Attachment 3: “1339AS Addenda”; Attachment 4: "Integrated Logistics Support SOW"; and Exhibit A "DD Form

CLIN 0015

Production Year Two (2) for Mobile Facility Side Opening Type B P/N 1339AS501-1 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "Drawing Package 1339AS463";

Production Year Two (2) for Mobile Facility Side Opening Type B P/N 1339AS501-1 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "NAVAIR 1339AS Series Drawings"; Attachment 3: “1339AS Addenda”; Attachment 4: "Integrated Logistics Support SOW"; and Exhibit A

CLIN 0016

Production Year Two (2) for Mobile Facility Integration unit P/N 1339AS900-2 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "Drawing Package 1339AS463";

Production Year Two (2) for Mobile Facility Integration unit P/N 1339AS900-2 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "NAVAIR 1339AS Series Drawings"; Attachment 3: “1339AS Addenda”; Attachment 4: "Integrated Logistics Support SOW"; and Exhibit A

CLIN 0017

Production Year Two (2) for Mobile Facility Side Opening with Double Doors P/N 1339AS1000-1 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "Drawing Package 1339AS463"; Attachment 3: “1339AS Addenda”, and Exhibit A "DD Form 1423, Contract Data Requirements List". The total

Production Year Two (2) for Mobile Facility Side Opening with Double Doors P/N 1339AS1000-1 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "NAVAIR 1339AS Series Drawings"; Attachment 3: “1339AS Addenda”; Attachment 4: "Integrated Logistics Support SOW";

CLIN 0018

Production Year Two (2) for Mobile Facility Side Opening Type C P/N 1339AS1101-1 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "Drawing Package 1339AS463"; Attachment 3: “1339AS Addenda”, and Exhibit A "DD Form 1423, Contract Data Requirements List". The total maximum ordering

Production Year Two (2) for Mobile Facility Side Opening Type C P/N 1339AS1101-1 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "NAVAIR 1339AS Series Drawings"; Attachment 3: “1339AS Addenda”; Attachment 4: "Integrated Logistics Support SOW"; and Exhibit A

CLIN 0019

Production Year Three (3) for Mobile Facility Type A P/N 1339AS700-1 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "Drawing Package 1339AS463"; Attachment

Production Year Three (3) for Mobile Facility Type A P/N 1339AS700-1 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "NAVAIR 1339AS Series Drawings";

Attachment 3: “1339AS Addenda”; Attachment 4: "Integrated Logistics Support SOW"; and Exhibit A "DD Form

CLIN 0020

Production Year Three (3) for Mobile Facility Type A P/N 1339AS500-1 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "Drawing Package 1339AS463"; Attachment

Production Year Three (3) for Mobile Facility Type A P/N 1339AS500-1 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "NAVAIR 1339AS Series Drawings";

Attachment 3: “1339AS Addenda”; Attachment 4: "Integrated Logistics Support SOW"; and Exhibit A "DD Form

CLIN 0021

Production Year Three (3) for Mobile Facility Side Opening Type B P/N 1339AS501-1 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "Drawing Package 1339AS463"; Attachment 3: “1339AS Addenda”, and Exhibit A "DD Form 1423, Contract Data Requirements List". The total maximum ordering

Production Year Three (3) for Mobile Facility Side Opening Type B P/N 1339AS501-1 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "NAVAIR 1339AS Series Drawings"; Attachment 3: “1339AS Addenda”; Attachment 4: "Integrated Logistics Support SOW"; and Exhibit A

CLIN 0022

Production Year Three (3) for Mobile Facility Integration unit P/N 1339AS900-2 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "Drawing Package 1339AS463";

Production Year Three (3) for Mobile Facility Integration unit P/N 1339AS900-2 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "NAVAIR 1339AS Series Drawings"; Attachment 3: “1339AS Addenda”; Attachment 4: "Integrated Logistics Support SOW"; and Exhibit A

CLIN 0023

Production Year Three (3) for Mobile Facility Side Opening with Double Doors P/N 1339AS1000-1 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "Drawing Package 1339AS463"; Attachment 3: “1339AS Addenda”, and Exhibit A "DD Form 1423, Contract Data Requirements List". The total

Production Year Three (3) for Mobile Facility Side Opening with Double Doors P/N 1339AS1000-1 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "NAVAIR 1339AS Series Drawings"; Attachment 3: “1339AS Addenda”; Attachment 4: "Integrated Logistics Support SOW";

CLIN 0024

Production Year Three (3) for Mobile Facility Side Opening Type C P/N 1339AS1101-1 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "Drawing Package 1339AS463"; Attachment 3: “1339AS Addenda”, and Exhibit A "DD Form 1423, Contract Data Requirements List". The total maximum ordering

Production Year Three (3) for Mobile Facility Side Opening Type C P/N 1339AS1101-1 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "NAVAIR 1339AS Series Drawings"; Attachment 3: “1339AS Addenda”; Attachment 4: "Integrated Logistics Support SOW"; and Exhibit A

CLIN 0025

Production Year Four (4) for Mobile Facility Type A P/N 1339AS700-1 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "Drawing Package 1339AS463"; Attachment

Production Year Four (4) for Mobile Facility Type A P/N 1339AS700-1 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "NAVAIR 1339AS Series Drawings";

Attachment 3: “1339AS Addenda”; Attachment 4: "Integrated Logistics Support SOW"; and Exhibit A "DD Form

CLIN 0026

Production Year Four (4) for Mobile Facility Type A P/N 1339AS500-1 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "Drawing Package 1339AS463"; Attachment

Production Year Four (4) for Mobile Facility Type A P/N 1339AS500-1 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "NAVAIR 1339AS Series Drawings";

Attachment 3: “1339AS Addenda”; Attachment 4: "Integrated Logistics Support SOW"; and Exhibit A "DD Form

CLIN 0027

Production Year Four (4) for Mobile Facility Side Opening Type B P/N 1339AS501-1 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "Drawing Package 1339AS463";

Production Year Four (4) for Mobile Facility Side Opening Type B P/N 1339AS501-1 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "NAVAIR 1339AS Series Drawings"; Attachment 3: “1339AS Addenda”; Attachment 4: "Integrated Logistics Support SOW"; and Exhibit A

CLIN 0028

Production Year Four (4) for Mobile Facility Integration unit P/N 1339AS900-2 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "Drawing Package 1339AS463";

Production Year Four (4) for Mobile Facility Integration unit P/N 1339AS900-2 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "NAVAIR 1339AS Series Drawings"; Attachment 3: “1339AS Addenda”; Attachment 4: "Integrated Logistics Support SOW"; and Exhibit A

CLIN 0029

Production Year Four (4) for Mobile Facility Side Opening with Double Doors P/N 1339AS1000-1 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "Drawing Package 1339AS463"; Attachment 3: “1339AS Addenda”, and Exhibit A "DD Form 1423, Contract Data Requirements List". The total

Production Year Four (4) for Mobile Facility Side Opening with Double Doors P/N 1339AS1000-1 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "NAVAIR 1339AS Series Drawings"; Attachment 3: “1339AS Addenda”; Attachment 4: "Integrated Logistics Support SOW";

CLIN 0030

Production Year Four (4) for Mobile Facility Side Opening Type C P/N 1339AS1101-1 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "Drawing Package 1339AS463"; Attachment 3: “1339AS Addenda”, and Exhibit A "DD Form 1423, Contract Data Requirements List". The total maximum ordering

Production Year Four (4) for Mobile Facility Side Opening Type C P/N 1339AS1101-1 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "NAVAIR 1339AS Series Drawings"; Attachment 3: “1339AS Addenda”; Attachment 4: "Integrated Logistics Support SOW"; and Exhibit A

CLIN 0031

Production Year Five (5) for Mobile Facility Type A P/N 1339AS700-1 in accordance with Section J, Attachment 1:

"Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "Drawing Package 1339AS463"; Attachment 3:

Production Year Five (5) for Mobile Facility Type A P/N 1339AS700-1 in accordance with Section J, Attachment 1:

"Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "NAVAIR 1339AS Series Drawings";

Attachment 3: “1339AS Addenda”; Attachment 4: "Integrated Logistics Support SOW"; and Exhibit A "DD Form

CLIN 0032

Production Year Five (5) for Mobile Facility Type A P/N 1339AS500-1 in accordance with Section J, Attachment 1:

"Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "Drawing Package 1339AS463"; Attachment 3:

Production Year Five (5) for Mobile Facility Type A P/N 1339AS500-1 in accordance with Section J, Attachment 1:

"Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "NAVAIR 1339AS Series Drawings";

Attachment 3: “1339AS Addenda”; Attachment 4: "Integrated Logistics Support SOW"; and Exhibit A "DD Form

CLIN 0033

Production Year Five (5) for Mobile Facility Side Opening Type B P/N 1339AS501-1 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "Drawing Package 1339AS463";

Production Year Five (5) for Mobile Facility Side Opening Type B P/N 1339AS501-1 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "NAVAIR 1339AS Series Drawings"; Attachment 3: “1339AS Addenda”; Attachment 4: "Integrated Logistics Support SOW"; and Exhibit A

CLIN 0034

Production Year Five (5) for Mobile Facility Integration unit P/N 1339AS900-2 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "Drawing Package 1339AS463";

Production Year Five (5) for Mobile Facility Integration unit P/N 1339AS900-2 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "NAVAIR 1339AS Series Drawings"; Attachment 3: “1339AS Addenda”; Attachment 4: "Integrated Logistics Support SOW"; and Exhibit A

CLIN 0035

Production Year Five (5) for Mobile Facility Side Opening with Double Doors P/N 1339AS1000-1 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "Drawing Package 1339AS463"; Attachment 3: “1339AS Addenda”, and Exhibit A "DD Form 1423, Contract Data Requirements List". The total

Production Year Five (5) for Mobile Facility Side Opening with Double Doors P/N 1339AS1000-1 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "NAVAIR 1339AS Series Drawings"; Attachment 3: “1339AS Addenda”; Attachment 4: "Integrated Logistics Support SOW";

CLIN 0036

Production Year Five (5) for Mobile Facility Side Opening Type C P/N 1339AS1101-1 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "Drawing Package 1339AS463"; Attachment 3: “1339AS Addenda”, and Exhibit A "DD Form 1423, Contract Data Requirements List". The total maximum ordering

Production Year Five (5) for Mobile Facility Side Opening Type C P/N 1339AS1101-1 in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "NAVAIR 1339AS Series Drawings"; Attachment 3: “1339AS Addenda”; Attachment 4: "Integrated Logistics Support SOW"; and Exhibit A

SECTION C - DESCRIPTIONS AND SPECIFICATIONS

The following have been modified:

DESCRIPTIONS AND SPECIFICATION

CLINs 0001- 0006: The contractor shall manufacture, test and deliver the First Article Test (FAT) Mobile Facility (MF) units in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)";

Attachment 2: "NAVAIR 1339AS Series Drawings"; Attachment 3: “1339AS Addenda”; Attachment 4: “Integrated Logistics Support SOW”; and Exhibit A "DD Form 1423, Contract Data Requirements List".

CLINs 0007-0036: The contractor shall manufacture and deliver the Mobile Facility (MF) units in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "NAVAIR 1339AS Series Drawings"; Attachment 3: “1339AS Addenda”; Attachment 4: “Integrated Logistics Support SOW”; and Exhibit A "DD Form 1423, Contract Data Requirements List".

CLINs 0037-0038: The contractor shall manufacture and deliver the Mobile Facility (MF) units in accordance with Section J, Attachment 3: “1339AS Addenda”.

CLINs 0039-0048: The technical data to be furnished hereunder shall be in accordance with Exhibit A, Contract Data Requirements List, DD Form 1423.

The Contractor shall provide the supplies and/or services in accordance with Section J, Attachment 1: "Statement of Work (SOW) Mobile Facilities (MF)"; Attachment 2: "NAVAIR 1339AS Series Drawings"; Attachment 3:

“1339AS Addenda”; Attachment 4: “Integrated Logistics Support SOW”; and Exhibit A "DD Form 1423, Contract Data Requirements List".

SECTION F - DELIVERIES OR PERFORMANCE

52.211-8 TIME OF DELIVERY (JUN 1997)

(a) The Government requires delivery to be made according to the following schedule:

REQUIRED DELIVERY SCHEDULE

ITEM

NUMBER

MAX

QTY

WITHIN DATE AFTER

DELIVERY ORDER

DELIVERY ADDRESS

1 Each

Contractor First Article Qualification Testing shall commence within 90 days After Date of Contract (ADC) in accordance with (IAW) FAR 52.209-3.

The draft First Article Acceptance Test Plan (CLIN 0042) shall be submitted within 60 days ADC IAW CDRL A003.

The First Article Test Report (CLIN 0043) shall be submitted within 300 days ADC IAW CDRL A003A.

MF Type A P/N 1339AS700-1 Completion of the First Article Test unit is required within 270 Days After Contract (DAC).

Delivery is FOB Destination

0002 1 Each with (IAW) FAR 52.209-3.

The draft First Article Acceptance Test Plan (CLIN 0042) shall be submitted within 60 days ADC IAW CDRL A003.

The First Article Test Report (CLIN 0043) shall be submitted within 300 days ADC IAW CDRL A003A.

MF Side Opening Type A P/N 1339AS500-1

0003 1 Each with (IAW) FAR 52.209-3.

The draft First Article Acceptance Test Plan (CLIN 0042) shall be submitted within 60 days ADC IAW CDRL A003.

The First Article Test Report (CLIN 0043) shall be submitted within 300 days ADC IAW CDRL A003A.

MF Side Opening Type B P/N 1339AS501-1

0004 1 Each with (IAW) FAR 52.209-3.

The draft First Article Acceptance Test Plan (CLIN 0042) shall be submitted within 60 days ADC IAW CDRL A003.

The First Article Test Report (CLIN 0043) shall be submitted within 300 days ADC IAW CDRL A003A.

MF Integration Unit P/N 1339AS900-2

0005 1 Each with (IAW) FAR 52.209-3.

The draft First Article Acceptance Test Plan (CLIN 0042) shall be submitted within 60 days ADC IAW CDRL A003.

The First Article Test Report (CLIN 0043) shall be submitted within 300 days ADC IAW CDRL A003A.

MF Side Opening w/ Double Doors P/N 1339AS1000-1

0006 1 Each with (IAW) FAR 52.209-3.

The draft First Article Acceptance Test Plan (CLIN 0042) shall be submitted within 60 days ADC IAW CDRL A003.

The First Article Test Report (CLIN 0043) shall be submitted within 300 days ADC IAW CDRL A003A.

MF Side Opening Type C P/N 1339AS1101-1

0007 MF Type A P/N1339AS700-1, Production Year One, if ordered, delivery shall be made within 180 DAYS ARO, provided that release for production has been authorized.

Production Year One shall be from Government Release for Production through 365 days after Government Release for Production.

0008 MF SO Type A P/N 1339AS500-1, Production Year One, if ordered, delivery shall be made within 180 DAYS ARO, provided that release for production has been authorized.

Production Year One shall be from Government Release for

0009 MF SO Type B P/N 1339AS501-1, Production Year One, if provided that release for production has been authorized.

Production Year One shall be from Government Release for

0010 MF Integration Unit P/N 1339AS900-2, Production Year One, if ordered, delivery shall be made within 180 DAYS ARO, provided that release for production has been authorized.

Production Year One shall be from Government Release for

0011 MF SO w/ DD P/N 1339AS1000-1, Production Year One, if ordered, delivery shall be made within 180 DAYS ARO, provided that release for production has been authorized.

Production Year One shall be from Government Release for

Delivery is FOB Destination.

0012 MF Type C P/N 1339AS1101-1, Production Year One, if ordered, delivery shall be made within 180 DAYS ARO, provided that release for production has been authorized.

Production Year One shall be from Government Release for

0013 MF Type A P/N1339AS700-1, Production Year Two, if ordered, delivery shall be made within 180 DAYS ARO, provided that release for production has been authorized.

Production Year Two shall be from Government Release for Production through 730 days after Government Release for

0014 MF SO Type A P/N 1339AS500-1, Production Year Two, if ordered, delivery shall be made within 180 DAYS ARO, provided that release for production has been authorized.

Production Year Two shall be from Government Release for

0015 MF SO Type B P/N 1339AS501-1, Production Year Two, if ordered, delivery shall be made within 180 DAYS ARO, provided that release for production has been authorized.

Production Year Two shall be from Government Release for

0016 MF Integration Unit P/N 1339AS900-2, Production Year Two, if ordered, delivery shall be made within 180 DAYS ARO, provided that release for production has been authorized.

Production Year Two shall be from Government Release for

0017 MF SO w/ DD P/N 1339AS1000-1, Production Year Two, if ordered, delivery shall be made within 180 DAYS ARO, provided that release for production has been authorized.

Production Year Two shall be from Government Release for

0018 MF Type C P/N 1339AS1101-1, Production Year Two, if ordered, delivery shall be made within 180 DAYS ARO, provided that release for production has been authorized.

Production Year Two shall be from Government Release for

0019 MF Type A P/N1339AS700-1, Production Year Three, if ordered, delivery shall be made within 180 DAYS ARO, provided that release for production has been authorized.

Production Year Three shall be from Government Release for Production through 1,095 days after Government Release for

0020 MF SO Type A P/N 1339AS500-1, Production Year Three, if ordered, delivery shall be made within 180 DAYS ARO, provided that release for production has been authorized.

Production Year Three shall be from Government Release for

0021 MF SO Type B P/N 1339AS501-1, Production Year Three, if ordered, delivery shall be made within 180 DAYS ARO, provided that release for production has been authorized.

Production Year Three shall be from Government Release for

0022 MF Integration Unit P/N 1339AS900-2, Production Year Three, if ordered, delivery shall be made within 180 DAYS ARO, provided that release for production has been authorized.

Production Year Three shall be from Government Release for

0023 MF SO w/ DD P/N 1339AS1000-1, Production Year Three, if provided that release for production has been authorized.

Production Year Three shall be from Government Release for

0024 MF Type C P/N 1339AS1101-1, Production Year Three, if ordered, delivery shall be made within 180 DAYS ARO, provided that release for production has been authorized.

Production Year Three shall be from Government Release for

0025 MF Type A P/N1339AS700-1, Production Year Four, if ordered, delivery shall be made within 180 DAYS ARO, provided that release for production has been authorized.

Production Year Four shall be from Government Release for Production through 1,460 days after Government Release for

0026 MF SO Type A P/N 1339AS500-1, Production Year Four, if ordered, delivery shall be made within 180 DAYS ARO, provided that release for production has been authorized.

Production Year Four shall be from Government Release for

0027 MF SO Type B P/N 1339AS501-1, Production Year Four, if ordered, delivery shall be made within 180 DAYS ARO, provided that release for production has been authorized.

Production Year Four shall be from Government Release for

0028 MF Integration Unit P/N 1339AS900-2, Production Year Four, if ordered, delivery shall be made within 180 DAYS ARO, provided that release for production has been authorized.

Production Year Four shall be from Government Release for

0029 MF SO w/ DD P/N 1339AS1000-1, Production Year Four, if provided that release for production has been authorized.

Production Year Four shall be from Government Release for

0030 MF Type C P/N 1339AS1101-1, Production Year Four, if ordered, delivery shall be made within 180 DAYS ARO, provided that release for production has been authorized.

Production Year Four shall be from Government Release for

0031 MF Type A P/N1339AS700-1, Production Year Five, if ordered, delivery shall be made within 180 DAYS ARO, provided that release for production has been authorized.

Production Year Five shall be from Government Release for Production through 1,825 days after Government Release for

0032 MF SO Type A P/N 1339AS500-1, Production Year Five, if ordered, delivery shall be made within 180 DAYS ARO, provided that release for production has been authorized.

Production Year Five shall be from Government Release for

0033 MF SO Type B P/N 1339AS501-1, Production Year Five, if ordered, delivery shall be made within 180 DAYS ARO, provided that release for production has been authorized.

Production Year Five shall be from Government Release for

0034 MF Integration Unit P/N 1339AS900-2, Production Year Five, if ordered, delivery shall be made within 180 DAYS ARO, provided that release for production has been authorized.

Production Year Five shall be from Government Release for

0035 MF SO w/ DD P/N 1339AS1000-1, Production Year Five, if ordered, delivery shall be made within 180 DAYS ARO, provided that release for production has been authorized.

Production Year Five shall be from Government Release for

0036 MF Type C P/N 1339AS1101-1, Production Year Five, if provided that release for production has been authorized.

Production Year Five shall be from Government Release for

0037-0038 In accordance with 1339AS Addenda Delivery is FOB Destination

0039-0048 1 Lot In accordance with the applicable Contract Data Requirements List (CDRL), DD Form 1423, Exhibit A.

In accordance with the applicable Contract Data Requirements List (CDRL), DD Form 1423, Exhibit A.

Delivery is FOB Destination.

The Government will evaluate equally, as regards time of delivery, offers that propose delivery of each quantity within the applicable delivery period specified above. Offers that propose delivery that will not clearly fall within the applicable required delivery period specified above will be considered nonresponsive and rejected. The Government reserves the right to award under either the required delivery schedule or the proposed delivery schedule, when an offeror offers an earlier delivery schedule than required above. If the offeror proposes no other delivery schedule, the required delivery schedule above will apply.

OFFEROR'S PROPOSED DELIVERY SCHEDULE

WITHIN DAYS AFTER

ITEM NO. QUANTITY DATE OF CONTRACT

(b) Attention is directed to the Contract Award provision of the solicitation that provides that a written award or acceptance of offer mailed or otherwise furnished to the successful offeror, results in a binding contract. The Government will mail or otherwise furnish to the offeror an award not later than the day award is dated. Therefore, the offeror should compute the time available for performance beginning with the actual date of award, rather than the date the written notice of award is received from the Contracting Officer through the ordinary mails. However, the Government will evaluate an offer that proposes delivery based on the Contractor’s date of receipt of the contract or notice of award by adding (1) five calendar days for delivery of the award through the ordinary mails, or

(2) one working day if the solicitation states that the contract or notice of award will be transmitted electronically.

(The term “working day” excludes weekends and U.S. Federal holidays.) If, as so computed, the offered delivery date is later than the required delivery date, the offer will be considered nonresponsive and rejected.

SECTION I - CONTRACT CLAUSES

52.209-3 FIRST ARTICLE APPROVAL--CONTRACTOR TESTING (SEP 1989)

(a) The Contractor shall test 1 unit(s) of Lot/Item: 0001 (1339AS500-1, 1339AS501-1, 1339AS700-1, 1339AS900-2, 1339AS1000-1, 1339AS1100-1) as specified in this contract. At least 14 calendar days before the beginning of first article tests, the Contractor shall notify the Contracting Officer, in writing, of the time and location of the testing so that the Government may witness the tests.

(b) The Contractor shall submit the first article test report within 300 calendar days from the date of this contract to SEE DISTRIBUTION ADDRESSES IN CDRL A003A marked "FIRST ARTICLE TEST REPORT: Contract No. TBD , Lot/ Item No. 0001 ". Within 30 calendar days after the Government receives the test report, the Contracting Officer shall notify the Contractor, in writing, of the conditional approval, approval, or disapproval of the first article. The notice of conditional approval or approval shall not relieve the Contractor from complying with all requirements of the specifications and all other terms and conditions of this contract. A notice of conditional approval shall state any further action required of the Contractor. A notice of disapproval shall cite reasons for the disapproval.

(c) If the first article is disapproved, the Contractor, upon Government request, shall repeat any or all first article tests. After each request for additional tests, the Contractor shall make any necessary changes, modifications, or repairs to the first article or select another first article for testing. All costs related to these tests are to be borne by the Contractor, including any and all costs for additional tests following a disapproval. The Contractor shall then conduct the tests and deliver another report to the Government under the terms and conditions and within the time specified by the Government. The Government shall take action on this report within the time specified in paragraph (b) above. The Government reserves the right to require an equitable adjustment of the contract price for any extension of the delivery schedule, or for any additional costs to the Government related to these tests.

(d) If the Contractor fails to deliver any first article report on time, or the Contracting Officer disapproves any first article, the Contractor shall be deemed to have failed to make delivery within the meaning of the Default clause of this contract.

(e) Unless otherwise provided in the contract, and if the approved first article is not consumed or destroyed in testing, the Contractor may deliver the approved first article as part of the contract quantity if it meets all contract requirements for acceptance.

(f) If the Government does not act within the time specified in paragraph (b) or (c) above, the Contracting Officer shall, upon timely written request from the Contractor, equitably adjust under the Changes clause of this contract the delivery or performance dates and/or the contract price, and any other contractual term affected by the delay.

(g) Before first article approval, the acquisition of materials or components for, or the commencement of production of, the balance of the contract quantity is at the sole risk of the Contractor. Before first article approval, the costs thereof shall not be allocable to this contract for (1) progress payments, or (2) termination settlements if the contract is terminated for the convenience of the Government.

(h) The Government may waive the requirement for first article approval test where supplies identical or similar to those called for in the schedule have been previously furnished by the offeror/contractor and have been accepted by the Government. The offeror/contractor may request a waiver.

SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

The Table of Contents has changed from:

Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION PAGES DATE

Exhibit A Exhibit A CDRLs 10 Attachment 1 SOW 3 Attachment 2 Drawing Package

1339AS463

Attachment 3 1339AS Addenda 3 to:

Exhibit/Attachment Table of Contents

DOCUMENT TYPE DESCRIPTION PAGES DATE

Exhibit A Exhibit A CDRLs 10 Attachment 1 SOW 3 Attachment 2 NAVAIR 1339AS Series

Drawings

Attachment 3 1339AS Addenda 3 Attachment 4 Integrated Logistics

Support SOW

Attachment 5 Questions & Answers

SECTION L - INSTRUCTIONS, CONDITIONS AND NOTICES TO BIDDERS

INSTRUCTIONS TO OFFERORS

L – [ 1] CONTENT OF PROPOSALS

PART A GENERAL INSTRUCTIONS

1.0 GENERAL

The Offeror is required to submit sufficient information concerning the following areas to enable Government personnel to fully ascertain capabilities of the Offeror to perform the requirements. The proposal must be sufficient in detail and scope to permit evaluation and provide the evaluators a clear understanding of the Offeror’s capability to meet or exceed the defined elements as required by the solicitation. All proposals must clearly and convincingly demonstrate that the Offeror has a thorough understanding of the requirements, associated risks and is able, willing and competent to devote the resources necessary to meet the requirements, and that the Offeror has valid and practical solutions for all requirements and potential risk areas. The Offeror must respond to all requirements of the solicitation and not alter or rearrange the solicitation. The Offeror has the burden of proof to demonstrate compliance with all the evaluation factors and or subfactors identified in this solicitation. The Offeror is advised that the Government may incorporate into the final contract strengths included in the Offeror’s proposal deemed beneficial to the Government. With the exception of the Price volume, no cost or pricing information should appear in any volume

In presenting material in the proposal, the Offeror is advised that quality of information is more important than quantity. Clarity, brevity, and logical organization should be emphasized during proposal preparation. The Offeror is responsible to present enough information to allow the Government to evaluate the proposed work effort, support, and approach, as well as the price proposal without opening discussions. Statements that the prospective Offeror understands, or can and/or will comply with, the specifications, and paraphrasing the requirements or parts thereof without supporting information are considered inadequate by the Government, and may render a rating of unacceptable. For the purpose of this solicitation, relevance is defined as something that has a logical connection with the matter under consideration. Such aspects of relevance include the type of effort (e.g., technical design, logistics development, testing, production), the type of requirements (e.g., shipboard, environmental), similarity, complexity, contract type, contract dollar value, the division of the company that will perform the work, and degree of participation by principal subcontractors, team members, or critical team members. Recency is defined as performance within 5 years of the date of this proposal submission.

The Offeror must include any data that illustrates the adequacy of the various assumptions, approaches, and solutions to problems. Failure to address a specific factor or subfactor, or element clearly may be considered a deficiency. There is no need to repeat information in more than one volume if an overlap exists; the detailed information must be included in the most logical place and summarized and referenced in other areas.

Unnecessarily elaborate brochures or other presentation materials beyond that sufficient to…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .