Amendment 0001. Construction. Excavation. Concrete foundation, sidewalk, sewer and water utilities.
Solicitation number
N6660423Q0008
Issued by

About this file

This document is an amendment to a solicitation for construction services. The amendment reduces the period of performance from 165 days to 150 days for site preparation, excavation of a 38 foot by 62 foot concrete foundation, connection to utilities, and disposal of arsenic contaminated soil from the Naval Undersea Warfare Center Division Newport in Rhode Island. Offerors are advised that up to 80 cubic yards of arsenic contaminated soil may need to be disposed of offsite, and existing excavated soil may be reused as backfill if recapped with engineering controls as specified. The amendment also adds a contract clause for variation in estimated quantities and provides updated questions and answers regarding soil disposal and reuse options.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1301025957 W2022-178-04 B101M

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

1. Provide Questions and Answ ers #1 through #2. See continuation sheet.

2. Update Section F Delivery information.

3. Add Clause 52.211-18 Variation in Estimated Quantity (pursuant to Q&A#1) in Section I.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 17-Oct-2022

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N6660423Q0008

X 9B. DATED (SEE ITEM 11)

06-Oct-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

17-Oct-2022

CODE

NAVAL UNDERSEA WARFARE CENTER

JOSEPH SCARPA, CODE 0222, 401-832-1499,

CONTRACTS DEPARTMENT

1176 HOWELL STREET, BLDG. 1258

NEWPORT RI 02841-1708

N66604 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N6660423Q0008

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

GENERAL INFO - AMENDMENT 0001

Questions and Answers

Question #1: To mitigate excessive costs, will the Navy provide a location on the base to store the excess arsenic contaminated soils in lieu of disposal off-site?

Answer #1: Offeror should include an allowance within its Contract Line Item Number (CLIN) 0001 price for proper off-site disposal of 80 cubic yards arsenic-contaminated soil. Should actual number of cubic yards vary either way by more than 15 percent, an equitable adjustment may be requested by either party.

Consistent with Appendix 2 of the Specification, NUWCDIVNPT may provide a temporary soil storage location to be coordinated with the construction manager once the contract is awarded. Soil must remain on site for analytical testing to be performed by an environmental professional—at Contractor expense—to determine appropriate disposal decision. All excess soil not to be used as backfill or that has been stockpiled for 60 days must be disposed of accordingly off site. Contractor shall provide Bill of Lading for all arsenic soil which leaves the site for disposal.

No soil may be stockpiled on site for more than 60 days without prior approval. Additional detailed information pertaining to soil control can be found in the “Naval Station Newport Soil Management Plan” and “Naval Station Newport Erosion and Sediment Control” instructions attached as Appendix 2 and Appendix 3 respectively in the project specification.

Question #2: Can existing soils excavated from trenches be reused as backfill in trenches or will the soils need to be exported and replaced with clean backfill?

Answer #2: Excavated arsenic soil may be used as backfill. This reused arsenic soil must be recapped with approved engineering controls as outlined in the Specification and drawings. Additional detailed information may be found in the “Naval Station Newport Soil Management Plan” and “Naval Station Newport Erosion and Sediment Control” instructions attached as Appendix 2 and Appendix 3 of the Specification.

End of Questions and Answers

If you cannot participate in this contracting opportunity, please email a brief explanation such that we can improve our contracting processes. Submit comments to joseph.scarpa6.civ@us.navy.mil or (401) 832-1499 with copy to alexander.olarte.civ@us.navy.mil or (401) 832-2648.

SECTION F - DELIVERIES OR PERFORMANCE

The following Delivery Schedule item for CLIN 0001 has been changed from:

DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

165 dys. ADC 1 NAVAL UNDERSEA WARFARE CENTER, DIV NPT

SEE SCHEDULE

SEE SCHEDULE

NEWPORT RI 02841-1708

FOB: N/A

N66604

To:

DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

150 dys. ADC 1 NAVAL UNDERSEA WARFARE CENTER, DIV NPT

SEE SCHEDULE

SEE SCHEDULE

NEWPORT RI 02841-1708

The following Delivery Schedule item for CLIN 0002 has been changed from:

CAGE

165 dys. ADC 1 NAVAL UNDERSEA WARFARE CENTER, DIV NPT

SEE SCHEDULE

SEE SCHEDULE

NEWPORT RI 02841-1708

To:

CAGE

150 dys. ADC 1 NAVAL UNDERSEA WARFARE CENTER, DIV NPT

SEE SCHEDULE

SEE SCHEDULE

NEWPORT RI 02841-1708

The following have been modified:

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 15 calendar days after the date the Contractor receives notice of award, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 150 days after award. The time stated for completion shall include final cleanup of the premises.

(End of clause)

PROJECT SEQUENCING

Building 101M Foundation Work under this contract must be sequenced with two projects by others as follows:

Building 101M Foundation: Scheduled completion is 31 Mar 2023.

Building 101M/102 Electrical: Concurrent with B101M Foundation and through 14 Apr 2023.

Building 101 Modular Office Delivery and Installation: Scheduled completion is 2 May 2023.

End of text

UPDATE TO DELIVERY DATE

For proposal purposes, the estimated date of Building 101M Foundation contract award is 1 Nov 2022. The government reserves the right to award sooner or later if necessary. The delivery start and end dates in Section F will be updated at award based upon actual contract award date.

End of provision

SECTION I - CONTRACT CLAUSES

The following have been added by reference:

52.211-18 Variation in Estimated Quantity APR 1984

(End of Summary of Changes)