This document outlines key personnel for a federal construction contract. The contract requires a quality control manager, site safety and health officer, and superintendent. It also details site preparation, excavation, construction of a 38 by 62 foot concrete foundation, installation of utility connections, soil removal and disposal, cleanup, and repair work. Services include slump and compressive strength testing, connection to existing water and sewer lines, proper disposal of excess arsenic soil, and returning the work area and surrounding land to its pre-construction condition. The related solicitation is for these site development and construction services at a Navy facility.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

LIST OF KEY PERSONNEL

Attachment J-5

Following Contractor key personnel are approved for contract N66604-22-P-0649. Changes to below list require approval in accordance with C-237-H002 Substitution of Key Personnel (NAVSEA) (OCT 2018).

Name
Position
Effective Date
Termination Date
Quality Control (QC) Manager
Effective date of contract
Site Safety and Health Officer (SSHO)
Effective date of contract
Superintendent
Effective date of contract

* To be provided by Offeror with submittal of quotation and to be approved by Contracting Officer.