This amendment modifies a solicitation for the production of Very Low Frequency transducers. The amendment extends the proposal due date from June 15, 2022 to July 11, 2022 at 2:00 PM Eastern Time. It also provides responses to industry questions. The first question asked about the deliverable required for the final 20% payment, to which the response clarified that final payment is made upon government acceptance of the First Article as qualified. The second question asked about the deliverable for the final 20% payment for Milestone 3, to which the response described the drawings package approval and incorporation into the contract's Product Baseline upon resolution of audit comments. No other terms of the solicitation were changed by this amendment.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
See page 2 for details.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 13-Jun-2022
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X N6660422R0149
X 9B. DATED (SEE ITEM 11)
05-May-2022
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
13-Jun-2022
CODE
NAVAL UNDERSEA WARFARE CENTER
TAYLOR CURTIS, , CODE 0222,
CONTRACTS DEPARTMENT
1176 HOWELL STREET, BLDG. 1258
NEWPORT RI 02841-1708
N66604 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N6660422R0149
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION A - SOLICITATION/CONTRACT FORM
The required response date/time has changed from 15-Jun-2022 02:00 PM to 11-Jul-2022 12:00 AM.
The following have been added by full text:
GENERAL INFO: AMENDMENT 0002
AMENDMENT 0002
The purpose of Amendment 0002 is to:
1. Extend the proposal due date and time to Monday, July 11th, 2022 at 14:00pm EST.
2. Respond to questions from industry as follows:
QUESTION #1: What is the deliverable required to release the final payment of 20%? Milestone #4 already requires Delivery of the First Article Transducer and its receipt by the Government.
RESPONSE #1: Final Payment is when the First Article (FA) is accepted as qualified by the Government.
QUESTION #2: What is the deliverable required to release the final payment of 20%? Milestone #3 already requires submission of the complete drawing package and its review and acceptance by the TPOC subsequent to the FCA/PCA Audit.
RESPONSE #2:
a. Upon completion of the Functional Configuration Audit (FCA)/Physical Configuration Audit (PCA) and resolution of all comments/issues/discrepancies, the Government will approve the drawing package and will convert each drawing in the package with its respective numbered revisions to a revision “-“. The Government will induct the revision “-“ drawing package and it will become under government Configuration Management control. This revision “-“ drawing package forms the Product Baseline.
i. Upon completion of (a), the Contractor can bill for the final 20% of the drawing package.
b. The Government will incorporate the Product Baseline and First Article approval into the contract and will provide official and approved Product Baseline drawing package to the Contractor.
All other terms and conditions remain unchanged.
(End of Summary of Changes)