This solicitation seeks proposals for a five-year indefinite delivery/indefinite quantity production contract for Very Low Frequency transducers in support of the Navy's Acoustic Augmentation Support Program. The Naval Undersea Warfare Center Division, Newport will award a single firm fixed price ID/IQ contract for manufacturers to produce, test, inspect, package and deliver first article and production VLF transducers meeting the performance requirements of the respective VLF Critical Item Performance Specification. The solicitation includes proposed milestone progress payments covering preliminary configuration review, final configuration review, material receipt, transducer delivery, drawing package submission and production documentation release, material ordering and receipt. Responses are due under solicitation number N6660422R0149. The North American Industry Classification code is 334511 and the small business size standard is 1,250 employees.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VLF CLIN 0001 Milestones (First Article Transducers) Severable/Cumulative Percent CLIN 0001

Price Milestone Completion Verification Method

1. Preliminary Configuration Review (PCR) Completion Severable 20%

PCR is conducted IAW the SOW. TPOC receives, reviews, and accepts contractor-submitted PCR presentation package and supporting technical documentation.

2. Final Configuration Review (FCR) Completion Cumulative - based on milestone #1 20%

FCR is conducted IAW the SOW. TPOC receives, reviews, and accepts contractor-submitted FCR presentation package and supporting technical documentation.

3. First Article material received Cumulative - based on milestones #1 and #2. 20% Contractor provides internal report to TPOC which provides proof of purchased material receipt (receipt report and date received).

4. Delivery of First Article Transducers Cumulative - based on milestones #1, #2, and #3. 20% Contractor delivers First Article Transducers and the Government receives them.

TOTAL: 80%

VLF CLIN 0002 Milestones (Drawing Package) Severable/Cumulative Percent CLIN 0002

Price Milestone Completion Verification Method

1. Final Configuration Review (FCR) completion Severable 50%

IAW CDRL B001, contractor submits draft copy of complete drawing package prior to FCR. TPOC reviews and accepts noting any discrepancies identified during the FCR.

2. First Article-Physical Configuration Audit (FA-PCA) completion Cumulative - based on milestone #1 10%

IAW CDRL B001, contractor submits complete drawing package prior to FA-PCA. TPOC reviews and accepts noting any discrepancies identified during the FA-PCA.

3. Functional Configuration Audit/Physical Configuration Audit (FCA/PCA) completion

Cumulative - based on milestones #1 and #2 20% IAW CDRL B001, contractor submits complete drawing package prior to FCA/PCA. TPOC reviews and accepts noting any discrepancies identified during the FCA/PCA.

TOTAL: 80%

VLF PRODUCTION CLINs Milestones Severable/Cumulative Percent CLIN Price Milestone Completion Verification Method

1. Drawings and Production Documentation released. Severable 15%

DCMA representative receives, reviews, and accepts contractor-submitted Product Baseline Drawing listing and supporting technical documentation. Contractor provides internal report to DCMA representative which provides proof of release of production documentation.

2. Material Ordered Cumulative - based on milestone #1 15% Contractor provides internal report to DCMA representative which provides proof that the material was ordered (PO number and date issued).

3. 90% of material line items received. Cumulative - based on milestones #1 and #2 20% Contractor provides internal report to DCMA representative which provides proof that the material was received against the purchase orders (PO) which were placed.

TOTAL: 50%

Solicitation N66604-22-R-0149 for VLF Transducers Proposed Milestone Progress Payment Plan

Solicitation N66604-22-R-XXXX for VLF Transducers Proposed Milestone Progress Payment Plan

Milestones

File details come from the government source that posted it. Updated .