RFI 8-13 Q_A.pdf

PDF 218 KB Posted

Attached to
Construction-B80 2nd Floor Interior Renovation Project Federal contract opportunity
Solicitation number
N6660421R0360
Issued by
Department of the Navy Naval Sea Systems Command

About this file

This document contains questions and answers related to a federal construction contract opportunity. The contract involves interior renovations and repairs to rooms and stairs in Building 80 for the Department of the Navy Naval Sea Systems Command. Specifically, the work includes demolishing existing finishes and a masonry wall, constructing a 30-person and 12-person conference room, and building two handicapped accessible restrooms. According to the document, the government will move and store property within the work area prior to construction starting, and contractors are not required to provide temporary storage for government materials. Contractors must have an active CAGE code to receive drawings and specifications, but do not need JCP certification.

View the file

Other files for this federal contract opportunity

Other files attached to Construction-B80 2nd Floor Interior Renovation Project, newest first.
File Type Posted
RFI 8_16.pdf PDF
B80 2nd Floor Upgrade Site visit 7_28.pdf PDF
RFI 8_12 Q_A.pdf PDF
Additional Photos of the Jobsite.pdf PDF
B80 2nd FLoor RFI Q-A.pdf PDF
Attachment_4_ Covid Questionare.pdf PDF
Attachment 3 Past Performance Questionare.pdf PDF
N6660421R0360.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

- For the Mohawk Carpet tile, color 988 Undertone. What is the style? There are multiple Mohawk carpet tile styles with the color 988 Undertone.

ANSWER: Manufacturers and materials specified are intended to convey the desired final appearance and are not intended to limit the selection of equal color from other manufacturers. The carpet style was not specified for the same purpose. Selected Contractor will need to submit carpet products, with samples, that meet the requirements specified in the contract documents. Reference project specification section 09.68.00 for additional information.

- Division 1, Section 3.3.6 directs the Contractor to provide their own restroom facilities. Please confirm that government restrooms are NOT available for contractor use.

ANSWER: The Contractor will need to provide their own restroom facilities as specified in the Contract Documents.

- Will the Contractor be able to cordon off and control access within confines of the construction work area?

ANSWER: The Contractor will not be allowed to cordon off or control access within the confines of the entire construction work area. This contract work will be performed during normal business hours in an occupied building, where access to adjacent areas will require access through portions of the Construction work area. Reference contract drawing sheet G-101 General Notes for more information.

- Please confirm that the government will move all government property within the construction work area before operations begin. Is the contractor required to provide temporary storage for those materials (cubicles, desks, computers, etc.)?

ANSWER: The Government will move and store all Government Property currently located within the construction work area, prior to the start of construction. The Contractor is not responsible for moving or temporarily storing any Government Property within the construction area.